lhc access system 1 edms: 88808518 january 2008 global tests of the lhc access system outcome p....

18
LHC ACCESS SYSTEM 1 EDMS: 888085 18 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January 2008

Upload: samuel-day

Post on 18-Jan-2018

223 views

Category:

Documents


0 download

DESCRIPTION

LHC ACCESS SYSTEM 3 EDMS: January 2008 Main Test Objectives Test the Access System when doing a patrol of all the LHC points In « Access Mode », test the correct system behaviour when one or more EIS-beam becomes unsafe In « Beam Mode », test the triggering of all the « EIS- BEAM» and external interfaces (BI, LBDS) in case of intrusion, door opening inside the LHC or Emergency stop. Test the access delegation operation with the Experiments In collaboration with AB/OP, prepare the LHC Access operation and train the users

TRANSCRIPT

Page 1: LHC ACCESS SYSTEM 1 EDMS: 88808518 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January

LHC ACCESS SYSTEM

1EDMS: 888085 18 January 2008

Global Tests of the LHC Access system

Outcome

P. Ninin, T. Petterson, S Grau, T. Ladzinski

18th January 2008

Page 2: LHC ACCESS SYSTEM 1 EDMS: 88808518 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January

LHC ACCESS SYSTEM

2EDMS: 888085 18 January 2008

Global tests

• Organization:- Organized by Silvia Grau and Pierre Ninin- Performed by a large team of TS/ASE- In excellent collaboration with AB/OP (to help searching

LHC, giving access, driving EIS-beam equipment, etc…)• From Monday 7th to Sunday 13th January

Page 3: LHC ACCESS SYSTEM 1 EDMS: 88808518 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January

LHC ACCESS SYSTEM

3EDMS: 888085 18 January 2008

Main Test Objectives

• Test the Access System when doing a patrol of all the LHC points

• In « Access Mode », test the correct system behaviour when one or more EIS-beam becomes unsafe

• In « Beam Mode », test the triggering of all the « EIS-BEAM» and external interfaces (BI, LBDS) in case of intrusion, door opening inside the LHC or Emergency stop.

• Test the access delegation operation with the Experiments

• In collaboration with AB/OP, prepare the LHC Access operation and train the users

Page 4: LHC ACCESS SYSTEM 1 EDMS: 88808518 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January

LHC ACCESS SYSTEM

4EDMS: 888085 18 January 2008

Test Strategy

LHC1LHC1.8LHC2

LHC3

LHC4

LHC5LHC6

LHC7

LHC8

LHC1LHC1.8LHC2LHC3LHC4LHC5LHC6LHC7LHC8

Step 1: Factory acceptanceStep 2: Site acceptance

Step 3: Global acceptance

Page 5: LHC ACCESS SYSTEM 1 EDMS: 88808518 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January

LHC ACCESS SYSTEM

5EDMS: 888085 18 January 2008

Monday 7th – Sunday 13th January

• Monday: - Move the system from “installation” to “operation”

• Tuesday to Thursday: - Patrol the LHC

• Thursday evening- Closing the LHC and move to BEAM mode

• Friday- System test in Access mode

• Saturday: - System test in Beam mode

• Sunday: - Move the system back to “installation” mode

Page 6: LHC ACCESS SYSTEM 1 EDMS: 88808518 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January

LHC ACCESS SYSTEM

6EDMS: 888085 18 January 2008

Patrolling the LHC

• Simplified quick patrol of the 160 access sectors : - All patrol boxes have been rearmed and sectors quickly searched.

• Seal (“Plombage”): - Emergency exit handles on all doors and access points

• Teach the people to open doors the normal way • Emergency opening with the “emergency handle” is of course still possible

- After the tests, the seals have been left on most doors

• Patrol procedure- AB patrol procedure not used with the exception of LHC8- ATLAS real patrol procedure done (without SSA)- CMS patrol procedure attempt

Page 7: LHC ACCESS SYSTEM 1 EDMS: 88808518 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January

LHC ACCESS SYSTEM

7EDMS: 888085 18 January 2008

Patrolling the LHC

• Some people had to work in the sectors being searched:- List of authorised workers was provided before the tests - Workers were ready with the “biometry” and the dosimeter, no

particular problem reported to access LHC in general mode- Access given to workers in restricted mode in the patrolled area

• Access to experiments allowed throughout the whole week:- Grids removed at PX24 and ULX15 access points to allow access to

ALICE and ATLAS during the tests. - One guardian was placed next to each missing grid to control access- Only one door forced between the ATLAS cavern and the service area

(which had to be re-patrolled)- Atlas suspended work Saturday, due to the almost permanent BIW

signals resonating….- Alice representative in CCC during the tests to inform the experiment

in case of real “evacuation”

Page 8: LHC ACCESS SYSTEM 1 EDMS: 88808518 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January

LHC ACCESS SYSTEM

8EDMS: 888085 18 January 2008

Tests in access mode

• “One or more EIS-beam becomes unsafe”• Initial state:

- LHC fully searched, - “Access mode”- All EIS-beam are safe

Eis-beam:Power converters: LHC 2,3,7,818kV & 400V cells: LHC 2,3,7,8TEDs: TI2 & TI8Access Safety Blocks: LHC 3External interfacesBeam Imminent WarningLHC beam dumpBeam interlock systemSSASPS access system

Page 9: LHC ACCESS SYSTEM 1 EDMS: 88808518 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January

LHC ACCESS SYSTEM

9EDMS: 888085 18 January 2008

Tests in access mode

• Test case A: One EIS-beam becomes unsafe: - Result:

• the system goes to access-off• Test case B: Two EIS-beam become unsafe:

- Result: • the system goes to access-off • and BIW (Beam Imminent Warning) sirens start

• Systematic tests done, for each EIS-beam, one by one• Tests were successful.• Remarks:

- First time LHC went to “access-off”, after BIW : • evacuation siren in point 6, fire alarm and ODH alarms in point 6,

and 3 minutes later AUG in point 8. • All false alarms, but resulting in two fire-brigade interventions.

Page 10: LHC ACCESS SYSTEM 1 EDMS: 88808518 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January

LHC ACCESS SYSTEM

10EDMS: 888085 18 January 2008

Tests in beam mode

• Test case: Move into « safe position » all « EIS-Beam» and external systems (BI, LBDS) in case of:

- Intrusion, - Door opening inside the LHC - Emergency stop.

• Initial state:- LHC fully searched and closed (leaving some people in, on purpose, for the tests)- “beam mode”- EIS-beam unsafe (18 KV cells “ON”, power converters “ON”, TEDs “OUT”, etc…)

• A sample of all types of doors tested all around the LHC: - inter-site doors, sector doors, end of zone doors, trapdoors, ventilation doors,

access point (both PAD and MAD), etc…• One real AUG done in LHC 7: OK• Outcome: Tests successful

- All intrusions detected- Interlocks triggered all the EIS-Beam to move into SAFE

position

Page 11: LHC ACCESS SYSTEM 1 EDMS: 88808518 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January

LHC ACCESS SYSTEM

11EDMS: 888085 18 January 2008

EIS-Beam and external interfaces

• Beam Imminent Warning when two “EIS-Beam” go unsafe: should actually be “Evacuation siren” rather than BIW

• A power converter and its associated power distribution cell are currently considered as two independent EIS-Beams: should be considered as a single one

• On several occasions the TEDs could not be moved. Still unclear why.

• On several occasions: LASS saw TEDTI8 “OUT” (actually “not IN”) although it was “IN”. Position Sensor issue?

• Electrical problems with two power converters (warm magnets in point 3 and 7) – under investigation

• LBDS: triggered as foreseen, timing of signals to be investigated

• BIS: final system not installed

Page 12: LHC ACCESS SYSTEM 1 EDMS: 88808518 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January

LHC ACCESS SYSTEM

12EDMS: 888085 18 January 2008

Test Results

• Access system installation was completed just before Christmas• Project team is satisfied of the test outcome

- 6 days extensive use of LASS and LACS- All LASS and LACS functionalities tested- Many lessons learned

• Post-mortem data analysis still ongoing- Not easy due to the multiple data sources

• Some external systems not in final configuration- Test of the interfaces (LBDS, PC, BIC,…) but not of the complete chain

Page 13: LHC ACCESS SYSTEM 1 EDMS: 88808518 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January

LHC ACCESS SYSTEM

13EDMS: 888085 18 January 2008

LHC ACCESS CONTROL SYSTEM - LACS

• Improvements seen in software since the LHC7 and LHC8 (TI8 test) summer tests:

- Human interface to LACS works fine but should be improved (slow response, could be more human friendly, occasional restart of the application)

- IHM Lass data representation to be controlled- Video matrix migrated to a dedicated PC

• System diagnostics still have to be improved• Token distributor issue:

- problem under investigation:• Either common mode in key distributor • or evolution not in phase between HW & SW • Contractors and supplier contacted

• Some minor non-conformities to be fixed- Mechanical : equipment mounting (locks), PAD fine tuning…- Information stickers

• Access point software- User information and local IHM to be improved

Page 14: LHC ACCESS SYSTEM 1 EDMS: 88808518 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January

LHC ACCESS SYSTEM

14EDMS: 888085 18 January 2008

LHC ACCESS SAFETY SYSTEM

• The LHC Access Safety System behaves as specified• A few relays had to be changed, a few problems solved on line• Diagnostic module and interface with TI still to be developed• Homogenization to be done between the LASS software installed for TI8

test (LHC7 & 8) in November 06 and the version deployed on the other LHC sites (LASS V.2)

Page 15: LHC ACCESS SYSTEM 1 EDMS: 88808518 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January

LHC ACCESS SYSTEM

15EDMS: 888085 18 January 2008

Next stages

• LASS- Once the key distributor issue is corrected, the LASS can be

used as it stands today to ensure the safety of the personnel in the LHC.

- Preparation of version 2 including all modifications/upgrades • required by AB/OP (patrol behaviour, evacuation instead of BIW in

case of two EIS beam are Unsafe…)• Sectorization changes (new doors…)• Minor software upgrades• Ideally before the LHC start-up• Expect 6 months of development and testing of new software

version

• On site- Personnel permeability of the 160 access sectors – i.e. closing

the small loopholes still open.• To be followed up by DSO and OP acceptance tests

Page 16: LHC ACCESS SYSTEM 1 EDMS: 88808518 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January

LHC ACCESS SYSTEM

16EDMS: 888085 18 January 2008

Other lessons learned

• Training for using the access system- All users : film prepared, soon integrated in the CERN

training- Firemen :

• How to enter the machine without loosing the patrol - procedures, training and keys…

• Inform firemen before and during the tests

Page 17: LHC ACCESS SYSTEM 1 EDMS: 88808518 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January

LHC ACCESS SYSTEM

17EDMS: 888085 18 January 2008

To be done

• Test specific TI8 loop as done for LHC2• Test delegation operation by the experiments• Test all the fire doors and crinolines when installed • Install Material Access Device personnel detection• Interface with the Atlas Safety System.

Page 18: LHC ACCESS SYSTEM 1 EDMS: 88808518 January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January

LHC ACCESS SYSTEM

18EDMS: 888085 18 January 2008

Magali’s conclusion (AB/OP)

• Excellent collaboration between TS and AB

• Overall a very successful and interesting week• To be followed up by DSO and OP acceptance tests