mailing address: p.o. box 1642 houston, tx 77056-5310 … · 2015-05-06 · taurus 70 (10,915 hp)...
TRANSCRIPT
5400 Westheimer Court
Houston, TX 77056-5310
713.627.5400 main
Mailing Address:
P.O. Box 1642
Houston, TX 77251-1642
June 10, 2015
Kimberly D. Bose, Secretary
Federal Energy Regulatory Commission
888 First Street, NE
Washington, DC 20426
Re: Algonquin Gas Transmission, LLC, Docket No. PF15-12-000
Monthly Progress Report
Dear Ms. Bose:
On February 20, 2015, the Director of the Office of Energy Projects of the Federal
Energy Regulatory Commission (“Commission”) issued a letter to Algonquin Gas Transmission,
LLC (“Algonquin”) in the above-referenced docket approving Algonquin’s request to use the
pre-filing review process for the Atlantic Bridge Project. Pursuant to Section 157.21(f)(6) of the
Commission’s regulations,1 Algonquin herewith submits its monthly progress report for the
Atlantic Bridge Project.
Should you have any questions regarding this filing, please contact me at (713) 627-5113
or DeAndra Black at (713) 627-5350.
Respectfully submitted,
/s/ Chris Harvey
Chris Harvey
Director, Rates and Certificates
Enclosures
cc: Maggie Suter (FERC)
Danny Laffoon (FERC)
1 18 C.F.R. §§ 157.21(f)(6) (2014).
20150610-5174 FERC PDF (Unofficial) 6/10/2015 11:41:27 AM
1
Algonquin Gas Transmission, LLC and Maritimes & Northeast Pipeline, L.L.C.
Atlantic Bridge Project - FERC Docket No. PF15-12-000
FERC Pre-Filing Process
MONTHLY PROGRESS REPORT
Period Ending: May 31, 2015 Report No. 3
By letter order dated February 20, 2015, Algonquin Gas Transmission, LLC (“Algonquin”) and
Maritimes & Northeast Pipeline, L.L.C. (“Maritimes”) (collectively, the “Applicants”), were
granted approval by the Federal Energy Regulatory Commission (“FERC”) to utilize FERC’s Pre-
Filing Review Process for the Atlantic Bridge Project (“Project”) with facilities proposed in New
York, Connecticut, and Massachusetts. The Project has been assigned Docket No. PF15-12-000.
This Monthly Progress Report provides a brief summary of significant Project activities or changes
that have occurred over the last month (May 2015). Activities and milestones covered in this
report are associated with the FERC Pre-Filing Review Process, field surveys, landowner survey
permission, Project facilities, agency contacts, and stakeholder outreach. A summary is provided
below.
1.0 FERC NEPA REVIEW
Pre-filing conference calls were held with FERC staff, Project team members, and agency
representatives on May 5, 2015 and May 19, 2015. These bi-weekly calls will continue
throughout the Pre-Filing Review Process.
FERC held public scoping meetings from May 11 - May 14, 2015 in the Project area.
Meetings were held in Yorktown, NY, Glastonbury, CT, Weymouth, MA and Franklin,
MA. The FERC scoping period opened on April 27, 2015 and closes on June 11, 2015.
2.0 PROJECT ROUTING AND FACILITIES
Algonquin has reduced the overall Project facilities to reflect current expectations for customer
participation in the Atlantic Bridge Project. The Atlantic Bridge Project capacity has been reduced
from 153,000 dekatherms per day (“Dth/d”) as reported in the April 1, 2015 monthly report to
132,000 Dth/d. The changes in pipeline and aboveground facilities for the Project are described
in more detail in the following sections.
Pipeline Facilities
The total length of pipeline for the Project has been reduced from 18.4 miles to 6.3 miles, a
reduction of approximately 12.1 miles from the previous Project scope (see updated Figure 1.1-1).
This reduction has been achieved through the removal of the Upstream Ramapo Take-up and
Relay, Cromwell Discharge Loop, and Q-1 System Loop from the Project scope. The remaining
proposed Project pipeline segments are all take-up and relay construction.
20150610-5174 FERC PDF (Unofficial) 6/10/2015 11:41:27 AM
2
Table 2.1 provides a side-by-side comparison of the original 222,000 Dth/d Project scope, the
previously modified 153,000 Dth/d scope and the new 132,000 Dth/d scope. The 222,000 Dth/d
scope was filed with FERC in the Applicant’s March 23, 2015 preliminary drafts of Resource
Report 1 (General Project Description) and Resource Report 10 (Alternatives). The 153,000 Dth/d
modified scope was filed with FERC on April 2, 2015 in the Applicant’s monthly progress report.
Table 2.1: Atlantic Bridge Project Pipeline Facility Scope Changes
Pipeline Facility Original Scope
222,000 dekatherms per
day (“Dth/d”)
Pipeline Length (Miles)
Previously Modified Scope
153,000 Dth/d
Pipeline Length (Miles)
New Project Scope
132,000 Dth/d
Pipeline Length (Miles)
Upstream Ramapo Take-up
and Relay 1.3 1.3 Removed from scope
Stony Point Discharge Take-
up and Relay 5.9 4.0 4.0
Southeast Discharge Take-up
and Relay 3.9 2.3 2.3
Cromwell Discharge Loop 10.6 7.2 Removed from scope
Chaplin Discharge Loop 2.5 Removed from scope -
G-2 System Loop 2.2 Removed from scope -
Q-1 System Loop 10.2 3.6 Removed from scope
Total: 36.6 18.4 6.3
Aboveground Facilities
In addition to the pipeline changes, the compression horsepower (“hp”) scope for the Project has
been modified with the new 132,000 Dth/d scope. This includes the installation of Taurus 70 units
at each station rated at 10,915 hp each (see Table 2.2 below) instead of the Taurus 60 units (7,700
hp each) included with the 153,000 Dth/d scope. In addition, the proposed Centaur 50 unit
horsepower has been increased by 200 hp at the Chaplin Compressor Station. In summary, the
total amount of additional compression proposed by the Project under the new 132,000 Dth/d scope
is 29,630 hp, which is 6,630 hp more than the 153,000 Dth/day scope but 1,400 hp less than the
original 222,000 Dth/d scope.
The new 132,000 Dth/d scope also includes the removal of the Fall River metering and regulating
(“M&R”) station from the Project and the addition of piping modifications at the existing
Westbrook M&R Station located in Westbrook, Maine on the Maritimes system.
Table 2.2 provides a side-by-side comparison of the original 222,000 Dth/d Project scope, the
previously modified 153,000 Dth/d scope and the new 132,000 Dth/d scope.
20150610-5174 FERC PDF (Unofficial) 6/10/2015 11:41:27 AM
3
Table 2.2: Atlantic Bridge Project Aboveground Facility Scope Changes
Project Facility Original Scope
222,000 Dth/d
Previously Modified Scope
153,000 Dth/d
New Project Scope
132,000 Dth/d
Compressor Stations
Oxford Compressor
Station
Oxford, CT
Add Taurus 70 (10,915 hp)
gas plus cooling
Add Taurus 60 (7,700 hp) gas
plus cooling
Add Taurus 70 (10,915 hp)
gas plus cooling
Chaplin Compressor
Station
Chaplin, CT
Add Taurus 60 (7,700
hp) gas plus cooling,
Replace two existing 42-
ppm NOx Taurus 60 gas
fired compressor units
(6,950 hp each) with two
new 9-ppm NOx Taurus
60 gas fired compressor
units (7,700 hp each).
Add Centaur 50 (6,100
hp) gas plus cooling,
Replace two existing 42-
ppm NOx Taurus 60 gas
fired compressor units
(6,950 hp each) with two
new 9-ppm NOx Taurus
60 gas fired compressor
units (7,700 hp each).
Add Centaur 50 (6,300
hp) gas plus cooling
Replace two existing 42-
ppm NOx Taurus 60 gas
fired compressor units
(6,950 hp each) with two
new 9-ppm NOx Taurus
60 gas fired compressor
units (7,700 hp each).
Weymouth
Compressor Station
Weymouth, MA
Taurus 70 (10,915 hp) gas
plus cooling
Add Taurus 60 (7,700 hp) gas
plus cooling
Taurus 70 (10,915 hp) gas
plus cooling
Total Compression
Increase: 31,030 hp 23,000 hp 29,630 hp
Meter and Regulator Stations
Yorktown M&R
Station,
Yorktown, NY
Install OPP facilities for
existing station
Install OPP facilities for
existing station No change
Somers M&R Station
Somers, NY
Install over pressure
protection (“OPP”) facilities
for existing M&R station
Removed from scope -
Danbury M&R Station
Danbury, CT
Install OPP facilities for
existing station
Install OPP facilities for
existing station No change
Salem Pike M&R
Station
Norwich, CT
Construct new M&R station
to replace existing
Construct new M&R station to
replace existing No change
Needham Regulator
Station
Needham, MA
Modify existing regulator
station
Modify existing regulator
station No change
Pine Hills M&R
Station
Plymouth, MA
Rebuild existing M&R station Rebuild existing M&R station No change
Plymouth M&R
Station
Plymouth, MA
Rebuild existing M&R station Rebuild existing M&R station No change
Fall River M&R
Station
Fall River, MA
Not part of original scope Rebuild existing M&R station Removed from scope
Westbrook M&R
Station,
Westbrook, ME
Existing M&R station under
evaluation
Existing M&R station under
evaluation
Added to Project scope.
Proposed piping modifications
at existing Westbrook M&R
Station.
20150610-5174 FERC PDF (Unofficial) 6/10/2015 11:41:27 AM
")
")
")
!
!
!
!
!
!
!
N E W Y O R K
M A S S A C H U S E T T S
C O N N E C T I C U T
N E W H A M P S H I R EV E R M O N T
R H O D EI S L A N D
N E W J E R S E Y
M A I N E
Androscoggin
Ulster
Worcester
Suffolk
Litchfield
Orange
Berkshire
Bristol
HartfordDutchess
Greene
Fairfield
Plymouth
Franklin Middlesex
ColumbiaHampden
Albany
Tolland
Norfolk
Windham
New LondonNew Haven
Morris
Hampshire
Schoharie
Providence
Westchester
Kent
Bergen
Putnam
Washington
Essex
Rensselaer
Nassau
PassaicRockland
Barnstable
Dukes
Queens
Bronx
Newport
Hudson
New Yo
rk
Union Kings
Middlesex
Essex
Bennington
Windham Cheshire Hillsborough Rockingham
MerrimackSullivanWindsor
York
Cumberland
Strafford
Belknap
Existing Oxford C/SIncrease HP
Existing Chaplin C/SIncrease HP
ProposedWeymouth C/S
DANBURY
NEEDHAM
YORKTOWN
PLYMOUTH
PINE HILLS
SALEM PIKE
WESTBROOK
Stony Point Discharge Take-Up and Relay (4.0 miles)
Southeast Discharge Take-Up and Relay (2.3 miles)
Legend") Compressor Station (C/S) (Proposed Modification)") Compressor Station (C/S) (Proposed New)! M&R Station (Modification Required)! M&R Station (Proposed New)
Proposed PipelineExisting Maritimes & Northeast PipelineExisting Algonquin Gas Transmission PipelineState BoundaryCounty Boundary
Created on 6/10/2015
!K0 40Miles
Atlantic Bridge Project
Project Overview MapFigure 1.1-1
Algonquin Gas Transmission, LLCMaritimes & Northeast Pipeline, L.L.C.
RegionalSuppliers
Atlantic BridgeProject
QC
ON
NB
NSNY
ME
PA
VT NH
MA
NJ
CT RI Maritimes & NortheastAlgonquinTexas Eastern
20150610-5174 FERC PDF (Unofficial) 6/10/2015 11:41:27 AM
5
3.0 LANDOWNER SURVEY PERMISSION
Table 3.1 summarizes the status of landowner survey permission for the Atlantic Bridge Project.
Table 3.1: Status of Survey Permission for the Atlantic Bridge Project
Project Facility Survey Permission Granted (%)
Pipeline Facilities
Stony Point Discharge Take-up and Relay 83%
Southeast Discharge Take-up and Relay 95%
4.0 FIELD SURVEYS
Civil Surveys
Civil surveys for the Project are ongoing. Algonquin has completed about 95 percent of
the centerline survey for the Project pipelines and about 90 percent of the detailed pipeline
survey.
Algonquin has also completed approximately 95 percent of the civil surveys required for
the aboveground facilities.
Algonquin is in the process of obtaining survey permission for the remaining parcels that
have not yet been surveyed.
Geotechnical Surveys for Horizontal Directional Drilling Evaluation
Algonquin is currently conducting a geotechnical survey to recover rock core samples to
document existing subsurface conditions and bedrock properties along the proposed HDD
alignments. The geotechnical survey work will continue through the spring and summer
of 2015.
Wetland and Waterbody Surveys
2015 wetland and vernal pool surveys were completed for the Q-1 System Loop in May
2015.
Threatened & Endangered Species Surveys
Algonquin continues to informally consult with federal and state resource agencies
including the USFWS, NMFS, State Natural Heritage Programs, and State fisheries and
wildlife agencies.
Phase 2 bog turtle surveys were started in May 2015 in New York.
An Indiana bat and Northern long-eared bat survey protocol is being prepared in
anticipation of June 2015 surveys.
20150610-5174 FERC PDF (Unofficial) 6/10/2015 11:41:27 AM
6
Cultural Resource Surveys
The cultural resources identification field surveys for the Project resumed in May 2015
where landowner access has been obtained.
Archaeological site evaluations also commenced in May 2015 along the Stony Point
Discharge Take-up and Relay.
Historic architectural properties identification survey is planned to commence in June
2015.
Cultural resource identification survey fieldwork progress is as follows:
Table 4.1: Cultural Resource Survey Progress
Atlantic Bridge Project Facility
Archaeological
Identification Survey
Fieldwork Progress
Archaeological Site
Evaluation Fieldwork
Progress
Aboveground
Resource
Identification Survey
Fieldwork Progress
Stony Point Discharge Take-up and Relay 79% 100% (for known sites) 0%
Southeast Discharge Take-up and Relay 91% To Be Determined (TBD) 0%
NY Aboveground Facilities 100% N/A 0%
CT Aboveground Facilities 100% N/A 0%
MA Aboveground Facilities N/A N/A 0%
5.0 STAKEHOLDER OUTREACH
Algonquin participated in a Massachusetts Energy Facilities Siting Board public hearing
held in the Town of Weymouth on May 27, 2015.
6.0 AGENCY CONTACTS
Algonquin received a letter response from the Connecticut Department of Energy and
Environmental Protection (“CTDEEP”) Natural Diversity Data Base on May 22, 2015.
Algonquin met with the U.S. Fish and Wildlife Service New England Field Office on May
15, 2015 to discuss the Project and federally endangered and threatened species.
Algonquin met with the CTDEEP on May 20, 2015 to provide an overview of the Project
and discuss anticipated permits and approvals. Algonquin also informed the CTDEEP of
the reduced project scope.
Algonquin informed both the New England and New York Divisions of the U.S. Army
Corps of Engineers of the reduced scope of facilities and requested a pre-application
meeting to coordinate the permitting process.
Algonquin informed the New York State Department of Environmental Conservation
(“NYSDEC”) of the reduced scope of facilities although the New York segments were not
changed. Algonquin is coordinating a project briefing meeting with the NYSDEC.
20150610-5174 FERC PDF (Unofficial) 6/10/2015 11:41:27 AM
Document Content(s)
AB Monthly Status Report No 3.PDF.....................................1-7
20150610-5174 FERC PDF (Unofficial) 6/10/2015 11:41:27 AM