Major construction projects –
current and upcoming
March 19, 2018
Project Management unit
McTavish Gate
Project 15-058
Existing conditions
▪ Gate deterioration
▪ Water drainage issues
▪ Redpath Hall stairs
deterioration
▪ Underground water
mains need to be
upgraded.
Project description
▪Restoration of the gate itself.
▪Resurfacing of the roadway/sidewalk.
▪Addition of bike racks, hydraulic bollards.
▪ Improve lighting.
▪ Improve connection with University Centre ‘terrace’.
▪Waterproof Redpath Hall foundation (north side only).
▪Redpath Hall stairs reconstruction.
▪Replacement of 2 water mains and addition of a meter
chamber.
Proposed design
By EKM
Leacock Amphitheatre
Project 15-056
Existing conditions
➢Leacock Building (1965) façades and foundation
show varying degrees of damages and
deterioration.
➢Concrete structure west and south of Leacock has
deteriorated over time due to water infiltration and
insufficient drainage capacity.
Project description
Phase I – Leacock Building:
▪Repairs to façades and exterior glass walls (“curtain walls”)
▪ Improvements to vestibules to make them universally accessible
▪Waterproofing of the foundation
Phase II - Areas south and west of Leacock Building:
▪Will be demolished, rebuilt and redesigned
▪Will be transformed into a multi-purpose exterior amphitheatre.
Proposed design
Proposed design
Schedule
PROJECT PHASE START DATE END DATE
Phase I (Leacock Building) March 2018 Oct. 2018
Phase II (Amphitheatre) April 2019 Sept. 2019
McIntyre/LSC garageRepair damaged structure
Project 11-099
Project description
▪ Repair or rebuild deteriorated sections
of concrete slabs
▪ Replace existing HVAC systems
▪ Replace existing drainage systems
▪ Code upgrades
Project description (cont’d)
▪ Exterior: envelope repairs to south portion of parking
Schedule
PROJECT PHASE START DATE END DATE
Construction June 2018 Aug. 2020
Substantial Completion /
CommissioningAug. 2020 Oct. 2020
Occupancy / Delivery Oct. 2020
University CentreReplacement of HVAC system & electrical distribution
Project 12-231
Existing conditions
➢ Ventilation system and
perimeter heating systems
are obsolete (1965);
replacement parts are no
longer available.
➢ Electrical distribution
system also needs to be
replaced.
Project description
▪ Replace entire existing HVAC system.
▪ Build new mechanical room for kitchen HVAC system in basement of the
building.
▪ Replace the building’s electrical distribution systems.
▪ Addition of a new washroom given high building occupancy.
▪ Bring building up to the most recent building codes with respect to the
electromechanical systems.
Schedule
PROJECT PHASE START DATE END DATE
Construction April 2018 Winter 2019
Occupants relocation March/April 2018 Progressive return
Full occupancy Jan. 2019
Bensadoun School of Retail Management
Project 17-141
Project description
▪ Phase 1: Renovation of the east façade and part of the south façade of
the Bronfman Building for the Bensadoun School of Retail Management
(part of the Desautels Faculty of Management).
▪ Phase 2: Renovation of a section of the main and second floors of the
Bronfman Building for the Bensadoun School of Retail Management.
Project description
Main floor 2nd floor
Sherbrooke façade McTavish façade
Proposed design
Schedule
PROJECT PHASE DATE
Phase I Summer 2018
Phase II Fall 2018
Stewart-Biology BuildingWest wing redevelopment
Project 14-125
Project update
▪ Work completed:
• Lot 0: users moved out in September 2017
• Lot 1: selective demolition and partial asbestos decontamination
in January 2018
▪ Work to come:
• Lot 2: complete demolition and asbestos decontamination
by July 2018
• Lot 3: tender process by May and June 2018 for fit-out
▪ Tentative end date:
• by Winter 2020 (Lot 3/fit-out - substantial completion)
Proposed design (south-east façade)
Proposed design (lab, W2 level)
Macdonald-Harrington BuildingEnvelope renovation
Project 11-041
Project update
▪ Work completed
• Excavation, installation of drainage system, soil decontamination and
backfilling
• Foundation: Repairs and waterproofing
• Masonry: South façade and south chimney
• Windows: All wooden windows removed, restoration in progress.
• Roof: Annex roof completed
▪ Work to come (& tentative end dates):
• Masonry: North, east, and west façades masonry repair (by Oct. 2018)
• Windows: Wooden windows restoration and installation, aluminum windows replacement (by Jan. 2019)
• Roof: Main roof (by Oct. 2018)
▪ Tentative project completion date: March 2019
Macdonald EngineeringMasonry restoration
Project 13-064
Project update
▪ Work completed:
• North and south sections of Macdonald wing: reconstruction of masonry
walls to be completed by end of April 2018
▪ Work to come:
• Central section of the Macdonald wing: masonry restoration and rain
water management interventions
• Electrical wing: masonry restoration and roof replacement.
▪ Tentative end date:
• Full project completion by spring of 2019.
Roddick GatesRestoration and redesign
Project 15-057
Project update
▪ Work completed:
• Rehabilitation of monument – incl. foundation, two center columns and
stonework
• Improvement of drainage system
• Renovation of half-moon by the city
• Installation of paving stones and landscaping on east side
▪ Work to come:
• Complete the replacement of underground electrical cables and conduit
infrastructure.
• Installation of granite benches, hydraulic and fixed bollards, new lighting and
interactive wayfinding tactile screen.
• Landscaping and furniture installation on the west side
▪ Tentative completion date: May 2018
Other projects
▪ Replacement of HVAC systems
(to be completed between March and December 2018)
• Lyman Duff
• Rutherford
• Burnside
• Ferrier
• Education
• Macdonald-Stewart Library
Other projects (cont’d)
▪ Other current projects (funded by SIF program):
• Wong: upgrades to the high-temperature metals laboratory
(“foundry”) – August 2018
• Rutherford: upgrades to the Nanotools Microfabrication
Laboratory – August 2018
• Construction of new emergency power facility (to house two
generators) – November 2018
Other projects (cont’d)
https://www.mcgill.ca/construction/