ltcp meeting 02-10-05
TRANSCRIPT
Maumee River (East Side) Maumee River (East Side) Public Meeting Public Meeting
Long Term Combined Sewer Overflow Control Plan Input
February 10, 2005
Discussion AgendaDiscussion Agenda
• Program Overview• Combined Sewer Overflows
• Maumee River• Identification of Alternative Types• Potential Siting of Control Facilities• Opportunity for Input
CSO Control PlanningCSO Control Planning
• The City must control CSO discharges according to the consent decree
• Alternatives are being evaluated with respect to their feasibility, associated benefits and costs
• Public input on alternatives considered is sought in tonight’s meeting
Project TimelineProject Timeline
• The Long Term Control Plan Document is scheduled to be submitted to USEPA in July 2005
• A review and modification period will follow the plan submittal
• The work identified in the plan is to be completed by August 31, 2015
Combined Sewer Area Combined Sewer Area OverviewOverview
Maumee River (East Side) Maumee River (East Side) Combined AreaCombined Area
Maumee River Maumee River Overflow FrequencyOverflow Frequency
CSO # per Year
4 165 286 147 308 49 25
Maumee River Maumee River Overflow VolumeOverflow Volume
CSO Volume (MG)
4 75 306 57 778 19 115
Alternative EvaluationAlternative Evaluation
• Alternative Evaluation is based on reducing the frequency of overflow to 0 – 12 times / year
• Total elimination of overflows would only occur in the most costly alternatives
Type of AlternativesType of Alternatives
• Alternative selection is a combination of performance and suitability considerations
• There are a number of types of alternatives
CSO Control OptionsCSO Control Options
• Storage – holds excess flow until capacity is available
• Treatment – cleans flow before it is discharged – disinfects and removes pollutants
• Separation – provides new sanitary or storm sewers so that combined sewers are eliminated
• Flow reduction / rerouting can enhance the above options
Storage Basin Facility Storage Basin Facility Basic InformationBasic Information• Type of facility: concrete tank either concealed
or visible• Land area required: 3 – 10 acres• Typical siting locations: waterfront property,
parks, other vacant parcels near rivers• Other requirements: some sewer work to bring
flow to the site; building for support functions
Basin Storage FacilitiesBasin Storage FacilitiesStorage alternatives can be below grade as basins or Storage alternatives can be below grade as basins or tunnels. Generally some access hatches or support tunnels. Generally some access hatches or support structures are present.structures are present.
Storage Basin Facilities – Storage Basin Facilities – Pros and ConsPros and Cons• Pros
• Most work is limited to one location and the adjacent areas are not disturbed
• Volume and frequency of discharge to the river is reduced • Site can be designed to be aesthetically pleasing
• Cons• Use of land for other activities is limited• Construction activities are generally 2 – 3 years in duration
limiting the use of sites during that period• A building is required for support facilities• Some untreated overflow will remain
Storage Tunnel Storage Tunnel Basic InformationBasic Information• Type of facility: below ground tunnel• Land area required: limited land requirements –
most work is along a linear corridor and is not visible from the surface
• Typical siting locations: about 60 – 75 feet below grade; linear corridors (such as streets)
• Other requirements: drop shafts and discharge points with pump stations and control of floatables
Storage Tunnel Facilities – Storage Tunnel Facilities – Pros and ConsPros and Cons• Pros
• Most work is performed underground and at construction shaft locations, minimizing land needs
• Volume and frequency of discharge to the river is reduced • Toledo has successfully constructed similar projects
• Cons• Difficult to clean and access• Some untreated overflow will remain• A building would be required to house support facilities
Storage TunnelsStorage Tunnels
Storage tunnels primarily consist of large Storage tunnels primarily consist of large underground pipes 12 – 15 feet in diameter. underground pipes 12 – 15 feet in diameter. There are additional support structures that There are additional support structures that would be located at the end of the tunnel.would be located at the end of the tunnel.
Treatment Facility Treatment Facility Basic InformationBasic Information• Type of facility: smaller concrete tank with
screening and disinfection capability• Land area required: 2-5 acres• Typical siting locations: waterfront property,
parks, other vacant parcels near rivers• Other requirements: some sewer work to bring
flow to the site; above ground building to house equipment
Treatment Facilities – Treatment Facilities – Pros and ConsPros and Cons• Pros
• Most work is limited to one location and the adjacent areas are not disturbed. Facility footprint is smaller than storage facility.
• Small storms are stored. Larger storms discharge partially treated water.
• Water that goes to the river has been treated for bacteria.• Cons
• Treatment generally requires construction of a good size building, this building is larger than required for a storage only alternative due to more equipment.
• Facility is more complex to operate and maintain than a storage only basin.
Treatment FacilitiesTreatment Facilities
Three large treatment facilities in the Detroit Three large treatment facilities in the Detroit Area. These facilities generally require a Area. These facilities generally require a fairly large building.fairly large building.
Sewer Separation Sewer Separation Basic InformationBasic Information• Constructs a new sewer to separate flow• Generally requires 3 – 6 months to complete
work on a street; 1 – 2 years to complete work in an area
• Generally doesn’t involve land acquisition
Sewer Separation – Sewer Separation – Pros and ConsPros and Cons• Pros
• Upgrades the sewer system• Eliminates CSO discharges• Minimal property requirements
• Cons• May increase total amount of pollutants to the
waterways• Disruptive to individual property owner
Sewer SeparationSewer Separation
Sewer separation requires construction of new Sewer separation requires construction of new sewers in areas where a single pipe system exists.sewers in areas where a single pipe system exists.
Flow Reduction/Rerouting – Flow Reduction/Rerouting – Pros and ConsPros and Cons• Pros
• Addresses problem at the source• Could be considered best environmentally• Could reduce basement or surface flooding
• Cons• Generally not adequate to solve the entire
problem• Most disruptive to individual property owners• Administratively intensive program
Flow Reduction / Rerouting Flow Reduction / Rerouting PhotosPhotos
EPA CriteriaEPA Criteria
• The primary concern in other CSO Plans around the country is the frequency at which CSOs discharge
• The control of bacteria is important• Other items of concern
• Volume of discharge• Pollutants in discharge• Measurable impacts on waterways
Siting Issues / ConcernsSiting Issues / Concerns
• Consider• Areas of open space (sites), reasonably close to
outfalls• Current use of existing sites & associated impacts
due to construction or long term use• Ownership of sites• “Fatal flaws” such as environmental or geotechnical
issues• Opportunities for secondary benefit – e.g.
brownfield reuse, coordination with other projects
Maumee (East Side) Maumee (East Side) Potential SitesPotential Sites• Potential sites
• Potential sites have been identified based on location of open space
• Currently evaluating the feasibility of these sites• No decisions have been made about the use or non-
use of any site
Locations for Potential Locations for Potential Storage or TreatmentStorage or Treatment
Potential Flow ReductionPotential Flow Reduction
Storage Basin Sizing – Storage Basin Sizing – I-280 Right of WayI-280 Right of WayFrequency of Overflow
Required Storage Volume
0 per year 9 MG
1-3 per year 2 MG
4-7 per year 0.4 MG
8-12 per year 0.2 MG0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
0 per year 1-3 per year 4-7 per year 8-12 per year
Potential Sites – Potential Sites – I-280 Right of WayI-280 Right of Way
Storage Basin Sizing – Storage Basin Sizing – Main St. & Nevada OverflowsMain St. & Nevada Overflows
Frequency of Overflow
Required Storage Volume
0 per year 20 MG
1-3 per year 8 MG
4-7 per year 3 MG
8-12 per year 1 MG 0.0
5.0
10.0
15.0
20.0
25.0
0 per year 1-3 per year 4-7 per year 8-12 per year
Potential Sites – Potential Sites – International ParkInternational Park
Storage Basin Sizing – Storage Basin Sizing – Oakdale AreaOakdale AreaFrequency of Overflow
Required Storage Volume
0 per year 34 MG
1-3 per year 14 MG
4-7 per year 3 MG
8-12 per year
1 MG
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
0 per year 1-3 per year 4-7 per year 8-12 per year
Potential Sites – Potential Sites – Oakdale AreaOakdale Area
Storage Tunnel AlternativeStorage Tunnel Alternative
Storage Tunnel SizingStorage Tunnel SizingFrequency of Overflow
Storage Volume / Diameter
0 per year 63 MG 28 ft
1-3 per year
24 MG 17 ft
4-7 per year
6 MG9 ft
8-12 per year
3 MG6 ft
0
10
20
30
40
50
60
70
Existing Tunnels 0 per year 1-3 per year 4-7 per year 8-12 per year
Evaluations Are ContinuingEvaluations Are Continuing
• Additional cost development and comparison to benefits are ongoing
• Better definition of potential sites and discussions with property owners / operators
• More technical evaluations (will support cost assessment)
How You Can HelpHow You Can Help
• Provide feedback on the alternative types through the various stations
• Let us know what you like and don’t like and the type of alternative
• Give us feedback on the potential sites • Provide other comments on what is important to
you• Ask questions at the various station locations