Page 1: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Maintenanceof

Traffic (MOT)

By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of Roadway Design

Page 2: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

RPMs missing on lane lines - Index 600, Sheet 13 requires RPMs to be installed on all lane lines at 5 feet center to center in the approach and transition of the lane shift.

Page 3: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Temporary Lane Separator has white delineators - Index 600, Sheet 11 requires orange tubular markers or orange and white vertical panels.

Page 4: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

White temporary lane separator was installed - Index 600, Sheet 11 requires the temporary lane separator to be yellow.

Page 5: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Pedestrian signal pole is placed in plastic drum encased by milling material - Spec 102-9.1 requires all temporary traffic control devices to be a QPL product which ensures crashworthiness.

Page 6: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Drop-off is greater than 3 inches located within the clear zone behind curb and gutter [Index 600, Sheet 10 requires a barrier for drop-offs greater than 3 inches within the clear zone or 1:4 shoulder treatment].

Page 7: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Mixing of devices at driveway - Index 600, Sheet 9 prohibits intermixing of devices.

Page 8: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Use of non-standard pedestrian channelization on bridge [Index 600, Sheet 2 requires use of pedestrian channelizing device listed on the QPL].

Page 9: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

• Need advanced Signs.

Page 10: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Above ground hazard located in clear zone [Index 600, Sheet 3 requires a 14 clear zone for 35 mph [posted speed limit].

Page 11: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

• Business entrance signs were on portable sign stands [Index 600, Sheet 6 requires all signs to be posted when work operation exceeds one day].

• Clear Sight distance not adequate. [Index 600, Sheet 2 requires adequate clear sight distance.

Page 12: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

The third cartridge in the Quadguard crash cushion was a Type II - Per the QPL Vendor Drawings, it should be a Type I.

Page 13: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Crash cushion cartridge is damaged/crushed - Replace damaged cartridges per manufacturer’s requirements.

Page 14: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Crash cushion nose support missing - Nose support is required per the manufacturer’s installation manual.

Page 15: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Loose nuts on anchor bolts for crash cushions installed on concrete - QPL Vendor Drawing require 120 ft-lbs.

Page 16: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Debris/above ground hazard in clear zone - Index 600, Sheet 3 requires 30 foot clear zone (runout). The stockpiled debris is between the departure line and the clear zone which shall be free of hazard.

Page 17: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Barrier and crash cushion are not offset which causes the transition panel to be attached improperly - Index 415, Sheet 9 requires the barrier and crash cushion to be aligned and slightly offset when a transition panel is installed.

Page 18: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Crash cushion foundation thickness questionable on shoulder - QPL Vendor Drawings require minimum of 6” of asphalt.

Page 19: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Transition from guardrail to temporary barrier wall is not standard - Index 414, Sheets 9, 10, and 13 provides standard attachment to bridge rail – Type K barrier is required.

Page 20: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Barrier wall on bridge does not have transition pattern - Index 414, Sheet 8 requires transition units anchor pattern of 3, 3, 2, 1.

Page 21: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Barrier wall was not transitioned from freestanding to staked – Arrows below represent the transition pattern - Index 414, Sheet 8 requires transition units anchoring pattern of 1, 2, 3, 3, staked/anchored.

Transition Stakes/Anchors 1 2 3 3 Existing StakesStake Stakes Stakes Stakesper unit per unit per unit per unit

Direction of Traffic

Page 22: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Nonstandard connection to bridge railing -Index 414, Sheet 9 requires transition splice to connect Type K to bridge railing.

Page 23: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Nonstandard connection to bridge railing -Index 414, Sheet 9 requires transition splice to connect Type K to bridge railing.

Page 24: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Deflection space behind low profile barrier has stored material and other debris - Index 412,

Sheet 2 requires 9 inches deflection space.

Page 25: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Deflection space behind low profile barrier is not free and clear of material [Index 412, Sheet 2 requires 9 inches deflection space]

Page 26: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Type K Barrier is located within the deflection space of the low profile barrier wall - Index 412, Sheet 2 requires nine inches of deflection space.

Page 27: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

White delineators are used on low profile barrier and the object marker is missing [Index 600, Sheet 12 requires orange tubular markers with white sheeting. Index 412, Sheet 1 requires a Type I object marker placed at end of barrier].

Correct

Page 28: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Type K abutting Low Profile Barrier - The Design Standards do not provide a connection detail for dissimilar barriers that deflect different amounts.

Page 29: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Old anchor plate bolts are on traffic side of barrier - Cut off to prevent vehicle from snagging.

Page 30: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Less than two foot of paved deflection behind barrier wall on a 1:10 slope - Index 414, Sheet 6 requires 2 feet of paved deflection space on a 1:10 slope for 45 mph or greater.

Page 31: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Missing anchor plate - Index 415, Sheet 4 requires two anchor plates on barrier abutting crash cushion.

Page 32: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Stored material is located within the deflection space - Index 415, Sheet 1 requires two feet of deflection space for 45 mph speed or less.

Page 33: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Overlap of temporary barrier and no clear space between walls - Index 415, Sheet 6 requires a minimum of six sections of barrier wall at overlap and two feet of clear space between the walls.

Page 34: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Type K Barrier has partial fill in the deflection space - Index 414, Sheet 7 requires a minimum of 5’ wide back fill for the full height of the barrier.

Page 35: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Barrier wall staked on back side - Index 414, Sheet 6 requires barrier to be staked on the traffic side.

Page 36: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Type K Barrier wall was staked in median - Index 414, Sheet 7 requires barrier to be freestanding in the median.

Page 37: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Use of Index 415 barrier wall connecting pins for Type K [Index 414, Sheet 4 requires a rectangular top plate connecting pin – pin used for 415 barrier is weakened due to snake pin hole which is located at shear point and cannot be substituted]

Page 38: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Barrier wall connection loops missing and broken - Replace barrier. Specs. 102-9.1 requires that all traffic control devices meet acceptable standards as outlined in American Traffic Safety Services Association (ATSSA’s) “Quality Guidelines for Temporary Traffic Control Devices and Features”.

Page 39: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Drainage slots are filled with milling material - Spec 102 requires traffic control devices to be maintained.

Page 40: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Overlap of temporary barrier and no clear space between walls - Index 415, Sheet 6 requires a minimum of six sections of barrier wall at overlap and two feet of clear space between the walls.

Page 41: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Barrier placed on non flat surface - Index 415, Sheet 1 requires 1:10 or flatter surface.

Page 42: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Transition from guardrail to temporary barrier wall is not standard - Index 414, Sheets 9, 10, and 13 provides standard attachment to bridge rail – Type K barrier is required.

Page 43: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Barrier installed on top of curb – blunt end in clear zone [Index 415, Sheet 1 requires 2 feet of paved deflection space on a 1:10 slope for 45 mph or less].

Page 44: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Barrier is installed backwards [Index 414, Sheet 4 provides the details of connection between barrier units].

Page 45: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

No transition from freestanding to backfilled barrier [Index 414, Sheet 8 requires staked transition of 1, 2, 3, 3 in advance of backfilled barrier].

Page 46: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Index 600 Sheet 6Effective July 2014

Page 47: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

Single Post Median Barrier Mounted Sign Support

Effective July 2014

Page 48: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

48

Index 600 Sheet 12Longitudinal Channelizing Devices (LCD)

Pedestrian Longitudinal Channelizing Devices

Effective July 2014

Page 49: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

49

Index 600 Sheet 12Longitudinal Channelizing Devices (LCD)

Pedestrian Longitudinal Channelizing Devices

Effective July 2014

Page 50: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

50

Index 600 Sheet 12Longitudinal Channelizing Devices (LCD)

PAY ITEM102-74-5 Pedestrian Longitudinal Channelizing Device, per foot.

Effective July 2014

Page 51: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

01/04/14

Barrier Delineators

Sheeting:Yellow or White

Sheeting: 3 inches wide by 4 inches

highType IV or XI

Placed on top of temporary barrier wall

Effective July 2014

Page 52: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

52

Index 600 Sheet 4Temporary Raised Rumble Strips

Molded Engineered Polymer

Effective Jan 2015

Page 53: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

53

Index 600 Sheet 4Molded Engineered Polymer Rumble Strip

Effective Jan 2015

Page 54: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

54

Index 600 Sheet 4Molded Engineered Polymer Rumble Strip

Effective Jan 2015

Page 55: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

55

Index 600 Sheet 4Removable Polymer Rumble Strip

Effective Jan 2015

Page 56: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

56

Index 600 Sheet 4Removable Polymer Rumble Strip

Effective Jan 2015

Page 57: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

57

Index 600 Sheet 4Removable Polymer Rumble Strip

Effective Jan 2015

Page 58: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

58

Index 600 Sheet 4

PAY ITEM102-909- Temporary Raised Rumble Strips - per day

NOTE: Payment is ONE per day that rumble strips are used on a project, regardless ofthe number of sets used each day or the number of times installed or relocated in a day.

Effective Jan 2015

Page 59: Maintenance of Traffic (MOT) By: Stefanie D. Maxwell, P.E. Specialty Engineer, Office of Construction Ezzeldin Benghuzzi, P.E. MOT Engineer, Office of

QUESTIONS ????????????????

CONTACT:STEFANIE MAXWELL, P.E. [email protected]

EZZELDIN BENGHUZZI, P.E. [email protected]