magnox update to nuleaf peter roach, strategic programmes director september 2012

15
Magnox update to NuLeAF Peter Roach, Strategic Programmes Director September 2012

Upload: wells

Post on 18-Jan-2016

47 views

Category:

Documents


0 download

DESCRIPTION

Magnox update to NuLeAF Peter Roach, Strategic Programmes Director September 2012. Magnox. One generating nuclear site Three defuelling nuclear sites Six decommissioning nuclear sites One hydro-electric plant Owned by Energy Solutions - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Magnox update to NuLeAF Peter Roach, Strategic Programmes Director September 2012

Magnox update to NuLeAF

Peter Roach, Strategic Programmes Director

September 2012

Page 2: Magnox update to NuLeAF Peter Roach, Strategic Programmes Director September 2012

Magnox

• One generating nuclear site• Three defuelling nuclear sites• Six decommissioning nuclear sites• One hydro-electric plant

• Owned by EnergySolutions• Working for the sites’ owner, the

Nuclear Decommissioning Authority

Page 3: Magnox update to NuLeAF Peter Roach, Strategic Programmes Director September 2012

Lifetime phases of the sites

Generation

Defuelling

Final site clearance

Care and maintenance preparations

Care and maintenance

Page 4: Magnox update to NuLeAF Peter Roach, Strategic Programmes Director September 2012

The MODP

Magnox Optimised Decommissioning Programme (MODP)

The work programme that is being delivered by Magnox and EnergySolutions on behalf of the Nuclear Decommissioning Authority

Page 5: Magnox update to NuLeAF Peter Roach, Strategic Programmes Director September 2012

5

Th

e m

ain

ele

me

nts

• Maximise the value from the remaining operating site at Wylfa (and Oldbury until it ceased generation in February 2012)

• Complete the Magnox Operating Programme (MOP) - dealing with the remaining spent fuel

• Deliver early care and maintenance at Bradwell and Trawsfynydd

• Deliver a safe interim care and maintenance state at Chapelcross and Dungeness

• Pioneer innovative and transformational ways of working through the introduction of Strategic Programme delivery with a view to minimising lifetime costs

• Safe implementation of the Berkeley active waste vaults retrieval project to address one of the highest hazards

• Reshape and reduce our workforce in line with the MODP whilst providing strong and responsive support to our people

The MODP

Page 6: Magnox update to NuLeAF Peter Roach, Strategic Programmes Director September 2012

Lifetime phases of the sites

Generation

Defuelling

Final site clearance

Care and maintenance preparations

Care and maintenance

Page 7: Magnox update to NuLeAF Peter Roach, Strategic Programmes Director September 2012

Car

e an

d m

aint

enan

ce

Intermediate Level Waste retrieved and packaged

Fuel Element Debris retrieved, encapsulated or dissolved

Reactors – deplant, buildings cladTurbine hall – deplanted, demolishedConventional buildings – constructed, demolished Site and land restoration

Cooling ponds drained, sealed and skips disposed of

Low Level Waste and conventional waste managed

Def

uelle

d si

tes

Page 8: Magnox update to NuLeAF Peter Roach, Strategic Programmes Director September 2012

Fuelled sites

• Oldbury – generated £300 million extra

revenue from 2008 – 2012 through inter-

reactor transfer and extended generation

• Wylfa – secured extended generation

• Dungeness A – defuelling completed

• Chapelcross - cooling pond one drained

• Sizewell A – major asbestos stripping

project completed

Page 9: Magnox update to NuLeAF Peter Roach, Strategic Programmes Director September 2012

Decommissioning sites

• Berkeley – The reactors were the first in the UK to enter safestore, while the first Intermediate Level Waste (ILW) recovered from the vaults and placed into fit-for-purpose interim storage• Hinkley Point A – turbine hall backfilled in conjunction with EDF Energy

• Hunterston A – ILW store sealed and ready to be commissioned

Page 10: Magnox update to NuLeAF Peter Roach, Strategic Programmes Director September 2012

Accelerated sites

• Bradwell – • the turbine hall has been demolished

• a fuel element debris dissolution plant

is being built

• the pond has been drained and painted

• work has begun to construct an interim

storage facility for ILW.

• Trawsfynydd –

• the reactors are being prepared for

safestore

• ILW is being placed into interim storage

• the ponds are being scabbled

Page 11: Magnox update to NuLeAF Peter Roach, Strategic Programmes Director September 2012

Lifetime phases of the sites

Generation

Defuelling

Final site clearance

Care and maintenance preparations

Care and maintenance

Page 12: Magnox update to NuLeAF Peter Roach, Strategic Programmes Director September 2012

12

MODP care and maintenance dates

Page 13: Magnox update to NuLeAF Peter Roach, Strategic Programmes Director September 2012

MODP outcomes

• Waste is dealt with earlier than originally planned and hazard is reduced

• Lead and learn means that experience is shared between the sites improving delivery as each programme develops

Page 14: Magnox update to NuLeAF Peter Roach, Strategic Programmes Director September 2012

MODP outcomes

• Care and maintenance is broughtforward – savings 34 site years fromthe total required to get all the sites to that phase

• Adding all the benefits togetherleads to a lifetime saving of£1.3 billion

Page 15: Magnox update to NuLeAF Peter Roach, Strategic Programmes Director September 2012

Questions?

15

Follow progress

twitter.com/magnoxsites

flickr.com/magnoxsites

youtube.com/magnoxsites