management control system in spvs for infratsructure projects_a k gupta_05082008

53
Paper Title: Management Control System in SPVs for Infrastructure Projects Author’s Name: Anil Kumar Gupta Affiliation: Director Public Private Partnership, Ministry of Railways, Government of India, New Delhi Mailing Address: Room No. 537, Rail Bhawan, New Delhi-110001 Phone No. 011-23382783, Fax 011-23382783 Email [email protected] 1

Upload: anil-kumar-gupta

Post on 08-Feb-2017

83 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

Paper Title: Management Control System in SPVs for Infrastructure Projects

Author’s Name: Anil Kumar Gupta

Affiliation: Director Public Private Partnership, Ministry of Railways,

Government of India, New Delhi

Mailing Address: Room No. 537,

Rail Bhawan, New Delhi-110001

Phone No. 011-23382783, Fax 011-23382783

Email [email protected]

1

Page 2: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

Management Control System in SPVs for Infrastructure Projects

ABSTRACT

Project Management challenges in Infrastructure is enormous in the face of abysmal past

record of government departments in project execution and growing investment need to

meet with the projected GDP growth of our country. Indian Railways (IR) is also

witnessing similar pressure on faster project execution front due to larger need for

investment in capacity augmentation and modernization projects. This paper examines

the project management experiences on Delhi Metro Rail Corporation and IR, the latter

having relied primarily on three models for project execution: dedicated construction

units under zonal railways, independent construction organizations under departmental

fold and Public Companies or Special Purpose Vehicles (SPVs) created for specific

project or group of projects. Delhi Metro Project is the biggest success story in

infrastructure project management during the last one decade in India. The author having

worked on this project for five years in the planning as well as construction he describes

in detail the success story in the project management of the 4.5 km underground corridor,

from Vishwa Vidyalaya station to Kashmere Gate station, which was commissioned in

December 2004 about seven months in advance of the scheduled date setting new

benchmarks for standards in safety, quality, environmental and public utility

management. The paper also briefly describes the 2007-08 performances of IR’s zonal

construction unit at Chennai and Rail Vikas Nigam Limited (RVNL), an SPV. The author

then goes on to propose a new management control system containing six key elements:

Leader, Organizational Structure and Work Culture, Responsibility Triangles,

Contracting Framework, Project Management Consultant, Monitoring System, and

Buffer Management and System Review. The construction unit of IR, RVNL and DMRC

have been evaluated and compared on this new management control system and based on

it model characteristics of the management control system for SPVs created for executing

infrastructure projects have been proposed.

2

Page 3: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

INTRODUCTION

General

Developing countries, like India, needs huge investments in infrastructure.

According to one estimate1 about US$ 500 billion is required to be invested in

infrastructure during the next five years if India has to achieve 10% growth rate in

GDP. This requires faster execution of projects posing major challenges in Project

Management. The present Indian scenario in Project Management is not

encouraging. Often Governments announce big projects but fail to get them

executed for years. As per a Government of India (GOI) report2 568 major

projects costing over Rs. 2 lakh crore covering 16 different sectors suffered an

average cost overrun of 22.7%. A further peak into the details provide a grim

picture: two projects under Health and Family Welfare sector suffered a cost

overrun of 388.2%; 17 projects under Urban Development sector suffered a cost

overrun of 108%; and 2 projects under Water Resources suffered an overrun of

198%. Similarly the scenario on time overruns is also grim: 3-240 month in Coal

sector; 171 months in Information & Broadcasting; 8-168 months in Power; and

6-147 months in Road sector.

Railway Projects

Project Management scenario on Indian Railways is also not encouraging. During

year 2008-09 IR would invest about Rs.37,500 crore out of which more than

Rs.11,000 crore would be invested in construction of new railway lines including

doubling and gauge conversion3. During year 2007-08 total 2300 km of Broad

Gauge lines (including 155 km new line and 500 km doubling) were completed

and another 3500 km line is targeted to be completed next year. However with the

sanction of several more projects each year, the number of projects on the shelf of

IR is increasing year after year and with that the time and cost overruns are also

increasing. The report cited above puts the average time overruns on railway

project at 8-168 months. Most of the time overrun could be attributed to the

rationing of fund allotment as numerous projects compete for adequate fund every

3

Page 4: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

year. For an example of cost overrun one may look at the Udhampur-Katra new

railway line project that was sanctioned in year 1995 at Rs. 189 crore. The cost

was revised to Rs.540 crore in year 2006 and the project is still ongoing.

Railway Project Companies

In order to overcome the departmental limitations in expeditious project

execution, Ministry of Railways (MOR) has gone for creation of dedicated project

companies, also known as Special Purpose Vehicles (SPVs), under the Indian

Companies Act 1956 for executing special railway projects. Konkan Railway

Corporation, created in 1990 for executing and operating 760 km coastal railway

line connecting Mangalore to Mumbai was the first such SPV. Since then a

number of SPVs have been created for executing various railway projects such as

Mumbai Rail Vikas Corporation (MRVC), Rail Vikas Nigam Limited (RVNL),

and Dedicated Freight Corridor Corporation of India Limited (DFCCIL). Gupta

and Roy, 20084 have brought out among other things the need, form and

success/failures of such SPVs in managing railway projects. KRCL succeeded in

completing a technologically complex project in a record 7 years time which was

the first of its kind in Independent India. It also succeeded in developing cutting

edge construction expertise and achieved the best project management standards

in railways. Mumbai Rail Vikas Corporation was created in 2001 for up gradation

of suburban railway infrastructure in Mumbai. RVNL was created in 1993 for

executing Rs. 15,000 crore National Rail Vikas Yojana involving important

capacity augmentation projects, three mega bridges and several port linking

projects. DFCCIL was created in 2006 for execution of the prestigious Dedicated

Rail Freight Corridor connecting the four metro cities in India.

Urban Infrastructure Projects

The general experience of execution of mega urban infrastructure projects in

cities and big towns hasn’t been encouraging either. In Kolkata, 16 km

underground metro line had taken 23 years for completion between 1972 and

1995. The city had experienced massive disruption to traffic and routine city life

4

Page 5: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

during the underground construction. The experience was such that it had created

a question mark about the feasibility of construction of another underground

Metro line in any other city in India.

For commuting public in cities in India the nightmarish scenes of construction on

roads for sewer, fly over and pipe lines have become daily routine not evoking

any serious reaction at all. These projects create traffic chaos with pot holed roads

filled with mud and dirt, unruly road diversions, no traffic signage etc. Over and

above there would be ugly signboards reading “Inconvenience is Regretted, Work

in Progress”. Not many people question why the commuters have to necessarily

go through this horrible experience for months and often years? Even if someone

dare to question, the reply from the topmost bureaucrats might be: “We have to

bear this if we want better infrastructure to be built in city”5. There appears to be a

sense of helplessness at such project sites with no clear organizational structure or

management control system in sight for tackling such project management

challenges. Lack of successful urban project management models further

perpetuates this sense of helplessness and people continue to think that this is the

way infrastructures in cities are built.

Delhi Metro Project

Delhi Metro’s project management has been a contrasting experience than what

was witnessed elsewhere. It created new benchmarks in completing works before

target, managing traffic at work sites in a manner much smoother than existing

before the start of construction work, achieving international standards of safety

and quality management, creating a brand building platform for contractors and

designers, and utilizing latest technology in the most cost effective manner for

completing the phase-I of the project in a record time of 7 years as against a time

frame of 10 years set in the detailed feasibility report in 1995. Officers, engineers,

contractors, designers and consultants having experience on this project have

increased their market value tremendously and are in great demand in the

government as well as in private sector.

5

Page 6: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

Present Treatment to Project Management

Literature on project management exists mainly focusing on private sector that

too for non-infrastructure projects. There is hardly any literature analyzing

success in project management of infrastructure projects in government sector in

India. Project management in government or public sector managed projects in

India is mainly discussed in conferences and seminars. But these are related more

to study of failures in terms of delays, cost overruns, accidents, poor public image

etc than to case studies of successes. A review of time and cost overruns on

projects in India reveals following principle reasons6:

• No committed fund

• Commencement of construction without proper investigation and planning

• Faulty contract packaging resulting into poor selection of contractors

• Undue hardships to public resulting into court interventions

• Inferior construction technology

• Frequent changes in chief executive

• Delay in land acquisition

• Casual and indifferent project management

• Contractors failing on the job

• Midway changes in the scope of work and poor management of the same

• Poor decision making process

Awareness of above reasons is necessary yet it is important to know how these

reasons were overcome in successful infrastructure projects. This brings out the

importance of studies of good success stories of project management, which are

rare in India. Insights into DMRC’s success in executing phase-I of the Delhi

Metro Project will serve this very purpose. Comparison with the project

management control systems adopted in IR and a railway SPV would further

bring forward the elements of management control system that could be adopted

elsewhere in order to replicate the same success stories.

6

Page 7: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

Some of the questions that are targeted for answer in this paper are: How is IR

managing railway projects? What is the reason that IR has been creating new

SPVs for executing such projects? How did DMRC succeed in executing metro

project so well while Kolkata Metro failed to achieve the same level of success?

How is DMRC different than a railway SPV like RVNL? Does any Management

Control Framework emerge out of study of these models of execution of projects?

Can this framework be implemented in a government department or only an SPV

be able to do this?

PROJECT EXECUTION BY IR

Construction Units of Zonal Railways

IR is organizationally divided into 16 zonal railways based on regional

jurisdiction. Each such zonal railway is headed by a General Manager (GM) and

the organisation under him consists of 9 line departments (known as Open Line in

railway parlance) each headed by a officer known as Principle Head of

Department (PHOD). Smaller construction works are executed by the respective

technical line departments. However for carrying out bigger projects a separate

Construction unit headed by Chief Administrative Officer (CAO) functions under

each GM. CAO is generally from civil engineering (commonly known as

Engineering within IR) department7. This is a multidisciplinary unit including

Signalling & Telecommunication (S&T) and Electrical engineering officers and

having separate finance and personal services working independent of the line

departments. These units are project organizations for zonal railways. Some zonal

railways viz Northern Railway (Delhi), East Central Railway (Hajipur) have more

than one Construction units based on the size and number of sanctioned projects

as well as annual fund allocation. Recently, for speedier execution of important

projects, Construction units specific to such project has been created; three such

units (for development of new production/ workshop units) in East Central

Railway and one such unit (for Jammu and Kashmere railway project) in Northern

7

Page 8: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

Railway have been created in recent years. All these organizational units are

extensions of the departmental set up of the IR.

Separate Departmental Organizations

MOR has also created special units for execution of bigger Projects. Metro

Railway in Kolkata was executed by such a special organization which later was

converted into an operating railway like 16 other zonal railways. Similarly Central

Organization for Railway Electrification (CORE) was created at Allahabad in

1972 for executing railway electrification projects over IR. Both these

organizations are now headed by separate GMs. Further, Northeast Frontier

Railways based at Guwahati has a construction organization under a GM separate

from the Open Line GM. But these organizational units are also departmental set

up of the IR created for a specific or group of railway projects.

Railway Project Cycle

A typical new line railway project starts from sanction of Preliminary Engineering

cum Traffic Survey (PETS) in the railway budget. On completion of PETS the

preliminary cost of the project and its financial viability is arrived and the project

gets examined by the Extended Railway Board8 and later placed before Cabinet

Committee on Economic Affairs (CCEA) for approval. If approved, the project

gets included either in the regular Railway Budget or in the Supplementary

Demand for approval of the Parliament. Once a project is approved by the

Parliament, Final Location Survey (FLS) is carried out and detailed project

estimate is prepared which require sanction of the Railway Board before incurring

expenditure on the project. This takes anywhere between one to two years time

and in some big projects only part estimates are prepared at a time and sanction of

detailed estimate for the entire project takes several years.

Performance of Construction unit at Chennai

Performance of CAO/ Construction, Southern Railway, Chennai was studied for

the purposes of this paper9. The unit consists of 2018 government staff including

8

Page 9: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

117 Group A officers. As on 31.03.2008 the unit had on its shelf 40 railway line,

6 bridge and 184 road over/under bridge projects which were sanctioned in the

railway budget ranging from 1990-91 till 2007-08. Based on fund allotted to the

unit for the year (Rs.905 crore) 15 railway line projects and 3 bridge projects were

targeted for completion during financial year 2007-08. Against this it spent

Rs.899 crore and completed 3 projects while 5 other projects were waiting for

CRS’s inspection after physical completion as on 31.03.2008. Rest all other

targeted projects remained physically incomplete. One of the reason for this was

mismatch between fund required for completing these projects (Rs. 1734 crore)10

and fund allotted during the year (Rs. 570 crore)11. Rest of the fund went into

ongoing non-targeted projects. At the beginning of financial year 2007-08 an

amount of Rs. 8,243 crore was required to complete all major sanctioned projects

in the unit, which was more than 9 times the fund allotment during the year. It

carried out 10 PETS that were sanctioned in railway budget 2007-08. It is also

executing elevated Mass Rapid Transport Project (Metro) line between Chennai

Beach and St. Thomas Mount. The first phase of this project between Chennai

Beach and Tirumailai was sanctioned in railway budget in year 1983-84 and was

completed in 1997. The second phase of 11 km extension from Tirumailai was

sanctioned in 1996-97 and completed in 2007. The 5 km third phase was

sanctioned in 2006-07 and is under progress.

Details of on-going projects submitted every month by CAO’s unit (known as

MCDO) doesn’t indicate original estimated cost of the project at the time of

sanction. CAO/ Southern Railway is maintaining a column ‘Anticipated Cost’

which shows the latest estimated cost. Hence actual cost overrun on each project

was difficult to know. Practically they cannot be considered as cost overrun as

there might have been change in scope of work, project might have been taken up

in parts, or fund might have been allotted over a long period of time. As described

hereabove, even targets set at the beginning of a year might not be realistic hence

performance cannot be judged on this basis alone. There appear to be only one

unit to measure the productivity, annual project expenditure per staff, which was

0.44 crore for the CAO, Chennai.

9

Page 10: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

RAIL VIKAS NIGAM LIMITED

RVNL was created in January 2003 for executing National Rail Vikas Yojana

costing Rs. 15,000 crore in a short period of five year time. This comprised 34

projects at Rs 8000 crores for strengthening of Golden Quadrilateral12 and

diagonals, 22 port connectivity projects at Rs 3000 crores and 4 mega bridges at

Rs 3500 crores. Subsequently several projects were changed and as on 31st March

200813 it had 53 projects on its shelf including one mega bridge, out of this 13 are

being executed by zonal railways while the funding is through RVNL. The main

purpose of creating this SPV was for dedicated and alternate funding through

public private partnership funding and better project management.

As brought out by Gupta and Roy, 2008, RVNL has been successful in faster

project execution but not so in designing PPP models for private financing except

already existing BOT-SPV model in port linking projects. Now Railway Board

has permitted Indian Railway Finance Corporation to raise market debt for

lending to RVNL for financing projects. Funds are also being provided through

railway budget as is done for Construction units. The projects are being funded

through equity (11), loan from Asian Development Bank (7), market borrowing

through IRFC (11), capital fund flows from Railway Budget (9) and private

funding through Public Private Partnership (PPP) (7)14. In the five years of its

existence it has been successful in completing only 6 projects against the initial

target of 56 projects, while 17 are in various stages of completion. There are still

18 projects which have not taken off at all. In financial terms it has spent Rs.4019

crore during this period. During the same period zonal railways have completed 9

projects for RVNL at a total cost of Rs. 1633 crore.

Performance of Chennai unit of RVNL

RVNL is executing projects through its field units each headed by Chief Project

Manager. These units are multidisciplinary in nature under one administrative

head similar to the CAO’s unit in Construction organization. For the purpose of

this paper the performance of one field unit based at Chennai was studied15. This

10

Page 11: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

unit is headed by a Chief Project Manager having a team of 11 officers and 9

other staff under him. The unit works under one roof with a 250 sq.m office at

Chennai. The unit was assigned 4 railway projects of which it has completed one

and rest three are on-going. It is assisted by a Project Management Consultant

(PMC) for each project. A total of 80 PMC staff is working on these projects. The

unit is in existence for the last 3 years in which it has spent an amount of Rs.506

crore of which Rs. 258 crore was spent in year 2007-08. The unit is self sufficient

in terms of every resource a project organization should have except that contracts

are awarded by the RVNL headquarters in Delhi. The productivity in terms of

annual project expenditure per staff (including PMC staff) is 2.6 crore which is

about six times the productivity of CAO’s unit at Chennai. Of course it didn’t

have any scarcity of fund allotment and there was no priority list for the project

and all the four projects were equally important.

Current Trends in the Organization

Over the years the organization has become bulkier with unproductive layers

creeping in, procedures has become lengthier and Schedule of Power, through

which tender and other administrative power is delegated to the organization by

MD, has become more conservative16. A comparative table is shown in Exhibit-1

highlights some these changes.

Exhibit-1

RVNL Earlier RVNL Now

Flatter organization with CPM

reporting to Director Project

Intermediate layer of Executive Director

has been created.

CPM empowered to call Single

and Special Limited Tenders up to

Rs. 5-10 crore.

Now only Open Tenders permitted up to

Rs. 15 crore.

11

Page 12: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

CPM’s power of purchasing stores

through quotation-Rs. 5 lakh each

time with no Annual limit

Rs.10 lakh each time with Rs. 50 lakh

annual limit

With leaner corporate office

approvals used to be granted by

the headquarters within a few

hours or at most a few days.

Now with much bulkier corporate office it

is more procedure oriented in which

approvals take days or even weeks.

When a contractor failed, CPM

was empowered to take corrective

action such as offloading works to

other contractor in the interest of

achieving target.

A time consuming procedure to be

followed for any risk and cost tender.

Project completion takes a beating.

The trend seen in RVNL could be said to be a natural trend for any public SPV as

it grows older. The challenge for project manager is to guard against such decline

that shifts focus from achieving project completion targets to making procedures

more accountable.

PROJECT MANAGEMENT AT DELHI METRO PROJECT

General

Before analyzing the success of DMRC it is necessary to place on record a

perspective that was the hallmark of its approach toward managing the mega

project. Any new urban infrastructure project brings major investments in the city

development. Hence the agency developing the infrastructure is in a better

position to manage and maintain the civic amenities such as roads, traffic safety,

utilities and pedestrian footpaths affected by the project during its possessions of

site, than the usual line agencies responsible for maintaining these services. The

12

Page 13: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

three main reasons are: better availability of fund, simpler processes and direct

return to the project in terms of faster and safer work. There should not be any

hoarding on the road at a project site reading phrases such as ‘Inconvenience is

Regretted’, ‘Work in progress’, ‘Please bear with us’17. All these messages

indicate poor planning, incompetence of agency and callous approach toward

public and are first indication that the project is likely to have accidents, cost

overrun, time overrun or otherwise the project is being executed at the additional

cost of public, who pays in terms of higher fuel cost, pollution, accidents and

general inconvenience. The hoardings at the project site should be a welcoming

sign for the public identifying with the agency and the contractor and further

expecting better roads, smother traffic flow and safer environment.

A rail based transport system for Delhi was first proposed in 1969-70 by Central

Road Research Institute. During the period 1970-1995 several studies were

carried out which suggested several alternatives ranging from MRTS, LRT,

Magnetic Levitation and Tramway. Present system is based on a RITES report for

198.5 km Integrated Multimodal MRTS consisting of elevated, underground and

surface corridors. A Detailed Project Report (DPR) was prepared in 1995 for

Phase-I consisting of 65.11 km to be completed in 10 years by 2005 with a loan

from Japan Bank of International Cooperation to the extent of 62.5% of the

completion cost. Delhi Metro Rail Corporation (DMRC) was registered in May

1995 as a Special Purpose Vehicle (SPV) under the Companies Act 1956 with

equal equity participation from the GOI and Government of Delhi for

implementation of the project. The phase-I of the project was approved by the

government for implementation in September 1996. DMRC started functioning in

November 1997 with the appointment of Managing Director, Dr. E. Sreedharan.

He handpicked other senior officers including the functional directors and created

an organization of his choice. A General Consultant (GC), a consortium of five

international companies PCI, JARTS and Tonichi from Japan, PBI from USA and

RITES from India, was appointed through open international competitive bid for

assisting DMRC in the project implementation. GC appointment was due to a pre-

condition for the financing from JBIC and it played a very important role in the

13

Page 14: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

project management. Phase-I consisted of three corridors which were significantly

modified by DMRC as compared to the recommendation in DPR in order to take

up the busiest corridor first and bring the alignment directly above the congested

roads rather than along the existing railway tracks that was suggested in DPR.

Actual field work commenced in October 1998 on an 8.5 km stretch between

Shahdara and Tis Hazari. In spite of loss of almost three years since the DPR, Dr.

Sreedharan decided to keep 2005 as the target year for completion of the phase-I

of the project, thus reducing the construction period from 10 years to 7 years. The

target set in 2002 for commissioning of various sections of the phase-I of the

project and corresponding achievements are shown in Exhibit-2.

Exhibit-2

Section Length (km)

Target Date as in 2002

Commissioning Date

Shahdara-Tis Hazari 8.0 Dec 2002 Dec 2002

Tis Hazari-Tri Nagar 4.7 Sept 2003 Sep 2003

Tri Nagar-Rithala 8.8 Mar 2004 Mar 2004

Vishwa Vidyalaya-Kashmere Gate 4.0 Dec 2004 Dec 2004

Kashmere Gate-Central Secretariate 5.5 Sep 2005 Sep 2005

Barakhamba Road-Kirti Nagar 6.0 June 2005 Dec 2005

Kirti Nagar-Dwarka 16.4 Sep 2005 Dec 2005

It makes almost incredible reading of the above report card for a project that is the

biggest urban intervention in India since independence. The project was executed

in a very difficult urban environment, under the critical scrutiny of media and

VVIPs. It was executed with latest construction and operational technologies that

were not available in India. The phase-I was executed at a reasonable cost of

Rs.10,500 crore through the best usage and indigenization of costly technology

and international expertise that brought down the cost per km of corridor

drastically on the subsequent sections. The leadership of Dr. Sreedharan played

the most important role in this success story.

14

Page 15: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

The project was recognized as the best training ground for contractors,

consultants, engineers, suppliers and all other stakeholders as every new bid

witnessed frenzied competition lowering down rates. Each such entity that

worked on the project came out with greater value for itself as success and

expertise was assured through excellent management control system followed on

the project. In order to have a closer look at this value proposition the project

management of contract MC1A has been described hereunder.

Management of Contract MC1A

Salient features of Contract

The contract number stands for Metro Corridor 1A and meant for civil and

electrical & mechanical works for underground corridor between Vishwa

Vidyalaya and Kashmere Gate stations. It consisted of 4.5 km of tunnel including

400 m of depot approach and four stations. The design and construct lump sum

cost contract was awarded to KSHI JV, a joint venture of four Companies:

Kumagai Gumi, Skanska, HCC and Itochu; at a lump sum cost of Rs.900 crore

and provisional sum of Rs.33 crore (for risky and variable nature of works such as

testing, artwork, architectural finishes and utility diversions which were paid by

DMRC on actual basis). The contract began on 22nd May 2001 and the completion

date was 25th July 2005 with 218 weeks provided for execution of the contract.

Contract Structure

The contract payment was structured on pre fixed milestones against which each

bidder quoted specific payment. These milestones were structured under a series

of Cost Centers: 01-Preliminary Activities, 02-Design, 03-Civil Structures etc.

The total of such payments made up the lump sum cost. However the bid

evaluation was done on the basis of present value of such payments offered by

each bidder. The cumulative curve of such payments has to match the physical

progress proposed by the contractor through a project schedule generally based on

the milestones but also including other non-payment activities. The curves are

15

Page 16: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

generally ‘S’ shaped and hence called S-curve. The S-curves for concrete pouring

for permanent structure and milestone payments for MC1A contract are shown in

Exhibit-3.

Exhibit-3

Concrete Consumption

0

5000

10000

15000

20000

25000

1-Apr-0

2

1-May-02

1-Jun-0

2

1-Jul-02

1-Aug

-02

1-Sep-02

1-Oc t-0

2

1-Nov -02

1-Dec -02

1-Jan-03

1-Feb-03

1-Mar-03

1-Apr -03

1-May-03

1-Jun-03

1-Jul-03

1-Aug-03

1-Sep-03

1-Oc t-0

3

1-Nov -03

1-Dec -03

1-Jan-0

4

1-Feb-0

4

1-Mar-

04

Time Period

Conc

rete

Qty

0

50000

100000

150000

200000

250000

300000

Monthly Concrete QtyActual Monthly Qty Cumulative Concrete Qty Cumulative Concrete Qty

Payment S-Curve

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

Jun-01

Aug-01Oc t-0

1Dec-01

Feb-02Apr-0

2Jun-02

Aug-02Oct-0

2Dec-02

Feb-03Apr-0

3Jun-03

Aug-03Oct-0

3Dec-03

Feb-04Apr-0

4Jun-04

Aug-04Oct-0

4Dec-04

Feb-05Apr-0

5Jun-05

Mill

ions

Months

Cum

ulat

ive

INR.

Equ

ival

ent Cumm.

INR Equi.

S-curve for Milestone Payments S-curve for concrete

Site Organization

Monitoring strategy included building site organization and designing a

framework of control, reviews, reporting and scheduling. GC’s project

management organization was organized parallel to the DMRC’s organization

while its site organization was organized parallel to the contractor’s site

organization so that the communication and line of command across the project is

efficient and transparent. A lean organization consisting of a Chief Resident

Engineer, a Resident Engineer, five Section Engineers and 4 other engineers from

GC and a Deputy Chief Engineer with two Executive Engineers from DMRC was

deployed for monitoring the contractor’s work. The organizational structure for

monitoring MC1A contract is shown in Exhibit-4.

Planning and Scheduling

While planning and scheduling the work the contractor adopted a strategy of latest

start and highest economy. It prepared a schedule that proposed construction work

in three phases using same temporary structural steel three times on the project.

Key resources like concrete batching, rebar fabrication, plant and equipments,

16

Page 17: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

testing laboratory etc were centralized for better control and monitoring. A

uniform procedure was specified by DMRC for project monitoring across all

contracts based on Primavera software. The contractor used to submit 3 month

rolling program every month showing past month’s progress and planning for

next 3 months which was discussed in monthly meeting at the corporate office of

DMRC. Similarly a 4 week rolling program used to be discussed in the weekly

meeting with the contractor at project office. An ISO 14001 compliant

management plan and procedures were developed for defining each project

activity and monitoring of quality, safety and environment.

SE Section B

Exhibit-4

PM

SM Section

PL (MC1A)

SM Section

SM Section

SM Section Line of Command

Line of communication

CPM-Chief Proj Manager; PM-Proj Manager; CRE- Chief Resident Engineer; RE-Resident Engineer; SE-Section Engineer; EE-Executive Engineer; PL-Proj Leader; PM- Production Manager; SM-Section Manager; RMs-Resource Managers

RMs 1,2,3,4

Proj DirDir Proj

CPM (MC)

Dy. CE

E. E.-1

PM (MC)

CRE

RE

SE Section A

SE Section C

SE Section D

SE Spl

E. E.-2

MD

Monitoring Strategy

Monitoring strategy was directed toward changing behavior of the contractor’s

organization. Hence separate measurement units for different departments such as

construction, quality, and safety, of the contractor were applied for keeping each

of them motivated and energized. Simple measurements such as volumes of

earthwork and concrete and respective S-curves were used to reflect overall

progress and controlling demand rates for achieving the target. DMRC and GC

adopted a hot and cold strategy- too harsh in the beginning even at the cost of

17

Page 18: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

progress in order to force the contractor to mobilize well to face the challenge;

cyclical harshness in the middle for course correction and lenient toward the end

pushing the progress and making the contractor succeed. A series of meetings

chaired by officials at different levels from DMRC, GC and Contractor were

structured which were attended by staff from each of them to monitor progress,

resolve complex issues and obtain commitments from each stake holder.

Production Management

At a project site, production management refers to managing the physical progress

of work so as to achieve the targeted date of completion of certain portion of

work. MC1A contractor’s production management was controlled by the

Production Manager who also managed the centralized common resources.

Pipelining on common resources helped the contractor to monitor the progress of

work and accelerate progress. Weekly concrete production and rebar fabrication

plans, sectional monthly targets, daily concreting priority list etc. helped the

contractor to create competition among the four sections and push the progress

where it could be best achieved. A reward system was initiated for sections for

achieving their monthly targets: two days extra salary if target gets achieved; 4

days extra if the target got overshot by 10%. This award was provided to every

worker/engineer/supervisor deployed in the section irrespective of whether he is

employed by the contractor or its sub-contractor. This production management

strategy was a great success. It was noticed that generally the sections focused on

preparatory works at site in the first two weeks of each month and there was

intense concreting in the last two weeks right up to the night shift of the last date

of a month.

Health and Safety Management

Health and safety management of the contractor was lead by a Health and Safety

Manager who reported directly to the head of the contractor’s team, the Project

Leader, and was independent of the Production Manager. Some basic safety rules,

like wearing helmet and safety boot were applied to everyone visiting the work

18

Page 19: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

site irrespective of his position and affiliation. Even MD DMRC visiting the site

followed this principle. Initially works had to be stopped at sites due to non-

availability of these protective equipments with the workers. This led to

inculcation of discipline which not only helped in developing safe and tidy work

sites but also generated motivation among workers and supervisors whose loyalty

was ensured to the project. An open and transparent system of reporting incidents

(not just accidents) and substandard safety practices was established in which

non-reporting of an incidence was treated more serious than occurrence of an

incidence. Focus was on taking corrective and preventive measures after

occurrence of an incidence so that its repetition and serious accidents could be

avoided. In order to institutionalize the learning from previous incidents a safety

compendium was maintained with the history and respective corrective and

preventive measures taken. This used to be discussed regularly during safety drills

and job training at site with workers and engineers. Contractor’s and sub-

contractors’ workers did have access to DMRC and GC site staff for any serious

grievance connected with payment of salary, protective equipment,

reimbursement of Provident Fund at the time of leaving the unit and

compensation for injury or fatality. This ensured minimum disruption, least

accidents, higher motivation, availability of work force and higher work output.

Quality Management

Contractor’s quality management team was headed by a Quality and Environment

Manager who reported directly to the Project Leader in a manner similar to the

Health and Safety manager. Quality management at the project was based on

conformance to the approved procedures and methodology and open and

transparent reporting of defects in works and non-conformances to such

procedures. Defects in design and permanent works were reported through non-

conformance notices while other defects were reported through site instructions

issued by the Resident Engineer to the Contractor. Once issued, each such report

had to be addressed by the Contractor through corrective and preventive measures

for enabling the Resident Engineer to agree to close the report. Closure of each

19

Page 20: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

such important report led to revision of the respective method statements and

work procedures. Contractor followed its own similar system where the Quality

and Environment Manager raised such reports and production teams had to

comply them for their closures. The practice inculcated a work culture which was

system based rather than individual based and this later helped in jacking up

progress toward the completion of the project like well laid foundation helps

jacking up run rate in slog overs of a one day cricket match. This system was

initially resisted by Indian firms who didn’t follow it earlier but was so well

received subsequently that it became the training ground for these firms. Defect

reporting was supplemented through periodic inspection schedules at all levels

starting from MD DMRC to the Section Engineer of the GC. Some of these

inspections were: RE’s daily inspection, Construction Manager’s weekly

inspection, CPM’s fortnightly inspection, Director’s monthly inspection and

MD’s quarterly inspection, weekly safety and environmental inspection,

designer’s weekly inspection, and surprise night inspection.

Traffic and Work Site Management

The biggest challenge in planning the construction was to manage the traffic and

provide a neat and tidy work environment for the workers as well as the public

commuting near the work site. The work was to be executed on cut and cover

construction methodology requiring excavation on the road itself.

Mismanagement at this front was the biggest irritant for public at Kolkata Metro

project. Even before invitation of tender, DMRC had conducted traffic studies

identifying minimum number of lanes of traffic to be maintained on each affected

road, widening of existing roads, diversion of traffic away from work site where

required, introduction of one way traffic, improvements to rotaries and

intersection etc. The Contractor was required to even widen two bridges for

allowing diversion of buses and other traffic through them. The Contractor itself

appointed head of the department of transportation of School of Planning and

Architecture, Delhi as consultant for developing detailed traffic management plan

for period before, during and after construction including phasing plan. Road

20

Page 21: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

signage system was also designed including its positioning for information to

public. Many practices were introduced at the construction site for the first time in

Delhi such as full height steel hoarding all along work site for complete visual and

physical separation of traffic from site, blinking lights on the hoarding for

guidance during night, steel decking for maintaining minimum number and width

of traffic lanes for excavation under road, traffic regulating staff at each

intersection and road diversion, security controlled access and exits at all work

sites. In one of the studies done by a city news magazine in 2003 it was found that

crime rate under the civil lines police station had gone down during the

construction phase of the project. This was attributed by the researcher to above

mentioned arrangements at the site. All the above construction practices were

copied from practices adopted in Bangkok, Hong Kong, Singapore and Japan

where DMRC and GC staff had visited for training. Now many of these practices

are being adopted by other authorities at their work sites but none of them have

been able to achieve the standard existing on Delhi Metro project.

Environmental Management

DMRC’s contract documents prepared by GC’s experts had incorporated all the

elements of environmental management system in compliance to ISO 14001. The

leading two foreign firms in the KSHI JV were also ISO 14001 compliant

companies. But these were not enough for ensuring implementation of these

requirements at site. One conversation with a Japanese Section Manager at site in

the initial days of project may be sited here: when he was asked by the author

(working as Resident Engineer on the project) why he was not ensuring the

standards followed in Japan at the work site when the Contractor was being paid

for that standard, the reply was ‘this is India not Japan, if all other contractors

work here to a much lower environmental standard then why he should be forced

to adopt international standard’. This conversation shows the importance of

international exposure for the authority’s and project management consultant’s

staff and the need for forceful compliance of these standards even from

international contractors. Had DMRC not ensured this exposure and allowed free

21

Page 22: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

hand to its project team for ensuring compliance, international standards might

not have been brought to Delhi. Some of the best working practices introduced

first time on any infrastructure project in India were: tyre washing system for

cleaning of truck tyres before it entered the public road from work site, water

sprinkling system for dust control, silent generators, and conservation of ground

water by recharging and taking it to the Delhi Jal Board’s filtration plant. The

implementation of these systems ensured that MC1A work site became the first to

get ISO 14001 certification, not only on Delhi Metro project but also on any

major infrastructure project in India during construction.

Human Resource Management

Projects are temporary organizations with large number of fresh recruits hence

there nurturing is immensely important for all the stakeholders. DMRC

acknowledged this and ensured good HR practices with all stakeholders. All top

and middle level managers/ engineers of DMRC and GC were sent to metros

around the world for training at project sites. On return they became trainers for

their junior staff. A set of training modules was prescribed for all workers and

engineers at work site. Compulsory training in construction methodology, quality

and safety management systems was imparted to all new recruits at work site. GC

used to organize such training for its own and DMRC’s staff. GC’s expatriate

managers and experts took lead in preparation and conduct of such training

modules while contractor’s expatriate staff and safety/ quality/ environment

managers took lead for training of their and sub-contractors’ staff. Contractor’s

best and most experienced brains were employed for development of management

procedures, method statements, work procedures, inspection and testing

procedures and training modules which were subsequently used for training to

local staff. GC ensured that without such approved procedure no site work could

be started.

22

Page 23: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

Managing Local Authorities

Local authorities play very important role in the success of an urban infrastructure

project. Their support in approvals, utility diversion and traffic management is

essential for the success of such project. Generally they are treated indifferently or

as adversary by the project authorities. There is a temptation to force contractors

and consultants to handle them. DMRC had a relationship of cooperation, mutual

respect and assistance with MCD, DJB, PWD, NDMC and DDA18. Some of

actions taken by DMRC in this regard are listed as: their officers were taken into

confidence in preparing relocation plans and their working contractors were

assigned the job of utility diversions, road repairs etc.; work was considered

completed only after satisfaction and official confirmation of representatives of

these authorities; retired engineers of local authorities and retired police officials

were employed by the contractor for managing utilities and traffic issues;

expertise gained at the project site in managing their utilities were shared with

them e.g. DJB got immensely benefited due to drastic reduction in block period

for diversion works on water mains by adoption of new methodology; irrigation

department was given rock fills free of cost for protection of Yamuna bund; DJB

was given additional raw water collected through dewatering process at work site

that were earlier allowed for disposal in open drains by the Ground Water Board;

group site visits were organized for each local authority with get together parties

for acknowledging their cooperation and considering them as important

stakeholders; soil filling, repairs and restoration of offices, road repairs,

improvement to utilities were some other means through which a cordial

relationship was ensured.

Managing Property Owners

Land acquisition is the single biggest reason for delays in a project. Court cases

initiated by property owners create big stumbling block in project execution.

Proactive role of the project authorities are usually not witnessed on infrastructure

projects. DMRC used various mechanisms for obtaining advance possession of

23

Page 24: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

land ahead of the legal land acquisition proceedings to avoid delay in land

acquisitions: individual deals for land use, access to property, protection to

property, providing temporary accommodation to occupants, advance

compensation etc. DMRC even agreed for negotiated settlements with individual

owners for temporary control of land for facilitating construction work.

Winning Public Support

Community interaction programs were organized every quarter near the work site

for interaction and feedback from public, property owners, commuters and other

people interested in providing valuable inputs. Such meetings were chaired by

Director of DMRC while representatives from local authorities and traffic police

were also invited. Public grievances, property owners’ and occupants’ problems,

local authorities’ suggestions were addressed in such meetings. These meetings

provided valuable inputs for improvements at work site and in traffic

management. Representatives from media used to be invited periodically to visit

the work site for explaining the construction methodology and efforts being made

to address concerns of public. Schools and colleges along the corridor were

helped with land filling in low lying play ground, construction of higher boundary

walls etc. Adjacent buildings witnessing vibration induced by construction

activity were instrumented for vibration and crack monitoring so that the

occupants’ confidence could be won and corrective and preventive measures

could be taken in time. All these ensured good public image and helped build trust

with the public.

EMERGING MANAGEMENT CONTROL FRAMEWORK

Delhi Metro Project was executed by an organization consisting of officers mostly

from IR including its MD. It is also a public sector SPV similar to many other

SPVs created by MOR for executing projects. Hence, a natural question arises as

to what was different at this project that enabled it to get successfully completed

in a record time, without cost overruns and with such wide public support.

Description of aspects of MC1A contract management provided hereabove would

24

Page 25: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

be useful for project stakeholders. But finding out management control system

existing at Construction units of IR, RVNL and DMRC would be much more

valuable learning for the Government and policy makers. A critical comparative

study of the three organizations on this framework would further help to find out

what management control should be generally applied to such project

organizations.

There could be many perspectives of looking at the management control system in

an organization. Existing literature on the subject focuses more on basic elements

such as types of goals, complexity, mode of control, focus on activity, basis of

control and the organizational structure. A lot of literature exists using these

elements. Anthony and Young, 200219, while describing the Management Control

Systems of a nonprofit organization stress on nature of organization structure,

responsibility centers, goal congruence of all responsibility centers, and fit

between programs and responsibility centers. He goes on to add that management

control is fundamentally behavioral and various tools are effective only to the

extent they influence behavior. Hofstede, 198120, states that the type of control

depends on four criteria: whether objectives are ambiguous or un-ambiguous,

outputs are measurable or non-measurable, effects of management intervention

are known or unknown, and activity is repetitive or non-repetitive. He suggests

six types of management control: routine control, expert control, trial-and-error

control, intuitive control, judgmental control and political control; based on

whether one or more of the criteria doesn’t satisfy the first alternative mentioned.

Anthony and Young, 2002, also state that Management Control System depends

on external environment of the organization. The external environment for a joint

venture SPV between state government and central government is different from

that of a state government or a central government SPV. Similarly the external

environment of the Construction unit of IR would be different from that of an

SPV. Similarly, the internal environment in a project organization which has to

operate train services too on completion of project (like DMRC) would be

different from a purely construction organization (like RVNL). Harrison and

Lock, 200421, suggest three critical systems of project management: Organization,

25

Page 26: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

Planning and Control, and Human Systems. They state that a project manager,

working in a matrix organization (like Railways), cannot be complete master of

decisions affecting the project. Such manager must operate in a decision making

matrix. They further state that in a pyramid structure (that of Railways) ‘Authority

Gap’ or ‘Responsibility without Power’ is common and is not conducive to

project implementation. Based on these literatures and his own experience in IR

and DMRC, the author proposes a new Management Control System for project

organizations having following critical elements:

• Leader

• Organizational Structure and Work Culture

• Project Management Consultancy

• Contracting Framework

• Responsibility Triangles

• Monitoring System

• Buffer Management and System Review

The Managing Director of the SPV is the Leader who plays the nodal role in the

control system. The SPV being a new project organization the Leader has to build

it and its work culture suitable for delivering the project in time and within

estimated cost. A new organization is neither experienced nor adequately

equipped to handle the project management on its own. Hence it has to hire either

a single project management consultant (general consultant) for the entire project

or several project management consultants, one for each major contract for

bringing in required expertise and experience in project management. Contracting

is the mode of transaction through which a project is executed. There are different

contracting models for executing the entire project as a whole or various parts of

the project and the selection of the contracting model depends on several

important parameters. The SPV must have a rich contracting framework for need

based usage for fulfilling its overall objective. The next important element in

project management is the allocation of responsibilities within the organization of

the SPV and among SPV, project management consultant and contractor. This is

26

Page 27: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

the nervous system of the management control system which ensures coherent

actions at all fronts and that each stakeholder plays its role to the fullest. It is often

said that the day a project schedule is made it starts slipping. Hence the Leader

must have a monitoring system built in the contracts through key dates and

buffers and their adherence being watched through a full proof mechanism.

Monitoring provides information about the health of project which has to be

properly acted upon by various stakeholders through a mechanism called buffer

management including recovery and encashment of buffers in order to achieve the

project goal. A review of the management control system along with the buffer

management is necessary to safeguard against slackness or undue bureaucracy

creeping in and also to continually improve the control system for the changing

circumstances and new projects/ contracts. This entire relationship between the

seven critical elements of the proposed management control system for an

infrastructure project SPV is shown in the control cycle in Exhibit-5.

Organizational Structure and Work Culture

Responsibility Triangles

SPV Board of Directors

Leader

Leader

Lea

der L

eader

Contracting Framework

Project Management Consultant

Monitoring System

Buffer Management and System Review

Exhibit-5

27

Page 28: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

In order to elaborate each of the above elements the management control of the

three project organizations, Construction unit of IR, RVNL and DMRC were

analyzed on this control system. The result has been described hereunder.

EVALUATION ON THE PROPOSED MANAGEMENT CONTROL

SYSTEM

The Leader

Project organizations, being temporary organizations created for a specific project

or a set of projects, are most affected by the quality of leadership and

independence and liberty given to him for achieving the project objectives.

Hofstede, 1981, suggests political control when objectives are ambiguous. A new

organization created for specific project(s) has a clear objective of completing the

project(s) in time and within estimated costs. However there exist conflicts of

perceived interests and/or values due to people coming from different

background; lack of knowledge about means-ends relationships due to

inexperience in the organization and internal environmental turbulence vis a vis

relationship with the external environment in the Government and Ministries.

Each new project organization looks toward the leader who could give direction

and structure the organization in a way that reduces the internal turbulence by

creating a balance with the external environment and yet achieves the

organizational objectives.

All major infrastructure projects in India, including Delhi Metro, Kolkata Metro

and Konkan Railway were sanctioned after prolonged studies and several

feasibility reports. Such studies were carried out by the existing government

bureaucracy and even the consultants were not sure at the time of preparation of

the report whether the project would actually get started. Hence, once the project

is sanctioned the Leader of the organization which is going to implement it should

be allowed to review the Detailed Project Report (DPR) of the project so that the

failure of the project should not be blamed on the DPR at all. Right from

identification of a project till commissioning of railway line there are several

28

Page 29: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

layers of planning and coordination which are not directly under the control of a

CAO. Hence such review is not possible in Construction units, but certainly it is

possible to some extent in RVNL.

If we look at the construction organizations in the IR, CAO is the leader. Let us

analyze his position, power and responsibility. The CAO doesn’t have a fixed

tenure and on an average an officer may work as the CAO of a particular

construction unit for two years. He works at the pleasure of Member Engineering,

who is the member-in-charge in the Railway Board for all railway projects.

However for all administrative purposes he works under GM of the zonal railway.

This is typical example of a matrix structure where dual control exists over CAO.

Generally during the construction life of a project several CAOs might head the

construction unit. No major project could be identified with one CAO except

smaller projects that might have a short construction life. A CAO’s performance

is judged in a comparative sense vis a vis his predecessor’s. In true sense a CAO

is more of a bureaucratic head than a leader.

Many people question why Dr. Sreedharan wasn’t so successful while he was

serving IR where he reached the top position of Member Engineering in the

Railway Board before he took the reins of Konkan Railway Corporation (KRCL)

as Chairman and Managing Director. Dr. Sreedharan continued with the KRCL

till the project was almost complete. Both KRCL and DMRC projects were

identified with one leader till the project was complete. In both the organizations

Dr. Sreedharan was among the first employees joining the new SPV. He obtained

complete freedom, as a pre-condition of joining the organization, to select his own

team of functional Directors and other senior officials, creating his own

management control rather than copying the existing models. It is interesting to

note that the Chairman and Managing Director’s post now stands removed from

KRCL and Member Engineering, Railway Board is the ex-officio Chairman of the

SPV. Dr. Sreedharan further got the liberty of reviewing the DPR in DMRC

which resulted in identification of better corridors, adoption of different

contracting framework and selection of latest technology for implementation of

29

Page 30: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

the project. For the purpose of providing a glimpse of the result of such reviews

the contract packaging in DPR and that adopted by DMRC for u/g metro corridor

is shown in the Exhibit-6.

Exhibit-6

DPR Stage Actually Adopted by DMRC

• 10 Civil Structure Contracts.

• Construct Only.

• Tender Documents are prepared on the basis of traditional multi-contract implementation Strategy

• Several E&M Contracts

• Several Ventilation/AC Contracts

• Two Contract MC1A & 1B.

• Design & Construct

• The Packaging is done based on proposed method of construction i.e.(Cut & Cover vs Tunnel Boring)

• Civil Engg. Electrical & Mechanical, Lighting(AC & Ventilation) all combined.

Compare this with RVNL, where during the last five years of existence of the

organization, two MDs were posted. Further the MD didn’t get the freedom in

selection of either functional Directors or other senior officers, who are actually

selected by Public Enterprise Selection Board and the Railway Board

respectively. Within the Railway Board too, officers from different departments

are selected by the respective Members of the Board. MD has full freedom in

matters relating to how the project is going to be executed but not in matters

relating to the creation of organizational structure, work culture, procedures,

financing, long term Concessioning or maintenance of the project etc. The Board

of Directors of the company is mostly guided by the Railway Board’s policy or

the existing policies in other railway PSUs in respect of company matters and

Chairman22 and part time government Directors have upper hand in these

matters.

In order to know how Dr. Sreedharan used his leadership to create new

organizational structure and work culture in KRCL and DMRC, let us look at his

dynamic style of management listed out in following points23:

30

Page 31: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

• a unique corporate mission and culture with the sole thrust on creating a

world class metro

• fast track decision making process

• discouraged paper work and relied more on meetings for decision making

• ample delegation of power-accountability with power

• redefined the role of finance- made it equally accountable along with the

executive for project’s success

• kept himself constantly in touch with officers and staff-sets an example

himself

• fear of audit and vigilance not allowed to cramp the executive’s working

• led from the front and not pushing from the rear

• no political or bureaucratic interference allowed in decision making

• reviewed the DPR and made the corridors more people friendly and

changed the contract packaging to his choice

• built a slim but effective officer oriented organization eliminating

ineffective layers such as clerks, peons, and assistants

• selected officers of his choice preferably outside from Delhi who came not

for being in Delhi but for performing

• screened even railway officers posted in GC

• placed high premium for integrity- officers with doubt sent back to their

parent cadres overnight

• field staff irrespective of rank wore uniforms and protective gear

• discouraged witch hunting for genuine mistakes-owned the mistaken

decisions of officers

Success of any project depends largely on the success of contractors deployed.

But there are always disputes between the authority and contractor on various

31

Page 32: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

matters. In such cases, the MD of a project SPV must be seen by the contractor as

a neutral adjudicator rather than a party to the dispute. Contractor must be assured

of fair deal in the form of appeals at higher levels for any grievance. MD, DMRC

had positioned himself as a neutral and highest appellate authority and each

contractor had full faith in him. MD used to have periodic review meetings with

the senior management representatives of the constituent firms of the Contractor.

He also used to meet the Project Director of GC and heads of other consulting

firms periodically to address their concerns and at the same time impress upon

them the need for better mobilization at site for achieving the progress. This is the

reason that most of the contractual disputes were resolved through reconciliations

and only few arbitration proceedings were initiated.

Organizational Structure and Work Culture

Anthony and Young, 2002, state that management control function of non-profit

organizations is affected by external and internal environment. A project

organization’s ownership greatly determines this external environment. The

external environment of a CAO’s unit is determined by its relationship with the

Open Line organization of the IR. RVNL being a fully owned GOI SPV under the

MOR, its relationship with the Ministry and the Open Line is different from that

of a CAO’s unit. DMRC being a 50-50 joint venture between Delhi Government

and GOI (under Ministry of Urban Development) its external environment is

totally different than that of RVNL. Flexibility and independence that DMRC and

its MD enjoy could be attributed to a great extent to its typical positioning in

which neither the State Government’s bureaucracy nor the Central Government’s

bureaucracy could significantly influence its internal environment. KRCL is also

a joint venture of the governments of the four beneficiary states of the Project and

the GOI, however state Governments jointly owned only 49% of the shares

whereas GOI owned 51%. This is the reason why KRCL is completely under the

control of MOR and state governments have only nominal say in its affairs. If we

compare the organizational positioning of the above three SPVs, DMRC is the

best placed followed by KRCL and RVNL in that order.

32

Page 33: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

Zonal Railway’s Open Line organization’s prime responsibility is to operate and

maintain the railway system and carry passengers, goods and parcels safely and

efficiently. That is the prime reason for creation of dedicated Construction units

for faster project execution. The organization has the same departmental hierarchy

as prevalent in Open Line. But as the Construction unit is under one head, CAO, it

is a cohesive multidisciplinary unit having common objective of executing

projects faster. It has a leaner organization and as described in para 2 a better

work culture than the Open Line. In terms of Harrison and Lock, 2004, the

organizational structure is more like project matrix24. The unit doesn’t have any

freedom of hiring staff, selecting officers, arranging trainings or giving

promotions. These units being temporary project units, all the posts are temporary

in nature and charged to project estimates hence the staff and officers work under

their Open Line cadres without having any prospect of any higher service benefits

on account of performance. Senior officers work for uncertain tenures in these

units as their transfer and postings are controlled by either the Open Line or

Railway Board by the respective departments. The departmental culture is visible

even in the contracting system as each department under the CAO does its own

contracts for separate elements of the project. This perpetuates the

departmentalism further and the opportunity of reaping the benefit of a real

multidisciplinary team is lost. There are many projects where civil engineering

element has been completed but S&T or Electrification elements are not complete

due to either contract not awarded or failure of the contractor. Vice versa also

occurs in other railway projects. If a contractor fails to perform, the CAO has to

follow the government and Central Vigilance Commission rules for hiring another

contractor that is focused more on process rather than timely project completion.

However the biggest visible value addition is in the functioning of finance

department, which in CAO’s unit has joint responsibility and ownership in the

project’s success thus facilitating speedier decision making.

RVNL has a comparatively much leaner organization than the CAO’s unit and has

a corporate structure. It has a staff strength of 350 which is way below the staff

strength (2018) of CAO/ Chennai whereas its project expenditure in 2007-08 of

33

Page 34: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

Rs. 1422 crore was much higher than the CAO’s expenditure of Rs. 899 crore.

But the departmental segregation of IR is still visible. Functional Directors:

Director Project, Director Operation, Director Personnel and Director Finance are

all representing their respective departments: Civil Engineering, Traffic,

Personnel and Finance respectively. As against this, DMRC’s organizational

structure to some extent has demolished the departmental culture of Railways.

The functional Directors in DMRC are: Dir Project & Planning, Dir Works, Dir

Operation, Dir Electrical, Dir Rolling Stock and Director Finance. The present

incumbent on Director Operation is an S&T officer from IR whereas Dir Finance

is a non-Railway officer. In spite of a larger and older organization than RVNL,

DMRC is still a flat organization with no intermediate layer between Dir and

CPM, whereas such a layer now exists in RVNL.

There is much better work culture, empowerment and tender practices in RVNL

than those in Construction units. GM of a zonal railway has the power to accept a

tender for work costing Rs. 100 crore whereas MD RVNL has unlimited powers.

CPM of the RVNL has Rs. 15 crore open tender power. Stores procurement in

Construction organization is through Stores department of Open Line whereas a

CPM could procure stores up to Rs. 10 lakh through quotation which is a much

faster process. All tenders are invited on two packet system with separate

technical and financial bids as against one packet system in practice on

Construction units. Good contractors are attracted to work in RVNL as they get

faster payment and have to deal with leaner project team and neutral PMC.

With the passage of time RVNL is becoming more bureaucratic and procedure

oriented. In this process it has a danger of coming closer to the Construction units.

With many railway projects to execute, project execution might just become a

routine work rather than a mission. Some examples cited by CPM Chennai in his

interview are: earlier field units in RVNL were empowered to go for single and

special limited tenders but now they could call only open tenders; earlier one

combined contract used to be awarded for Engineering, S&T, and Electrical

works for a project, but now with the increase in number of officers from S&T

34

Page 35: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

and Electrical departments in RVNL there is increased demand for separate

contracts for each discipline on the same project. There is a genuine chance that in

near future RVNL may completely stop calling one composite tender for a

railway project.

Biggest change witnessed in the work culture of DMRC vis a vis IR and RVNL is

the demolishing of departmental culture. This was possible through the use of

following:

• Use of multi discipline composite contracts like MC1A and MC1B;

• Reducing the number of departmental hierarchy up to the top to only

three: Civil engineering, Electrical engineering and Finance;

• Making operation as a general cadre, which officers from any

department can join;

• Filling the top finance posts (Director and GM) from outside Railways.

DMRC’s corporate culture25 has following important expressions that reflect its

organizational structure and culture:

• The Organization must be lean but effective;

• Our construction activities should not inconvenience or endanger public

life nor should lead to ecological or environmental degradation;

• The Corporation must project an image of efficiency, transparency,

courtesy and “we mean business” attitude;

• Our staff should be smartly dressed, punctual, polite and helpful to the

customers;

• Employees should discharge their responsibilities with pride, perfection

and dignity.

In contrast to above the Corporate Vision, the Corporate Mission and the

Corporate Objectives of RVNL26 contains just one sentence toward its

35

Page 36: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

organizational structure and culture: ‘To maintain a cost effective organizational

set up’. Lot of lessons should be learned from DMRC, which established a work

culture to which every engineer now wants to be a part of.

Project Management Consultant

Project management consultant (PMC) is nowadays an essential element in any

infrastructure project. It is widely in use in highway sector and gradually being

adopted in other sectors. There is no such practice existing on IR and there is an

acute shortage of officers up to Junior Administrative Grade and supervisory staff,

whereas number of sanctioned and ongoing projects is increasing year after year.

There is also increasing need for packaging bigger and multi-departmental

contracts, as described hereabove, in order to avoid multiple numbers of contracts

on the same project. This has increased the burden of supervision, planning,

procurement, tendering, measurement, billing, progress reporting, quality and

safety monitoring in the Construction organization. At present, CAO’s unit has to

carry out all these roles departmentally without any assistance from any

consultant. As it predominantly awards Item Rate Contract, its supervisory force

is mostly pre-occupied with measurement and billing with hardly any time left for

expediting progress, checking safety or controlling quality at site.

There are broadly two types of project consultancy practices existing in India. The

first one is contract specific PMC that is being used in highway projects. RVNL is

also using this type of PMC. Success of RVNL in achieving higher productivity

with lesser number of railway staff has been largely due to such PMCs. PMC

assists the RVNL in progress reporting, safety and quality monitoring, and

measurement and billing. Adoption of contract specific PMC on the Construction

units would mean a large number of PMCs, which will become unmanageable.

The second type of PMC is project specific, where one PMC is appointed for all

the contracts on the project. This type of PMC, also known as general consultant,

was used in DMRC. This practice is useful only when the Organization has been

specifically created to execute one large project. General Consultant of DMRC

36

Page 37: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

played a crucial role in reviewing the DPR, designing the Systemwide contracting

framework, managing the international biddings, developing the contract

management system and monitoring framework, and bringing in and dissipating

international expertise in India for the phase-I of the Delhi Metro project. It is the

acknowledgement of this key role played by GC in its success that DMRC has

awarded the general consultancy for the phase-II also to the same consortium.

Acknowledging the role of PMC, Railway Board has constituted a committee of

senior officers for suggesting a PMC model suitable for CAO’s unit and

developing model tender document for its selection. CAO’s unit handles many

railway projects of varying sizes simultaneously and there are more than one

contract for a project. Hence neither the contract specific nor the project specific

PMC would be suitable. Hence a new model has to be designed as hybrid between

the two. A new organization specific PMC is being devised for construction

organization, in which one PMC would be there under each CAO, working across

many contracts and projects.

Contracting Framework

Contracting is the mechanism through which an organization approaches the

construction market and hires a contractor for executing a project or part of a

project. There are various types of contracts and various ways of selecting a

contractor. The choice of contracting depends on the objective of the project

authority which could be any or a combination of following:

• Faster Construction

• Smaller number of Interfaces

• Less Intensive Supervision

• Project Financing or part funding of project

• Lower Life Cycle Cost

• Superior Asset Reliability

37

Page 38: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

• Less Frequent Maintenance

• Lower Maintenance Duration

Based on the degree of risk allocation to the contractor, contract structures could

be classified as shown in Exhibit-7.

Item Rate Contract

Build to Design Contract

Design and Build Contract

Design, Build and Finance Contract

Design, Build, Finance and Maintain Contract

Increasing Degree of Risk allocation to Contractor

Exhibit-7

Project authority’s supervision, planning, monitoring, coordinating and

interfacing efforts reduces as the risk allocation to contractor increases.

Item rate contract is the oldest form of government contracting in India in which

tender is based on percentage above or below quote by bidders on a pre-drafted

schedule of rates for various basic elements like various types of earthwork,

various types of concreting, numerable building fittings etc. Contractor does work

as per the direction and drawing of the government authority and payment is

made on the basis of quantity of each item of work so executed by the contractor.

Scope of contract is defined only in terms of name and approximate value of

work. Build to design is a contract in which tender is invited for rates of specific

work which is already defined and designed, such as standard unit of residential

unit, each girder/ column/ pile of a viaduct, each ton of steel girder etc. In design

and build contract the designing responsibility also lies with the contractor and

tender is either on a lump sum cost basis or per unit floor area, per meter of span

of bridge, per unit length of tunnel etc. Payments to the contractor in ‘Build to

Design’ and ‘Design and Build’ contracts should be made on milestone basis such

as completion of certain percentage of floor, wall, roof, completion of work etc.,

which avoids the tedious work of measuring each element of work. Other two

38

Page 39: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

contract structures involve additional responsibility on the contractor for

financing and maintaining the project assets as the case may be.

Construction units on IR generally use the age old Item Rate contract. Tenders are

called even before design begins. This is the reason the contracts are smaller in

size, ill planned and each technical department does its own contracting as they

have different schedules of items. RVNL has freedom in selecting contract size

and type. Usually bigger and multi discipline contracts are awarded by it. But they

also follow same item rate contracting mode as is being done by the Construction

units. However DMRC has gone for judicious selection of contracting structures

based on certain specific objectives:

• ‘Item Rate’ for site preparation and miscellaneous works, where work is

not defined in advance.

• ‘Build to Design’ for elevated corridors where standard design of girders

are being used.

• ‘Design and Build’ for the first two under ground metro contracts MC1A

and MC1B.

• Subsequent underground metro contracts of Phase-I on ‘Build to Design’

• Under ground contracts in phase-II on ‘Design and Build’

• ‘Design, Build, Finance, and Operate’ Concession for Airport Line

excluding civil structure, which is being done on ‘Design and Build’

contract.

Let us analyze DMRC’s strategy in contract selection for under ground metro

corridors. It adopted Design and Build contract for MC1A and MC1B contracts to

place the design risk on the contractor due to lack of experience in handling

tunnel design separately. However after the experience of MC1A and MC1B

contracts, DMRC gained the required experience and it went for Build to Design

contracts in subsequent contracts in Phase-I. However in the second phase in

order to meet the deadline of commonwealth games in 2010, volumes of work and

39

Page 40: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

hence number of contracts increased hence it again adopted Design and Build

contract for reducing its own supervision work load. It adopted PPP

Concessioning for Airport Line in order to put the commercial and operational

risk on the private concessionaire and went to build the civil infrastructure, where

it had enough experience, with its own money. Even with Design and Construct

Lump Sum Contract it used provisional sums for paying for uncertain items of

work such as architectural finishes, utility diversions, art works etc. Risks on

these were better managed by DMRC so the contractor was allowed payment on

actual basis with certain percentage mark up for its overhead and only indicative

costs were provided in the contracts against each of these items.

Responsibility Triangles

Any mega infrastructure project’s success depends on three most important

stakeholders: project authority, contractor and PMC. They have already been

described in previous paras. But another important management control element

is the allocation of responsibility of project management among the three. This

relationship could be explained in terms of Responsibility Triangles for CAO’s

unit, RVNL and DMRC as shown in Exhibit-8.

PMC

AuthorityAuthority

PMC

Design Consultants

Contractor

CAO

Contractor

RVNL

Authority

Contractor

Exhibit-8

DMRC

The existing CAO’s unit doesn’t have a PMC, however in technically complex

projects there are design consultants who prepare design for the project and plays

a minor role of managing design changes during project execution. The contractor

has minimum responsibility of project management and this is entirely borne by

the authority. Existing system doesn’t make the contractor responsible for any

40

Page 41: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

poor quality work or errors in measurement after the work has been paid by the

concerned authorities. The engineers and supervisors are liable for such

deficiencies and they are under constant threat of vigilance and audit for the same.

RVNL has allotted the responsibility of billing, measurement, quality, safety and

progress reporting on the PMC. Hence all its project management responsibility is

equally shared with PMC. However contractor’s responsibility is almost left

unaltered as compared to the CAO’s model. But the biggest concern in this model

is lack of deterrence against wrong measurement, sub-standard work and unsafe

practices by the PMC staff. The PMC contract value is hardly 2 to 3 % of the

project cost, hence its security deposit (maximum @10%) is barely 0.2 to 0.3% of

the project cost. With this meager deterrence, the problem of accountability &

rent seeking among PMC personnel cannot be tackled.

DMRC adopted an ideal model in which it allotted the responsibility of project

management equally among the three stakeholders as following:

Project Authority

• Payment, Variations and other contract management issues

• Planning, procurement and tendering

• Overall responsibility

Contractor • Contractor’s own Safety and Quality monitoring

• Monthly Progress Reporting

• Measurement and Billing

PMC • Safety and Quality monitoring

• Parallel Progress Reporting

• Checking of measurement and bills

• Assist Client in planning

In this model, the contractor is required to have its own system and organization

for safety and quality management. Progress reporting, measurement and billing

are also carried out by the contractor, who is primarily responsible for these

41

Page 42: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

activities. At the same time, PMC would be counter checking all these activities

including submissions of contractor. By this arrangement, contractor’s

responsibility increases, for which he is properly incentivized by quick release of

70% of billed amount (within 3 days of submission of bill). The facility of quick

payment is withdrawn in case of detection of fraudulent or over billing. This

ensured proper discharge of the responsibility by the contractor and at the same

time left the DMRC with energy and resources that was applied in coordination

with local authorities, addressing the concerns of public and arranging prompt

land acquisition to facilitate the successful project execution.

A government construction organization consists of three important structural

elements: Leader, System and Individual; who share among them the risks of

misjudgement in award of contract, poor quality of work, error in payment to

contractor, and physical progress at site. It will be interesting to see how the

responsibility triangle looks like among these three: CAO’s unit, RVNL and

DMRC (Exhibit-9).

DMRC

Individual Individual

Leader Leader

CAO System

RVNL

Leader

System

Individual

System

Exhibit-9

CAO’s unit is functioning mostly on individual’s responsibility and accountability

in all the above mentioned risk elements. The leader has hardly any accountability

for any of these except in individual capacity when he is accepting the tenders.

There is hardly any credible system for ensuring these aspects on the project.

Even in cases where a tender is examined by a tender committee, individual

tender committee member is responsible for any misjudgement. Hence the

individuals behave in a way that would safeguard him from any future vigilance

42

Page 43: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

cases and organization’s objective takes a back seat in his mind. At RVNL, due to

an improved system and greater power and flexibility given to the leader, the

responsibility triangle is a balanced one. However in case of DMRC, the system is

more robust and the Leader takes maximum responsibility, even owning the

mistakes done by an employee during course of honest discharge of duty. Fear of

vigilance is never allowed to restrict the ingenuity and initiative of an employee in

DMRC. Hence the organization delivers much better.

Monitoring System

Common practice in project management in Government sector is resource

efficiency, i.e. the cheapest cost. But this leads to stretching of project resulting in

delays that causes more cost. Current trend in modern project management

practices is to pursue time efficiency which reduces the cost of tied up money,

avoids cost overruns, and gets early revenues and higher returns. Time efficiency

could be achieved only with an effective monitoring and buffer management

system. The project monitoring system should be able to provide timely warning

of the project slippages from its schedule, have reserve resources and alternative

solutions to enable the project authority and the contractor to take suitable

remedial measures to recover the lost ground. Hence each project contract should

be structured with a series of key dates in such a manner that it provides spare

time, known as buffer, to the authority at strategic locations. Exhibit-10 shows a

typical infrastructure project having three contracts linked together.

Buffer

Critical Chain = L Buffer = L/2

KD 6

Chain -1

Chain - 2

KD 1 KD 2 KD 3

KD 4

KD 5

Exhibit-10

Commissioning

43

Page 44: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

KD1, KD2 etc. are the intermediate key dates for a contract represented by the

horizontal bar which is the critical chain in the project network. The two inclined

bars represent two other contracts that are joining the horizontal bar at KD4 and

KD5 respectively. These two contracts would also have similar key dates, which

are not shown in the exhibit for keeping the diagram simple, with the completion

date or an intermediate key date matching with the KD4 and KD5. In order to

have an effective buffer management for each contract, a buffer equal to one third

to half the length of the chain (contract completion duration) should be kept. If the

loss of the three buffers, represented by slippage in each key date, is monitored

and timely corrective measures are taken commissioning could be achieved in

time or before time.

Exhibit-11 shows the list of important Key Dates of MC1A contract whose

description has been presented earlier in the paper.

Exhibit-11

Key Date Description of Key Date

KD1

KD5

KD8A

KD8B

KD8C

KD9

KD10

KD11

KD12

Preliminary Design 14 Weeks

Definitive Design 39 Weeks

Hand Equipment Rooms to SYS01 & SYS02-113 Weeks

Hand Concourse to SYS04 –155 Weeks (70%), station complete

Handover Basic Structure to SYS 05-120 Week

Hand Track way to SYS 03 – 120 Weeks (54%), tunnel complete

Power on to Station/Tunnels – 186 Weeks

Handover for Integrated Testing-193 Weeks

Completion of Works – 218 Weeks

In the above exhibit, SYS01, SYS02, SYS03, SYS04 and SYS05, are Systemwide

contracts for signaling and telecommunication, over head power, track, fare

collection, and escalators and lifts. They are called Systemwide contracts because

they are common for all corridors and they interface with every civil contract.

Each of them represents a specific technology which should be common for the

44

Page 45: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

entire system of the metro. These SYS contracts interface with the MC1A

contract at KD8A, KD8B, KD8C and KD9. These are not the completion but the

beginning of field work at site by the respective contractors. In this project

commissioning of MC1A contract (KD12) coincides with certain other key dates

of each of the Systemwide contracts. In order to feel the hidden buffer, let us

compare KD8B with KD12. On KD8B tunnel and all four stations should have

been completed except for architectural finishing. Between KD8B and KD12

there lies 63 weeks (30% of project duration). Whereas the actual work involved

in testing and commissioning was done in one third of this time.

Project monitoring for MC1A contract was carried out at two levels; at corporate

level the project was monitored through Key Dates keeping watch on various

contracts simultaneously. At contract level the project was monitored through

milestone schedules and periodic primavera charts submitted by the contractors.

Contrary to this, project monitoring in the CAO’s unit is overloaded in terms of

taking measurements of work done at site, making payments and arranging

railway supplied materials to the contractors. For a typical new railway line

project rails, concrete sleepers, points and crossings, track fittings, ballast and

such other important constituents are arranged through different sources and most

of them are centralized at Railway Board or Open Line level. Even movement of

these materials up to the site is done through railway system which requires

enormous monitoring and coordination efforts. There is hardly any time or staff

left for monitoring quality and progress of the actual physical works at site. The

departmental staff is ill-trained in modern project management practices and there

is hardly any involvement of professional project management consultants in this

work. Moreover contracts have no intermediate key dates for monitoring the stage

completion of project and the contract has just one date of completion. Penalties

are linked to the delays after the completion date. Hence until the completion date

expires and the project actually gets delayed there is hardly any systematic

mechanism for expediting the work. But in most of the cases the delays cannot be

attributed to the contractor solely as railway fails to meet its own part of

commitments.

45

Page 46: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

Even RVNL contracts don’t have intermediate Key Dates. There is no concept of

milestone payments hence neither corporate level nor contract level monitoring

framework is available. Still due to the assistance from PMC and committed

availability of funds, projects are completed faster by RVNL as compared to the

performance of CAO’s units.

Buffer Management and System Review

After the intermediate key dates and buffer, the next important element for

achieving project goals is buffer management. The basic input to enable this to

work is the visible implication of a day’s delay to the authority and the contractor,

which must be known to every worker and engineer working on the project. The

implication in the Delhi Metro project phase-I was laid down as following:

• To DMRC

o Each day that the project is delayed, the cost goes up by Rs. 1.4

crore due to inflation and DMRC gets deprived of Rs. 89 lakhs of

net revenue

o Each day saved will benefit the city to the extent of Rs.4.5 crore in

terms of fuel saved & other social benefits

• To MC1A contractor

o 0.005% of contract price every day (Rs. 5 lakh) if a Key Date is

missed but refundable when subsequent Key Date is achieved.

In order to spread the importance of each day and as a constant reminder to

everyone electronic project clocks placed at strategic locations and all offices

continued showing the number of days left to commissioning.

For any infrastructure project, delays are rule rather than exceptions. As soon as a

contract is signed and a schedule is prepared the project starts slipping. Exhibit-2

shows the actual concreting progress during the first few months of concreting,

which is shown below the planned S-curve. Projects seldom go from success to

46

Page 47: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

disaster overnight. Most projects are behind schedule from day one. The

important aspect of Management Control System is to get these early warning

signs and required actions should be taken. Let us look at what corrective actions

MC1A contractor took to manage the slippages:

• Revising the construction methodology

• Taking up parallel works by abandoning earlier planned phasing

• Introducing night shift

• Deployment of additional sub-contractors

• Deputing senior management representative during night shift

• Simplifying temporary works using the experience gained at site

With each slipping day, the demand rate of concreting became higher and revised

S-curve became sharper and sharper. DMRC and GC’s project team forced the

contractor to think of new solutions for catching up the progress. The contractor

failed to achieve KD8A and KD9 resulting in levy of penalties for each passing

day. At one point of time the cumulative penalty deducted from contractor’s bills

had become more than Rs. 15 crore. Contractor was forced to decide on higher

resource mobilization in order to save the losses and even get repayment by

achieving next Key Date.

DMRC utilized the buffer kept in testing and commissioning as described above.

It had strategically started the construction on elevated rail corridor between

Shahdara and Tis Hazari, without the project management of GC, quite ahead of

beginning of works in metro corridor. This allowed it to gain experience in testing

and commissioning of various systems, which helped it to target big reduction in

time of this activity on MC1A contract. The project management team negotiated

with the contractors for finding a solution through which a win-win solution could

be achieved for all contractors as well as DMRC. As part of this solution MC1A

contractor was allowed to provide phased access to the SYS contractors; partial

opening of stations was agreed so that the train services could be started with

47

Page 48: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

minimum amenities; already expired Key Dates were rescheduled as a

compromise for preponing of the final commission date; penalties already

deducted was refunded; and finally DMRC even agreed to offer some cash

incentive for such preponing as a compensation for mobilizing additional

resources. All these buffer management initiatives helped to commission the

MC1A line on 18th December 2004, about seven months in advance of scheduled

date of 25th July 2005.

Buffer management is non-existent in the CAO’s unit due to multiple reasons

such as non-availability of intermediate key dates in the contract, lack of direct

correlation between the delays in completion of project and the losses to railway,

lack of freedom in taking special measures to recover the lost time. As hundreds

of sanctioned project vie for attention and fund, Railway Board’s objective is to

find out which and how many projects could be commissioned in a particular year

against that year’s budget allocation. Hence if a particular project slips, another

one might get higher attention to achieve the annual target of commissioning new

lines and spending the allocated fund.

The existing procedure for contract management in RVNL doesn’t allow the type

of negotiated arrangements for catching up the slippages and preponing of the

contract completion date as seen in DMRC. Further due to multiple project

portfolios and no clear financial implication of delay or preponing there is hardly

need for any such strategic measure.

With the commissioning of a project or a part of the single project, the SPV

leadership should review the elements of the existing management control system

and make necessary changes in it prior to beginning the next project or part of the

single project. Such changes might either be to guard against complacency or to

benefit from the past experience. Such system reviews were inherent in DMRC

and they resulted in decisions such as: which contract type to adopt; whether to

involve GC or carry out project monitoring by own team; whether to involve GC

in selective aspects of the project requiring higher expertise; deploying new field

48

Page 49: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

units; review of organizational issues etc. As commissioning of various corridors

used to take place once or twice every year, such system reviews were taking

place on almost regular basis. This is one of the important reasons why DMRC is

still delivering projects ahead of scheduled time even in phase-II of the Delhi

metro project in spite of the organization getting older. In case of Construction

units of IR such system review is centralized at the Railway Board level and is

done for all Construction units on IR. At RVNL this is reflected through changes

in schedule of powers, organizational structure and in decision- whether contract

for a new project should be multi-disciplinary or not. As discussed hereabove,

changes in RVNL so far hasn’t helped in faster execution of projects rather it has

made the procedures more cumbersome and organization more bulky. SPV should

be cautious while tightening procedures to check malpractices as it might be

detrimental to the faster execution of projects.

Key findings of the evaluation of the three project organizations studied

hereabove have been summarized in Exhibit-12. This also contains

recommendation for Management Control System for an SPV created for

executing infrastructure projects.

Exhibit-12

Characteristics Construction Unit of IR

RVNL DMRC Suggested for SPV

Leader

Fixed Tenure No 3 years 13 years till year 2010

Not less than 5 years

Authority to review DPR

No No Yes Yes, in order to transfer full accountability for the success of the project on Leader

Freedom to select team

No Limited Maximum Necessary for effectiveness of the Leader

Adjudication for Contractual Dispute

Partly Partly Fully Contractor should see him as a Neutral Adjudicator

Organizational Structure and Work Culture

Positioning of SPV

Tied to Open Line Organization

Tied to MOR and IR Equidistance from GOI and State Government

If JV, 50:50 ownershipbetween GOI and State, otherwise have leader as CMD

49

Page 50: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

Characteristics Construction Unit of IR

RVNL DMRC Suggested for SPV

Operational Responsibility

No No Yes Desirable for SPV

Size of Organization

Leaner than IR Leaner than Construction Unit

Leaner finance, HR and operation in project phase than RVNL

Project phase must have very lean finance, HR and operation departments

Departmentalism Maximum Lower than Construction units of IR

Minimum Break the departmental structure of the sponsoring Ministry

Layers Flatter than Open Line

Flatter than Construction Units

Flatter than RVNL Heads of field units should directly report to functional directors

Corporate work culture

No Minimal Maximum Should have overt and dominant

Power Delegation

Lower, butincreasing year after year

Higher than Construction Units

Similar to RVNL Liberal power delegation to cutting edge executives ensures accountability.

Project Management Consultant

Availability No Yes, in every project For selected corridors/ contracts

Should be integral part of the control system

Type N.A. Contract specific General Consultant Single Project SPV- General Consultant Multi Project SPV- Contract Specific Construction Units-Organization specific

Contracting Framework

Spectrum of Contract structures

Only Item rate Contract

Only Item Rate Contract

Four contract structures

Should have full spectrum from Item Rate to Design Build Finance and Maintain

Risk allocation mechanism

Only price variation clause

Only price variation clause

Price variation, provisional sum and different contract structures

Should use wide range of options for optimum risk allocation among SPV and contractor

Multi-disciplinary contracts

No Yes, but decreasing trend

Widely used Should use for leaner organization, better work culture and checking departmentalism

Responsibility Triangles

Distribution of project responsibility

No PMC, heavily loaded on project authority

Equally heavily loaded on RVNL and PMC, contractor is lightly loaded

Balanced among the three

Balanced distribution among the three

Distribution of risk of misjudgement

Heavily loaded on individual

Balanced among individual, leader and system

Heavily loaded on system and leader, light on individual

Individual should be safeguarded from the risk of misjudgement

Monitoring System

Intermediate key No No Yes Should be adopted for better

50

Page 51: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

Characteristics Construction Unit of IR

RVNL DMRC Suggested for SPV

dates project monitoring

System wide contract and buffer planning

No No Yes Necessary for ensuring timely commissioning of complex projects

Levels of monitoring

Only one level, every one monitors same targets

Only one level, every one monitors same targets

Two level monitoring: project level through milestones, and at corporate level through key dates

Two level monitoring: project level through milestones, and at corporate level through key dates

Buffer Management and System Review

Presence No No Yes Should be integral part of control system

Visible implication of a day’s delay

Not known Not known Known across the organization and to all stakeholders

Should be known across the organization and to all stakeholders

Control system review for better project delivery

Centralized at Ministry level, minimal at construction units

System getting more procedure oriented and bureaucratic year by year

Yes, different system for every new project corridor/ contract

Necessary for continual improvement, and check against slackness and danger of tightening procedure to the detriment of progress

Conclusion

The comparative study of project management in Construction organization on

IR, RVNL and DMRC has provided key insights into management control system

for such project organizations. The detailed description of project management of

MC1A contract in DMRC provides answers to questions beginning with ‘What’

or ‘How’ related to the success of project execution by DMRC. Whereas the

comparative study and resulting management control system provide answer to

questions beginning with ‘Why’. Key lessons from this study could be

summarized as following:

• If the SPV is a JV, 50:50 ownership between GOI and State Government

is better otherwise CEO should be CMD.

• The CEO should be the first employee to be appointed to an SPV and he

should be allowed complete freedom in building the organization and

creating a new work culture conducive for faster project execution.

51

Page 52: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

• The CEO should review the DPR of a project to avoid any loose ends that

could derail the project during execution.

• Departmental structure of the sponsoring department or Ministry should

be broken while building the organization.

• PMC should be an integral part of project management.

• SPV should use a rich contracting framework having range of choices

suitable for strategic selections for achieving project goals.

• Judicious allocation of responsibility among various stakeholders

galvanizes the entire project team.

• System wide contracting network with intermediate key dates and two

level monitoring is necessary for effective monitoring.

• Buffer management should be used to expedite delayed projects and

prepone date of commissioning of project.

• System should be reviewed after experience of each project for continual

improvement and checking slackness.

The Management Control Framework emerging from the case study of DMRC

although do not exactly apply to the Construction units of IR and RVNL, still the

insights obtained from the comparative study is valuable. Lessons so derived can

help in making them and other similar project SPVs more effective, efficient, and

responsive and in creating better project SPVs.

Notes and References

1 Statement by Deputy Chairman, Planning Commission, GOI as published in internet edition of Financial Express dated December 4 2007; down loaded from http://www.financialexpress.com/news/India-must-hike-infra-spend-to-9-of-GDP/246584/ on 30.04.2008. 2 Annual Report 2003-04 of Ministry of Statistics and Program Implementation, as quoted by MD, Delhi Metro Rail Corporation in a presentation at IIM Bangalore in 2004. 3 Budget speech of Minister of Railways while presenting Railway Budget for year 2008-09 4 Gupta, Anil Kumar and Roy, Shyamal, 2008, ‘Public Private Partnership in Railways: A New Approach’, IIMB Management Review, Vol. 20 No.1, pp 6-10. 5 Replied by a retired Chief Secretary in a Public Policy Seminar at IIM Bangalore in year 2004 in response to a question regarding endless trouble several under construction flyovers were causing to public in Bangalore city.

52

Page 53: Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008

6 Extracted from a presentation made by MD, DMRC at IIM Bangalore in year 2004. 7 CAO units have started coming up for special projects under other technical departments too. 8 Extended Railway Board consists of Railway Board Members, and representatives from other Central Government Ministries such as Finance Ministry and Planning Commission. It plays the same role as Public Investment Board (PIB) of GOI. 9 The study was based on the Monthly Progress Report sent by the CAO/Southern Railway, Chennai for the period ending 31.03.2008. It contained the March 2008 progress as well as the cumulative progress for the entire financial year 2007-08. 10 It is the aggregate of the differences of latest estimated cost and cumulative expenditure incurred till 31.03.2007 for each project. 11 This is the aggregate of fund allotted to each of theses projects in the Railway Budget 2007-08. 12 Quadrilateral formed by the lines connecting the four metro cities of Delhi, Chennai, Kolkata, and Mumbai. 13 Based on Monthly Progress Report for March 2008 prepared by RVNL for the Railway Board. 14 As per the Annual Financial Statement for year 2006-07 downloaded from www.rvnl.org. 15 Study was done through telephonic interview of Mr. Pradeep Gaur, Chief Project Manager, Chennai on 10th April 2008. 16 Arrived at through interviews of some officers working on RVNL. 17 No such hoarding is erected at any DMRC project site. One can only find a decent full height continuous hoarding bearing ‘Delhi Metro’ and the Contractor’s name. Hoarding is more as a good advertisement for an excellent project site rather than a sorry statement for troubles loaded on public. 18 MCD- Municipal Corporation of Delhi; DJB-Delhi Jal Board; PWD- Public Works Department; NDMC-New Delhi Municipal Corporation; and DDA- Delhi Development Authority. DMRC even took several officers from these authorities on deputation who later took absorption with it. 19 Anthony, Robert N. and Young, David W., 2002, ‘Management Control in Nonprofit Organizations’, McGraw Hill, Part III Management Control Systems, Chapter 8, pp 373-396. 20 Hofstede, Geert, 1981, ‘Management Control of Public and Not-For-Public Activities’, Accounting, Organizations and Society, Vol.6, No.3, pp193-211. 21 Harrison, Fredrick and Lock, Dennis, 2004, ‘Advanced Project Management A structured Approach’, Gower Publishing Ltd., England, pp 12-64. 22 Member Engineering is the ex-officio Chairman of RVNL. 23 Stated by the MD himself in a presentation given at IIM Bangalore in year 2004. 24 Other two forms suggested by Harrison and Lock are functional matrix and balanced matrix. These are the project organizations created in an existing matrix organization. IR is a matrix form of organization. 25 Downloaded from http://www.delhimetrorail.com/corporates/about_us.html on 30.04.2008 26 Downloaded from http://www.rvnl.org/profile06.php , http://www.rvnl.org/profile07.php, and http://www.rvnl.org/profile08.php .

53