legal and safety (cv14)
TRANSCRIPT
Legal and Safety (CV14) ED2 Engineering Justification Paper
ED2-NLR(A)-SPEN-001-SAF-EJP
Issue Date Comments
Issue 0.1 March 2021 Issued for SRG
Issue 0.2 April 2021 Revised to incorporate review comments
Issue 1 30th June 2021 Draft Submission
Issue 2 30th November 2021 Final Submission
Scheme Name RIIO-ED2 – CV14 – Legal and Safety
PCFM Cost Type Non-Load Related – Other
Activity Legal and Safety
Primary Investment Driver
Regulatory and legal responsibilities to manage and operate a safe network
Reference ED2-NLR(A)-SPEN-001-SAF-EJP
Output Type Legal and Safety
Cost SPD £4.715m SPM £4.385m
Delivery Year 2023-2028
Reporting Table CV14
Outputs included in ED1 Yes/No
Business Plan Section Ensure a Safe and Reliable Electricity Supply
Primary Annex Annex 4A.18: Legal and Safety (CV14) Strategy
Spend Apportionment ED1 ED2 ED3
£m £9.100m £m
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
1
Technical Governance Process
Project Scope Development IP1(S)
To be completed by the Service Provider or Asset Management. The completed form, together with an accompanying report, should be endorsed by the appropriate sponsor and submitted for approval.
IP1 – To request project inclusion in the investment plan and to undertake project design work or request a modification to an existing project IP1(S) – Confirms project need case and provides an initial view of the Project Scope IP2 – Technical/Engineering approval for major system projects by the System Review Group (SRG)
IP2(C) – a Codicil or Supplement to a related IP2 paper. Commonly used where approval is required at more than one SRG, typically connection projects which require connection works at differing voltage levels and when those differing voltage levels are governed by two separate System Review Groups. IP2(R) – Restricted Technical/Engineering approval for projects such as asset refurbishment or replacement projects which are essentially on a like-for-like basis and not
requiring a full IP2 IP3 – Financial Authorisation document (for schemes > £100k prime) IP4 – Application for variation of project due to change in cost or scope
PART A – PROJECT INFORMATION
Project Title: RIIO ED2- CV14 – Legal and Safety
Project Reference: ED2-NLR(A)-SPEN-001-SAF-EJP
Decision Required: To give concept approval for the CV14 – Legal & Safety Strategy within the RIIO-
ED2 price control period.
Summary of Business Need:
SP Distribution (SPD) and SP Manweb (SPM) have regulatory and legal responsibilities to manage and operate a safe
network. This includes responsibilities as a building and asset owners and employer for workplace safety. This paper
specifically covers the engineering justification for our RIIO-ED2 proposals in Asbestos Management, Metal Theft, Earthing
Upgrades and Safety Recreational Sites.
Summary of Project Scope, Change in Scope or Change in Timing:
SP Energy Networks shall undertake programmes of work to manage the risk and legal responsibilities relating to asbestos
management, metal theft, earthing upgrades and safety recreational sites across our SPD and SPM license areas.
Expenditure Forecast (in 2020/21 Prices)
Recommended Scheme Investment Profile Total
(£m)
Incidence (£m)
2023/24 2024/25 2025/26 2026/27 2027/28
CV14 – Asbestos Management – Surveys and
Signage (SPM) 1.015 0.203 0.203 0.203 0.203 0.203
CV14 – Asbestos Management – Containment or
Removal (SPM) 0.634 0.127 0.127 0.127 0.127 0.127
CV14 – Metal Theft (SPM) 0.529 0.106 0.106 0.106 0.106 0.106
CV14 – Earthing Upgrades (SPM) 1.205 0.241 0.241 0.241 0.241 0.241
CV14 – Safety Recreational Sites (SPM) 0.893 0.179 0.179 0.179 0.179 0.179
CV14 – Associated Pension Costs (SPM) 0.109 0.023 0.022 0.022 0.022 0.020
SPM Subtotal 4.385
CV14 – Asbestos Management – Surveys and
Signage (SPD) 0.953 0.191 0.191 0.191 0.191 0.191
CV14 – Asbestos Management – Containment or
Removal (SPD) 0.634 0.127 0.127 0.127 0.127 0.127
CV14 – Metal Theft (SPD) 0.409 0.082 0.082 0.082 0.082 0.082
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
2
CV14 – Earthing Upgrades (SPD) 1.503 0.301 0.301 0.301 0.301 0.301
CV14 – Safety Recreational Sites (SPD) 1.132 0.226 0.226 0.226 0.226 0.226
CV14 – Associated Pension Costs (SPD) 0.084 0.018 0.017 0.017 0.017 0.015
SPD Subtotal 4.715
This Proposal 9.100
PART B – PROJECT SUBMISSION
Proposed by David Cupples / Charlie Dodds Signature Date: 30/11/2021
Endorsed by Matthew Jones Signature Date: 30/11/2021
PART C – PROJECT APPROVAL
Approved by Malcolm Bebbington Signature
Date: 30/11/2021
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
3
1. Contents 2. Introduction ........................................................................................................................................................ 4
3. Background Information .................................................................................................................................. 4
4. Needs Case ....................................................................................................................................................... 11
5. Optioneering .................................................................................................................................................... 12
6. Detailed Analysis .............................................................................................................................................. 13
7. Deliverability and Risk .................................................................................................................................... 14
8. Future Pathways – Net Zero ........................................................................................................................ 18
9. Conclusion ........................................................................................................................................................ 19
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
4
2. Introduction This paper covers the proposed activity in RIIO-ED2 relating to CV14 Legal and Safety that are not
covered in individual EJPs. The workstreams included are;
• Asbestos Management
• Metal Theft
• Earthing Upgrades
• Safety Recreational Sites
The following legal and safety workstreams are not included with this paper and are covered in
standalone or associated EJPs;
• Site Security (ED2-NLR(A)-SPEN-002-SAF-EJP)
• Fire Protection (ED2-NLR(A)-SPEN-003-SAF-EJP)
• Fire Blankets (Included within ED2-NLR(A)-SPEN-001-SWG-EJP)
• Shallow Cables (Weaver Sluices)( ED2-NLR(A)-SPM-002-SAF-EJP)
SP Distribution (SPD) and SP Manweb (SPM) have regulatory and legal responsibilities to manage and
operate a safe network. This includes responsibilities as a building and asset owners and employer
for workplace safety. This paper specifically covers the engineering justification for our RIIO-ED2
proposals in Asbestos Management, Metal Theft, Earthing Upgrades and Safety Recreational Sites.
The timing of investment proposed within this paper ensures SP Energy Networks continues to
meet its regulatory and legal responsibilities to manage and operate a safe and resilient network.
This investment is spread
3. Background Information
3.1. Asbestos Management
Regulatory Requirements The Control of Asbestos Regulations 2012 (CAR 2012), Part 2, Regulation 4, places a legal duty on
SP Distribution and SP Manweb to manage asbestos within the sites and buildings within our
network. The Health and Safety Executive have published an Approved Code of Practice (ACoP) -
L143 ‘managing and working with asbestos’ which provides guidance for duty holders on complying
with CAR 2012.
CAR 2012 sets out the responsibility of SPD and SPM to carry out assessment of all premises to
determine the presence of asbestos, and duty to manage the risk associated where asbestos is
identified.
SP Energy Networks Strategy SP Energy Networks’ Asbestos Management Strategy, SMS-11-013 Issue No.7, describes the overall
management strategy and defines the minimum standards required to be implemented for the
management of asbestos containing materials (ACMs) in network premises and assets.
The Management Strategy is built around 10 ‘Minimum Standards’ that are applied to ensure
compliance with the legal duty and safety of all who may come into contact with our premises or
assets.
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
5
These standards are as followings
• Minimum Standard 1 – Locating and Recording the Condition of ACMs.
• Minimum Standard 2 – Identification of the Location of ACMs.
• Minimum Standard 3 – Information, Instruction and Training.
• Minimum Standard 4 – Monitoring the Condition of Identified ACMs.
• Minimum Standard 5 – Assessment of Asbestos Work
• Minimum Standard 7 – Notifiable Non-Licensed Work
• Minimum Standard 8 – Non-Licensed Work
• Minimum Standard 9 – Monitoring Asbestos Removal Works
• Minimum Standard 10 – Emergency Procedure
RIIO-ED1 Activity Within RIIO-ED1 we have an ongoing asbestos management programme to keep our records on
ACMs within our network assets up to date and manage the removal / containment / disposal of
asbestos where necessary. SP Energy Networks have a management survey report for every
substation location and as part of our management programme undertake review inspections of all
sites where ACMs have been identified. The frequency of re-inspection is based on risk rating from
the inspection reports as outlined in Table 1 below and set out in SMS-11-013.
Health Index (Report Rating) Re-Inspection Timescale (years)
5 High 10-12 0.5
4 Medium 7-9 1
3 Low 5-6 4
2/1 Very Low 2-4 8 Table 1- Asbestos Re-Inspection Timescales
Where re-inspection identifies issues relating to the condition of ACMs and the associated risk is
above acceptable limits intervention is undertaken. Interventions may include but not limited to the
following;
• Installation of asbestos signage.
• Containment of asbestos at location to reduce risk.
• Removal and disposal of asbestos in line with appropriate regulations.
• Clean-up and disposal of loose asbestos in line with appropriate regulations.
• Testing of suspected ACMs and air testing where necessary.
All works are carried out by licensed asbestos contractors where required and waste disposed in
accordance with current hazardous waste regulations.
Figure 1 and Figure 2 below provided a summary view of performance to date within RIIO-ED1,
forecast cost and volumes for the remaining 2 years, and forecast cost and volumes for the RIIO-
ED2 preferred option for asbestos management detailed within this paper
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
6
Figure 1- Summary of SPM ED1 to ED2 CV14 Asbestos Management
Figure 2 - Summary of SPD ED1 to ED2 CV14 Asbestos Management
Costs and volumes relating to asbestos management works being undertaken at Frodsham and
Rainhill 132kV Substations are set out in ED2-NLR(A)-SPM-001-CIV-EJP and are excluded from this
paper.
3.2. Metal Theft
Regulatory Requirements The Electricity Safety, Quality and Continuity Regulations 2002 (ESQCR) Part 2 (6) states “A
generator or distributor shall be responsible for the application of such protective devices to his
network as will, so far as is reasonably practicable, prevent any current, including any leakage to
earth, from flowing in any part of his network for such a period that that part of his network can no
longer carry that current without danger”. Metal theft on the network is predominantly linked to the
copper tape and cable used for earthing purposes at our substation sites and when stolen can leave
the network assets in an unsafe condition. Therefore, under ESQCR requirements SPD and SPM
must undertake action to remediate following metal theft and where necessary undertake actions to
prevent further metal theft.
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
7
RIIO-ED1 Activity Within the RIIO-ED1 price control period to date metal theft has seen a marked reduction in
intervention requirements from that of DPCR5. Table 2 below outlines the RIIO-ED1 intervention
rate to date. The majority of interventions have been undertaken at our substations sites, with the
most common being the replacement of stolen copper earthing.
License DPCR5 RIIO-ED1
10/11
(No)
11/12
(No)
12/13
(No)
13/14
(No)
14/15
(No)
15/16
(No)
16/17
(No)
17/18
(No)
18/19
(No)
19/20
(No)
20/21
(No)
SPM - 462 200 95 262 98 372 61 49 35 17
SPD - 297 242 392 219 128 31 46 38 17 19
Table 2 - Summary of Metal Theft Interventions in DPCR5 & RIIO-ED1
Within RIIO-ED1 there is an ongoing programme to roll out the use of Smart locks on our
substation sites within the SPM area. This has been credited with assisting reducing the number of
metal theft incident in the SPM area linked to unauthorised access using stolen or copied keys. It is
expected that the smart lock rollout will be completed across both SPD and SPM areas over RIIO-
ED1 and RIIO-ED2.
Figure 3 and Figure 4 below provided a summary view of performance to date within RIIO-ED1,
forecast cost and volumes for the remaining 2 years, and forecast cost and volumes for the RIIO-
ED2 preferred option for metal theft detailed within this paper
Figure 3 - Summary of SPM ED1 to ED2 CV14 Metal Theft
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
8
Figure 4 - Summary of SPD ED1 to ED2 CV14 Metal Theft
3.3. Earthing Upgrades
Regulatory Requirements The upgrading of earthing at secondary substations ensures the SP Energy networks is compliant
with national and international standards as well statutory legislation and licence requirements. The
Technical specification for earthing and bonding at secondary substations is aligned with the current
releases of ESQC Regulations, BS EN50522, ENA TS 41-24 and ENA EREC S34.
SP Energy Network’s Policy The publication of the Technical specification for earthing and bonding at secondary substations
EART-03-003 in February 2020 is to be complied with for all new installations and where significant
work is being undertaken on that substation or asset in terms of pole mounted equipment this is
when the pole is being replaced but the plant is still in good fit for purpose condition.
In the case of Pole mounted substations, the separation is from the HV earthing system and the LV
Neutral earth is now set at a minimum of 20m, as shown in Figure 5 below, this is completed when
the PM transformers is replaced and covered under the asset replacement unit cost.
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
9
Figure 5 - Pole Mounted S/S Earthing Diagram
RIIO-ED1 Activity SP Energy Network’s substation earthing policy (EART-03-003) was updated in February 2020 to
take account of the latest standards as set out in Section 3.3.1. As a result, no programme of
standalone earthing upgrade works have been undertaken within RIIO-ED1, although sites where
asset replacement has taken place all new assets are installed to current policy.
Figure 6 and Figure 7 below provided a summary view of performance to date within RIIO-ED1,
forecast cost and volumes for the remaining 2 years, and forecast cost and volumes for the RIIO-
ED2 preferred option for earthing upgrade detailed within this paper
Figure 6 - Summary of SPM ED1 to ED2 CV14 Earthing Upgrade
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
10
Figure 7- Summary of SPD ED1 to ED2 CV14 Earthing Upgrade
3.4. Safety Recreational Sites
Regulatory Requirements As a responsible network operator, the requirement to maintain a safe and secure network is a key
deliverable and as such during the RIIO-ED2 period we will as part of the OHL modernisation
program, to design solution that will reduce the risk caused by our overhead apparatus that crosses
or is in proximity of recreational sites.
SP Energy Network’s Policy A recreational site is defined within SP Energy Network’s Asset Inspection and Condition
Assessment Policy Asset-01-021 as follows;
“For the purposes of this policy, the term recreational area is defined as areas used by members of
the public for leisure or recreational activities, where their normal/expected activities may increase
the risk of contact with live conductors.”
The risk classification for poles located in or in the vicinity of a recreational area/site are Higher than
Normal Risk.
RIIO-ED1 Activity Following programmes of intervention at recreational sites in both SPD and SPM, undertaken in
DPCR5, relatively low volumes of intervention have been progressed within RIIO-ED1 price control
to date. Figure 8 and Figure 9 below provided a summary view of performance to date within RIIO-
ED1, forecast cost and volumes for the remaining 2 years, and forecast cost and volumes for the
RIIO-ED2 preferred option for safety recreational sites detailed within this paper.
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
11
Figure 8 - Summary of SPM ED1 to ED2 CV14 Safety Recreational Sites
Figure 9 - Summary of SPD ED1 to ED2 CV14 Safety Recreational Sites
4. Needs Case
4.1. Asbestos Management Within SPD and SPM licence areas, the electricity network and substations were first constructed in
the 1930s, with major expansion of the network in the 1960s and 1970s when asbestos was in
regular use in the construction and electrical plant industry due to its fire-resistant properties.
Therefore, ACMs likely to be present in proportion of our substations and assets.
As we continue to modernise our network and replace or refurbish substations and assets, SP
Energy Networks are dutybound to manage the risk from asbestos. A programme of ongoing
inspections, surveys and testing are required to facilitate proposed works within RIIO-ED2 as well as
ongoing maintenance of the networks assets.
Two named projects are being undertaken at Frodsham 132kV and Rainhill 132kV indoor
substations which include CV14 Asbestos Management expenditure. The associated costs are not
included within this paper. For details in relation to these projects please refer to the project specific
EJP ED2-NLR(A)-SPM-001-CIV-EJP.
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
12
It is expected that during RIIO-ED2 the ongoing programme for Asbestos Management shall
continue.
4.2. Metal Theft Metal theft continues to be an issue although incident numbers have fallen in recent years. The rate
of metal theft incidents can be impacted by external factors including scrap metal price. It is
therefore necessary for SPD and SPM to have a reactive policy in place to undertake repairs to the
network whenever metal theft occurs. This ensures SPD and SPM comply with ESQCR
requirements in relation to maintaining a safe network.
4.3. Earthing Upgrades The requirement to undertake Earthing upgrades is to mitigate against high Earth Potential Rise
(EPR) or step and touch potential. The SP Energy Networks Secondary Substation Earthing policy
EART-03-003 Issue 01 that sets out the new separation between earthing systems for pole mounted
and ground mounted substation. This policy demonstrates compliance with the latest national and
international standards.
4.4. Safety Recreational Sites The protection of the public from the inadvertent contact with overhead lines and recreational sites
such as fishing sites, caravan/ camping sites, etc is a key public concern and as such we are required
to reduce this risk by employing suitable solutions/designs. As a responsible network operator SP
Energy Networks attribute greater risk to sites where overhead lines cross or are in the vicinity of
land used for recreational purposes. Therefore, intervention is required at recreational sites where
the risk is perceived to be greater than acceptable to reduce the risk level as far as reasonably
practicable.
5. Optioneering Option 2 as set out below is deemed the “do minimum” activity required by SP Energy Networks to
ensure compliance with regulatory and legislative requirement across our SP Distribution and SP
Manweb license areas.
Option Status Comments
1 Do Nothing Rejected This option would result in SPD and SPM not
complying with current regulatory requirements
and legislation. Therefore, this option was
rejected.
2 Undertake Legal and Safety
Programmes to meet Legal
Requirements
Adopted This is deemed as the “do minimum” option.
Table 3 - Investment Options
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
13
6. Detailed Analysis
6.1. Option 2 – Undertake Legal and Safety Programmes to meet legal
requirements (Do minimum Option)
Asbestos Management This option consists of undertaking the necessary inspection, testing and actions to manage the risk
of asbestos within our asset base. This shall be carried out in accordance with our Asbestos
Management Strategy SMS-11-013 ensuring compliance with CAR 2012.
Metal Theft This option entails the continuation of a reactive programme to rectify damage and replace stolen
assets to substations and plant following metal theft incidents.
Earthing Upgrades Earthing upgrades will be identified on a scheme by scheme basis as part of the modernisation
design, and as part of the asset replacement program for ground mounted substations where the
asset requiring the earthing upgrades is not being replaced under CV7, but other works are being
undertaken
Safety Recreational Sites The options for each recreational site differ due to the voltage and the complexity of the design
required to reduce or remove the risk completely however the design is required to ensure that SP
Energy Networks operates a safe overhead network and as such when modernisation of the
overhead line is due we will as part of that overall design look to reduce this risk.
6.2. Options Technical Summary Table # Option Technical Summary
2 Undertake Legal and
Safety Programmes to
meet legal requirements
SP Energy Networks shall undertake programmes of work to manage
the risk and legal responsibilities relating to asbestos management,
metal theft, earthing upgrades and safety recreational sites across our
SPD and SPM license areas.
Table 4 - Options Technical Summary
6.3. Options Cost Summary Table Table 5 below outlines the costs associated with option considered.
Option CV Cost Breakdown RIIO ED2
Total (£m)
Option 2
(Adopted)
CV14 Asbestos Management – Surveys and Signage (SPM) 1.015
CV14 Asbestos Management – Containment or Removal (SPM) 0.634
CV14 Metal Theft (SPM) 0.529
CV14 Earthing Upgrades (SPM) 1.205
CV14 Safety Recreational Sites (SPM) 0.893
CV14 Associated Pension Costs (SPM) 0.109
SPM TOTAL 4.385
CV14 Asbestos Management – Surveys and Signage (SPD) 0.953
CV14 Asbestos Management – Containment or Removal (SPD) 0.634
CV14 Metal Theft (SPD) 0.409
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
14
Option CV Cost Breakdown RIIO ED2
Total (£m)
CV14 Earthing Upgrades (SPD) 1.503
CV14 Safety Recreational Sites (SPD) 1.132
CV14 Associated Pension Costs 0.084
SPD TOTAL 4.715 Table 5 - Cost Summary Table
Asbestos Management The unit costs and volumes for Asbestos Management are based on the ongoing RIIO-ED1 asbestos
management programme and latest available 2020/21 framework prices.
Metal Theft The unit costs for metal theft interventions within ED2 were developed from an assessment of the
average expenditure per intervention to date in RIIO-ED1 revised to 2020/21 price base. Predicted
volumes for metal theft interventions within RIIO-ED2 have been based on the average of the most
recent years reported volumes within RIIO-ED1.
Earthing Upgrades The unit costs for the earthing upgrades are based on the current wood Pole OHL framework
contract using an average length of earthing required to achieve the required resistive value and the
separation between earthing systems. Table 1Table 6 below provides a breakdown of the unit costs
for earthing upgrades.
Earthing Upgrades Unit Cost
OHL LV Earthing £683.34
OHL HV Earthing £292.86
Total Unit cost for OHL Earthing £976.20
GM Substation Earthing Unit Cost* £3796.69 *Unit cost has been extracted from GM Substation Unit Costs. Refer to Annex 5A.5 Unit Cost Manual.
Table 6 - Earthing Upgrades Unit Costs Summary
Safety Recreational sites The unit costs calculation for recreational sites was based on the previous costs delivered over the
last 2 price reviews, the unit costs varies from site to site due to the complexity of the solution and
as such the variance in the costs is significant.
7. Deliverability and Risk
7.1. Preferred Option The preferred option for Legal and Safety in RIIO-ED2 is Option 2 and shall be to undertake the
following programmes of work;
• Continuation of Asbestos Management in line with Strategy SMS-11-013,
• Continuation of our reactive programme where incidents of metal theft occur on the
network,
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
15
• Carry out a targeted programme of earthing upgrade on assets where other works are being
undertaken in RIIO-ED2, that do not include asset replacement, to comply with current
standards,
• Programme of works to reduce or remove the risk from live overhead conductors at
locations identified as recreational sites.
7.2. Sensitivity of Preferred Option The costs used to drive the programmes within this paper are based on actuals and frameworks unit
costs for the works forecast within RIIO-ED2. In addition, the programmes are required works to
comply with legal and regulatory requirements and there are no other alternative options available.
Therefore, no additional sensitivity analysis was undertaken and no impact to the proposed option.
7.3. Expenditure & Delivery Profile The total proposed expenditure of £9.100m across RIIO-ED2 is presented in Table 7 below
followed by the delivery profile volumes in Table 8. The delivery profile is consistent across all 5
years of RIIO-ED2. Note that costs relating to the named projects at Frodsham 132kV and Rainhill
132kV Substations are not included within this paper and can be found in the dedicated EJP (EJP
ED2-NLR(A)-SPM-001-CIV-EJP)
CV Activity 23/24
(£m)
24/25
(£m)
25/26
(£m)
26/27
(£m)
27/28
(£m)
Total
(£m)
SPM CV14 Asbestos Management – Surveys and Signage 0.203 0.203 0.203 0.203 0.203 1.015
SPM CV14 Asbestos Management – Containment or Removal 0.127 0.127 0.127 0.127 0.127 0.634
SPM CV14 Metal Theft 0.106 0.106 0.106 0.106 0.106 0.529
SPM CV14 Earthing Upgrades 0.241 0.241 0.241 0.241 0.241 1.205
SPM CV14 Safety Recreational Sites 0.179 0.179 0.179 0.179 0.179 0.893
SPM CV14 Associated Pension Costs 0.023 0.022 0.022 0.022 0.020 0.109
SPD CV14 Asbestos Management – Surveys and Signage 0.191 0.191 0.191 0.191 0.191 0.953
SPD CV14 Asbestos Management – Containment or Removal 0.127 0.127 0.127 0.127 0.127 0.634
SPD CV14 Metal Theft 0.082 0.082 0.082 0.082 0.082 0.409
SPD CV14 Earthing Upgrades 0.301 0.301 0.301 0.301 0.301 1.503
SPD CV14 Safety Recreational Sites 0.226 0.226 0.226 0.226 0.226 1.132
SPD CV14 Associated Pension Costs 0.018 0.017 0.017 0.017 0.015 0.084
Table 7 - Summary of Expenditure Profile
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
16
CV Activity 23/24
(Vol)
24/25
(Vol)
25/26
(Vol)
26/27
(Vol)
27/28
(Vol)
Total
(Vol)
SPM CV14 Asbestos Management – Surveys and Signage 684 684 684 684 684 3420
SPM CV14 Asbestos Management – Containment or Removal 18 18 18 18 18 90
SPM CV14 Metal Theft 42 42 42 42 42 210
SPM CV14 Earthing Upgrades 101 101 101 101 101 505
SPM CV14 Safety Recreational Sites 7 7 7 7 7 35
SPD CV14 Asbestos Management – Surveys and Signage 469 469 469 469 469 2345
SPD CV14 Asbestos Management – Containment or Removal 18 18 18 18 18 90
SPD CV14 Metal Theft 28 28 28 28 28 140
SPD CV14 Earthing Upgrades 126 126 126 126 126 630
SPD CV14 Safety Recreational Sites 9 9 9 9 9 45
Table 8 - Summary of Delivery Profile
7.4. SP Manweb Company Specific Factors As a result of the unique interconnected design of our network within SP Manweb license area costs
relating to CV14 – Asbestos Management works have been accounted for within our company
specific factors. It has been determined that £0.20m of our CV14 – Asbestos Management and
associated volumes, are as a result of the SP Manweb network design. Refer to Annex 4A.25 - SP
Manweb Company Specific Factors for further details.
7.5. Risk Our Asbestos Management Programme is the continuation of RIIO-ED1 with similar volumes being
delivered. These are delivered using our framework licensed asbestos contractors to carry out our
surveys and containment or removal works. Therefore, we see no risk to the deliverability of our
asbestos programme.
Metal Theft is a reactive strategy and reliant on the number of incidents that occur. Given the RIIO-
ED2 forecast and recent trends are significantly lower than that delivered in early RIIO-ED1. There
remains a risk that fluctuations in incidents year on year will mean delivery may vary from the
current forecast however we believe this is manageable within our forecast plan.
Our Earthing Upgrade interventions within RIIO-ED2 shall be delivered alongside our asset
modernisation programmes utilising the same contractors and resource. There is a need to manage
and assess the land and planning rights associated with additional earthing, this will become more
demanding under the new standards. We will keep this risk under ongoing review.
Safety recreational sites is a relatively low volume programme of work in comparison to our wider
overhead line strategies within RIIO-ED2. Therefore, we foresee no risks in the deliverability of this
programme outside the site-specific solutions varying.
7.6. Stakeholder Engagement Robust stakeholder engagement has been completed to identify what is important for customers in
RIIO-ED2, and to gain insights from key stakeholders such as manufacturers, community energy
groups, water and transportation companies, business groups, academia and asset managers from a
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
17
range of industry. This ensures that the views and needs of all key stakeholders, as well as customer
acceptability, are reflected in the proposed costs and volumes in this paper.
Below is a summary of key relevant outcomes from stakeholder engagement for this programme of
works. The views of the stakeholders can be explored in more detail in Annex 3.1: Co-creating our
RIIO-ED2 business plan with our stakeholders, and in Annex 4A.18: Legal and Safety (CV14)
Strategy.
Customer Feedback
• “How SPEN manages health and safety regulation" was ranked 5/24 and 4/24 by domestic
and commercial customers respectively. – Reliability Triangulation C1.2
• The majority of domestic customers (72%) agree SPEN should continue to proactively invest
to resolve potential safety risks and perceive it as an 'inbuilt' responsibility that SPEN have.
The majority of customers are also happy to accept a bill increase if it is necessary to keep
the network safe. – Reliability Triangulation C2.14
Investing in Legal and Safety programmes of work within this paper support this by ensuring our
network assets are in a safe and compliant condition.
Manufacturers
• Manufacturers provided the following views:
o Modernisation is essential to ensuring network resilience;
o Given customers’ increasing reliance on electricity, it is important to have a focus on
reducing fault rates as well as reducing the extent of impact of faults on customers;
o Increasing grid dynamic response capabilities has allowed many utilities worldwide to
improve existing infrastructure performance and quality of supply.
This programme of works will improve network resilience / reduce the impact of faults / improve
network dynamic operability by upgrading our assets to ensure compliance with latest regulations
and replacing damaged / stolen earthing while supporting overall resilience of the network.
Energy Consultants
• Energy consultants agreed that SP Energy Networks should continue to utilise proven
interventions on network assets, and there has been clear support for SP Energy Networks
to continue investing in network resilience [to reduce faults].
This EJP sets out a range of proven interventions including through all the programmes within this
paper. SP Energy Networks have also sought to adopt proven innovative alternatives wherever
possible and provide cost-efficiency.
Local Governments
• Local governments agreed with SP Energy Networks’ approach of managing risk by focusing
on replacing and modernising the poorest condition & highest risk assets.
This paper sets out how SP Energy Networks are intervening, across a number of programmes, on
our poorest condition and highest risk assets.
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
18
8. Future Pathways – Net Zero
8.1. Primary Economic Driver The key driver for this proposal is to ensure compliant with legal obligations and managing safety risk
from the network.
8.2. Pathways and End Points Carrying out the legal and safety activities detailed within this paper are a necessary requirement to
maintain the safety, resilience and reliability of the distribution network under all decarbonisation
pathways. As society continues to decarbonise and the role of the network becomes more critical
to customers, it is increasingly critical that fire safety of our network is maintained and improved.
8.3. Asset Stranding Risks There is not considered to be any asset stranding risk associated with this programme. All Primary
and Grid sites are intended to be occupied for the forecast asset life.
8.4. Losses / Sensitivity to Carbon Prices It has not been necessary to consider losses of carbon pricing as part of this investment programme.
8.5. Future Asset Utilisation The works being carried out in relation to asbestos removal and earthing upgrade are ensuring that
these areas of the Network are fit for future use / repowering.
8.6. Whole Systems Benefits Whole system solutions have been considered as part of this proposal. No alternatives have been
identified that could be provided through a whole systems solution. The completion of this scheme
will maintain the integrity of the distribution network and its enduring ability to facilitate wider
whole system benefits.
8.7. Environment and Sustainability
Operational and embodied carbon emissions The Legal and Safety programme has the potential to result in embodied carbon from the delivery of
interventions required. There is unlikely to be any impact on SPEN’s Business Carbon Footprint
(BCF).
Supply chain sustainability For us to take full account of the sustainability impacts associated of the Legal and Safety
programme, we need access to reliable data from our suppliers. The need for carbon and other
sustainability credentials to be provided now forms part of our wider sustainable procurement
policy.
Resource use and waste Potential interventions may result in the consumption of resources and the generation of waste
materials.
Where waste is produced it will be managed in accordance with the waste hierarchy which ranks
waste management options according to what is best for the environment. The waste hierarchy gives
ED2-NLR(A)-SPEN-001-SAF-EJP – CV14 Legal and Safety
19
top priority to preventing waste in the first instance, then preparing for re-use, recycling, recovery,
and last of all disposal (e.g. landfill).
Biodiversity / natural capital Due to the nature of the proposed interventions, it is unlikely that there will be any impact in
relation to biodiversity and natural capital.
Preventing pollution Due to the nature of the proposed interventions, it is unlikely that there will be any impact in
relation to pollution. However, SPEN will always follow all relevant waste regulations and will make
sure that special (hazardous) waste produced or handled by our business including asbestos is
treated in such a way as to minimise any effects on the environment.
Visual amenity Due to the nature of the proposed interventions, it is unlikely that there will be any impact in
relation to visual amenity.
Climate change resilience Due to the nature of the proposed interventions, it is unlikely that there will be any impacts in
relation to future changes in climate.
9. Conclusion SPD and SPM propose to undertake programmes of work within RIIO-ED2 price control period to
manage legal responsibilities and safety risks relating to asbestos management, metal theft, earthing
standards and recreational sites. Most of these programmes are continuing from established RIIO-
ED1 works apart from Earthing Upgrades, where a change in standards is driving a step change in the
level of work at HV ground and pole mounted substations.
Predicted costs: £ 9.100m (£4.385m – SPM, £4.715m - SPD)
• Timing of investment: 2023 – 2028
• Volumes: 7510 (4260No SPM, 3250 No SPD)
CV Activity Total (£m)
SPM CV14 Asbestos Management – Surveys and Signage 1.015
SPM CV14 Asbestos Management – Containment or Removal 0.634
SPM CV14 Metal Theft 0.529
SPM CV14 Earthing Upgrades 1.205
SPM CV14 Safety Recreational Sites 0.893
SPM CV14 Associated Pension Costs 0.109
SPD CV14 Asbestos Management – Surveys and Signage 0.953
SPD CV14 Asbestos Management – Containment or Removal 0.634
SPD CV14 Metal Theft 0.409
SPD CV14 Earthing Upgrades 1.503
SPD CV14 Safety Recreational Sites 1.132
SPD CV14 Associated Pension Costs 0.084