LHC ACCESS SYSTEM

1Edms: 856718

LAAWGStatus Report – 10th July 2007

P. Ninin, L. Scibile, T. Ladzinski

Page 2: LHC ACCESS SYSTEM 1 Edms: 856718 LAAWG Status Report – 10th July 2007 P. Ninin, L. Scibile, T. Ladzinski

LHC ACCESS SYSTEM

2Edms: 856718

Dash board – 10 July 07

Cable Access Control Access Safety Commis.

Access

Points

Other

Eis

Soft &

IHM

Control

Racks

Soft Hard

Loop

Power

System

LHC1 Tested +W35

4/6 Instal. Test Instal. Dev. Instal. Instal. W33-35

L1.8 Tested 1/1 OK-NC Dev. Installed Dev. Instal. Instal. W33-35

LHC2 >W32 W28-37 W28-37 Dev. W28-33 Design Design

Deliv. W39-41

LHC3 Tested+W32

1/1 Instal. Dev. Constr. Design Design

Instal. TBD

LHC4 OK-NC 5/5 OK-NC OK-NC OK OK Tested OK, NC OK, NC

LHC5 Test, CMS?

4/5 Instal. Test Installed OK Instal. Instal. TBD

LHC6 Test Instal Instal. Dev. Design TBD Design

Deliv. TBD

LHC7 OK-NC 1/1 Instal. Test Test OK V1 Test Test W29-31

LHC8 OK-NC 4/5 OK OK-NC OK OK V1 Test OK, NC OK, NC

CCR OK Completed with NC OK OK Test OK On-going

CCC OK Completed with NC OK OK Test OK On-going

Page 3: LHC ACCESS SYSTEM 1 Edms: 856718 LAAWG Status Report – 10th July 2007 P. Ninin, L. Scibile, T. Ladzinski

LHC ACCESS SYSTEM

3Edms: 856718

Important points concerning the Exp. Areas.

• COMMON to all:- Access procedure to the non-interlocked area

• LHCB- Test after final installation of fences and shielding wall- Patrol procedure- PZ85 renovation

• ATLAS- SSA: pilot installation in June/July, available in September- Partial commissioning planned W33-35- PX15 Access Point upgrade

• CMS- Installation of the remaining access points (UPX56)- Cabling of the Patrol devices in the cavern- Commissioning planned POSTPONED and to be planned!- PM54 Access Point Design & Installation

• ALICE- W28-W37 installation- W39-W41 commissioning- Work preparation

Page 4: LHC ACCESS SYSTEM 1 Edms: 856718 LAAWG Status Report – 10th July 2007 P. Ninin, L. Scibile, T. Ladzinski

LHC ACCESS SYSTEM

4Edms: 856718

Actual difficulties

• New LACS SW version acceptance tests on-going

• Planning reshuffling- LHC5 installation postponed due to CMS cabling availability end of

August- LHC7, LHC1, LHC1.8 functional tests preparation

• Summer 2007

- TI8 and TI2 tests preparation• Meeting the 7 October deadline for LHC2 relies on timely (end July)

cabling and manufacturing of grids/doors

• Team Focus on the Non-conformities follow-up- LACS software- Access point ergonomy

Page 5: LHC ACCESS SYSTEM 1 Edms: 856718 LAAWG Status Report – 10th July 2007 P. Ninin, L. Scibile, T. Ladzinski

LHC ACCESS SYSTEM

5Edms: 856718

Layout of LHCb in UX85 Area

Page 6: LHC ACCESS SYSTEM 1 Edms: 856718 LAAWG Status Report – 10th July 2007 P. Ninin, L. Scibile, T. Ladzinski

LHC ACCESS SYSTEM

6Edms: 856718

LHC5 - CMS

Page 7: LHC ACCESS SYSTEM 1 Edms: 856718 LAAWG Status Report – 10th July 2007 P. Ninin, L. Scibile, T. Ladzinski

LHC ACCESS SYSTEM

7Edms: 856718

ATLAS

Page 8: LHC ACCESS SYSTEM 1 Edms: 856718 LAAWG Status Report – 10th July 2007 P. Ninin, L. Scibile, T. Ladzinski

LHC ACCESS SYSTEM

8Edms: 856718

ATLAS

Page 9: LHC ACCESS SYSTEM 1 Edms: 856718 LAAWG Status Report – 10th July 2007 P. Ninin, L. Scibile, T. Ladzinski

LHC ACCESS SYSTEM

9Edms: 856718

LHC2- ALICE

Page 10: LHC ACCESS SYSTEM 1 Edms: 856718 LAAWG Status Report – 10th July 2007 P. Ninin, L. Scibile, T. Ladzinski

LHC ACCESS SYSTEM

10Edms: 856718

ALICE - Access via PX24