lhc access system 1 edms: 88808518 january 2008 global tests of the lhc access system outcome p....
DESCRIPTION
LHC ACCESS SYSTEM 3 EDMS: January 2008 Main Test Objectives Test the Access System when doing a patrol of all the LHC points In « Access Mode », test the correct system behaviour when one or more EIS-beam becomes unsafe In « Beam Mode », test the triggering of all the « EIS- BEAM» and external interfaces (BI, LBDS) in case of intrusion, door opening inside the LHC or Emergency stop. Test the access delegation operation with the Experiments In collaboration with AB/OP, prepare the LHC Access operation and train the usersTRANSCRIPT
LHC ACCESS SYSTEM
1EDMS: 888085 18 January 2008
Global Tests of the LHC Access system
Outcome
P. Ninin, T. Petterson, S Grau, T. Ladzinski
18th January 2008
LHC ACCESS SYSTEM
2EDMS: 888085 18 January 2008
Global tests
• Organization:- Organized by Silvia Grau and Pierre Ninin- Performed by a large team of TS/ASE- In excellent collaboration with AB/OP (to help searching
LHC, giving access, driving EIS-beam equipment, etc…)• From Monday 7th to Sunday 13th January
LHC ACCESS SYSTEM
3EDMS: 888085 18 January 2008
Main Test Objectives
• Test the Access System when doing a patrol of all the LHC points
• In « Access Mode », test the correct system behaviour when one or more EIS-beam becomes unsafe
• In « Beam Mode », test the triggering of all the « EIS-BEAM» and external interfaces (BI, LBDS) in case of intrusion, door opening inside the LHC or Emergency stop.
• Test the access delegation operation with the Experiments
• In collaboration with AB/OP, prepare the LHC Access operation and train the users
LHC ACCESS SYSTEM
4EDMS: 888085 18 January 2008
Test Strategy
LHC1LHC1.8LHC2
LHC3
LHC4
LHC5LHC6
LHC7
LHC8
LHC1LHC1.8LHC2LHC3LHC4LHC5LHC6LHC7LHC8
Step 1: Factory acceptanceStep 2: Site acceptance
Step 3: Global acceptance
LHC ACCESS SYSTEM
5EDMS: 888085 18 January 2008
Monday 7th – Sunday 13th January
• Monday: - Move the system from “installation” to “operation”
• Tuesday to Thursday: - Patrol the LHC
• Thursday evening- Closing the LHC and move to BEAM mode
• Friday- System test in Access mode
• Saturday: - System test in Beam mode
• Sunday: - Move the system back to “installation” mode
LHC ACCESS SYSTEM
6EDMS: 888085 18 January 2008
Patrolling the LHC
• Simplified quick patrol of the 160 access sectors : - All patrol boxes have been rearmed and sectors quickly searched.
• Seal (“Plombage”): - Emergency exit handles on all doors and access points
• Teach the people to open doors the normal way • Emergency opening with the “emergency handle” is of course still possible
- After the tests, the seals have been left on most doors
• Patrol procedure- AB patrol procedure not used with the exception of LHC8- ATLAS real patrol procedure done (without SSA)- CMS patrol procedure attempt
LHC ACCESS SYSTEM
7EDMS: 888085 18 January 2008
Patrolling the LHC
• Some people had to work in the sectors being searched:- List of authorised workers was provided before the tests - Workers were ready with the “biometry” and the dosimeter, no
particular problem reported to access LHC in general mode- Access given to workers in restricted mode in the patrolled area
• Access to experiments allowed throughout the whole week:- Grids removed at PX24 and ULX15 access points to allow access to
ALICE and ATLAS during the tests. - One guardian was placed next to each missing grid to control access- Only one door forced between the ATLAS cavern and the service area
(which had to be re-patrolled)- Atlas suspended work Saturday, due to the almost permanent BIW
signals resonating….- Alice representative in CCC during the tests to inform the experiment
in case of real “evacuation”
LHC ACCESS SYSTEM
8EDMS: 888085 18 January 2008
Tests in access mode
• “One or more EIS-beam becomes unsafe”• Initial state:
- LHC fully searched, - “Access mode”- All EIS-beam are safe
Eis-beam:Power converters: LHC 2,3,7,818kV & 400V cells: LHC 2,3,7,8TEDs: TI2 & TI8Access Safety Blocks: LHC 3External interfacesBeam Imminent WarningLHC beam dumpBeam interlock systemSSASPS access system
LHC ACCESS SYSTEM
9EDMS: 888085 18 January 2008
Tests in access mode
• Test case A: One EIS-beam becomes unsafe: - Result:
• the system goes to access-off• Test case B: Two EIS-beam become unsafe:
- Result: • the system goes to access-off • and BIW (Beam Imminent Warning) sirens start
• Systematic tests done, for each EIS-beam, one by one• Tests were successful.• Remarks:
- First time LHC went to “access-off”, after BIW : • evacuation siren in point 6, fire alarm and ODH alarms in point 6,
and 3 minutes later AUG in point 8. • All false alarms, but resulting in two fire-brigade interventions.
LHC ACCESS SYSTEM
10EDMS: 888085 18 January 2008
Tests in beam mode
• Test case: Move into « safe position » all « EIS-Beam» and external systems (BI, LBDS) in case of:
- Intrusion, - Door opening inside the LHC - Emergency stop.
• Initial state:- LHC fully searched and closed (leaving some people in, on purpose, for the tests)- “beam mode”- EIS-beam unsafe (18 KV cells “ON”, power converters “ON”, TEDs “OUT”, etc…)
• A sample of all types of doors tested all around the LHC: - inter-site doors, sector doors, end of zone doors, trapdoors, ventilation doors,
access point (both PAD and MAD), etc…• One real AUG done in LHC 7: OK• Outcome: Tests successful
- All intrusions detected- Interlocks triggered all the EIS-Beam to move into SAFE
position
LHC ACCESS SYSTEM
11EDMS: 888085 18 January 2008
EIS-Beam and external interfaces
• Beam Imminent Warning when two “EIS-Beam” go unsafe: should actually be “Evacuation siren” rather than BIW
• A power converter and its associated power distribution cell are currently considered as two independent EIS-Beams: should be considered as a single one
• On several occasions the TEDs could not be moved. Still unclear why.
• On several occasions: LASS saw TEDTI8 “OUT” (actually “not IN”) although it was “IN”. Position Sensor issue?
• Electrical problems with two power converters (warm magnets in point 3 and 7) – under investigation
• LBDS: triggered as foreseen, timing of signals to be investigated
• BIS: final system not installed
LHC ACCESS SYSTEM
12EDMS: 888085 18 January 2008
Test Results
• Access system installation was completed just before Christmas• Project team is satisfied of the test outcome
- 6 days extensive use of LASS and LACS- All LASS and LACS functionalities tested- Many lessons learned
• Post-mortem data analysis still ongoing- Not easy due to the multiple data sources
• Some external systems not in final configuration- Test of the interfaces (LBDS, PC, BIC,…) but not of the complete chain
LHC ACCESS SYSTEM
13EDMS: 888085 18 January 2008
LHC ACCESS CONTROL SYSTEM - LACS
• Improvements seen in software since the LHC7 and LHC8 (TI8 test) summer tests:
- Human interface to LACS works fine but should be improved (slow response, could be more human friendly, occasional restart of the application)
- IHM Lass data representation to be controlled- Video matrix migrated to a dedicated PC
• System diagnostics still have to be improved• Token distributor issue:
- problem under investigation:• Either common mode in key distributor • or evolution not in phase between HW & SW • Contractors and supplier contacted
• Some minor non-conformities to be fixed- Mechanical : equipment mounting (locks), PAD fine tuning…- Information stickers
• Access point software- User information and local IHM to be improved
LHC ACCESS SYSTEM
14EDMS: 888085 18 January 2008
LHC ACCESS SAFETY SYSTEM
• The LHC Access Safety System behaves as specified• A few relays had to be changed, a few problems solved on line• Diagnostic module and interface with TI still to be developed• Homogenization to be done between the LASS software installed for TI8
test (LHC7 & 8) in November 06 and the version deployed on the other LHC sites (LASS V.2)
LHC ACCESS SYSTEM
15EDMS: 888085 18 January 2008
Next stages
• LASS- Once the key distributor issue is corrected, the LASS can be
used as it stands today to ensure the safety of the personnel in the LHC.
- Preparation of version 2 including all modifications/upgrades • required by AB/OP (patrol behaviour, evacuation instead of BIW in
case of two EIS beam are Unsafe…)• Sectorization changes (new doors…)• Minor software upgrades• Ideally before the LHC start-up• Expect 6 months of development and testing of new software
version
• On site- Personnel permeability of the 160 access sectors – i.e. closing
the small loopholes still open.• To be followed up by DSO and OP acceptance tests
LHC ACCESS SYSTEM
16EDMS: 888085 18 January 2008
Other lessons learned
• Training for using the access system- All users : film prepared, soon integrated in the CERN
training- Firemen :
• How to enter the machine without loosing the patrol - procedures, training and keys…
• Inform firemen before and during the tests
LHC ACCESS SYSTEM
17EDMS: 888085 18 January 2008
To be done
• Test specific TI8 loop as done for LHC2• Test delegation operation by the experiments• Test all the fire doors and crinolines when installed • Install Material Access Device personnel detection• Interface with the Atlas Safety System.
LHC ACCESS SYSTEM
18EDMS: 888085 18 January 2008
Magali’s conclusion (AB/OP)
• Excellent collaboration between TS and AB
• Overall a very successful and interesting week• To be followed up by DSO and OP acceptance tests