lesson 4 activity based costing- abc
TRANSCRIPT
Lesson 4Activity Based Costing- ABC
By,
C.A.Kankanamge
1
Activity Based Costing- ABC
Learning Objectives :
At the end of the session :
1. Student should understand the Activity Based Costing ( ABC) Concepts
2. Students should compare traditional costing method with the ABC
3. Prepare cost sheet by using the ABC method
2
Total Cost of Product/ Service Unit
• Direct Material Cost = xxxx
• Direct Labour Cost = xxxx
• Total Direct Cost / = xxxxx
Prime Cost
(+) Overhead Cost = xxxx
Total Cost = xxxxx
3
Example : Traditional Costing Method
• XYZ Company manufactures and sells two types of tables: Standard and Luxury.
• Annual sales, direct labor hours, and total direct labor hours per year are provided below
Total labor hrs. required
Standard: 2,000 units * 5 labor hours per unit
10,000
Luxury: 10,000 units * 4 labor hours per unit
40,000
Total Labor Hours 50,000 4
Standard Luxury
Direct Materials $25 $17
Direct Labor ($12 per hour)
$60 ($ 12 per hr x 5hrs)
$48 ($ 12 per hr x 4rs)
Costs for materials and labor cost for each table are provided below:
5
• Manufacturing overhead costs total $800,000 every year. The breakdown of these costs among the company’s six activity cost pools is given below.
• The following six activities contribute to overall overhead costs.
6
Estimated Manufacturing Overhead Cost
StandardLuxury
Total
Labor related $80,000 10,000 hrs 40,000hrs 50,000 hrs
Machine setups $150,000 3000 set ups
2,000set ups
5,000set ups
Parts administration $160,000 50parts 30parts 80parts
Production orders $70,000 100 orders 300 orders 400orders
Material receipts $90,000 150 receipts
600 receipts
750 recipts
General factory machine hours
$250,000 12,000hrs 28,000 hrs 40,000
7
• Traditional Overhead Absorption Rate =
Total Budgeted Overhead
Total Labor hrs /Machine hrs
• Using the predetermined overhead rate approach with labor hours, the predetermined overhead rate is equal to $16 per labor hour ($800,000 / 50,000 labor hours). Using this information, we can design the total cost for each product.
8
Unit Cost - Using Traditional ApproachStandard
Luxury
Direct materials $25 $17
Direct labor $60 $48
Manufacturing overhead applied:
Standard: 5 labor hours * $16 per labor hour
$80
Luxury: 4 labor hours * $16 per labor hour
$64
Unit product cost $165 $1299
Activity-Based Approach to Determine Overhead
• Using the activity-based costing approach, we can determine overhead rates for each activity that is relevant to production.
• The activities listed below are given in this example but companies usually break down the relevant activities.
10
Activity-Based Costing
• Activity-based costing is a method of assigning indirect costs to products and services by identifying cost of each activity involved in the production process and assigning these costs to each product based on its consumption of each activity.
11
Activity Cost Pools• An activity cost pool is an aggregate of all the costs
associated with performing a particular business task, such as making a particular product. By pooling all costs incurred in a particular task, it is simpler to get an accurate estimate of the cost of that task.
Cost Driver• Factor or variable which has a cause and effect
relationship with the total cost. The cost driver is the ’cause’, and the ‘total cost incurred’ is the effect of it.
• If we take an example of fuel cost of running a car, the cost driver (cause) would be ‘No. of Kms Run’, and the total cost (effect) would be ‘total cost of fuel’. The relationship is quite clear. Higher the no. of km run, higher would be the total cost of fuel.
12
Formula – Overhead Rate Per Cost Driver
13
Overhead Rate Per Cost Driver
14
15
16
Example : Activity Cost Driver
ActivityCost
Driver (activity)
Overhead Cost
Estimated Units
Rate
Purchasing Materials
Pieces of materials
$ 200,000100,000 pieces
$ 2 per piece
Machine Setups
Machine setups
800,000 400 setups 2,000 per setup
InspectionsInspection hours
400,0004,000
inspect. hours
100per
inspect. hour
Running Machine
Machine hours
600,00020,000 mach. Hours
30per
machine hour
Total Overhead
$ 2,000,000 17
Methods used for Activity-Based Costing (Steps)
1. Identify the activities that consume resources and assign costs to those activities.
Purchasing materials would be an activity, for example.2. Identify the cost drivers associated with each activity. A cost driver is an activity or transaction that causes costs to be incurred. For the purchasing materials activity, the cost drivers could be the number of orders placed or the number of items ordered. Each activity could have multiple cost drivers.3.Compute a cost rate per cost driver unit. The cost driver rate could be the cost per purchase order, for example.4. Assign costs to products by multiplying the cost driver rate times the volume of cost driver units consumed by the product. For example, the cost per purchase order times the number of orders required for Product A for the month of December would measure the cost of the purchasing activity for Product A for December. 18
Activity Estimated MOHTotal per Activity
Overhead Rate
Labor related $80,000 50,000 hours $1.60 per labor hour
Machine setups $150,000 5,000 setups $30.00 per setup
Parts administration
$160,000 80 parts $2,000 per part
Production orders
$70,000 400 orders $175 per order
Material receipts $90,000 750 receipts $120 per receipt
General factory machine hours
$250,000 40,000 machine hours
$6.25 per machine hour
19
• Next, for each product, we can use the calculated overhead rates to determine the overhead Cost.
20
Standard Luxury
Activity Expected Activity
Overhead applied
Expected Activity
Overhead applied
Labor-related 10,000 $16,000 40,000 $64,000
Machine setups
3,000 $90,000 2,000 $60,000
Part administration
50 $100,000 30 $60,000
Production orders
100 $17,500 300 $52,500
Material receipts
150 $18,000 600 $72,000
General factory machine hours
12,000 $75,000 28,000 $175,000
Total $316,500 $483,500
Units produced
2,000 Units produced
10,000
Overhead cost per unit
$158.25 Overhead cost per unit
$48.3521
Unit Cost Card Using Activity-Based-Costing Approach
Standard Luxury
Direct materials $25 $17
Direct labor $60 $48
Manufacturing overhead applied:
Standard: $158.25
Luxury: $48.35
Unit product cost $243.25 $113.35
22
Thank You.
23