man andmachinerests
DESCRIPTION
TPS+1 Engineering Sub Group in LinkedIn Simulation of Machine and Man of a simple one piece flow line : with case 4 addedTRANSCRIPT
- 1. LinkedIn group: TPS+1 ENGINEERINGPrepared by Casey NgMachine and ManWorks and WastessimulationCASE IV
2. KEEP THEMACHINE BUSY5 OPERATORS x 5MACHINESCASE I 3. OP510SecondsOP420SecondsOP350SecondsOP220SecondsOP110SecondsMaterialStockFinishedStockRackA BCE D5 Operators x 5 Machines 4. OP510SecondsOP420SecondsOP350SecondsOP220SecondsOP110SecondsMaterialStockFinishedStockRackA BCE D4 x1 x5 Operators x 5 Machines 5. OP510SecondsOP420SecondsOP350SecondsOP220SecondsOP110SecondsMaterialStockFinishedStockRackA BCE D49 x28 x16 x5 Operators x 5 Machines 6. KEEP THE MANBUSY1 OPERATOR x 5MACHINESCASE II 7. OP510SecondsOP420SecondsOP350SecondsOP220SecondsOP110SecondsMaterialStockFinishedStockRackA15 x1 Operator x 5 Machines 8. MULTIPLE PARTSIN ONE MACHINE1 OPERATOR x 5MACHINESCASE III 9. OP510SecondsOP350SecondsOP220SecondsOP110SecondsMaterialStockFinishedStockRackA? x1 Operator x 5 MachinesOP480 Seconds0~4 x0~4 x 10. Add Autoloaderand Unloader1 OPERATOR x 5MACHINESCASE IV 11. OP510SecondsOP220SecondsOP110SecondsMaterialStockFinishedStockRackA? x1 Operator x 5 MachinesOP480 Seconds0~4 xAutoUnloaderAutoLoader0~4 xOP360Seconds