logan water alliance beenleigh wwtp … wwtp ..... 31 appendices appendix a site meeting minutes...
TRANSCRIPT
LOGAN WATER ALLIANCE
BEENLEIGH WWTP UPGRADE: PROCESS COMMISSIONING AND OPTIMISATION
PROGRAM
TASK NUMBER: 90-12-08
MARCH 2014
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 2 of 37 Rev: 1
Approval Register
Date
Project Manager Submitted 30/01/2014
Planning & Project Management Team Review
Program Review
Controlled Document – Change Register
Revision Section
Changed Change Description Initial Date
A All Preparation of Draft Report LF 16/01/2014
B All Reviewed PG 26/02/2014
C All Draft report format SS 04/03/2014
D All Internal Review TP/LF 12/03/2014
E Executive
Summary, 4, 5, 7, 8
Program Review Comments Addressed LF 27/03/2014
1 All Final Report Format SS 27/03/014
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 3 of 37 Rev: 1
TABLE OF CONTENTS
EXECUTIVE SUMMARY ................................................................................................................................. 6
1. INTRODUCTION ................................................................................................................................. 8
1.1 Objectives ........................................................................................................................................ 8
1.2 Scope ............................................................................................................................................... 8
1.3 Business Drivers .............................................................................................................................. 9
2. PLANNING CONTEXT ...................................................................................................................... 10
2.1 Background .................................................................................................................................... 10
2.2 Previous Studies ............................................................................................................................ 10
2.3 Amended DA limits ........................................................................................................................ 11
3. METHODOLOGY .............................................................................................................................. 13
3.1 Program timeline and key components ......................................................................................... 13
3.2 Site Meeting Attendees .................................................................................................................. 15
4. STUDY OUTCOMES ......................................................................................................................... 16
4.1 Study Overview .............................................................................................................................. 16
4.2 Current WWTP Capacity ............................................................................................................... 16
4.3 Improvements to Maintain 14 ML/d Capacity ................................................................................ 18
4.3.1 Operational Adjustments ........................................................................................................... 18
4.3.2 Outstanding Works .................................................................................................................... 21
4.4 Recommended Upgrades to Increase Above 14 ML/d Capacity .................................................. 21
4.4.1 Chemical Dosing ........................................................................................................................ 21
4.4.2 Ditch Velocity ............................................................................................................................. 22
4.4.3 Enhanced Aeration Control and Aeration System Upgrade ...................................................... 22
4.4.4 Summary of Upgrades and Controls ......................................................................................... 23
4.5 External Influences ........................................................................................................................ 24
4.5.1 Trade Waste Monitoring ............................................................................................................ 24
4.5.2 Network Flow Pacing ................................................................................................................. 25
5. CAPITAL WORKS IMPLICATIONS ................................................................................................. 29
6. PARALLEL VERSUS SERIES OPERATION ................................................................................... 31
7. CONCLUSIONS ................................................................................................................................ 32
8. RECOMMENDATIONS ..................................................................................................................... 34
9. REFERENCES .................................................................................................................................. 35
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 4 of 37 Rev: 1
FIGURES
Figure 2-1: Release limits currently applied at Beenleigh WWTP (Schedule C Table 1 of the current DA) ..
................................................................................................................................................. 12
Figure 3-1: Key Phases in the Process Commissioning and Optimisation Program ................................. 14
Figure 3-2: Schematic of Process Commissioning and Optimisation Program Timeline .......................... 14
Figure 4-1: Capacity Limits at Beenleigh WWTP ....................................................................................... 17
Figure 4-2: Published Settling Characteristics Based on Effluent N Ratios and SRT (Hartley, 2014) ...... 19
Figure 4-3: Settling Characteristics (sSVI) during Study Period Based on averaged effluent N ratios ..... 20
Figure 4-4: Recommended upgrades and improvements (green boxes) that will enhance the WWTP
capacity, not including upgrades to tank sizes ................................................................................................ 24
Figure 4-5: Continuous Inflow Data for 3 Inlet Mains, showing variability in LCC Pump Stations ............. 26
Figure 4-6: Total Continuous Inflow Data for 3 Inlet Mains, showing near bypass trigger during peaks and
extremely low flows at night (moving average simulates 15 min average parameter) .................................... 27
Figure 4-7: Schematic of the Main Pump Station Contributors to the Beenleigh WWTP .......................... 28
TABLES
Table 2-1: Key amendments to Beenleigh WWTP DA limits .................................................................... 11
Table 3-1: Site Meetings - Key Attendees List .......................................................................................... 15
Table 4-1: Trade waste monitoring sample data (range: 5th percentile to 95
th percentile over week
sampled and over 3 lab analysts) .................................................................................................................... 25
Table 5-1: Proposed Works – Interim and Target Capacity for Beenleigh WWTP ................................... 29
Table 5-2: Capital Works Program Adjustment Summary ........................................................................ 30
Table 6-1: Estimated Capacity, Advantages and Disadvantages to Series versus Parallel Configuration at
Beenleigh WWTP ............................................................................................................................................ 31
Appendices
Appendix A Site Meeting Minutes
Appendix B Process Commissioning and Optimisation Report (Ken Hartley, 2014)
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 5 of 37 Rev: 1
ABBREVIATIONS
ADWF Average Dry Weather Flow
BFP Belt Filter Press
BNR Biological Nutrient Removal
BOD Biological Oxygen Demand
COD Chemical Oxygen Demand
DA Development Approval
DO Dissolved Oxygen
LCC Logan City Council
LWA Logan Water Alliance
OD Oxidation Ditch
RAS Return Activated Sludge
SRT Sludge Retention Time
SVI Sludge Volume Index
sSVI Stirred Sludge Volume Index
VSD Variable Speed Drive
WAS Waste Activated Sludge
WWTP Waste Water Treatment Plant
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 6 of 37 Rev: 1
EXECUTIVE SUMMARY
Strategic planning for Logan City has been based on the design capacity for the Beenleigh WWTP of
15 ML/d ADWF. Previous studies have indicated that the WWTP is operating at a reduced capacity of 10 to
13 ML/d ADWF (GCW, 2006; JWP, 2009). A peer review of the process analysis (LWA, 2010) suggested
that the limited flow capacity was impacted by the ‘oxidation ditches in series’ configuration. The objective of
this current study was to determine the maximum capacity of Beenleigh WWTP with a parallel ditch
configuration, and to outline possible optimisation opportunities.
The main strategy was to implement a parallel ditch configuration and then gradually reduce the sludge
retention time (SRT), while observing treatment capabilities. The plant was operated at an SRT of 15 to 20
days for 3.5 months, then SRT of 10-15 days and SRT of <10 days for one month each. The results showed
that effluent limits could be met with an SRT of 10-15 days, however below 10 days SRT it started to show
reduced ammonia removal capabilities.
The Beenleigh WWTP has a capacity of 14 ML/d ADWF in the parallel oxidation ditch configuration, with the
current controls in place. The key bottleneck is the aeration capacity which is also affected by the level of
chemical oxidation demand (COD) in the influent wastewater, currently measured at an equivalent median
750 mgCOD/L. This is 34% greater than the COD load the WWTP was designed for and is the main
determinant for the WWTP capacity reduction from 15 ML/d. The capacity could effectively be increased with
appropriate automation and controls in place, which will reduce process variability and an upgrade to the
aeration system capacity.
Overall, the series configuration accommodates more process variability but reduces overall capacity to 10-
13 ML/d ADWF. A parallel configuration allows more process control and increases capacity to at least
14 ML/d ADWF but can be more sensitive to process variability. This could be managed if appropriate
controls and automation were implemented.
A number of outstanding works and operational improvements are required to maintain a 14 ML/d capacity.
These works include repairing the aerator paddles, repairing downstream aerator baffles, implementing SRT
control and undergoing structural inspection and maintenance of the oxidation ditches. To gain a further
increase in capacity beyond to 14-15 ML/d, enhancing the aeration capacity and control, installing vertical
baffles and optimising the chemical dosing is required.
In total, these Stage 1 works are estimated to cost $1.7m. Stage 1 is recommended to be implemented
immediately and would effectively increase the capacity to the desired 15 ML/d. However, if a capacity of
15 ML/d is not achieved via enhancing the aeration processes, then a slight upgrade to the aeration system
(such as diffusers in between existing surface aerators) will achieve this upgrade. These additional Stage 2
works are estimated at $0.7m.
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 7 of 37 Rev: 1
High instantaneous flow variability from the LCC operated catchments are causing issues in the WWTP
operation, especially in the form of triggering dry weather bypass alarms and other equipment issues at low
flows.
The Logan Water Alliance recommends that Logan City Council:
1. Retain the parallel oxidation ditch configuration to maintain a WWTP capacity of at least 14 ML/d
ADWF. This operational adjustment is to be based on the following:
a. Flow and aeration distribution – of 55%:45% OD1:OD2, where practicable with the current
operating constraints, to capitalise on volume capacities
b. Effluent N ratio– of 0.1 to 1 effluent ammonia to effluent nitrate ratio, where practicable to
improve settling performance and capitalise on volume capacities
2. Implement Stage 1 works in 2014/15 inclusive of the following:
a. Renewals/outstanding works: scum harvester adjustment, surface aerator paddle repair,
downstream baffle repairs and SRT control implementation,
b. Rectification/operational improvements: RAS pump refurbishment, sludge bin upgrade and
structural assessment and general clean of oxidation ditches
c. Capacity upgrade - enhanced aeration automation, installing upstream vertical baffles in
oxidation ditches and investigating chemical dosing for polishing only. This is recommended
to be carried out with the outstanding works, for the purposes of improving general operation.
3. Program Stage 2 works for implementation with the aim to increases the WWTP capacity to 15ML/d
pending the capacity improvements observed at the completion of Stage 1. Stage 2 works are
inclusive of the following:
a. Capacity upgrade - Upgrading the aeration system. This is recommended on the basis that
the Stage 1 works are insufficient to meet the 15 ML/d capacity.
4. Adopt proposed works as nominated to form part of Council’s Capital Works Program (refer
Section 5)
5. Undertake planning works to investigate LCC pump operation to reduce variability in flows entering
the WWTP, noting the impact of residential catchment diversions on the WWTP capacity
6. Continue trade waste investigations to determine any necessary changes to trade waste agreements
to reduce flow variability to the WWTP
7. Facilitate training of LCC operators and engineers to transfer knowledge and findings on the revised
plant operation
8. Facilitate the development of operational manuals to ensure that the adjusted operations of the
Beenleigh WWTP are documented to assist the future operation of the plant
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 8 of 37 Rev: 1
1. INTRODUCTION
Beenleigh Wastewater Treatment Plant (WWTP) has undergone several augmentations and upgrades over
the 2012/13 financial year to deliver improved performance and regulatory compliance. The works were
staged based on urgency and prioritisation, and include:
1. Retrofitted inlet works, new bypass, upgraded dewatering area and other minor works (completed)
2. Process commissioning and optimisation (this study)
3. Disinfection and clarification upgrade, if required
Additional minor works such as relocating the DO probes and adjusting the inlet weirs to the oxidation
ditches were required and implemented to ensure a controlled sampling study as part of the optimisation
process.
The need for a process commissioning and optimisation study was the result of previous consultant studies
indicating the WWTP has a capacity of approximately 10 to 13 ML/d Average Dry Weather Flow (ADWF)
(GCW, 2006; JWP, 2009), compared to the strategic planning requirement of 15ML/d ADWF. A peer review
of the process analysis (LWA, 2010) suggested that the limited flow capacity was impacted by the ‘oxidation
ditches in series’ configuration. An increase in capacity to 15 ML/d was considered possible if the oxidations
ditches were operated in parallel. As a result, this current study addresses the operation of parallel oxidation
ditches.
1.1 Objectives
The current study objective is to undertake a process commissioning and optimisation study following recent
minor augmentation works at Beenleigh WWTP to confirm the design capacity of the WWTP and to
maximise the operational capacity of the WWTP.
1.2 Scope
The scope of this study includes:
Reviewing background data and operating set-points
Collecting and analysing data over the programme duration
Liaising with the WWTP operators and relevant stakeholders
Reviewing and refining operating set-points
Identifying optimised process for the WWTP
Fine tuning the process, including setting process controls
This study considers optimising the capacity of the WWTP within the current bioreactor and clarifier volumes.
Therefore, this study does not investigate any upgrades to tank volumes.
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 9 of 37 Rev: 1
1.3 Business Drivers
Logan City Council (LCC) is committed to improving operational efficiencies and minimising the
environmental impact of its activities. The main business drivers that influence this study are: Improvement and
Compliance.
The key business driver for the Beenleigh WWTP Process Optimisation and Commissioning study is
improvement. This project offers the opportunity to increase the capacity of existing assets by improving the
current operation, and accommodating process improvement through the installation of automated controls.
The current wastewater flows are reaching the WWTPs capacity in series, with increasing non-compliances
largely due to the highly variable industrial flow contribution within the catchment. Although the installation of
a new bypass and other upgrades will assist in the operation of the WWTP, the capacity bottleneck of the
biological process remains.
A secondary business driver for the study is compliance. A legal obligation exists in the form of a
development approval (DA) or discharge licence and stipulates limits that ensure an environmental duty of
care to prevent or mitigate the risk of environmental harm under the Environmental Protection Act 1994.
Optimisation of the WWTP will also allow improved compliance. This optimisation study specifically focuses
on improving compliance for nutrient, solids and organics discharge limits by delivering improvements in the
biological and clarifier sections of the plant.
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 10 of 37 Rev: 1
2. PLANNING CONTEXT
This section outlines the planning context for this study, including an overview of the WWTP history and
background, key previous studies and current DA amendments.
2.1 Background
The Beenleigh WWTP plant was upgraded to a Biodenipho operation in 1999/2001 and later converted to
two oxidation ditches in series. The 1999/2001 plant upgrades involved a new inlet structure, basin
reconfiguration and upgrade, a new clarifier, thermophilic anaerobic digester and UV disinfection. The plant
was operated by Veolia under contract to GCW until March 2004 (GCW, 2006).The Beenleigh WWTP was
transferred from Gold Coast City Council (GCCC) to Logan City Council (LCC) in 2008, as part of the
Queensland Government boundary changes.
The current contributing catchment for the Beenleigh WWTP includes inflow from Beenleigh (approximately
two-thirds) and a largely industrial inflow from Stapylton (approximately one-third). Poor plant performance
during dry weather has often been attributed to industrial loads. Other issues at the WWTP were also
attributed to a lack of peak wet weather by-pass and insufficient equipment and upgrades.
The most recent upgrade at the WWTP was completed in January 2013, and included a wet weather
bypass, a retrofit of the inlet works and an upgrade of the sludge dewatering area. These upgrades reduced
key bottlenecks in the process. Scum harvester commissioning and other minor works were also included as
part of the upgrade package.
Currently, the WWTP biological process operates with 2 oxidation ditches and 4 clarifiers. The anaerobic
digester has been decommissioned for more than 5 years.
Logan City Council (LCC) has indicated its intention to maintain a capacity and licence discharge of 15 ML/d
ADWF to support regional strategic planning. A number of modelling and planning assessments (GCW,
2006; JWP, 2009) indicate that the Beenleigh WWTP has a capacity of 10-13 ML/d ADWF, based on series
configuration of the two oxidation ditches. A peer review in the Beenleigh WWTP Performance Improvement:
Detailed Planning Concept Report (LWA, 2010 – Task No. 90-10-41) indicated that this capacity could
effectively be increased if the oxidation ditches were operated in a parallel configuration.
2.2 Previous Studies
Model-Based Analysis of the Beenleigh Sewage Treatment Plant (GCW, 2006)
Two software packages were used to simulate processes within the Beenleigh WWTP: Biowin and WEST.
Both models provided similar results, and indicated that the WWTP capacity is approximately 13 ML/d ADWF
in series configuration and 15 ML/d ADWF in the original BioDenipho design configuration. However, the
study mentions that this was based on an ammonia break-through of 5 mg/L and therefore may be based on
a less stringent DA limits for ammonia.
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 11 of 37 Rev: 1
Beenleigh WWTP: Stormwater and Solids Handling Study (JWP, 2009)
Biological process modelling (including the clarifiers) was undertaken as part of the overall assessment to
determine unit capacities and the scope for upgrades. Detailed investigations were carried out based on a
superseded discharge licence which did not include bypassing directly to the river, and therefore
recommendations included bypassing peak flows to the clarifiers.
Model results indicated that if the plant was operated at a sludge retention time (SRT) of 15 days and a
stirred sludge volume index (sSVI) of 80 mL/g, the maximum ADWF achievable would be 10.6 ML/d (at sSVI
of 90 mL/g, the ADWF would drop further to 10 ML/d). At higher SRTs, this capacity would be reduced. It
was also stated that under the series configuration, the aeration system only had capacity for 7.6 ML/d
ADWF.
Beenleigh WWTP Performance Improvement Detailed Planning Concept Report (LWA, December
2010)
A peer reviewer (Ken Hartley) was engaged to review the biological treatment optimisation strategy. This
report concluded that parallel operation would simplify the process and allow improved sludge settle-ability
by appropriate aeration control. The study recommended that the WWTP undergo an optimisation study
(also known as EVOP) in a parallel configuration, to determine the maximum capacity, following the
installation of the new bypass.
2.3 Amended DA limits
New DA limits have been applied since the original peer review that accommodates parallel operation as an
alternative to increasing capacity. These changes have simplified the compliance analysis, which now
pertain only to nitrogen limits. As such, the capacity of the WWTP should be reviewed not only by the asset
volumes available, but also the limits applied in the DA.
Table 2-1 shows the amended DA limits as of August 2012, which have been adopted in the current study.
Table 2-1: Key amendments to Beenleigh WWTP DA limits
Parameter Previous DA
(2010) Current DA
(effective as of August, 2012)
Oxidised-N + ammonia-N
Short-term limit
Long-term limit
Maximum limit
Removed
Ammonia N Short-term limit
Long-term limit Removed
Total Nitrogen Median limit
Maximum limit
Reduced to 5 mg/L Reduced to 7.5 mg/L
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 12 of 37 Rev: 1
Figure 2-1 shows the shows the release limits currently applied at Beenleigh WWTP (Schedule C Table 1 of
the current DA).
Figure 2-1: Release limits currently applied at Beenleigh WWTP (Schedule C Table 1 of the current DA)
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 13 of 37 Rev: 1
3. METHODOLOGY
This section outlines the general methodology adopted for the study, including timeline profile and the key
stakeholders involved during the study period.
3.1 Program timeline and key components
The process commissioning and optimisation study is an ‘improve-as-you-go’ process that evolves as new
understandings of the WWTP are made, but based on a general implementation strategy.
The study is effectively categorised into five phases:
Phase A was the ‘baseline monitoring’ phase where data is collected and an extended sampling
regime is implemented. In this phase, historical data was also collected and a general understanding
of the WWTP developed.
Phase B was the start of parallel operation which commenced on the 17th of July 2013. The WWTP
was operated at a sludge retention time (SRT) of 15 to 20 days and the effluent monitored. During
this period, there was also a trial of ceasing all chemical dosing (for optimising biological nutrient
removal), improving the flow distributions between the ditches and improving the aeration control.
Phase C involved a reduction of the SRT at 10 to 15 days, with the effluent continued to be
monitored. At the end of this phase (November 2013), clarifier stress tests were undertaken over 3
days. This process included shutting down one clarifier at a time and throttling the return activated
sludge (RAS) pumps to determine the point of ‘stress’ and therefore establish an approximate
hydraulic capacity of the clarifiers.
Phase D was the further reduction of the SRT to <10 days. This coincided with the Christmas/New
Year period where additional wasting was carried out due to reduced biosolids truck movements. It
provided an opportunity to observe the WWTP behaviour under these limited conditions.
Phase E was the ‘post-analysis’ phase where the data was collated and final conclusions were
drawn to determine the likely capacity of the WWTP
A concurrent study was undertaken by the LCC Environmental Management Systems Team and the LCC
Trade Waste Department to determine the nutrient loading impacts from the three main catchments entering
Beenleigh WWTP.
Figure 3-1 and Figure 3-2 show the key phases of the study and an overview project timeline.
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 14 of 37 Rev: 1
Figure 3-1: Key Phases in the Process Commissioning and Optimisation Program
Figure 3-2: Schematic of Process Commissioning and Optimisation Program Timeline
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 15 of 37 Rev: 1
3.2 Site Meeting Attendees
Site meetings were conducted on a monthly basis during the study period to provide a general overview of
progress and ensure the involvement of key stakeholders. Meeting minutes are included in Appendix A.
Table 3-1 shows a list of site meeting attendees. The stakeholders mentioned in this list attended at least
one of the six general site meetings at Beenleigh WWTP over the study period.
Table 3-1: Site Meetings - Key Attendees List
Meetings Attendees Position
Leah Foley LWA Project Manager
Scott Francis LWA Project Director
Ken Hartley Technical Process Expert
Jason Lee Beenleigh WWTP Supervisor
David Wickman Beenleigh WWTP Operator
Bruce Willman Beenleigh WWTP Operator
Noel Robinson Beenleigh WWTP Operator
Kaja Thompson Beenleigh WWTP Operator
Imtiaj Ali LCC WWTP Process Engineer
Chitra Liyanage LCC WWTP Maintenance Engineer
Andrew Stevenson LCC Environmental Management Systems Coordinator
Kambez Akrami LCC Product Quality Systems Officer
Amy Flynn LCC Environmental Management System Officer
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 16 of 37 Rev: 1
4. STUDY OUTCOMES
This section provides a summary of the study outcomes. Appendix B includes theBeenleigh WWTP
Upgrade Process Commissioning & Optimisation Report (Hartley, 2014), which provides a detailed overview
of the study outcomes. This section also outlines the key upstream influences on the WWTP, namely trade
waste discharges (i.e. high strength COD) and dry weather flow variances during the study period.
4.1 Study Overview
The process commissioning and optimisation study period occurred from June to December 2013, with
parallel operation initiated on the 17th of July 2013. During this period there was minimal rainfall, with some
wet weather bypasses occurring mid to late November and December. The data was limited in December
due to reduced WWTP staff and laboratory analysts, especially over the Christmas/New Year period.
An automated wasting control was approved mid-way through the study period; however, due to delays in
implementation (due to heavy contractor workloads at Loganholme WWTP) and some minor software faults,
the wasting control was not functioning by the end of the study period.
Some DA non-compliances occurred over the study period due to process adjustments. In the initial two
months, maximum total nitrogen and ammonia limits were exceeded; however, this did not occur for the
remainder of the study period. In the last two months of the study period, the long-term phosphorus limit was
exceeded and was attributed to nitrate recycling. The exceedance occurred due to an add-on effect to non-
compliances earlier in the year during the January 2013 flood events. The same occurred during the study
period for biological oxygen demand (BOD).
4.2 Current WWTP Capacity
There are multiple factors that limit the WWTP capacity. Apart from volume limitations of the oxidation ditch
and clarifiers, the following process-related limitations were determined:
The key capacity bottleneck of the plant is the aeration system, limiting the WWTP to a capacity of
approximately 14 ML/d
The clarifier and oxidation ditch volumes limited the WWTP to 15 ML/d, with the following
considerations:
o Clarifier volume limits (related to the RAS pumps capacity) was considered capable to
achieve 3 x 15 ML/d peak flow, but were noted to be operating at a capacity of
approximately 20% less than their original design flows (based on anecdotal evidence from
WWTP operators)
o The oxidation ditch capacity minimises the achievable SRT
It was found in the study that the WWTP could operate with the current DA limits at a minimum 10-15 day
SRT. Below 10 day SRT, the WWTP tended towards insufficient nitrification. A more accurate SRT could not
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 17 of 37 Rev: 1
be determined during the study due to insufficient SRT controls in place. Sufficient controls will need to be
installed to ensure that process variability is minimised in future.
Figure 4-1 shows the capacity limits at Beenleigh WWTP.
Figure 4-1: Capacity Limits at Beenleigh WWTP
Aeration System and Chemical Oxygen Demand (COD) variability
The WWTP aeration capacity design of 15 ML/d average dry weather flow (ADWF) was based on a median
influent of 8.4 tCOD/d (equivalent to 560 mg COD/L). During the last two months of the study period, the
inflow median COD was 10.7 tCOD/d (equivalent to 750 mg COD/L). This increased load equates to a
reduced aeration capacity of 14 ML/d ADWF, and is the effective capacity of the WWTP with the current
control constraints.
The aeration capacity was identified as just sufficient for the current 90th percentile COD load (a peak load
parameter often used for design basis). As the aeration capacity is affected by the influent COD load, if the
influent load is reduced, such as reducing COD loads from industrial discharges, this would in turn increase
aeration capacity. A review of the trade waste agreement with Gold Coast (which currently limits COD
concentrations to 1000 mg COD/L) is recommended. In addition, regular monitoring is required of incoming
trade waste contributions to ensure compliance.
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 18 of 37 Rev: 1
Clarifier Volumes and RAS Pump Capacity
The clarifier stress test performed in late November showed that the clarifiers have sufficient capacity for the
current 13 ML/d flows. Calculated clarifier performance at the peak hydraulic flow of 45 ML/d (i.e. 3 x
15 ML/d ADWF) was shown to be sufficient with the current clarifier volumes, based on the following
conditions for median influent COD concentrations of 750 mg/L:
o Settleability (sSVI) of 65 mL/g at SRT no greater than 19 days
o Settleability (sSVI) of 80 mL/g at SRT no greater than 16 days
An average settleability of 70 mL/g sSVI is considered achievable with the DA limits.
The clarifier capacity, is also limited by the RAS pump capacity. Operator anecdotal evidence suggests that
the RAS pumps are operating at 20% less than design capacity due to wear and tear.
4.3 Improvements to Maintain 14 ML/d Capacity
The following operational adjustments and completion of outstanding works are required to achieve a WWTP
capacity of 14 ML/d, in a parallel configuration.
4.3.1 Operational Adjustments
The following operational adjustments are recommended to optimise the capacity of the WWTP in parallel
operation:
Maintaining appropriate flow and aeration distribution
Maintaining optimal effluent ammonia to nitrate ratio for improved settleability
The study outcomes were limited by existing process constraints such as lack of automation (e.g. wasting
control, aeration control). All adjustments should be documented in the operational manuals and procedures
to ensure these assist future operation of the WWTP.
Flow and Aeration Distribution
Oxidation Ditch 1 (OD1) has a larger reactor volume than Oxidation Ditch 2 (OD2), due to OD2’s sloping
walls. Likewise, each surface aerator (i.e. rotor) has the same power consumption with multiple rotors fitted
throughout the ditches.
Operation should be modified, as best as practicable, so that:
A flow distribution of OD1:OD2 = 55%:45% is achieved. The OD2 inlet weir should be placed higher
by 14 mm (calculated to reduce flow to 45% towards OD2)
The number of operating rotors within each ditch is matched to the flow. For OD1, five aerators
should be running and for OD2, four aerators should be running
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 19 of 37 Rev: 1
Effluent N Ratio and Settleability
Published oxidation ditch studies have shown that modification to the effluent N ratio (ammonia N: nitrate N)
affects the settleability performance in the clarifiers. Improving the setteability in the clarifiers effectively
increases the capacity of the WWTP.
Oxidation ditches have a different characteristic to fixed reactor biological nutrient removal (BNR) processes,
as the length of aeration zone can be extended or reduced based on DO set-points (i.e. operator settings),
as the oxidation ditch has no internal walls between zones. An extension of the aeration zone (where
nitrification occurs to reduce ammonia levels) will automatically create a reduction of the anoxic zone (where
denitrification occurs to reduce nitrate/nitrite levels), and vice versa.
As a result of this behaviour, greater control is available by adjusting effluent N ratios. Figure 4-2 illustrates
the relationship between settleability (measured in sludge volume index (SVI) or stirred sludge volume index
(sSVI)) and effluent N ratio. The relationship also changes based on SRT. This graph shows that there is an
ideal effluent N ratio range that will produce the best settleability for the wastewater sludge at each WWTP.
The key is to identify the optimal effluent N ratio range.
Figure 4-2: Published Settling Characteristics Based on Effluent N Ratios and SRT (Hartley, 2014)
Sampling during the study period was not performed to the same level of detail as in the published results;
however, the samples show a similar trend to the published data (refer Figure 4-2). Figure 4-3 shows the
study trends comparing sSVI with the effluent ammonia N:nitrate N ratio (Hartley, 2014). The sSVI
measurements were initiated just prior to the treatment configuration change to parallel for consistency, prior
to this change measurements were in SVI.
SRT 20d
SRT 10d
0
50
100
150
200
0.01 0.1 1 10 100
SS
VI o
r s
SV
I (m
L/g
)
Effluent NH3-N:NO3-N Ratio (3SRT average, Nrave)
Bucasia Ditch 1(SRT 17d)
Bucasia Ditch 2(10d)
Coolum(30d)-APT Online
Coolum(30d)-APT Offline
West Byron(20d)
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 20 of 37 Rev: 1
Figure 4-3: Settling Characteristics (sSVI) during Study Period Based on averaged effluent N ratios
The study showed the following general characteristics:
At an effluent N ratio between 1 and 3, a sludge settling characteristic between 100 and 150 mL/g
was exhibited
At an effluent N ratio between 0.1 and 1, a sludge settling characteristic between 50 and 90 mL/g
was exhibited
The improvement to settleability was attributed to the effluent N ratio modifications as the reduction in SRT
did not occur until the weeks after the improved settleability.
A consistent sSVI of 70 mL/g is considered achievable if appropriate DO control for the ideal effluent
ammonia N to nitrate N is put in place. The ideal effluent ammonia N to nitrate N is between 0.1 and 1. This
should ideally be met in conjunction with adhering to DA limits.
Start sSVI
0.01
0.1
1
10
100
1000
0
50
100
150
200
250
01-May 01-Jul 01-Sep 01-Nov 01-Jan
Final Eff N
Ratio
(60d M
A)
sSV
I (m
L/g)
ML SVI / sSVI
Eff NH3-N:NO3-N Ratio
60 per. Mov. Avg. (Eff NH3-N:NO3-NRatio)
ParallelOperation Start
100 - 150 mL/g sSVI
50 - 90 mL/g sSVI General lowering = Improve settling
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 21 of 37 Rev: 1
4.3.2 Outstanding Works
The conversion of the oxidation ditches to parallel was sufficient to inform the initial capacity assessment. To
maintain smooth operation of the WWTP, especially in parallel, several outstanding works still need to be
undertaken:
The scum harvesters have been installed and commissioned based on fixed weir operation (fully
closed). The parallel operation with the current method of aeration automation depends on moving
weirs to immerse aerators appropriately and maintain appropriate dissolved oxygen (DO) set points.
The water level is not high enough for the scum harvesters to appropriately remove scum in this new
configuration and there is a scum build up in the ditches. The scum harvester heights will need to be
adjusted to be submerged for effective operation.
Wasting automation controls were approved and installed at Beenleigh WWTP to improve the
stabilisation of SRT and provide more control over the process. Delays have occurred due to
software program errors which have recently been resolved. The control of SRT will need to be
implemented to improve WWTP stability.
The existing sludge bin is considered a bottleneck in the wasting process. Wasting is limited to the
amount the bin can hold, and the truck scheduling has been altered to accommodate and avoid
disruptions in the process (i.e. affecting SRT). The bin capacity is being addressed as part of the
Biosolids Management Strategy (LWA, 2013; Task No. 90-12-35).
The oxidation ditches and aerators are in need of maintenance works. The oxidation ditches have
not undergone a structural assessment or maintenance since 2000 and there are several aerators
with broken paddles and horizontal baffles. Maintenance and renewal works for these assets should
be undertaken and a regular preventative maintenance schedule reviewed.
4.4 Recommended Upgrades to Increase Above 14 ML/d Capacity
The following works are recommended to optimise the capacity of the WWTP in parallel operation:
Optimising chemical dosing usage
Reducing ditch velocities
Enhanced aeration control and aeration system upgrade
All upgrades and adjustments should be documented in the operational manuals and procedures to assist
future operation of the WWTP.
4.4.1 Chemical Dosing
Chemical dosing was ceased in the early stages of the study as a trial. Both ethanol and alum were
previously used, with:
ethanol used to improved denitrification (nitrate/nitrite removal)
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 22 of 37 Rev: 1
alum used for phosphorus ‘trimming’ on top of biological phosphorus removal and to improve
settling characteristics when required (usually during wet weather events)
After 3 months, alum dosing recommenced to mitigate DA non-compliance, as phosphorus values were
starting to increase due to nitrate recycling inhibiting the biological P process.
Rather than chemically treating the phosphorus directly with alum dosing, ethanol dosing could be applied to
reduce the nitrate recycle and indirectly treat biological P inhibition caused by the nitrate (Appendix B,
Hartley, 2014). Further consideration and testing would be required to ensure no lag time for sludge uptake
of ethanol in the form of intermittent dosing. This is not expected to be an issue, however should be verified
with the Beenleigh sludge characteristics.
It is recommended that further internal investigations could be carried out by the operators to assist in
enhancing the process through chemical dosing optimisation.
4.4.2 Ditch Velocity
Ditch velocities were recorded by plant operators during the study period:
OD1 had a flow velocity of 0.74 m/s with 5 rotors running
OD2 had a flow velocity of 0.58 m/s with 4 rotors running
The minimum velocity required to maintain solids in suspension is 0.2 m/s. Reducing the velocity could
effectively increase nitrification rates by increasing DO concentrations, which will subsequently increase
capacity. Inclined downstream horizontal baffles are in need of repair and there are no vertical upstream
baffles. Repairing the broken horizontal baffles may sufficiently reduce the oxidation ditch velocity.
If more improvements to the velocity reduction exist after these improvements, then upstream vertical baffles
should be installed to further reduce the velocities. The design and placement of the baffles will need to be
designed to account for other constraining factors in the WWTP, such as possible implementation of diffused
aeration grids (see section 4.4.3).
4.4.3 Enhanced Aeration Control and Aeration System Upgrade
Aeration control can ideally be linked in with the continuous measuring system at the effluent sampling point,
and further investigations should be undertaken to investigate this potential operational control. The
enhanced aeration control would operate under fixed weirs (i.e. closed) and altering the DO set-point
accordingly with the effluent results. The scum harvesters would be able to operate as per original design
under these settings. This enhancement would require upgrading the surface aerators to allow variable
speed operation (i.e. variable speed drives (VSDs)).
Care should be taken not to depend on effluent values if chemical dosing is enhancing the nutrient removal
process, as the settleability is more dependent on the ‘zone’ ratio rather than the effluent results ratio.
An upgrade solution for the aeration system could accommodate the increased incoming COD loads and
remove the capacity bottleneck in the WWTP. This would increase the WWTP capacity to the desired
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 23 of 37 Rev: 1
15 ML/d capacity. A simple solution involves installing diffused air grids between aerators (pers. comms, K
Hartley, 4 February 2014), rather than upgrading the surface aerator drives. This upgrade is highly
dependent on the future incoming COD assumptions, especially from the industrial portion of the catchment.
The upstream vertical baffles could pose a constraint to the removal of the diffuser grids during maintenance.
This conflict needs to be accounted for in the design. Additionally, the small spaces available between
surface aerators could exacerbate force on the diffuser grids at the location of the downstream baffles. This
may also affect equipment operation and integrity and needs to be reviewed in the design. There is also a
concern that the electrical supply to the site is currently insufficient to accommodate blowers for diffused
aeration. Due to all these concerns, care needs to be taken in the design of the aeration system upgrade.
The cost for upgrading the aeration system is expected to exceed the cost for converting surface aerators to
VSD operation. The enhancement of aeration control may be sufficient to increase the WWTP capacity to
15 ML/d. This needs to be trialled after installation. It is recommended that the installation of VSDs and
enhanced aeration control be implemented first and trialled before further aeration system upgrades are
considered.
4.4.4 Summary of Upgrades and Controls
Figure 4-4 shows the recommended upgrades (not including any upgrades to oxidation ditch or clarifier
volumes), which will assist in increasing the WWTP capacity. The figure also highlights alternative methods
to increase capacity which LCC has reduced control over, such as reducing influent COD concentrations or
less stringent DA limits.
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 24 of 37 Rev: 1
Figure 4-4: Recommended upgrades and improvements (green boxes) that will enhance the WWTP capacity, not including upgrades to tank sizes
4.5 External Influences
A number of upstream influences were identified during the study period, including trade waste (known and
suspected), which produces variable strength nutrients and organics, and also variability in dry weather flows
from upstream pump stations.
4.5.1 Trade Waste Monitoring
A trade waste monitoring programme was initiated by the LCC Environmental Management Systems Team
and the LCC Trade Waste Department as a concurrent study to determine trade waste impacts and
influences. The initial study was carried out from the 28th September to the 4
th October, with monitoring
stations installed at each of the three inlet mains entering the Beenleigh WWTP, as well as a monitoring
station at BE35 pump station (located in Yatala, a GCW precinct). A trade waste agreement is in place
between LCC and GCW, which limits COD concentrations to 1000 mg/L.
The concurrent study:
Observed key industrial influences and determined if results met with agreed discharge terms
Identified any abnormal peak loads over the week (not normally captured on the DA sampling day)
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 25 of 37 Rev: 1
Resolved any discrepancies between GCW and LCC test results (using QUU labs as an alternative
comparative)
Table 4-1 shows the trade waste monitoring sample data over the monitoring period. The data shows a
range of the 5th percentile to the 95
th percentile of data for the three inlet mains, and compared to definitions
of medium and high strength wastewater as outlined in Metcalf and Eddy (2005).
Table 4-1: Trade waste monitoring sample data (range: 5th
percentile to 95th
percentile over week sampled and over 3 lab analysts)
COD (mg/L) BOD (mg/L) TSS (mg/L) TN (mg/L) pH
BE35 line (Stapylton)
500 – 790 200 – 440 220 – 420 54 – 86 7.4 – 7.7
SPS106 line (BE48 - Bramley Court)
540 – 880 240 – 500 220 – 470 50 – 79 7.4 – 7.6
SPS134 (BE47 line – Spanns Rd)
400 – 590 190 – 320 130 – 230 52 – 78 7.4 – 7.6
High strength wastewater average (M&E, 2005)
800 350 400 70 -
Medium strength wastewater average
(M&E, 2005) 430 190 210 40 -
The total nitrogen (TN) for all three incoming mains is in a similar range; however, both the Stapylton and
SPS106 (BE48) pump stations show greater COD values than SPS134 (BE47). SPS134 (BE47) has
characteristics of medium-high strength wastewater, whereas the other two mains have characteristics of
high strength wastewater.
However, no COD exceedances were observed in the BE35 line or the BE35 pump station from Gold Coast
for this sampling period. Further testing will be required to verify this consistently.
Investigations are recommended to determine the cause of higher COD loads from SPS106 (BE48), and any
required mitigation measures. A possible pipework cross-connection between BE35 and SPS106 (BE48)
may allow mixing and could explain why the data from BE35 sampling point was higher than the data from
the BE35 inlet point at the WWTP.
Future strategic planning should consider a potential diversion of ‘domestic’ strength wastewater away from
Beenleigh catchment, effectively increasing the ‘industrial’ portion and thereby increasing COD loads.
Higher COD loads would ultimately lower the capacity of the WWTP.
4.5.2 Network Flow Pacing
Flow variability exists between the inlet mains at Beenleigh WWTP that originate from the Logan catchments
and the inlet from the Gold Coast (Staplyton). This fluctuation results in issues at the WWTP:
Dry weather peak flows:
o Cause infrequent dry weather bypass alarms and require manual prevention by operators,
and potentially resulting in non-compliance
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 26 of 37 Rev: 1
Low night flows:
o Clarifier launder pump burn out, due to no flows in launder and fixed speed RAS pumps
o Lack of effluent washwater available for belt filter presses (BFP) & inlet band screens
(equipment automated to cease operations if no washwater available, to protect assets)
Figure 4-5 shows flow from the three inlet mains entering the WWTP for the period of 20th to 21
st December
2013. A high variance in fluctuations can be observed for the Logan operated pump stations, especially for
SPS106 (BE48). BE35 (Gold Coast) operates very consistently in comparison.
Figure 4-6 shows the total continuous wastewater flow entering the WWTP for the same period. A dry
weather bypass occurred on the 20th December at approximately 8am. The 15 minute averaging of the
instantaneous flows in the software did not reduce the value to lower than the bypass trigger of 400 L/s, and
therefore the alarm was triggered. This has happened on several occasions and also on weekends where
the WWTP has no on-site staff.
Figure 4-5: Continuous Inflow Data for 3 Inlet Mains, showing variability in LCC Pump Stations
0
50
100
150
200
250
300
6:00:00 AM 12:00:00 PM 6:00:00 PM 12:00:00 AM 6:00:00 AM 12:00:00 PM 6:00:00 PM 12:00:00 AM 6:00:00 AM
Flo
w (L
/s)
Incoming flow from PS BE35 (Gold Coast)
Incoming flow from SPS135 ( BE48 - Logan)
Incoming flow from SPS106 (BE47 - Logan)
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 27 of 37 Rev: 1
Figure 4-6: Total Continuous Inflow Data for 3 Inlet Mains, showing near bypass trigger during peaks and extremely low flows at night (moving average simulates 15 min average parameter)
The inflow behaviour suggests that further planning and investigations should be undertaken for the Logan-
operated pump stations to determine possible improvements and minimise flow variability entering the
WWTP.
An immediate short-term solution to avoid unnecessary dry-weather bypass alarms is to increase the 15
minute average progressively by 5 minutes to no more than 30 minutes. It is expected that increasing to 20
minutes should reduce the number of alarms and avoid false bypassing but not delay triggering for a genuine
wet-weather event (pers. comms., S Rasmussen, LWA, 20th January 2014).
0
50
100
150
200
250
300
350
400
450
6:00:00 AM 12:00:00 PM 6:00:00 PM 12:00:00 AM 6:00:00 AM 12:00:00 PM 6:00:00 PM 12:00:00 AM 6:00:00 AM
Flo
w (L
/s)
Total inlet flow
Bypass trigger
3 per. Mov. Avg. (Total inlet flow)
Diurnal peak on dry weather day (20/12/2013)
Low flows (night period)
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 28 of 37 Rev: 1
Figure 4-7: Schematic of the Main Pump Station Contributors to the Beenleigh WWTP
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 29 of 37 Rev: 1
5. CAPITAL WORKS IMPLICATIONS
The total capital cost to maintain an interim 14 ML/d capacity and increase beyond is estimated as $2.4m.
The works for improving the Beenleigh WWTP capacity have been staged, as follows:
Stage 1 – Interim 14 ML/d Capacity and Target 14-15 ML/d Capacity
o Renewals and Outstanding Works: $0.5m
o Rectification/Operational Improvement: $0.7m
o Capacity Improvement: $0.5m
Stage 1 is estimated to cost in the $1.7m
Stage 2 – Target 15 ML/d Capacity: $0.7m (only required if 15 ML/d capacity not achieved by Stage
1 works)
Table 5-1 outlines the capital works items identified for Beenleigh WWTP.
Table 5-1: Proposed Works – Interim and Target Capacity for Beenleigh WWTP
Stage Proposed Works Estimated Cost
(2013$)
Stage 1 (FY14/15)
Renewals/Outstanding Works (Interim 14ML/d Capacity)
Scum harvester adjustment $- *
Implement SRT control $- *
Fix and/or renewal of surface aerator paddles (11 No.) $147,000
Repair and/or renewal of downstream baffles (11 No.) $242,000
30% Contingency $117,000
Stage 1 Renewals Sub -TOTAL $506,000
Rectification/Operational Improvement (Interim 14ML/d Capacity)
Refurbish RAS pumps $0**
Structural assessment and general clean of oxidation ditches*** $86,000
Sludge bin upgrade $438,000
30% Contingency $158,000
Stage 1 Rectification Sub -TOTAL $682,000
Capacity Improvement (Target 14-15ML/d Capacity)
Enhanced aeration control $147,000
Install VSDs on surface aerators $104,000
Install upstream vertical baffles $100,000
Optimise chemical dosing NA
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 30 of 37 Rev: 1
Stage Proposed Works Estimated Cost
(2013$)
30% Contingency $106,000
Stage 1 Capacity Improvement Sub -TOTAL $457,000
Stage 1 Total $1,645,000
Stage 2 (FY15/16)
Capacity Improvement (Target 15ML/d Capacity)
Upgrade aeration system (with diffused air grids and blowers for both oxidation ditches)
$540,000
30% Contingency $162,000
Stage 2 Capacity Improvement Sub -TOTAL $702,000
TOTAL (Stage 1 and 2) $2,347,000
NB: * Works to be implemented as part of plant operations by WWTP operators ** RAS pump refurbishment already included in maintenance budget.
*** Does not include cost of works from the outcomes of the structural assessment
Table 5-2 provides an overall summary of the capital works adjustment requirements. Overall the net change
to the program for the nominated works in 2014/2015 is $1.7m (Stage 1 works). Stage 2 works are not
recommended until an aeration capacity assessment has been undertaken after Stage 1 works have been
completed.
Table 5-2: Capital Works Program Adjustment Summary
CWP ID
Task Description Status Year Amendments Estimated
Cost (2013$)
New 90-12-08
Stage 1 – Renewals and Outstanding
Works:
Renewal of aerator paddles
Renewal of downstream baffles
Concept 2014/15 Add new item $506,000
New 90-12-08
Stage 1 – Rectification/ Operational Improvement:
Structural assessment and clean of oxidation ditches
Sludge bin upgrades
Concept 2014/15 Add new item $682,000
New 90-12-08
Stage 1 – Capacity Improvement (Target 14-15 ML/d Capacity)
Enhance aeration control
Install VSDs on surface aerators
Install upstream vertical baffles
Concept 2014/15 Add new item $457,000
New 90-12-08 Stage 2 – Beenleigh WWTP Target
15 ML/d Capacity
Concept 2015/16* Add new item $702,000
NB: Only recommended post an aeration assessment after Stage 1 works are completed.
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 31 of 37 Rev: 1
6. PARALLEL VERSUS SERIES OPERATION
The Beenleigh WWTP has been operated in a series configuration in recent years to counter peak wet
weather flows passing through the WWTP and the nutrient variances due to the high industrial portion of the
catchment. This would have reduced the overall capacity of the WWTP; however inflows prior to recent years
have been below 12 to 13 ML/d ADWF, which was within the capacity limit with the ditches in series
configuration.
The installation of the bypass now protects the process from wash-out. However, the high COD
concentrations entering the WWTP remain and this decreases the overall capacity of Beenleigh WWTP.
The outcomes from this study have shown that in parallel configuration the WWTP capacity is estimated to
be 14 ML/d and could be more, if appropriate controls are put in place. This is achievable in conjunction with
the somewhat reduced total nitrogen limits in the DA and reduced chemical dosing. The additional capacity
is achievable through the ability to improve the settleability of sludge through more control of the effluent N
ratio.
The disadvantages of the parallel configuration is that it is sensitive to insufficient aeration distribution
between the ditches (i.e. 5 rotors required in OD1; 4 rotors required in OD2 and in the appropriate locations),
and therefore sensitive to aerator failure. There is also a current issue with the scum harvesters; however
this is not insurmountable.
Figure 6-1 outlines the estimated capacity, advantages and disadvantages of each configuration at
Beenleigh WWTP.
Table 6-1: Estimated Capacity, Advantages and Disadvantages to Series versus Parallel Configuration at Beenleigh WWTP
Series Configuration Parallel Configuration
Estimated Capacity Capacity 10 to 13 ML/d Capacity 14 ML/d+
Advantages
More operational buffer (less sensitive to changes in influent)
Better settleability (due to control over effluent N ratio)
Reduced chemical consumption (due to
better control over settleability)
Disadvantages
Unable to control settleability through effluent N ratio
Scum harvesters require more design/operational consideration due to
moving water levels*
More sensitive to aerator failure (effluent N
ratio control lost)
Note: * Fixed weir operation is an alternate possibility, if VSDs were installed on aerators and enhanced DO control installed. The scum
harvester could then operate according to original design.
It is recommended that the WWTP is continued in parallel operation and appropriate automations and
adjustments are delivered over the next six months.
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 32 of 37 Rev: 1
7. CONCLUSIONS
As part of this current optimisation study, the capacity of the Beenleigh WWTP has been verified as
approximately 14 ML/d ADWF in the parallel oxidation ditch configuration. The key bottleneck is the aeration
capacity which is also affected by the level of chemical oxidation demand (COD) in the influent wastewater.
The reduced capacity is mainly due to the increased COD load of an equivalent median 750 mgCOD/L
(compared to a design load and flow of 560 mgCOD/L and 15 ML/d ADWF). The capacity could effectively
be increased with appropriate automation and controls in place, due to minimising process variability.
The WWTP was able to be operated to meet effluent limits with an SRT of 10-15 days, however below 10
days SRT, it started to show reduced nitrification (ammonia removal) capabilities.
In addition, some key operational adjustments will also assist in maintaining the 14 ML/d capacity, which
include appropriate flow and aeration distribution between ditches (OD1 55%; OD2 45%) and maintaining
appropriate effluent N ratio to improve settleability in clarifiers.
A number of outstanding and rectification works require completion at Beenleigh WWTP, to maintain
14 ML/d capacity and ensure good operation in the parallel configuration. This includes implementing SRT
process control automation, upgrading the sludge bin, structure assessment and maintenance of the ditches
and general repairs to the aeration equipment and ancillaries.
To target a capacity of 14-15 ML/d, the following works can be implemented: enhanced aeration control,
install upstream vertical baffles and optimising chemical dosing (ethanol and alum). These works are likely to
increase the capacity to the desired 15 ML/d and is expected to cost $0.5m.
In total, the outstanding, rectification and upgrade capacity works is estimated to cost $1.7m (Stage 1
works). This estimate is based on general cost estimates and includes 30% contingency. However, if a
capacity of 15 ML/d is not achieved via enhancing the aeration processes under Stage 1, then a slight
upgrade to the aeration system (such as diffusers in between existing surface aerators) will achieve this
upgrade, which estimated at $0.7m (optional Stage 2 works).
Overall, the series configuration accommodates more process variability but reduces overall capacity to 10-
13 ML/d ADWF. A parallel configuration allows more process control and increases capacity to at least
14 ML/d ADWF but can be more sensitive to process variabilities. This variability is a characteristic at
Beenleigh due to the high industrial portion of the catchment, however could be managed if appropriate
controls and automation were implemented.
Trade waste monitoring showed higher COD and other parameters from the Stapylton catchment but also
from the Mount Warren Park/Windaroo catchment area. A cross connection in the catchment between the
two inlet mains is suspected. Monitoring of the SPS134 (BE47) catchment exhibited residential wastewater
characteristics, as expected.
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 33 of 37 Rev: 1
A high flow variability from the LCC operated catchments are causing issues in the WWTP operation, in the
form of triggering dry weather bypass alarms during peak flows and reduced effluent for equipment operation
during low flows.
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 34 of 37 Rev: 1
8. RECOMMENDATIONS
The Logan Water Alliance recommends that Logan City Council should:
1. Retain the parallel oxidation ditch configuration to maintain a WWTP capacity of at least 14 ML/d
ADWF. This operational adjustment is to be based on the following:
a. Flow and aeration distribution – of 55%:45% OD1:OD2, where practicable with the current
operating constraints, to capitalise on volume capacities
b. Effluent N ratio– of 0.1 to 1 effluent ammonia to effluent nitrate ratio, where practicable to
improve settling performance and capitalise on volume capacities
2. Implement Stage 1 works in 2014/15 inclusive of the following:
a. Renewals/outstanding works: scum harvester adjustment, surface aerator paddle repair,
downstream baffle repairs and SRT control implementation,
b. Rectification/operational improvements: RAS pump refurbishment, sludge bin upgrade and
structural assessment and general clean of oxidation ditches
c. Capacity upgrade - enhanced aeration automation, installing upstream vertical baffles in
oxidation ditches and investigating chemical dosing for polishing only. This is recommended
to be carried out with the outstanding works, for the purposes of improving general operation
3. Program Stage 2 works for implementation with the aim to increases the WWTP capacity to 15ML/d
pending the capacity improvements observed at the completion of Stage 1. Stage 2 works are
inclusive of the following:
a. Capacity upgrade - Upgrading the aeration system. This is recommended on the basis that
the Stage 1 works are insufficient to meet the 15 ML/d capacity.
4. Adopt proposed works as nominated to form part of Council’s Capital Works Program (refer
Section 5)
5. Undertake planning works to investigate LCC pump operation to reduce variability in flows entering
the WWTP, noting the impact of residential catchment diversions on the WWTP capacity
6. Continue trade waste investigations to determine any necessary changes to trade waste agreements
to reduce flow variability to the WWTP
7. Facilitate training of LCC operators and engineers to transfer knowledge and findings on the revised
plant operation
8. Facilitate the development of operational manuals to ensure that the adjusted operations of the
Beenleigh WWTP are documented to assist the future operation of the plant
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Page 35 of 37 Rev: 1
9. REFERENCES
GCW, 2006, Model-Based Analysis of the Beenleigh Sewage Treatment Plant. Prepared by Damien
Batstone (AWMC, UQ) and Michael Burns (GCW). Prepared in January 2006.
JWP, 2009, Beenleigh WWTP: Stormwater and Solids Handling Study – Consolidated Report. Prepared in
November 2009.
LWA, 2014, Biosolids Management Strategy. Task Number 90-12-35.
LWA, 2010, Beenleigh WWTP Performance Improvement Detailed Planning Concept Report. Task Number
90-10-41.
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Rev: 1
Appendix A Site Meeting Minutes
Meeting Minutes
7600-000-P-MOM-PL-8229
MOM-PL-8229 Date issued: 13.06.2013 Page 1 of 3 Rev: A
MEETING MINUTES
MEETING: Task Kick-Off Meeting
MEETING NUMBER: 1
DATE: 13/06/2013
START TIME: 9:00am END TIME: 10:00am
TASK NUMBER: 90-12-08
TASK NAME: Beenleigh WWTP Upgrade - Process Commissioning & Optimisation
LOCATION: Commitment Room (Ground Floor) – LWA Office (106 City Road, Beenleigh)
CHAIRMAN: Leah Foley
ATTENDEES / APOLOGIES
NAME (Present = YES) ABBR
Leah Foley LF
Scott Francis SF
Ken Hartley KH
Daryl Ross DR
Chris Pipe-Martin CPM
Sandy Veeren SV
Wijay Tilakumara WT
Imtiaj Ali IA
Jason Lee JL
Darren Moore DM
Jackie Clutten JC
MINUTES
NUMBER: ITEM:
1. General introductions. LF outlined briefly the objective of the project – to undertake process optimisation investigations to determine Beenleigh WWTP ultimate capacity while operating the oxidation ditches in parallel configuration. Strategic planning has allocated 15 ML/d ADWF to Beenleigh WWTP however this has been in conflict with previous planning reports.
2. Safety:
· A Job Safety and Environment Analysis (JSEA) is being prepared and is to be understood and signed by all LWA team members before undertaking site inspections.
Meeting Minutes
7600-000-P-MOM-PL-8229
MOM-PL-8229 Date issued: 13.06.2013 Page 2 of 3 Rev: A
· Site visits will be supervised by Water Operations staff where appropriate.
3.
Scope of project:
· Operating & sampling regime to reduce SRT from 25 days (current). Other set points include
20 days SRT and 15 days SRT
· Clarifier stress test
Deliverable:
· Ken Hartley report
4.
KH discussed possible constraints to the project:
· Weir inlets – one weir to be set lower than other for 45%:55% flow split
· Aerator control to be modulated with outlet weir
· Ensure RAS flow pacing with WWTP influent (pumps already VSDs – controls required)
· Internal plant recycling (from dewatering system)– review to ensure that it does not impact on
process
KH discussed possible additional requirements:
· Measure oxidation ditch velocity – floating object with stopwatch
· Ethanol dosing may need to be relocated (alum dosing to remain as is)
· Control of inflow – via pump stations?
Action: JL and KH to ensure DO probe and control requirements are met so sampling can commence. JL to organise controls and other requirements to help speed up start date of optimisation sampling.
5.
IA raised concerns of variability of influent concentrations. General discussion indicating the trade waste
impact on the WWTP. Testing of trade waste flows from Stapylton occur once a month from GC at the
pump station, to meet compliance limits. IA indicated that over the past 4 months there appeared to be
a spike in influent concentrations every 3rd week.
6.
General discussion regarding sampling personnel. JL indicated that sampling appeared to be a lot – KH
indicated that the sampling regime also includes current routine WWTP sampling. CPM raised concerns
regarding increase to drinking water sampling next month. IA raised likely requirement for dedicated
operator to observe carryover, especially during clarifier stress test.
Action: IA, WT and JL to organise any additional operators for sampling assistance. Risk assessment and resourcing plan suggested by DR.
7.
CPM queried about SVI and the impact on UV disinfection. Concerns regarding the sensitivity of the
WWTP. KH discussed that the likelihood of exceedences is not critical and carryover will be minimal. IA
indicated that clarifier stress tests were the section of the sampling programme where carryover might
occur – dedicated additional personnel suggested. KH and IA indicated that duration of the clarifier
stress test is likely 2 to 4 days.
Meeting Minutes
7600-000-P-MOM-PL-8229
MOM-PL-8229 Date issued: 13.06.2013 Page 3 of 3 Rev: A
8.
General discussion regarding involvement of EHP. IA shared previous process with Loganholme WWTP
– WT indicated that the process commissioning was part of the upgrade with EHP. CPM raised
concerns that an informal process may not be ideal, due to recent issues with lagoon overflow at
Jimboomba WWTP, where EHP was informed prior to the spill event yet still issued a claim to council.
There were issues in the past where EHP tried to put conditions on the Beenleigh WWTP
bypass/upgrade, LWA did not accept. There were no non-compliances – therefore, no current TEP for
bypass. Bypass is designed for >3 x ADWF, with current ADWF at 12 ML/d.
Action: CPM to start discussions with EHP
9. Monthly meetings will be held to report on progress for relevant people and those interested to attend.
Meeting Minutes
7600-000-P-MOM-PL-8229
MOM-PL-8229 Date issued: 13.06.2013 Page 1 of 3 Rev: A
MEETING MINUTES
MEETING: Monthly Meeting
MEETING NUMBER: 2
DATE: 01/08/2013
START TIME: 9:30am END TIME: 11:00am
TASK NUMBER: 90-12-08
TASK NAME: Beenleigh WWTP Upgrade - Process Commissioning & Optimisation
LOCATION: Beenleigh WWTP
CHAIRMAN: Leah Foley
ATTENDEES / APOLOGIES
NAME (Present = YES) ABBR
Leah Foley LF
Ken Hartley KH
Jason Lee JL
David Wickman DW
Noel Robinson NR
Bruce Willman BW
Imtiaj Ali IA
Chitra Liyanage CL
Andrew Stevenson AS
MINUTES
NUMBER: ITEM:
1. General introductions. LF outlined briefly the meeting agenda.
2.
Changeover to parallel operations: · ODs were converted to parallel operation on · JL mentioned there has been issues with SCADA · JL/DW also indicated that the rotors (aerators) have been running too hard
o This issue is that during peak flows (dry weather) the water levels increases, requiring more energy input into the aerators – beyond the current motor limit
o DW pointed out that OD2 is maintaining DO better than OD1 o Rotor #5 is offline undergoing maintenance. Rotor #4 has undergone maintenance
Meeting Minutes
7600-000-P-MOM-PL-8229
MOM-PL-8229 Date issued: 13.06.2013 Page 2 of 3 Rev: A
and is back online now o Previous meeting between JL, CL & KH – it was decided to set an upper power limit
for the aerators, however this needs further consideration o Possible solution proposed by DW: extending level transmitter to avoid interference
from OD walls o Possible solution generally accepted: could override DO by lowering weirs – however
this needs controls set up o Need further discussion with LWA Engineer (Marlon Pritchard) – JL to action
3.
KH data analysis:
· KH presented trend plots of the previous 12 months of data (dated July 2012 to July 2013)
· Note that historical data for June was missing – JL to send
· From the KH analysis, the following was concluded:
o SRT currently 20 days
o The plant receives a high influent COD load, above the design load of Beenleigh
WWTP. This is attributed to industrial loads from Stapylton (BE35). KH informed that
WWTP COD design loads have been sourced from previous reports such as JWP.
The sample data is in the form of 24-hr composites and performed only on Tuesdays.
JL mentioned there has been occurrences in the past where effluent ammonia
mysteriously increases such as one event at 1am on a Saturday
o There has been a change of TN:TP ratios post-April, with influent TP spikes on
occasion
o Effluent ammonia increased, attributed to recent decrease in SRT
o TP appears to be decreasing over time. Alum may not be needed, based on the
current licence. AS notes that there is a continuous effluent improvement agreement
within the DA.
o Cycling of SRT, because waste control hasn’t been completed. Require Tenix sub-
contractor to complete control work. There are some interferences due to biosolids
truck scheduling. KH and JL have already worked out a possible schedule to avoid
intereferences.
o Regular spikes in effluent nitrate
o Changes from SVI to stirred SVI – date was 2/7/13
o BFP cake TS inversely proportional to SVI
Action: LF to see if Tenix sub-contractor sourcing could be sped up via LWA
4.
The following additional investigations have been identified:
· There is clearly no data available showing the loads entering from Gold Coast. AS informed
that there are sewer emission limits with industrial customers and GCC. There is also a
treatment agreement between GCC and LCC. Suggestions were raised to sample rising mains
to determine daily loads from the industrial catchment.
· A lot more alum is needed to reduce TP to lower than 1 mg/L. The current DA does not require
this, however there is a continuous effluent improvement agreement in the DA. KH proposes
Meeting Minutes
7600-000-P-MOM-PL-8229
MOM-PL-8229 Date issued: 13.06.2013 Page 3 of 3 Rev: A
trialing no alum, for a few months (need 3 sludge ages). JL had concerns that this would
negatively affect effluent results. It was proposed that alum would be switched off for a couple
of week and if this showed no negative impacts, to trial longer for a couple of months.
Action: AS to propose sampling project with the Trade Waste Department, to determine levels of COD and other concentrations entering Beenleigh WWTP from industrial catchment (Gold Coast).
Action: JL to trial no alum dosing for a few weeks. If no adverse effect on plant performance, to increase trial to 2-3 months.
5. LF to organise data and spreadsheets for KH analysis prior to monthly meetings.
6. LCC job organised by Phil Rech – email sent to JL for operators to book to for their time on this
additional work on this project.
7.
Monthly meetings will be held to report on progress for relevant people and those interested to attend.
AS to attend future meetings so that he can produce informal reports to EHP, regarding progress of this
project.
Next meeting in 1 month. LF to coordinate.
Meeting Minutes
7600-000-P-MOM-PL-8229
MOM-PL-8229 Date issued: 13.06.2013 Page 1 of 3 Rev: A
MEETING MINUTES
MEETING: Monthly Meeting
MEETING NUMBER: 3
DATE: 28/06/2013
START TIME: 10:00am END TIME: 11:15am
TASK NUMBER: 90-12-08
TASK NAME: Beenleigh WWTP Upgrade - Process Commissioning & Optimisation
LOCATION: Beenleigh WWTP
CHAIRMAN: Leah Foley
ATTENDEES / APOLOGIES
NAME (Present = YES) ABBR
Leah Foley LF
Scott Francis SC
Ken Hartley KH
Jason Lee JL
David Wickman DW
Noel Robinson NR
Bruce Willman BW
Imtiaj Ali IA
Chitra Liyanage CL
Andrew Stevenson AS
MINUTES
NUMBER: ITEM:
1.
WWTP performance review by JL, with input from NR & BW.
Changeover to parallel operations: · ODs were converted to parallel operation on 17th July · Some WWTP exceedances
o Ammonia & TN exceeded DA limits in first week of August (7th August) o Several faecal coliform exceedances (likely due to one microscreen of 3 units out of
action. Also may be issues with oxidation ditch outlet weirs moving to let more flow
Meeting Minutes
7600-000-P-MOM-PL-8229
MOM-PL-8229 Date issued: 13.06.2013 Page 2 of 3 Rev: A
through however causing surging in microscreens & UV. There is also a potential side issue that network pumps may not be coordinating enough to ensure smooth flows to the WWTP)
o CL to ensure coordination of microscreen repairs · UV system may be inadequate during peak flows. Need to monitor whether upstream
microscreens are overflowing when samples are exceeding DA limits
Action: JL/BW/NR – to monitor whether microscreens are overflowing when faecal coliforms samples are high.
Action: AS – to report to EHP regarding surging likely causing faecal coliform issues, therefore is partially EVOP related. IA to continue providing information to AS.
2.
Trade waste side project - progress: · AS has been in communication with Gold Coast Trade Waste and Logan Water Trade Waste
regarding monitoring project location o Most optimal location is pump station BE35 (located near Yatala Pies), which will give
the best indication of trade waste influences o The BE35 pipeline entering the inlet works (within WWTP site boundaries) is not
considered suitable for this sampling programme. There is some mixing in the pipeline and most of the pipeline up to the inlet works is pressurised
o Note that the pipeline up to the flowmeter at the inlet works is Gold Coast’s responsibility – as written into the agreement between Logan and Gold Coast.
o Note that Gold Coast Trade Waste samples a 24-hr composite sample over a week on a quarterly basis
o Logan Water is considering sampling every hour over 24 hours to observe any fluctuations or changes
o AS to continue actioning (still requires approval through management) · AS has been gathering quotes
o Sampler could be Logan Water Trade Waste or if unavailable, likely Royce Water Technologies
o AS will require input regarding the parameters to be sampled at BE35, when project approval has been confirmed. COD monitoring will be adopted, preferably online.
o IA raised concerns regarding cost of sampling, therefore sampling regime needs to be budgeted appropriately
o KH/IA/LF to provide additional parameter input (parameters and number of samples required per week) – LF to coordinate
3.
Wasting control automation progress:
· BWG Automation (Bashier) has sent out a quote for $8.5k
· IA is waiting on a quote from AIT – AI to chase up
· JL noted that LWA/BWG Automation needs to cover for liability of defects, therefore LWA and
BWG Automation need to make back-up copies of the programming information prior to any
work that may be performed by AIT
4. KH data analysis:
· KH presented trend plots of the updated data
Meeting Minutes
7600-000-P-MOM-PL-8229
MOM-PL-8229 Date issued: 13.06.2013 Page 3 of 3 Rev: A
· Note that some data was missing due to other heavy commitments at the WWTP, but will be
provided shortly
· From the KH analysis, the following was concluded:
o WWTP is receiving and handling above its COD design load
o There appears to be a weekly cycle in flows – as observed in the recent dry period
o TN:COD ratio – typical; TP:COD ratio – very low (attributed to trade waste with low
TP)
o Effluent SS – since March 2013 has been slowly trending upwards. Attributed to SRT
decrease from 30 to 25days. MLSS has crept downwards and SVI gradually trending
upwards
o Oxidation ditch 1 appears to be receiving a higher load than oxidation ditch 2
o Based on KH’s Figure 1 in report –it is more optimal to have 5 rotors operating in
oxidation ditch 1 based on aerator power, rather than 6 rotors. Oxidation ditch 2 has
been performing better at nitrification than oxidation ditch 1. This is correlated with
oxidation ditch 1 drawing less power per aerator than oxidation 2.
o The WWTP is exhibiting a low nitrification rate, which is likely due to the COD:TN ratio
· Suggests trial and error to operate OD1:OD2 at 5:4 ratio based on rotors (via aerator power –
which could be performed by measuring current on each aerator). This will produce an effluent
ammonia/nitrate level rough equal in concentration
o JL raised concerns regarding ensuring that rotors will not be electrically ‘tripped out’
(i.e. overloaded)
o JL to coordinate & liaise with KH
5.
Monthly meetings will be held to report on progress for relevant people and those interested to attend.
LF to be away on leave from mid to late September.
Next meeting in 1st week of October. LF to coordinate.
Meeting Minutes
7600-000-P-MOM-PL-8229
MOM-PL-8229 Date issued: 13.06.2013 Page 1 of 3 Rev: A
MEETING MINUTES
MEETING: Monthly Meeting
MEETING NUMBER: 4
DATE: 03/10/2013
START TIME: 9:30am END TIME: 11:00am
TASK NUMBER: 90-12-08
TASK NAME: Beenleigh WWTP Upgrade - Process Commissioning & Optimisation
LOCATION: Beenleigh WWTP
CHAIRMAN: Leah Foley
ATTENDEES / APOLOGIES
NAME (Present = YES) ABBR
Leah Foley LF
Scott Francis SC
Ken Hartley KH
Jason Lee JL
David Wickman DW
Noel Robinson NR
Bruce Willman BW
Imtiaj Ali IA
Chitra Liyanage CL
Andrew Stevenson AS
Steffi Mavani (work experience) SM
MINUTES
NUMBER: ITEM:
1.
WWTP performance review by JL, with input from DW & BW.
In parallel operation: · ODs were converted to rotor operation of 5:4 in OD1:OD2 · Weirs adjusted to 100% open · 3 of the 4 RAS meters have had interface issues and have been incorrectly reporting flow data.
This is still being resolved.
Meeting Minutes
7600-000-P-MOM-PL-8229
MOM-PL-8229 Date issued: 13.06.2013 Page 2 of 3 Rev: A
· No alum dosing in August or September · Microscreens have been repaired · Some WWTP exceedances
o Max effluent TN exceeded DA limits in third week of September, due to high nitrate o Long-term effluent phosphorus exceeded in third week of September (exceedance
contributed by high effluent phosphorus during January 2013 floods) o Max effluent BOD exceeded DA limits in 1st week of September o Faecal coliforms OK
· Effluent nitrate has been decreasing since reducing DO set points, slight effluent ammonia increase from zero
· Effluent phosphorus non-compliance due to nitrate recycling into anaerobic zone & switching off alum dosing
Action: AS to report to EHP regarding recent DA non-compliance, which have been EVOP related. IA to continue providing information to AS.
2.
Wasting control automation:
· No progress for funding
· From KH’s data: it can be observed that there has been cycling and variance of the SRT. This
is because wasting has been variable.
· Wasting so far has been based on operator decision and has also been affected by truck
scheduling in the past
· Note that Loganholme EVOP did not implement wasting control automation. However, there
were issues involved with the wasting and the solution was to use a spreadsheet instead to
estimate the wasting requirements. RAS is not flow paced at Loganholme WWTP
· Control of wasting will improve variance in the effluent and therefore help improve compliance
to DA limits
Action: SF – to begin discussions with Daryl Ross, regarding funding approval of wasting control automation.
3.
KH data analysis:
· KH presented trend plots of the updated data in his report sent out on 2nd October (Process
Review No. 4: Sept-13)
· The following was discussed:
o Optimising OD load distribution. KH suggests to maintain 55%:45% flow-split between
OD1:OD2
§ JL & operators to coordinate OD1:OD2 at 55%:45% split & liaise with KH accordingly
o Effluent ammonia to nitrate ratio has been decreasing over time (see graph D7 of KH
report). Ideally want effluent ammonia and nitrate to be the same and then observe
results.
§ JL/DW presented plant data performance showing DO & weir profiles. This
indicated that the weirs are still ‘hunting’ but generally OK, except when
Meeting Minutes
7600-000-P-MOM-PL-8229
MOM-PL-8229 Date issued: 13.06.2013 Page 3 of 3 Rev: A
weirs ‘max out’ (reach top level) and then DO drops significantly
§ KH suggests aeration tuning control. Possible external resources are AIT.
§ JL to investigate further regarding aeration tuning control. Possible student project.
o Stabilising SRT will reduce effluent variability and theoretically give more capacity
o Effluent phosphorus has increased in the past month. This is consistent with nitrate
recycling and no alum dosing.
§ There is an aim to be purely biological phosphorus removal, however if
results show continual DA non-compliance, then alum dosing will resume.
§ Phosphorus exceedance occurred at the same time as the clarifier blanket
carryover. This occurred because of blockages in the riser, with
denitrification occurring in the clarifier and causing rising sludge flocs.
Operators have mitigated the issue and vacuumed clarifiers.
o Effluent suspended solids performance appears to affect UV performance
o There has been an increase of electricity consumption since change of rotor
operations. The correlation between power usage and rotor usage has not yet been
concluded.
§ Action: JL/DW/KH to discuss.
· Scope forward
o Recommended to decrease SRT to 18 days. Controlled wasting is important to
maintain this value. Truck scheduling needs to be resolved to ensure it is not the
bottleneck
o Measure OD circulating velocities. Check is OD2 is faster than OD1.
o Action: JL to coordinate, with wasting control to be based on IA’s spreadsheet in the interim
4.
Trade waste monitoring programme - progress: · A meeting was conducted between Gold Coast, Logan Water Trade Waste and key Logan
Water personnel. JL was present at the meeting. · Each inlet main has a 24hr composite sampler, measuring from Friday 27th September for 1
week. Pump station BE35 also has a 24hr composite sampler. · Each sample will be tested by Gold Coast, Logan Water and an external lab (ALS). Logan
Water is paying for the external lab results. This will determine any discrepancy between lab methods.
· The meeting also highlighted that, in the past, the Gold Coast field sampler did not shake the sample when collecting from BE35, therefore past samples (especially for COD/BOD) may not be representative.
o AS to send through sampling results when available
5. Monthly meetings will be held to report on progress for relevant people and those interested to attend.
Next meeting in 1st week of November (Monday 4th November). LF to coordinate.
Meeting Minutes
7600-000-P-MOM-PL-8229
MOM-PL-8229 Date issued: 13.06.2013 Page 1 of 3 Rev: A
MEETING MINUTES
MEETING: Monthly Meeting
MEETING NUMBER: 5
DATE: 11/11/2013
START TIME: 9:30am END TIME: 10:45am
TASK NUMBER: 90-12-08
TASK NAME: Beenleigh WWTP Upgrade - Process Commissioning & Optimisation
LOCATION: Beenleigh WWTP
CHAIRMAN: Leah Foley
ATTENDEES / APOLOGIES
NAME (Present = YES) ABBR
Leah Foley LF
Scott Francis SC
Ken Hartley KH
Jason Lee JL
David Wickman DW
Noel Robinson NR
Bruce Willman BW
Imtiaj Ali IA
Chitra Liyanage CL
Andrew Stevenson AS
Kam Akroni KA
Steffi Mavani (work experience) SM
MINUTES
NUMBER: ITEM:
1.
WWTP performance review by JL, with input from DW & BW.
In parallel operation: · ODs already converted to rotor operation of 5:4 in OD1:OD2, but also inlet weir was raised to
14 mm higher to OD2 (to achieve optimum flow split OD1:OD2 of 55:45)
Meeting Minutes
7600-000-P-MOM-PL-8229
MOM-PL-8229 Date issued: 13.06.2013 Page 2 of 3 Rev: A
· Alum dosing re-initiated due to high effluent P concentrations, approximately 18th October · Generally, the WWTP has been performing well, especially since alum dosing was re-instated.
It has also been a long dry period. Increased wasting has been carried out, to meet new SRT target.
2.
Wasting control automation:
· Funding approved and purchase order raised
· AIT have not appeared onsite to complete task, due to high workload at Loganholme WWTP
inlet works
· Truck scheduling now organised for 2 loads on Tuesday and 2 loads on Thursday
Action: JL – to report when waste control automation has been completed.
3.
Trade waste monitoring programme - progress: · Results have been returned from each of the 3 labs (Logan, Gold Coast and Brisbane). · Each inlet main had a 24hr composite sampler, measuring from Friday 27th September for 1
week. Pump station BE35 also had a 24hr composite sampler, concurrently. · The trade waste agreement between Gold Coast and Logan has a limit of 1000 mgCOD/L.
Previous Gold Coast reporting was a quarterly analysis which was a composite over the 7 days, showing an average of 300 mgCOD/L. The average during this week of testing was 650 mgCOD/L.
· There was a clear discrepancy of COD and some other results between labs. · Further testing will be carried out accordingly, such as more focused monitoring on times
where there is an observed issue (such as on Saturdays). The trade waste department will also conduct a Catchment Monitoring Programme to investigate pump station BE48 catchment area.
o Action: KA/AS to send through any results or findings, when available
4.
KH data analysis:
· KH presented trend plots of the updated data in his report sent out on 8th November (Process
Review No. 5: Oct-13)
· The following was discussed:
o Noticeable cycling of flow during the recent long dry weather period
o During end of October to early November, COD was 8.6 tonnes/day, which is slightly
above the design of 8.4 tonnes/day
o TN:COD ratio fluctuations during dry period, due to fluctuations in COD
o Raw TP slowly increasing since July
o Uncertainty around long-term exceedance of effluent BOD. Need to the review
method of calculation (percentile function versus LARGE function in EXCEL)
§ Action: IA to liaise with KH to verify calculation procedures
o Effluent ammonia has decreased over this period with a corresponding nitrate
increase, whereas TN has remained the same. Recommendation to reduce DO – this
will increase effluent ammonia slightly to reduce TN, through balancing ammonia and
nitrate. Changes will fully stabilise after 3 sludge ages.
Meeting Minutes
7600-000-P-MOM-PL-8229
MOM-PL-8229 Date issued: 13.06.2013 Page 3 of 3 Rev: A
§ A fixed DO set point is recommended rather ‘adjust-as- you-go’
§ Operators now only changing once per week. Was 0.8 mg/L, currently
0.6 mg/L. KH recommends changing to 0.3 mg/L.
§ Action: JL to organise and liaise with KH accordingly
o Clarifier stress test recommended in the next month before the high rain period
§ Action: JL and KH to organise
o Ethanol dosing still switched off
§ AS flagged concerns around national tonnage load reporting, which have
been low for the past few years due to high chemical dosing. Optimisation
(and possible cessation of chemical dosing) could report higher loads, even
though chemical dosing has been optimised.
o Median SRT for last week was 17 days. Stabilisation of SRT is required to observe
performance.
o Queries regarding accuracy of MLSS hand-held measuring device, which does not
always report the same value as filter-paper test.
o SVI shows that there has been some response in the WWTP performance with better
settleability, however needs further investigation
o Faecal coliform performance has improved. This is likely due to more consistent
clarifier cleaning, regular UV maintenance (by Aquatech), no rain and new stainless
steel screens (local supplier).
o OD velocity not yet measured
§ Action: JL to organise velocity measurements and liaise with KH accordingly
o Operators indicated that surges are more noticeable now after parallel operation
· Scope forward
o Continue SRT at 17 days. Maintain controlled wasting until wasting automation is
implemented
o Clarifier stress tests to be carried out over the next month
o Measure OD circulating velocities. Check if OD2 is faster than OD1.
o Continue to monitor effluent TP and any reduction in nitrate recycling, to optimise
alum dosing
o Action: JL to coordinate
5. Monthly meetings will be held to report on progress for relevant people and those interested to attend.
Next meeting in a month’s time. LF to coordinate.
Meeting Minutes
7600-000-P-MOM-PL-8229
MOM-PL-8229 Date issued: 13.06.2013 Page 1 of 3 Rev: A
MEETING MINUTES
MEETING: Monthly Meeting
MEETING NUMBER: 6
DATE: 17/12/2013
START TIME: 9:30am END TIME: 10:30am
TASK NUMBER: 90-12-08
TASK NAME: Beenleigh WWTP Upgrade - Process Commissioning & Optimisation
LOCATION: Beenleigh WWTP
CHAIRMAN: Leah Foley
ATTENDEES / APOLOGIES
NAME (Present = YES) ABBR
Leah Foley LF
Scott Francis SC
Ken Hartley KH
Jason Lee JL
David Wickman DW
Noel Robinson NR
Bruce Willman BW
Imtiaj Ali IA
Chitra Liyanage CL
Andrew Stevenson AS
Kam Akroni KA
Amy Flynn AF
Kaja Thompson KT
Steffi Mavani (work experience) SM
MINUTES
NUMBER: ITEM:
1. KH sends his apologies to the group.
Meeting Minutes
7600-000-P-MOM-PL-8229
MOM-PL-8229 Date issued: 13.06.2013 Page 2 of 3 Rev: A
2.
WWTP performance review by JL, with input from operators.
In parallel operation:
· Current WWTP under heavy wasting to accommodate Christmas period where there will be only one operator attending and biosolids trucking expected to be slow
· MLSS – 3000 to 4000 mg/L · Trucking will likely be only 4 loads over the Christmas period · Ammonia has been fluctuating due to the high wasting – has been up to 6 mg NH4/L · DO levels were 0.3 mg/L for both ODs at the previous meeting (1 month ago). Currently, OD2
has a significantly higher set point whereas OD1 is maintaining OK. However, due to heavy wasting, the switching off of one rotor in OD2 has been delayed (ammonia issues)
· Oxidation ditch velocities measured: o OD1 - ~0.5 m/s o OD2 - ~0.7 m/s o KH has suggested vertical baffles to help slow down the velocity. This should
effectively increase the WWTP capacity o JL indicated that CL and Gary Goodliffe are intending to drain the ODs and inspect
the baffles in future. The last time this occurred was likely in 2000.
3.
Wasting control automation:
· Completed, however not in operation due to issues with the ‘maximum tonnes wasted’
parameter
· Waiting until after Christmas period to complete
Action: JL – to report when waste control automation has been completed.
4.
Trade waste monitoring programme - progress: · Improvement in the trade waste quality received from catchment has been observed, without
any measures put in place. This is likely due to trade waste customers becoming aware that wastewater is being monitored
o For example, there appears to be a reduction in COD inflow from Teys Brothers Abattoir
· An auto-sampler has been set up for composite sampling at pump station BE35 (pump station directing flow from Yatala/Stapylton catchment to the WWTP). KA hopes to receive some data after the Christmas period
· Chris Pipe-Martin is intending to organise a further COD monitoring trial for a couple of weeks, to better capture any significant peaks from trade wastes
· A catchment survey for pump station BE48 is going ahead for a couple of weeks by the Trade Waste Department
Action: KA/AS to send through any results or findings, when available
5.
Issues with catchment flows from pump stations:
· Issues are still existing from Loganholme mains (BE47 and BE48 mains entering the inlet
works) which show to fluctuate heavily during dry weather, whereas the BE35 mains have a
tendency to be consistent
· This is attributed to the pump set up in the catchment (Logan Water operations versus Gold
Meeting Minutes
7600-000-P-MOM-PL-8229
MOM-PL-8229 Date issued: 13.06.2013 Page 3 of 3 Rev: A
Coast Water operations)
· Alarms are still activated in the bypass, which operates based on 15 minute average intervals
and has occurred a couple times per week. This has required operator manual adjustment to
avoid dry weather discharge (potential for DA non-compliance)
· The process risk is possible dry weather exceedances during peaks in the flow, as well as
clarifier draw down issues during troughs in the flow (RAS pump still operating during low
flows). Faecal coliform results have also been affected by this. A stabilised flow is most ideal
for WWTP operation
· AF indicated that there was an Environmental Impact Assessment process already carried out
which involved the Operations Department. The risk to the WWTP due to pump station
operations was flagged during this process
Action: LF to re-flag issue via recommendations for further investigations in final report
6.
Clarifier stress tests:
· The tests have shown that Clarifier #3 discharge launder needs upgrading (the discharge
downpipe), even with the recent repairs/upgrades already performed on this clarifier
· Clarifier #1 and 2 are suction lift and may be drawing directly off the bottom of the clarifier
· Process of clarifier shut down for clarifier stress tests were as follows:
o Turned off Clarifier #4 (at this point, noted that Clarifier #3 was weaker)
o Turned off Clarifier #4 and #2
o Turned off Clarifier #4, #2 and #1
Action: KH to analyse and draw conclusions from clarifier stress test data
7.
Other notable information:
· Operators are generally satisfied with the operation of ODs in parallel, even though there are some final adjustments to be carried out to improve operation. They generally believe that operations have best benefited from the operational adjustments such as the stabilising of wasting (including improving truck schedule) and optimising the aeration – although the recent upgrades such as installation of the bypass would be a large contributor to the improvements
· The scum harvesters installed during the recent upgrade were designed for fixed weir operation. The new operation which requires moving outlet weirs is impeding the scum harvester operation
· Previous suggestion by KH was to perhaps control the aeration through power usage monitoring of rotors. However, JL communications with CL indicates that there is no equipment existing to record kW usage from each rotor
8. There will be no more monthly meetings as we are now at the end stages of the programme. The final
presentation will be held at the Logan Water Alliance office, expected in early February.
Beenleigh WWTP Upgrade: Process Commissioning & Optimisation Program
Document Number: 7600-000-P-REP-PL-8208
90-12-08 Date issued: 28/03/2014 Rev: 1
Appendix B Process Commissioning and Optimisation Report (Ken Hartley, 2014)
KEN HARTLEY PTY LTD
LOGAN WATER ALLIANCE
90-12-08
BEENLEIGH WWTP UPGRADE
PROCESS COMMISSIONING & OPTIMISATION
January 2014
1
16117:Ken Hartley
24-Jan-14
BEENLEIGH WWTP UPGRADE
PROCESS COMMISSIONING & OPTIMISATION
CONTENTS
ABBREVIATIONS
SUMMARY
1. PURPOSE
2. METHOD
3. RESULTS
3.1 Overview
3.2 Oxidation Ditch Flow Distribution
3.3 SRT Control
3.4 Aeration Control: N / sSVI
3.5 Phosphorus Removal / Alum Dosing
3.6 Nitrogen Removal / Ethanol Dosing
3.7 Clarifier Capacity
4. CONCLUSIONS & RECOMMENDATIONS
4.1 Conclusions
4.2 Recommendations
APPENDICES
1. References
2. Process Details
3. Clarifier Capacity Diagrams
4. Trend Plots
2
16117:Ken Hartley
24-Jan-14
ABBREVIATIONS
ADWF average dry weather flow
DEHP Department of Environment Protection
DO dissolved oxygen
EVOP evolutionary operation
MLSS mixed liquor suspended solids
OD oxidation ditch
RAS return activated sludge
SC secondary clarifier
SP setpoint
SRT solids retention time
sSVI stirred sludge volume index
WWF wet weather flow
WWTP wastewater treatment plant
3
16117:Ken Hartley
24-Jan-14
SUMMARY
The Beenleigh WWTP was originally a conventional oxidation ditch (OD) plant but at a
subsequent augmentation it was converted to a proprietary BioDenipho format with
anaerobic reactors for bio-P removal. Later, it was further converted to a two-stage
conventional BNR format with the two ODs operating in series and supplementary alum and
ethanol dosing.
Plant design capacity is 15 ML/d ADWF at a median load of 8.4 tCOD/d (560 mg/L); WWF
above 45 ML/d is bypassed. Operating experience suggested that the operating capacity may
be only 10-11 ML/d ADWF and two theoretical studies, both assuming retention of the
series OD format, rated the capacity at 11-13 ML/d ADWF. The main capacity bottleneck
identified was the reactor and clarifier volumes, combined with the historical sludge
settleability, which limited the maximum SRT achievable at the design load.
A subsequent review concluded that reversion to conventional parallel OD operation may
allow the design capacity to be achieved. Parallel OD operation would provide a greater
degree of operating flexibility which may allow improvement of sludge settleability and
reduction of chemical dosing.
An upgrade recently completed (2013) by the Logan Water Alliance has provided new
pretreatment, bypassing, scum harvesting and sludge dewatering facilities. However, before
deciding whether an upgrade may be required for the main biological process it was decided
to conduct an evolutionary operation (EVOP) program, similar to a 2012 program at the
Loganholme WWTP, to assess the actual operational capacity of the plant.
The EVOP program ran over the period Jul-Dec 2013. Regular process reviews were
undertaken and plant operational procedures adjusted progressively to improve
understanding of the plant operating characteristics, optimise performance and define the
operational capacity of the liquid stream process.
The main conclusions of the program are as follows:
1. The operational capacity of the plant is limited almost equally by the oxidation ditch and
clarifier volumes, oxidation ditch aeration capacity and RAS pumping capacity (20%
below its original capacity due to pump deterioration). Plant median capacity is 11
tCOD/d, equivalent to an ADWF of 14 ML/d at the current median influent strength of
750 mgCOD/L. The plant is currently operating close to its capacity, with a median flow
of 13 ML/d.
2. Operationally, the maximum capacity is also governed by the minimum SRT at which the
process can be reliably run. A process SRT of 10-15 days is the minimum at which the
effluent standards can be reliably met. It was not possible to determine an accurate SRT
during the study; over the last two months the calculated SRT was 14 days based on
wasting data and 10 days based on dewatered sludge cake produced. Improved RAS
wasting controls have been implemented.
3. It was demonstrated that appropriate oxidation ditch aeration control allowed both
effluent nitrogen and sludge settleability to be optimised. For the last two months of the
study the median values for effluent TN and sSVI were 4.7 mg/L and 68 mL/g
respectively. Ethanol dosing for denitrification was discontinued.
4
16117:Ken Hartley
24-Jan-14
4. A clarifier stress test confirmed that the clarifier behaviour conformed with theoretical
expectations.
5. The oxidation ditch scum harvesters are at a fixed level. Modifications are required to
enable them to function properly with a variable water level.
6. The oxidation ditch circulating velocity is significantly higher than the minimum necessary
to maintain the biomass in suspension. Installation of vertical baffles upstream of the
aerators to reduce the velocity would raise the dissolved oxygen profiles and enhance
nitrification. This would increase capacity by allowing operation at lower SRT.
7. It may be possible to reduce process variability and further increase capacity through a
range of modifications such as aeration control from ammonia probes, renewed use of
ethanol dosing to facilitate operation at shorter SRT and possibly reduce the need for
alum dosing, installation of vertical baffles to reduce circulating velocity and increase DO
concentration, and refurbishment of RAS pump.
8. Pursue a trade waste program aimed at reducing the variability of the plant influent.
5
16117:Ken Hartley
24-Jan-14
1. PURPOSE
The Beenleigh WWTP was originally a conventional oxidation ditch (OD) plant but at a
subsequent augmentation it was converted to a proprietary BioDenipho format with
anaerobic reactors for bio-P removal. Later, it was further converted to a two-stage
conventional BNR format with the two ODs operating in series and supplementary alum and
ethanol dosing.
Plant design capacity is 15 ML/d ADWF at a median load of 8.4 tCOD/d (560 mg/L); WWF
above 45 ML/d is bypassed. Operating experience has suggested that the operating capacity
may be only 10-11 ML/d ADWF and two theoretical studies, both assuming retention of the
series OD format, rated the capacity respectively at 13 ML/d (Gold Coast Water, 2006) and
11 ML/d (WorleyParsons, 2009). The main capacity bottleneck identified was the reactor
and clarifier volumes, combined with the historical sludge settleability, which limited the
maximum SRT achievable at the design load.
A subsequent peer review (Hartley, 2010) concluded that minor modifications and reversion
to parallel OD operation may allow the design ADWF capacity of 15 ML/d to be achieved.
Parallel OD operation would provide a greater degree of operating flexibility which may
allow improvement of sludge settleability and reduction of chemical dosing.
An upgrade recently completed (2013) by the Logan Water Alliance has provided new
pretreatment, bypassing, scum harvesting and sludge dewatering facilities. However, before
deciding whether an upgrade may be required for the main biological process it was decided
to conduct an evolutionary operation (EVOP) program, similar to that recently completed at
the Loganholme WWTP (Hartley, 2012), to assess the actual operational capacity of the
plant.
EVOP is a technique developed in the chemical process industries for maximising the rate of
learning during routine operation (Box & Draper, 1969). This is a structured method for
deliberate learning in which a continuous investigative routine becomes the basic mode of
operation and replaces normal static operation. It is based on the principle that it is
inefficient to run a plant in such a way that only a product is produced, rather, a process
should be operated so as to produce not only a product but also information on how to
improve the product.
This method of operation involves the operators in an ongoing process of continuous
improvement through planned variation of operating parameters and evaluation of results.
Understanding of the plant’s behaviour improves and the plant is continuously moved
towards the optimal operating regime. In the short term, for the purpose of determining a
practical capacity rating, the plant is operationally stressed to determine its response and
assess the load at which the effluent licence limits are likely to be exceeded.
6
16117:Ken Hartley
24-Jan-14
2. METHOD
During the test period the plant was operated in the parallel OD mode with the flowsheet
shown in Figure 2.1. Process details are listed in Appendix 2.
The operational capacity of the liquid stream processes is the maximum load the plant can
handle while reliably meeting the DEHP performance limits. The key performance limits are
summarised in Table 2.1.
The operational capacity of a treatment plant is generally different from the original design
capacity because of design and construction margins, differences between the design and
actual sewage qualities (strength, constituent ratios, variability), and operating skill levels.
Process failure is caused by the single component of the plant, referred to as the bottleneck,
which first exceeds its capacity. The capacity of the bottleneck governs the capacity of the
whole plant. The main potential bottlenecks at Beenleigh are as follows:
Table 2.1 Liquid Stream Key Effluent Limits (weekly monitoring)
Parameter
(mg/L)
50%ile
Long Term
80%ile
Short Term
90%ile
Long Term
Maximum
BOD mg/L
SS mg/L
NH3-N mg/L
TN mg/L
TP mg/L
pH units
Faecal coliforms cfu/100 mL
---
---
---
5
---
---
1502
15
23
---
---
3
---
6002
10
15
---
---
2
---
---
15
30
3
7.5
4
6.5-8.51
--- 1. Range of pH.
2. For faecal coliforms, the median of five consecutive grab samples taken over 24 hours shall not
exceed 150; four of the five samples shall not exceed 600.
Figure 2.1 Plant flowsheet with parallel oxidation ditch operation.
Effluent
Lagoon
AlumAlum
P P P P
Washwater
BFP BFP
Poly
WAS
RAS
Biosolids
Sludge Storage Tanks
Outlet
Weirs
Inlet
Weirs
Flow
Distributor
OD1
OD2
C1 C2 C3 C4
F
F
F
Septage
Scre
en
s
Grit T
an
ks
Anaer’bic
Reactor
Biofilter
Wet Weather Bypass > 3ADWF
Scum
Wetland
Alb
ert
Riv
er
Mic
roscre
en
s
UV
Dis
infe
ctio
n
Wa
sh
wa
ter
Scu
m
To be diverted to
Loganholme
Filtrate
7
16117:Ken Hartley
24-Jan-14
Flow distribution between the two ODs – theoretically, the optimum distribution
matching the relative volumes and aeration capacities (OD1:OD2 loads 55:45) will
minimise the required SRT and maximise treatment capacity.
Clarifier capacity – RAS flow governs thickening capacity and potential gross solids loss;
overflow rate governs effluent SS produced by clarification.
Biomass settleability (sSVI) – settleability is a key factor governing clarifier capacity.
SRT control – SRT also governs clarifier capacity: maximum capacity is achieved at the
minimum SRT (minimum MLSS for a given load) at which the effluent standards can be
met; steadiness of SRT control is important to minimise the average operating value
required.
OD aeration control – can be adjusted to minimise sSVI, and to minimise the
concentration and variability of effluent ammonia and TN.
The keys to achieving optimum results from the biological process are as follows:
Parallel (rather than series) operation of the two oxidation ditches with an optimum load split
(theoretically A:B 55:45 based on volumes and aeration capacities): Potentially, parallel
operation will maximise aeration capacity, facilitate improvement of sludge settleability,
reduce chemical consumption and improve tune-ability (Hartley, 2-Jul-13).
Minimising effluent variability so as to minimise the SRT at which the effluent standards can be
met: Theoretical SRTs at which the clarifiers reach their capacities at the design peak
load of 45 ML/d and 8.4 tCOD/d are: sSVI 110 mL/g – 15d; sSVI 95 – 18d; sSVI 80 – 22d;
sSVI 65 – 26d.
Close monitoring and control: Operators need to have a good understanding of the plant
behaviour at all times so they are not taken by surprise. Tuning transcends
troubleshooting.
Good understanding of the plant operating characteristics: Every experience with the plant
provides opportunity to move up the learning curve.
Attention to bottlenecks as they are discovered: Performance and capacity are limited by
bottlenecks which come into play during periods of duress. These can often be
overcome by operational measures.
The EVOP methodology implemented to assess the actual operational capacity of the plant
liquid stream processes is as follows:
1. Parallel (rather than series) operation of the two ODs with an optimum OD1:OD2 load
split (theoretically 55:45, but nominally 50:50). Aeration control by modulation of the
OD outlet weirs.
2. Systematically vary the plant control variables.
3. Measure the outcomes - data collection program.
4. Interpret the data and develop ideas for improvement through production of plant trend
plots, periodic process reviews, technical memos and EVOP meetings.
5. Re-adjust the process.
6. Conduct specific trials and tests on individual processes or the whole plant.
An overview of the whole program is set out in Table 2.2.
8
16117:Ken Hartley
24-Jan-14
Table 2.2 EVOP Strategy
Item
No.
Aim
Action Comments
1
Overall Strategy
Maximise plant capacity at which the
effluent licence limits can be reliably met.
At current load, test by defining the minimum SRT & sSVI at
which the licence can be met. To maximise capacity:
1. Operate ODs in parallel. This provides a degree of control
over sSVI and minimises reliance on ethanol. Shift ethanol
dosing to OD inlet channel.
2. Gradually decrease SRT to determine the minimum value at
which the effluent licence can be met.
3. Adjust the DO SP step-wise to determine the minimum sSVI
at which the effluent licence can be met.
4. Adjust the OD and clarifier flow distributions and the RAS
flow ratios such that parallel units potentially fail at the same
time.
5. Maintain steady operating conditions to minimise effluent
variability.
Goals:
Capacity: ADWF 15 ML/d @ 8.4 tCOD/d
requiring-
SRT 20d @ sSVI 90 mL/g, or 15d @ 110
mL/g
with effluent 90:50%ile variability limited
to:
NH3-N TN
SRT 20d 2:1 4:1
SRT 15d 1.5:1 2:1
2
OD 1-2 Flow Distribution
Distribute load between the two ODs to
match their relative operating aeration
capacities & volumes.
Theoretically:
OD1: 55% of total inflow
OD2: 45% of total inflow
Operate OD1 influent weir full down
Set OD2 influent weir 14mm above OD1
weir, or at same level as OD1 for a 50:50
split
3
SRT / WAS Control
Maintain a steady daily wasting rate to
hold SRT constant and minimise
variability of effluent quality.
Implement improved wasting control strategy to enable the same
fraction of the solids mass to be wasted each day. Allow for
effluent SS loss and solids recycle via the BFP filtrate return.
Monitor the daily OD SRT value calculated from the 7d MA
(moving average) WAS flow & the daily MLSS concentration.
9
16117:Ken Hartley
24-Jan-14
4
OD 1-2 Aeration Control: N / P /
sSVI
Positive control of aerobic & anoxic
fractions. To achieve in-spec N and P
and lowest sSVI with minimum doses of
ethanol and alum, tune aeration to
achieve optimum effluent
ammonia:nitrate ratio.
OD1: operate Aerators 2, 3, 4, 5 & 6 (1 & 7 off); control DO just
upstream of the OD inlet. OD2: operate Aerators 10, 11, 12 &
13 (8 & 9 off); control DO just upstream of the OD inlet. Shift
DO probes & control DO by modulating the outlet weirs. Tune
the DO control loops. Measure the OD velocities to determine
the potential for increase of average DO (nitrification
enhancement).
5
Phosphorus Removal / Alum Dosing
Alum dosing reduces pH and tends to
increase effluent SS concentration and
should be minimised.
Dose at one location only (anaerobic zone). Maintain a steady
dose rate at the minimum level required to meet the effluent P
limits. May not be needed. Can use ethanol to reduce nitrate if
bio-P removal is limited by nitrate.
6
Nitrogen Removal / Ethanol Dosing
Minimise or eliminate ethanol dosing.
Adjust DO setpoints to minimise effluent ammonia & nitrate.
Dose ethanol to the OD inlets (anoxic zones) to meet the
effluent N or P limits if necessary - the need is more likely at the
shorter SRTs.
7
Secondary Clarifier Flow
Distribution / Stress Test
Distribute flows so all clarifiers fail
simultaneously.
Distribute flow in close proportion to the RAS flows:
SC1:2:3:4 = 15:15:21:49 (as per existing clarifier inlet structure).
Conduct testing to assess the actual behaviour & capacity of the
clarifiers at the prevailing sSVI.
8
BFP Operation
Control BFP operation to maintain the
filtrate quality and daily return volume as
steady as possible over the week.
Operators to maintain as practicable through the investigation
period.
9 Load Variation
Minimise process disturbances.
Review and optimise control of plant flow streams - influent rising
mains, septage receival, BFP filtrate recycle (Item 8).
10
16117:Ken Hartley
24-Jan-14
10
Monitoring / Recording
Monitor the plant closely to identify
trends and respond appropriately.
Collect EVOP data. Record plant observations and comments.
11
Reviews / Reporting
Provide ongoing reviews and
documentation.
Prepare monthly process reviews and technical memos on
specific issues.
Conduct monthly operations meetings to review progress and
decide direction.
11
16117:Ken Hartley
24-Jan-14
3. RESULTS
3.1 Overview
Plant trend plots for the overall operating period Jul-12 to Dec-13, including the specific six-
month EVOP period 17-Jul-13 to 31-Dec-13, are shown in Appendix 5 (Plots A1 – E1, 20
plots trending 60 parameters). Parallel OD operation began on 17-Jul-13.
Plant operating data for the final two months, 1-Nov to 31-Dec-13, are summarised in Table
3.1. Features of note are as follows.
Loading
The median influent flow was 13 ML/d, 87% of the design ADWF. Rainfall was low and
the maximum day flow was only 65% of the design peak of 45 ML/d. See Trend Plot A1.
In contrast the plant median daily COD load of 10.7 t/d was 27% above the design value
of 8.4 t/d and the 90 percentile daily load was 55% above the design median (Trend Plot
A2). This arose because the median and 90 percentile COD concentrations were 34%
and 68% above the design figures. The median COD concentration was 750 mg/L
compared with the design strength of 560 mg/L.
The median influent TN:COD and TP:COD ratios were only 0.089 and 0.015, somewhat
lower than typical sewage values of 0.10 and 0.02 because of the significant industrial
inputs at Beenleigh. TN and TP concentrations were less variable than COD (Trend
Plot A3).
Trend Plot D1 shows that over the Nov-Dec period flow was distributed to OD1/OD2
in the proportions 55/45 in November (inlet weir levels 0mm/14mm above the concrete
weir sill) and 50/50 in December (0mm/0mm).
Effluent Quality
Effluent quality is trended in Plots B1-B4. All parameters conformed with the key
licence standards listed in Table 2.1 except for total phosphorus (90 percentile 2.6 mg/L,
above the limit of 2 mg/L - see Trend Plot B3).
Operation
SRT was calculated by two methods, (a) from the waste activated sludge (WAS) flows
extracted from the RAS system and the associated RAS SS analyses, and (b) from the
mass of dewatered sludge cake transported and the associated cake TS analyses. Trend
Plot D2 shows that the two SRT trends have similar patterns although for uncertain
reasons the cake value is generally lower than the WAS value with the gap increasing
over the EVOP period; an improved method of WAS SRT control was implemented
near the end of the EVOP period (Hartley, Oct-13; AIT, 2013). Over the November-
December period the SRT was reduced to determine the effect on plant performance;
median values were 14 days calculated from the WAS and 10 days calculated from the
dewatered cake.
Median MLSS concentration was 6.5 g/L (Trend Plot D2).
Median sSVI was 68 mL/g (Plot D7).
12
16117:Ken Hartley
24-Jan-14
Table 3.1 Plant Operating Data for Final Two Months of EVOP Period Parameter Key Targets Data for EVOP Period
1-Nov to 31-Dec-13
50%ile
Variability
90:50%ile
Plant Load
Sewage flow ML/d
COD conc mg/L
COD load t/d
TN conc mg/L
TP conc mg/L
TN:COD
TP:COD
ADWF 15
Process max 45
560
8.4
56
11
0.10 typical
0.02 typical
13.0
29.2 max
750
10.7
70
9.8
0.089
0.015
1.29
---
1.25
1.22
1.32
1.22
1.84
1.43
Effluent Quality
BOD mg/L
SS mg/L
NH3-N mg/L
TN mg/L
TP mg/L
F.cols cfu/100mL
10, LT 90%ile
15, LT 90%ile
3, max
5, LT 50%ile
7.5 max
2, LT 90%ile
150 max (50%ile of sample)
5
8
1.0
4.7
5.6 max
0.75
8
1.40 (90%ile 7)
1.38 (90%ile 11)
2.10 (max 2.5)
1.12
---
3.47 (90%ile 2.6)
1.60 (max 8)
Operation
SRT d
MLSS g/L
sSVI mL/g
ML pH units
Alum dose: mg solid/L
Ethanol dose mg/L
See footnote1
14 (WAS data)
10 (cake data)
6.5
68
7.4
44 (anaerobic reactor)
0
1.31
1.39
1.21
1.21
1.04
1.36
---
1. The theoretical bottleneck is clarifier capacity (Section 3.7). Theoretically, for sewage COD 560
mg/L, maximum SRTs at which design flows can be achieved are sSVI 65 mL/g, 26d SRT; sSVI 80
mL/g, 22d SRT; sSVI 95 mL/g, 18d SRT; sSVI 110 mL/g, 15d SRT. For sewage COD 750 mg/L, the
maximum SRTs at which design flows can be achieved are sSVI 65 mL/g, 19d SRT; sSVI 80 mL/g,
16d SRT; sSVI 95, 13d SRT; sSVI 110, SRT 11d.
2. Calculated from WAS data.
3. Calculated from dewatered cake data.
The various plant operating characteristics explored during the EVOP program (as listed in
Table 2.2) are discussed in the following Sections with reference to both the trend plots
appended and, for convenience, a key selection of trends shown in Figure 3.1.
3.2 Oxidation Ditch Flow Distribution
The flow distribution applied over the EVOP period is summarised in Trend Plot D1
appended. For the theoretical OD1:OD2 flow split of 55:45, the OD2 inlet weir should be
14 mm higher than for OD1 and the respective number of aerators operated in the two
ditches should be 5 and 4 with DO profiles as depicted in Figure 3.2 (Hartley, 2-Jul-13).
Trend Plot D1 shows the various inlet weir and aerator settings used over the test period.
Given the significant degree of data variability, it is difficult to discern in the trend plots any
direct effects of the different aerator and weir settings used. It is recommended that the
theoretical settings be adopted.
13
16117:Ken Hartley
24-Jan-14
Figure 3.1 Key trends from the EVOP program.
0
5
10
15
20
25
0
10
20
30
40
50
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
ML
SS
-14d
MA
(g
/L)
Re
acto
r S
RT
(14d
MA
, d)
ML
Te
mp
(d
egC
)
D2. SRT, MLSS, ML Temperature SRT(WAS, Sc 0.98) SRT(cake trucked) MLSS (g/L)
Start sSVI
0.01
0.1
1
10
100
1000
0
50
100
150
200
250
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
Fin
al E
ff N
Rat
io (
60
d M
A)
sS
VI (
mL
/g)
D7. sSVI , Effluent N Ratio ML SVI / sSVI Eff NH3-N:NO3-N Ratio 60 per. Mov. Avg. (Eff NH3-N:NO3-N Ratio)
0
4
8
12
16
20
0
100
200
300
400
500
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
Eth
an
ol D
os
e (m
gC
OD
/L)
Alu
m D
os
e(m
g s
olid a
lum
/L)
C. CHEMICALSC1. Plant Alum & Ethanol Consumption
Alum-Anaerobic Zone Alum-Total Ethanol
Licence TP90 LT 2mg/L
6.6
7
7.4
7.8
8.2
0
1
2
3
4
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
pH
TP
(m
g/L
)
B3. Effluent P & pH Effluent TP Effluent pH
Licence TN50 LT 5mg/L
Licence NH3 max 3mg/L
0
2
4
6
8
10
0
2
4
6
8
10
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
NH
3-N
, N
Ox-N
(mg
/L)
TN
(m
g/L
)
B2. Effluent N TN NH3-N NOx-N
0.1
1
10
100
0
1
2
3
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
Fin
al E
ff N
Rat
io (
60
d M
A)
Daily A
ve
Pro
be
DO
(m
g/L
)
D8. Aeration, Effluent N Ratio Ave Probe DO - OD1 Eff NH3-N:NO3-N Ratio 60 per. Mov. Avg. (Eff NH3-N:NO3-N Ratio)
14
16117:Ken Hartley
24-Jan-14
Figure 3.2 Operating DO profiles in Oxidation Ditches 1 and 2. The slopes of the lines
represent the average respiration rate at the design load (15 ML/d at 560
mgCOD/L). The solid lines show the DO profiles for an anoxic fraction of 0.4
with the feed entering at or close to the start of the anoxic zones. For OD1,
the dashed line shows the DO profile at the end of the aerobic zone for an
anoxic fraction of 0.33. The DO is controlled by the outlet weirs, using DO
Probe 1 in OD1 and Probe 2 in OD2. For effective control, at the start of the
EVOP program the probes were shifted from their original positions to the
locations shown.
3.3 SRT Control
As mentioned in 3.1 above, Trend D2 (Figure 3.1) shows that the separate SRT values
calculated from the WAS data and the cake data diverged significantly from September
onwards. The associated MLSS concentration is consistent with the cake-based SRT and the
variable influent COD concentration (Plot A2 appended). SRT ran at 15-20 days for the first
three months of the EVOP period and was then gradually decreased to about 10 days over
the last two months.
Possibly the SRT was higher when calculated from WAS because the periodic WAS SS
sample was collected at a time of day when the SS concentration was lower than the average
over the full wasting period. The improved method of WAS wasting control mentioned in
Section 3.1 above (Hartley, Oct-13; AIT, 2013) accounts for the variation in WAS
concentration over the wasting period.
3.4 Aeration Control: N / sSVI
Nitrogen Refer to Figure 3.1, Plot B2. After changeover to the new operating configuration, effluent
ammonia declined because of a high aerobic fraction in the ODs – daily average probe DO
was around 1.5 mg/L (Plot D8).
OD1
INL
ET
, 9
2
R6
, 6
1
R5
, 4
9R4
, 2
4
R3
, 1
2
Ro
tor
2,
0
R2
, 1
55
DO
2 E
xg
, 3
7
OU
TL
ET
, 4
0
DO
1 E
xg
, 9
7
DO
1 N
ew
, 8
6
R1
, 1
02
R7
, 7
3
0
1
2
0 155
Circuit distance (m)
DO
(m
g/L
)
Anoxic fraction 0.4 Anoxic fraction 0.33
OD2
R1
0, 1
56
R9
, 1
20
R6
, 6
1
R1
3, 5
8
R1
1, 1
6
Ro
tor
10
, 0
R1
2, 4
2
DO
1 E
xg
, 2
9
OU
TL
ET
, 3
3
DO
2 E
x'g
, 9
0
R8
, 9
4
INL
ET
, 8
6
DO
2 N
ew
, 8
0
0
1
2
0 155
Circuit distance (m)
DO
(m
g/L
)
15
16117:Ken Hartley
24-Jan-14
Conversely, nitrate increased because of the low anoxic fraction and the cessation of ethanol
dosing (Plot C1). Downward adjustment of the DO setpoints (Plot D8) increased the OD
anoxic fraction and reduced the nitrate.
The ammonia concentration rose again in Nov-Dec (Plot B2) when the SRT was reduced
(Plot D2) and the DO setpoint (SP) was further reduced (Plot D8). Overall, Plot B2 shows
that the effluent ammonia and TN licence limits can be met, without ethanol dosing, at an
SRT of 15 days by appropriate DO control.
Sludge Settleability Plot D7 (Figure 3.1) shows the relationship between the sludge settleability and the effluent
ammonia:nitrate ratio (60d or nominal 3SRT moving average). Both the nitrogen ratio and
the settleability are governed by the OD anoxic fraction and can therefore be controlled by
the DO setpoint. With appropriate DO control, it should be possible to hold the sSVI
below 70 mL/g.
The Beenleigh settleability characteristics are consistent with published data - see Figure 3.3
(Hartley, 2013). The Bucasia curve for an SRT of 10 days has an optimum sSVI of 65 mL/g at
an effluent ammonia:nitrate ratio between 0.1 and 1. The Beenleigh optimum matches this
precisely. Therefore, for maximum capacity, operate at an SRT of 10-15 days (based on
cake production or using the enhanced RAS wasting control system, AIT 2013).
Figure 3.3 Published oxidation ditch settleability characteristics.
3.5 Phosphorus Removal / Alum Dosing
Referring to Figure 3.1, Plots B3 and C1 show that when chemical dosing ceased in Jul-13,
effluent P increased excessively. There are two reasons for this: alum phosphorus
precipitation ceased and bio-P removal decreased due to greater nitrate recycle to the
anaerobic reactor (Plot B2). Alum dosing was restarted in October (Plot C1).
SRT 20d
SRT 10d
0
50
100
150
200
0.01 0.1 1 10 100
SS
VI o
r s
SV
I (m
L/g
)
Effluent NH3-N:NO3-N Ratio (3SRT average, Nrave)
Bucasia Ditch 1(SRT 17d)
Bucasia Ditch 2(10d)
Coolum(30d)-APT Online
Coolum(30d)-APT Offline
West Byron(20d)
16
16117:Ken Hartley
24-Jan-14
An alternative approach would be to dose ethanol to reduce nitrate recycle to the anaerobic
zone. Potentially, this approach could have two advantages – effluent TN and TP would
both be reduced, and the chemical cost may be lower. Total dewatered cake production
would be unchanged – cessation of alum dosing would reduce the total dry solids production
but this would be counterbalanced by an equivalent reduction in the cake solids
concentration (Hartley, 2013).
3.6 Nitrogen Removal / Ethanol Dosing
Plot B2 shows that the effluent TN and ammonia limits can be met by appropriate aeration
control with minimal need for ethanol dosing. However, as mentioned in 3.5 above, ethanol
dosing may offer advantages as an alum replacement.
Velocity measurements gave average circulating velocities in ODs 1 and 2 of 0.74 and 0.58
m/s (with five and four operating aerators respectively). These velocities are quite high given
the practical minimum to maintain MLSS in suspension is 0.2 m/s, and occur because the
aerators are fitted with inclined downstream baffles but no vertical upstream baffles.
Installation of vertical baffles to reduce the circulating velocity would increase the DO
concentration downstream of the aerators and enhance nitrification, potentially increasing
capacity.
3.7 Clarifier Capacity
Theoretical clarifier capacities are shown graphically in Appendix 3. Graphs are provided for
sewage mean COD concentrations of 190 mg/L at peak daily flow (560 mg/L at design
ADWF) and 250 mg/L (the wet weather strength associated with the actual median strength
of 750 mg/L during the EVOP program). The graphs show that RAS capacity is the limiting
factor; with the current stronger influent characteristics, the design peak flow capacity of 45
ML/d (3ADWF) can be met with an sSVI value of 65 mL/g and an operating SRT of up to 19
days, or 80 mL/g and 16 days (Table 3.1).
The current capacity would be slightly lower than this given the RAS pump capacities are
some 20% below their original values (Appendix 2).
A clarifier stress test was conducted over the three days 27 to 29-Nov-13 (average plant
inflow 13.5 ML/d). On 27-Nov the plant was operated with Clarifiers 1, 2 and 3 (Clarifier 4
off-line). Clarifiers 1-3 were each receiving 33% of the plant load compared with their
normal shares of 22%. On 28-Nov Clarifier 2 was first reduced to about 70% of its normal
flow, then taken off-line, increasing the Clarifier 1 & 3 loads to 50% each. From early on 29-
Nov, flow was distributed to Clarifiers 1 and 3 in the approximate proportions 0.25:0.75; in
other words, Clarifier 3, with 22% of the plant total clarifier area, was handling 10 ML/d, 75%
of the total plant dry weather flow, equivalent to its design maximum hydraulic load, at a
total plant COD load 27% above design (Table 3.1). Plant SRT at the time was about 10
days based on cake production (Trend Plot D2).
The behaviour of Clarifier 3 is shown in Figure 3.4. The overflow rate increased from about
0.5 m/h during the peak period on the 27th to 0.75 m/h on the 28th and to 1.1 m/h on the
29th. Effluent SS did not exceed 5 mg/L. At the highest loading the clarifier underflow SS
concentration reached about 2.5 g/L and the measured blanket height reached about two
thirds of the side water depth or 2m. This transfer of solids to the clarifiers reduces the
reactor MLSS concentration and increases the clarifier capacity.
The results of this clarifier stress test show that (a) the clarifier capacity is sufficient for the
current plant load - median flow 13 ML/d, median COD load 10.7 t/d (Table 3.1), (b)
Clarifier 3 RAS pumping capacity proved sufficient for the current load despite its
17
16117:Ken Hartley
24-Jan-14
Figure 3.4 Behaviour of Secondary Clarifier 3 during a stress test 27 to 29-Nov-13. Dia
27m, SWD 3m, bottom of feedwell 1.7m below surface. Fixed RAS flow 64 L/s
(5.5 ML/d). MLSS 6.7 g/L, sSVI 64 mL/g. Uo/Vs = overflow rate based on 30
minute moving average flow / mixed liquor settling rate. Parameters 1, 2 & 5
were measured, other parameters were calculated.
deterioration in capacity from 75 L/s to 64 L/s (Appendix 2), and (c) the clarifier behaviour
accords with theoretical expectations (Hartley, 2013).
3.8 Aeration Capacity
In their optimum configuration (Figure 3.2), the oxidation ditches have nine 45 kW aerators
operating. Table 3.2 shows that the aeration capacity is just sufficient for the current 90
percentile load day. Aerator capacity can be rated at a median plant load of 10.7 tCOD/d,
equivalent to 14 ML/d at 750 mgCOD/L. This is slightly less than the clarifier capacity
discussed in Section 3.7 above and represents the primary capacity bottleneck in the plant.
Table 3.2 Oxidation Ditch Total Aeration Capacity1
Aerators: 9 no. ea 45 kW
Field oxygen transfer rate at 1 kg/kWh: 9,700 kgO2/d
Oxygen demand at 15d SRT: 0.68 kgO2/kgCOD
Nov/Dec-13 50%ile COD load: 10,700 kg/d
Nov/Dec-13 90%ile COD load: 12,800 kg/d
Nov/Dec-13 90%ile oxygen demand: 8,700 kg/d
Aeration capacity peaking available on 90%ile load day: 9700 / 8700 = 1.11 1See Table 3.1 for plant loads.
3.9 Practical Issues
Two practical issues arose in relation to the aerators and the scum harvesters.
Aerators For optimum OD performance the single aeration and anoxic zones need to be contiguous,
with the DO probe controlling the anoxic fraction and the influent being fed near the start
of the anoxic zone as shown in Figure 3.2. However, if one of the aerators fails and a
standby unit needs to operate, the ideal reactor zonation is disrupted. This may increase the
effluent nitrogen level to some degree and necessitate temporary ethanol dosing. In the
event of an extended aerator outage the failed unit could be physically replaced by one of
the spare units.
1.RAS ratio
2.Blanket Level
4.Underflow Zone SS
5.Effluent SS
6.Overflow Rate 0
1
2
3
4
5
6
0
1
2
3
4
5
6
27/11 0:00 28/11 0:00 29/11 0:00
4.U
nd
erfl
ow
Zo
ne
SS
(g/L
)5
.Eff
luen
t S
S (m
g/L)
6.O
verf
low
Rat
e (m
/h)
1.R
AS
Rat
io2
.Bla
nke
t Le
vel (
dep
th f
ract
ion
) 3
.Uo
/Vs
Date & Time of Day
18
16117:Ken Hartley
24-Jan-14
Scum Harvesters The scum harvesters recently installed are set at a fixed level and are above the water
surface during low load periods. One way to address this operational problem would be to
modify the aeration controls so as to raise the water level to the appropriate value for scum
removal for a short period each day.
19
16117:Ken Hartley
24-Jan-14
4. CONCLUSIONS & RECOMMENDATIONS
4.1 Conclusions
The design median capacity of the Beenleigh WWTP is 15 ML/d ADWF at 8.4 tCOD/d (560
mg/L) with WWF above 45 ML/d bypassed. Operating experience and two previous studies
have suggested that the plant in its then series oxidation ditch configuration had an
operational capacity less than design. However, a more recent theoretical review concluded
that minor modifications and reversion from series to parallel oxidation ditch operation may
allow the design capacity to be achieved. The current six month EVOP program (17-Jul to
31-Dec-13) was therefore undertaken to assess the actual operational capacity of the plant
when operated in a parallel oxidation ditch format..
The specific aims of the EVOP program were to:
1. Optimise operational procedures for the plant liquid stream processes.
2. Determine the minimum SRT at which the effluent nitrogen targets can be reliably
achieved.
3. Define the operational capacity of the plant liquid stream processes.
The conclusions of the program are as follows.
Influent 1. During the last two months of the program (Nov/Dec-13) the median and peak influent
flows were 13 ML/d and 29 ML/d, 13% and 35% below the design values of 15 ML/d
ADWF and 45 ML/d peak.
2. The design median influent strengths for COD:TN:TP were 560:56:11 mg/L. However
the plant has a significant industrial load and over the last two months of the program
the corresponding median strengths were 750:67:11 mg/L. The median COD load was
10.7 t/d, 27% above the design value. Influent variability was high with a maximum COD
load of 13.7 t/d.
Effluent Quality 3. Over the last two months of the program all effluent quality parameters were within
licence limits except for the effluent 90 percentile TP concentration of 2.6 mg/L which
exceeded the licence limit of 2 mg/L. This can be controlled easily with increased
chemical dosing.
Operation 4. The plant was operated with the two oxidation ditches in parallel. Ethanol and alum
dosing were turned off at the start of the EVOP period, however alum was re-
introduced for the last two months to reduce TP. An alternative approach could be to
exchange alum dosing for ethanol dosing to reduce nitrate in the effluent and in the
recycle to the anaerobic zone.
5. The biological process was operated at a reactor SRT of 15-20 days during the first four
months. Over the last two months the SRT was decreased below 10 days, leading to a
rise in effluent ammonia.
6. SRTs calculated from biosolids cake produced were lower than those calculated from
RAS wasting data. The biosolids values are considered more reliable. An improved
method of RAS wasting control has been implemented. More effort is needed to
achieve reliable steady SRT control.
20
16117:Ken Hartley
24-Jan-14
7. It was demonstrated that oxidation ditch effluent ammonia and TN, and process sludge
settleability (sSVI), can be controlled through adjustment of the process anoxic fraction
using the DO control system. The sSVI control characteristics were demonstrated to
be consistent with published results from other plants.
8. The results of the clarifier stress test show that (a) the clarifier capacity is sufficient for
the current plant load - median flow 13 ML/d, median COD load 10.7 t/d (Table 3.1), (b)
Clarifier 3 RAS pumping capacity is sufficient for the current load despite its
deterioration in capacity from 75 L/s to 64 L/s (Appendix 2), and (c) the clarifier
behaviour accords with theoretical expectations (Hartley, 2013).
9. The scum harvester is fixed in level and is not compatible with DO control by varying
water level (rotor immersion).
Capacity 10. Despite the high COD load (Table 3.1), the plant was able to meet the effluent
standards. The plant is currently operating near its practical capacity. The biological
process capacity is limited by the oxidation ditch and clarifier volumes, oxidation ditch
aeration capacity and RAS pumping capacity (20% below the original capacity). Aeration
capacity appears to be the primary factor, limiting plant capacity to a median of 11
tCOD/d, equivalent to an ADWF of 14 ML/d at 750 mgCOD/L.
11. Operationally, the maximum capacity is also governed by the minimum SRT at which the
process can be reliably run. Control for minimum SRT variability will reduce effluent
variability and maximise capacity. A process SRT of 10-15 days is the minimum at which
the effluent standards can be reliably met. During the study it was not possible to
determine the operating SRT accurately.
12. The oxidation ditch circulating velocity is significantly higher than the minimum necessary
to maintain the biomass in suspension. Installation of vertical baffles upstream of the
aerators to reduce the velocity would raise the dissolved oxygen profiles and enhance
nitrification. This would increase capacity by allowing operation at lower SRT.
13. It may be possible to reduce process variability and further increase capacity to some
degree through control enhancements and improved tuning of controls. For example,
oxidation ditch aeration could be controlled from the ammonia probes rather than the
DO probes; in conjunction with this, ethanol dosing to reduce nitrate may allow
operation at shorter SRT, reducing MLSS and increasing clarifier capacity.
4.2 Recommendations
It is recommended that consideration be given to the following in order to optimise
performance and capacity:
1. Tune the SRT control system to reduce variability.
2. Tune the aeration control system to minimise SRT while meeting the effluent nitrogen
standards.
3. Control oxidation ditch aeration from ammonia, rather than oxygen, probes.
4. Improve tuning of all other process control systems to reduce variability.
21
16117:Ken Hartley
24-Jan-14
5. Reduce the minimum operating SRT by ethanol dosing to reduce oxidation ditch nitrate.
6. Investigate the interchangeability of ethanol and alum for supplementary nitrogen and
phosphorus removal at minimum cost.
7. Install vertical baffles in the oxidation ditches to reduce circulating velocities and
increase DO concentrations.
8. Investigate methods to achieve a practical scum harvesting capacity, possibly through
periodic oxidation ditch water level management integrated with DO control.
9. Refurbish the RAS pumps to restore their original capacities.
10. Pursue a trade waste program aimed at reducing the variability of the plant influent.
22
16117:Ken Hartley
24-Jan-14
APPENDIX 1: REFERENCES
AIT (2013), Beenleigh WWTP – Solids Retention Time (SRT), J3307-LCC-Beenleigh WWTP, Rev
B.
Box GEP & Draper NR (1969), Evolutionary Operation - A Statistical Method for Process
Improvement, John Wiley.
Gold Coast Water (2006), System Assessment Report for Beenleigh WWTP: Functional Area 2 -
Biological Treatment [with UQ modelling report appended].
Hartley Ken (2010), Beenleigh Wastewater Treatment Plant Upgrade: Peer Review, Logan Water
Alliance.
Hartley Ken (2012), Loganholme WWTP, Stage 7 Process Commissioning, Logan Water Alliance.
Hartley Ken (2013), Tuning Biological Nutrient Removal Plants, IWA Publishing, London.
Hartley Ken (2-Jul-13), Beenleigh WWTP EVOP Program, Technical Memorandum 1: Process
Tuning Strategy, v2.
Hartley Ken (4-Oct-13), Beenleigh WWTP EVOP Program, Technical Memorandum 2 – SRT
Control Strategy, v5.
Hartley Ken (19-Apr-13), Beenleigh WWTP EVOP Program, Technical Memorandum 3: Capacity
Envelopes.
WorleyParsons (2009), Beenleigh WWTP: Stormwater & Solids Handling Study - Consolidated
Report, Logan CC.
23
16117:Ken Hartley
24-Jan-14
APPENDIX 2: PROCESS DETAILS
Process Unit
Total reactor volume, ML
Anaerobic reactor volume, ML
Oxidation Ditches OD1 OD2 Total
Volume @ TWL, ML 5.20 4.58 9.78
Volume fraction 53% 47%
Circuit length, m 155 156
Max water depth, m 3.5 3.0
Aerators
No. 7 6 13
Length, m 9 9
Drive power, kW ea 45 45 585
Mixers
No. 2 2 4
Power, kW 5.5/4.0 5.5/4.0
Inlet weirs, length, m 5 5 10
Outlet weirs, length, m 5 5 10
Secondary Clarifiers 1-4 SC1 SC2 SC3 SC4 Total
Dia, m 27 27 27 33 ----
Surface area, m2 573 573 573 855 2573
SWD, m 3 3 3 4.5 ----
Feedwell dia, m 5.9 5.9 4.4 4.3 ----
Feedwell depth, m 1.7 1.7 1.7 1.8 ----
Underflow volume (below feedwell), m3 744 744 744 2309 4542
RAS capacity, L/s (VS pumps manually set)
DESIGN 75 75 75 244 469
CURRENT (Dec-13) 63 70 64 180 377
RAS drawoff
Influent flow split (based on RAS capacity) 15% 15% 21% 49% 100%
Suction lift From centre well
Details
BEENLEIGH WWTP - BIOPROCESS DETAILS
1.29
11.1
24
16117:Ken Hartley
24-Jan-14
APPENDIX 3: CLARIFIER CAPACITY DIAGRAMS
Based on the design RAS pump capacities listed in Appendix 2.
Sewage mean COD 190 mg/L at peak flow Sewage median COD 250 mg/L at peak
flow
SC 1-3 (ea)
SC 4
Settling LimitsTotal
SC 1-3 (ea)
SC 4
RAS LimitsTotal
Design 3ADWF
0
10
20
30
40
50
60
70
80
90
10 15 20 25 30
Cla
rifi
er
Ca
pa
cit
y (
ML
/d)
SRT (d)
sSVI 65 mL/g
Sewage COD 190 mg/L at peak flow
SC 1-3 (ea)
SC 4
Settling LimitsTotal
SC 1-3 (ea)
SC 4
RAS LimitsTotal
Design 3ADWF
0
10
20
30
40
50
60
70
80
90
10 15 20 25 30
Cla
rifi
er
Ca
pa
cit
y (
ML
/d)
SRT (d)
sSVI 80 mL/g
SC 1-3 (ea)
SC 4
Settling LimitsTotal
SC 1-3 (ea)
SC 4
RAS LimitsTotal
Design 3ADWF
0
10
20
30
40
50
60
70
80
90
10 15 20 25 30
Cla
rifi
er
Ca
pa
cit
y (
ML
/d)
SRT (d)
sSVI 95 mL/g
SC 1-3 (ea)SC 4
Settling LimitsTotal
SC 1-3 (ea)
SC 4
RAS LimitsTotal
Design 3ADWF
0
10
20
30
40
50
60
70
80
90
10 15 20 25 30
Cla
rifi
er
Ca
pa
cit
y (
ML
/d)
SRT (d)
sSVI 110 mL/g
SC 1-3 (ea)
SC 4
Settling LimitsTotal
SC 1-3 (ea)
SC 4
RAS LimitsTotal
Design 3ADWF
0
10
20
30
40
50
60
70
80
90
10 15 20 25 30
Cla
rifi
er
Ca
pa
cit
y (
ML
/d)
SRT (d)
sSVI 65 mL/g
Sewage COD 250 mg/L at peak flow
SC 1-3 (ea)SC 4
Settling LimitsTotal
SC 1-3 (ea)
SC 4
RAS LimitsTotal
Design 3ADWF
0
10
20
30
40
50
60
70
80
90
10 15 20 25 30
Cla
rifi
er
Ca
pa
cit
y (
ML
/d)
SRT (d)
sSVI 80 mL/g
SC 1-3 (ea)SC 4
Settling Limits
Total
SC 1-3 (ea)
SC 4
RAS LimitsTotal
Design 3ADWF
0
10
20
30
40
50
60
70
80
90
10 15 20 25 30
Cla
rifi
er
Ca
pa
cit
y (
ML
/d)
SRT (d)
sSVI 95 mL/g
SC 1-3 (ea)SC 4
Settling LimitsTotal
SC 1-3 (ea)
SC 4
RAS Limits
TotalDesign 3ADWF
0
10
20
30
40
50
60
70
80
90
10 15 20 25 30
Cla
rifi
er
Ca
pa
cit
y (
ML
/d)
SRT (d)
sSVI 110 mL/g
25
16117:Ken Hartley
24-Jan-14
APPENDIX 4: TREND PLOTS
PLOTS: Jul-12 to Dec-13
EVOP PERIOD: 17-Jul-13 to 31-Dec-13
A. PLANT LOADING
A1. Influent Flows
A2. Influent Strength
A3. Influent Nutrients
A4. Influent Nutrient Ratios
B. EFFLUENT QUALITY
B1. Effluent Organics
B2. Effluent N
B3. Effluent P & pH
B4. Effluent Faecal Coliforms
C. CHEMICALS
C1. Plant Alum and Ethanol Consumption
D. OPERATION – LIQUID STREAM
D1. OD Loading
D2. SRT, MLSS, ML Temperature
D3. RAS, WAS
D4. Aeration – OD1
D5. Aeration – OD2
D6. Electricity Consumption
D7. sSVI, Effluent N Ratio
D8. ML pH, Alkalinity
D9. Clarifier Effluent SS
E. OPERATION – SOLIDS STREAM
E1. BFP Cake TS
26
16117:Ken Hartley
24-Jan-14
Design ADWF 15 ML/d
Process Peak 45 ML/d
Influent Peak 75 ML/d
0
40
80
120
160
200
0
20
40
60
80
100
1-Jul 1-Sep 1-Nov 1-Jan 1-Mar 1-May 1-Jul 1-Sep 1-Nov 1-Jan 1-Mar 1-May
Rain
fall (m
m/d
)
Infl
ue
nt Flo
w (M
L/d
)
BEENLEIGH WWTP Jul-12 to Apr-14A. PLANT LOADING
A1. Influent FlowsRainfall Total Inf Influent Treated Start EVOP/Parallel OD Op'n 17-Jul
Design COD50 Conc 560 mg/L
Design COD50 mass 8.4 t/d
0
6
12
18
24
30
0
300
600
900
1200
1500
1-Jul 1-Sep 1-Nov 1-Jan 1-Mar 1-May 1-Jul 1-Sep 1-Nov 1-Jan 1-Mar 1-May
CO
D M
as
s (t/
d)
Co
nce
ntr
atio
n (m
g/L
)
A2. Influent Strength COD conc COD Mass
0
6
12
18
24
30
0
40
80
120
160
200
1-Jul 1-Sep 1-Nov 1-Jan 1-Mar 1-May 1-Jul 1-Sep 1-Nov 1-Jan 1-Mar 1-May
TP
(m
g/L
)
TN
(m
g/L
)
A3. Influent Nutrients TN TP
Licence BOD90 LT10 mg/L
Licence SS90 LT15 mg/L
0
10
20
30
40
0
10
20
30
40
1-Jul 1-Sep 1-Nov 1-Jan 1-Mar 1-May 1-Jul 1-Sep 1-Nov 1-Jan 1-Mar 1-May
SS
(m
g/L
)
BO
D (
mg
/L)
B.EFFLUENT QUALITYB1. Effluent Organics BOD SS
Typical Sew age TN:COD, 0.1
Typical Sew age TP:COD, 0.02
0.00
0.02
0.04
0.06
0.08
0.10
0.00
0.05
0.10
0.15
0.20
0.25
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
TP
:CO
D
TN
:CO
D
A4. Influent Nutrient Ratios TN:COD TP:COD
27
16117:Ken Hartley
24-Jan-14
Licence TN50 LT 5mg/L
Licence NH3 max 3mg/L
0
2
4
6
8
10
0
2
4
6
8
10
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
NH
3-N
, N
Ox-N
(mg
/L)
TN
(m
g/L
)
B2. Effluent N TN NH3-N NOx-N
Licence TP90 LT 2mg/L
6.6
7
7.4
7.8
8.2
0
1
2
3
4
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
pH
TP
(m
g/L
)
B3. Effluent P & pH Effluent TP Effluent pH
0
4
8
12
16
20
0
100
200
300
400
500
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
Eth
an
ol D
os
e (m
gC
OD
/L)
Alu
m D
os
e(m
g s
olid a
lum
/L)
C. CHEMICALSC1. Plant Alum & Ethanol Consumption
Alum-Anaerobic Zone Alum-Total Ethanol
Licence Max(50%ile) 150
1.E-02
1.E+00
1.E+02
1.E+04
1.E+06
1.E+08
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
F. co
lifo
rms (cfu
/100m
L)
B4. Effluent Faecal Coliforms Effluent F.coliforms
0
2
4
6
0
10
20
30
40
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
No
. o
f R
oto
rs O
pe
rati
ng
Inle
t W
eir
Level (
mm
ab
ove s
ill)
D. OPERATION - LIQUID STREAMD1. OD Loading
Inlet Weir Level - OD2 Inlet Weir Level - OD1 Rotors - OD2 Rotors - OD1
28
16117:Ken Hartley
24-Jan-14
0
5
10
15
20
25
0
10
20
30
40
50
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
ML
SS
-14d
MA
(g
/L)
WA
S F
low
(0.0
1xk
L/d
)
Re
acto
r S
RT
(14d
MA
, d)
ML
Te
mp
(d
egC
)
D2. SRT, MLSS, ML Temperature SRT(WAS, Sc 0.98) SRT(cake trucked) ML Temp MLSS (g/L) WAS Flow with 7d MA(brown)
0
6
12
18
0
3
6
9
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
RA
S / W
AS
Co
nc (g
/L)
RA
S R
ecycle
Rati
o
D3. RAS, WAS RAS Ratio (at design RAS flow) RAS Ratio (calc from MLSS & RAS SS) RAS Conc (measured) RAS Conc (calc from design RAS flow)
Des ign RAS f low 440 L/s
0
2
4
6
8
10
0
2
4
6
8
10
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
No
. o
f R
oto
rs O
pe
rati
ng
Daily A
ve
Pro
be
DO
(m
g/L
)
Eff
lue
nt N
(m
g/L
)
D4. Aeration - OD1 [Shows FE till 17-Jul-13]
Effluent NH3-N Effluent NO3-N Ave Probe DO OD1:NH3-N OD1:NO3-N Rotors Op.
0
2
4
6
8
10
0
2
4
6
8
10
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
No
. o
f R
oto
rs O
pe
rati
ng
Daily A
ve
Pro
be
DO
(m
g/L
)
Eff
lue
nt N
(m
g/L
)
D5. Aeration - OD2[Shows FE till 17-Jul-13]
Effluent NH3-N Effluent NO3-N Ave Probe DO OD2:NH3-N OD2:NO3-N Rotors Op.
0.0
0.5
1.0
1.5
2.0
2.5
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
kW
h /
kg
CO
D
D6. Electricity Consumption
29
16117:Ken Hartley
24-Jan-14
Start sSVI
0.01
0.1
1
10
100
1000
0
50
100
150
200
250
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
Fin
al E
ff N
Rat
io (
60
d M
A)
sS
VI (
mL
/g)
D7. sSVI , Effluent N Ratio ML SVI / sSVI Eff NH3-N:NO3-N Ratio 60 per. Mov. Avg. (Eff NH3-N:NO3-N Ratio)
0
50
100
150
200
250
6.0
6.4
6.8
7.2
7.6
8.0
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
Eff
lue
nt T
A (m
gC
aC
O3/L
)
ML
pH
D9. ML pH, Alkalinity ML pH OD1 ML pH OD2 Effluent TA
Start sSVI
0
50
100
150
200
25010
12
14
16
18
20
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
SV
I (m
L/g
)
Cak
e T
S (%
)
E. OPERATION - SOLIDS STREAME1. BFP Cake TS
Cake TS, BFP1 ML SVI / sSVI
0
5
10
15
20
1-Jul 1-Sep 1-Nov 1-Jan 1-Mar 1-May 1-Jul 1-Sep 1-Nov 1-Jan 1-Mar 1-May
Eff
lue
nt S
S (m
g/L
)
D10. Clarifier Effluent SS Final Eff-Comp SC1-Grab SC2-Grab SC3-Grab SC4-Grab
0.1
1
10
100
0
1
2
3
01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May 01-Jul 01-Sep 01-Nov 01-Jan 01-Mar 01-May
Fin
al E
ff N
Rat
io (
60
d M
A)
Daily A
ve
Pro
be
DO
(m
g/L
)
D8. Aeration, Effluent N Ratio Ave Probe DO - OD1 Eff NH3-N:NO3-N Ratio 60 per. Mov. Avg. (Eff NH3-N:NO3-N Ratio)