masterplan finalreport submitted

Upload: qiaoxin136

Post on 02-Jun-2018

237 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 MasterPlan FinalReport Submitted

    1/163

    Roanoke Rapids Sanitary District

    Distribution System Master Plan

    Project Number 31144-000

    July 2010

  • 8/10/2019 MasterPlan FinalReport Submitted

    2/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan iH&S Project No. 31144-000

    EXECUTIVE SUMMARY

    This report for the Roanoke Rapids Sanitary District (District) documents the

    Distribution System Master Plan and Water Audit. The purpose of this project

    was to study past and current water use in the District and predict futuredemands. Using the Districts hydraulic model, we identified current and future

    deficiencies and recommended improvements.

    The purpose of the water audit was to quantify water losses in the distribution

    system. The water audit results showed that the non-revenue water was 32

    percent by volume of the total water supplied for the 2007-2008 fiscal year.

    Average and maximum day demands in 2008 were 5.13 million gallons per day

    (mgd) and 8.08 mgd, respectively. Projected average and maximum day

    demands for the year 2030 including new wholesale customers, were 6.9 mgd

    and 10.9 mgd, respectively. The design capacity of the existing water treatment

    plant (12 mgd) is sufficient to meet the projected demands; however, restrictions

    that currently limit the plant to 10 mgd will need to be eliminated.

    Our evaluation showed system storage was adequate for existing and future

    demands, but firm pump capacity was deficient. We recommend a new 4,400

    gpm or 6.3 mgd pump that is efficient in the range of 235 to 255 feet of totaldynamic head.

    The Districts hydraulic model was used for assessing existing hydraulic

    conditions and for simulating the future conditions. Deficiencies were identified

    and the model was used to study alternatives to correct existing problems and

    meet future demands.

    We further assessed the condition of the distribution system by conducting field

    tests and interviews with District staff. Master meter tests revealed that the

    master meter at the WTP was under-registering by 7.0 to 9.2 percent which is

    approximately 139 million gallons annually. Hydraulic grade line tests showed

    several locations where closed valves are likely. C-factors tests showed that the

    unlined cast iron pipes in the system have lost about 70 percent of their original

  • 8/10/2019 MasterPlan FinalReport Submitted

    3/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan iiH&S Project No. 31144-000

    capacity due to tuberculation. We used these tests and fire flow tests to update

    the model to give more accurate hydraulic results. The model then was used to

    estimate available fire flows throughout the entire distribution system. Many

    areas were shown to have inadequate fire protection. Using the model and the

    Districts mapping records, as well as pipe replacement, pipe repair, and valve

    status records, we prioritized pipes in need of rehabilitation and recommended

    new pipes to provide adequate fire flows. The annual budget required to

    rehabilitate all the unlined cast iron pipes within the next twenty years is

    approximately $375,000. Pipe rehabilitation is critical for the District as a means

    to improve water quality and hydraulic capacity. Restoring or improving hydraulic

    capacity improves fire protection. Pipe rehabilitation is also an important step

    toward water conservation as it can greatly reduce water losses by decreasing

    leakage and the number of main breaks. Decreasing main breaks reduces the

    risk to public safety.

    Roanoke Rapids Sanitary District plans to begin selling water to the Town of

    Weldon in the near future. Using the hydraulic model, we evaluated pressures,

    available fire flows, and water quality assuming three possible meter locations.

    Based on this analysis, we recommend supplying the Town of Weldon from the

    12-inch water line at the intersection of Country Club Road and US 158.

    This report also recommends operational and capital improvements to the

    distribution system for improved pressures and water age with the proposed

    Weldon connection. Operational improvements can improve water quality.

    A capital improvement plan (CIP) was created to prioritize new pipes for fire

    protection as well as new transmission mains to improve hydraulic performance.

    The first phase of proposed improvements total approximately $1.6 million. To

    supply the Town of Weldon with 2 mgd, the next phase of improvements total

    $1.07 million. The third phase of improvements to supply projected growth by the

    year 2030 total $0.5 million.

  • 8/10/2019 MasterPlan FinalReport Submitted

    4/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan iiiH&S Project No. 31144-000

    TABLE OF CONTENTS

    EXECUTIVE SUMMARY ....................................................................................... i

    TABLE OF CONTENTS ....................................................................................... iii

    TABLE OF FIGURES ........................................................................................... vi

    TABLE OF TABLES ............................................................................................. ix

    1 Introduction ................................................................................................. 1-1

    1.1 Scope of WorkWater System Master Plan ........................................ 1-1

    1.2 Scope of Work - Water Audit ................................................................ 1-3

    1.3 Background Information ........................................................................ 1-3

    1.3.1 Tanks and Pump Stations .............................................................. 1-4

    1.3.2 Existing Model Update ................................................................... 1-6

    1.4 Purpose ................................................................................................ 1-7

    2 Water Requirements ................................................................................... 2-1

    2.1 Population Projections .......................................................................... 2-1

    2.1.1 Historical Population Records ........................................................ 2-1

    2.1.2 District Meter Count........................................................................ 2-1

    2.1.3 County Population Projections ....................................................... 2-3

    2.1.4 District Population Projections ........................................................ 2-6

    2.2 Water Demands .................................................................................... 2-7

    2.2.1 Historical Water Production ............................................................ 2-7

    2.2.2 Needed Fire Flows ......................................................................... 2-9

    2.2.3 Historical Water Billing ................................................................... 2-9

    2.2.3.1 Historical Industrial Billing Records ........................................ 2-112.2.3.2 Historical Wholesale Billing Records ..................................... 2-12

    2.2.3.3 Historical Domestic Demand.................................................. 2-14

    2.2.4 Conservation Measures ............................................................... 2-15

    2.2.5 Recent Water Use ........................................................................ 2-16

    2.3 Demand Projections and Water Requirements ................................... 2-17

    2.3.1 Assumptions for Projections ......................................................... 2-17

    2.3.2 Water Requirements Summary .................................................... 2-20

    3 Storage and Pump Evaluation .................................................................... 3-1

    3.1 Storage Requirements .......................................................................... 3-13.1.1 Elevated Storage ............................................................................ 3-1

    3.1.2 Emergency Storage........................................................................ 3-3

    3.2 Pumping Evaluation .............................................................................. 3-3

    3.2.1 WTP Pump Recommendations ...................................................... 3-4

    3.2.2 Becker Pump Station ...................................................................... 3-4

    4 Hydraulic Modeling ..................................................................................... 4-1

  • 8/10/2019 MasterPlan FinalReport Submitted

    5/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan ivH&S Project No. 31144-000

    4.1 Modeling Scenarios .............................................................................. 4-1

    4.2 Design Criteria ...................................................................................... 4-2

    4.2.1 Pressure ......................................................................................... 4-2

    4.2.2 Head Loss and Velocities ............................................................... 4-2

    4.2.3 Fire Flows ....................................................................................... 4-3

    4.2.4 Tank and Pump Performance ........................................................ 4-4

    5 Condition Assessment ................................................................................ 5-1

    5.1 Field Tests ............................................................................................ 5-1

    5.1.1 Master Meter Test .......................................................................... 5-1

    5.1.2 Hydraulic Gradient Tests ................................................................ 5-4

    5.1.3 C-Factor Tests ............................................................................. 5-10

    5.1.4 Fire Flow Tests ............................................................................. 5-14

    5.1.4.1 Fire Flow Test Number 5 ....................................................... 5-17

    5.1.4.2 Fire Flow Test Number 10 ..................................................... 5-17

    5.1.4.3 Fire Flow Test Number 11 ..................................................... 5-17

    5.1.4.4 Fire Flow Test Number 12 ..................................................... 5-18

    5.2 Other Methods of Condition Assessment ........................................... 5-20

    5.2.1 Pipe Age and Material .................................................................. 5-20

    5.2.2 Main Breaks: Replacement and Repairs ...................................... 5-22

    5.2.3 Valve Status ................................................................................. 5-22

    5.2.4 Available Fire Flows ..................................................................... 5-26

    5.2.5 Pressure ....................................................................................... 5-26

    6 Analysis and Recommendations ................................................................. 6-1

    6.1.1 Town of Weldon Connection2010 .............................................. 6-1

    6.1.1.1 Recommended Weldon Connection ........................................ 6-4

    6.1.2 Hydraulics with Future Demands ................................................... 6-5

    6.1.2.1 Recommendations to Improve Tank Performance................... 6-7

    6.1.2.2 Recommendations to Improve Fire Flows ............................. 6-11

    7 Water Quality Analysis ................................................................................ 7-1

    8 Infrastructure Renewal ................................................................................ 8-1

    8.1 Likelihood of Failure .............................................................................. 8-2

    8.1.1 Scoring Likelihood of Failure .......................................................... 8-2

    8.2 Consequence of Failure ........................................................................ 8-3

    8.2.1 Scoring Consequences .................................................................. 8-4

    8.3 Available Fire Flow ............................................................................... 8-5

    8.4 Risk ....................................................................................................... 8-5

    8.5 Prioritization and Rehabilitation ............................................................ 8-7

    9 Capital Improvement and RehabilitaTion Plans .......................................... 9-1

  • 8/10/2019 MasterPlan FinalReport Submitted

    6/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan vH&S Project No. 31144-000

    9.1 Capital Improvement Plan..................................................................... 9-1

    9.1.1 Right of Way and Permitting Issues ............................................... 9-7

    9.1.2 Funding Opportunities .................................................................... 9-8

    9.1.2.1 North Carolina Rural Economic Development Center .............. 9-9

    9.1.2.2 NCDENR Public Water Supply Section ................................... 9-9

    9.1.2.3 United States Department of Agriculture (USDA) RuralDevelopment Center ............................................................................. 9-10

    9.1.2.4 North Carolina Clean Water Management Trust Fund ........... 9-11

    9.1.2.5 Funding References .............................................................. 9-11

    9.2 Rehabilitation Plan .............................................................................. 9-12

    Appendix A Water Audit .................................................................................... a

    Appendix B Water Audit Grading Matrix ............................................................ g

    Appendix C Manufacturers Pump Curves ......................................................... o

  • 8/10/2019 MasterPlan FinalReport Submitted

    7/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan viH&S Project No. 31144-000

    TABLE OF FIGURES

    Figure 1-1: Roanoke Rapids Sanitary District Water Distribution System .......... 1-5

    Figure 2-1: Historical County Populations .......................................................... 2-2

    Figure 2-2: Historical Meter Count ..................................................................... 2-2

    Figure 2-3: Traffic Analysis Zone (TAZ) Population Densities ........................... 2-4

    Figure 2-4: Population Growth between 2000 and 2007 (from TAZ Data) ......... 2-5

    Figure 2-5: District Average Day Demand and Maximum Day Demand 1998to 2009 ......................................................................................................... 2-8

    Figure 2-6: Estimated Needed Fire Flows Based on Zoning ............................ 2-10

    Figure 2-7: Historical Water Billed and Produced by RRSD ............................ 2-11

    Figure 2-8: Historical Industrial Water Usage .................................................. 2-12

    Figure 2-9: Historical Wholesale Water Sold and Contractual AgreementRanges ....................................................................................................... 2-13

    Figure 2-10: Recent Per Capita Demand ......................................................... 2-14Figure 2-11: Percentage of Domestic, Wholesale, and Industrial Water

    Produced in 2009 ....................................................................................... 2-16

    Figure 2-12: Anticipated Population Growth Areas for Residential andCommercial Customers in RRSD ............................................................... 2-18

    Figure 2-13: Areas for Industrial Growth .......................................................... 2-19

    Figure 2-14: Water Requirements and WTP Capacity ..................................... 2-21

    Figure 5-1: Velocity Profile for 20-inch Pipe ....................................................... 5-2

    Figure 5-2: Hydraulic Grade Line Test 1, WTP to Rapids Tank ......................... 5-5

    Figure 5-3: Hydraulic Grade Line Test 2, WTP to Becker Farm Tank ................ 5-6

    Figure 5-4: HGL 1-A and 1-B, Calibration Results ............................................. 5-8

    Figure 5-5: Pipes with Possible Closed Valves near 11 thStreet Ball Park ......... 5-9

    Figure 5-6: HGL 2, Calibration Results .............................................................. 5-9

    Figure 5-7: Hydraulic Grade Line, WTP to Craige Street ................................. 5-12

    Figure 5-8: Gaston Road 12-Inch Pipe Fittings Removed in 2008 ................... 5-13

    Figure 5-9: Fire Flow Test Locations ................................................................ 5-15

    Figure 5-10: Fire Flow Test 5 Results - Pipes with Possible Closed Valve ...... 5-18

    Figure 5-11: Fire Flow Test Number 12 ........................................................... 5-19

    Figure 5-12: Estimated Pipe Installation Dates ................................................ 5-21

    Figure 5-13: Pipes Repaired since 2002 .......................................................... 5-23

    Figure 5-14: Pipes Replaced since 2002 ......................................................... 5-24

    Figure 5-15: Broken, Leaking, or Hard to Turn ValvesOctober 2009 ........... 5-25

    Figure 5-16: Available Fire Flows with Existing System ................................... 5-27

    Figure 5-17: Deficient Fire Flows with Existing System ................................... 5-28

    Figure 6-1: Possible Town of Weldon Connections ........................................... 6-3

  • 8/10/2019 MasterPlan FinalReport Submitted

    8/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan viiH&S Project No. 31144-000

    Figure 6-2: Pipes with Diameters 12-inch and Larger in Main Pressure Zone ... 6-6

    Figure 6-3: Tank Levels Under Varying Supplies to Weldon .............................. 6-7

    Figure 6-4: 2030 Peak Hour Pressures without Improvements .......................... 6-8

    Figure 6-5: Average Daily Tank Levels with Tank Connection Alternatives ....... 6-9

    Figure 6-6: Proposed Route for Improvements to Tank HydraulicConnections................................................................................................ 6-10

    Figure 6-7: Deficient Fire Flow on Jackson Street Between 5 thand 6thStreets ........................................................................................................ 6-12

    Figure 6-8: Deficient Fire Flows on 8 thand 9thStreets ..................................... 6-13

    Figure 6-9: Deficient Fire Flow at Industrial Area at Monroe Street ................. 6-15

    Figure 6-10: Fire Flow Improvement near Recommended WeldonConnection ................................................................................................. 6-17

    Figure 6-11: Fire Flow Improvements near I-95 Interchange ........................... 6-18

    Figure 6-12: Hales Branch Subdivision Deficient Fire Flows ........................... 6-20

    Figure 6-13: West End Deficient Fire Flows and RecommendedImprovements ............................................................................................. 6-22

    Figure 6-14: Fire Flow Improvements - Ransome Street Area ......................... 6-24

    Figure 6-15: Fire Flow ImprovementVirginia Ave ......................................... 6-25

    Figure 6-16: Fire Flow ImprovementsMitchell Street .................................... 6-26

    Figure 6-17: Fire Flow ImprovementsTown of Gaston ................................. 6-28

    Figure 7-1: Existing System Modeled Tank Water Levels with CurrentOperations .................................................................................................... 7-2

    Figure 7-2: Existing System Tank Water Age Improvements ............................. 7-3

    Figure 7-3: Existing System Tank Levels with Proposed OperationalImprovements ............................................................................................... 7-5

    Figure 7-4: Existing System Average Water Age ............................................... 7-7

    Figure 7-5: Existing System Average Water Age Using Becker Tank PumpStation with Current Operations .................................................................... 7-8

    Figure 7-6: Existing System Average Water Age Using ProposedOperations .................................................................................................. 7-10

    Figure 7-7: Existing System Average Water Age Using ProposedOperations with Becker Pump Station ........................................................ 7-11

    Figure 7-8: Tank Water Age Improvements Due to Weldon Connection ......... 7-12

    Figure 7-9: 2010 System Water Age with Supply to Weldon (Using CurrentOperations without Becker Tank Pump Station) ......................................... 7-13

    Figure 7-10: 2010 System Water Age with Supply to Weldon Using ProposedOperations (without Becker Tank Pump Station) ........................................ 7-14

    Figure 8-1: Bi-Directional Distribution Matrix of Overall Risk ............................. 8-5

    Figure 8-2: Pipe Failure Risk ............................................................................. 8-6

    Figure 8-3: Deficient Fire Flow Comparison after Rehabilitation ........................ 8-8

  • 8/10/2019 MasterPlan FinalReport Submitted

    9/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan viiiH&S Project No. 31144-000

    Figure 9-1: Capital Improvements ...................................................................... 9-6

    Figure A-1: M36 Water Balance Terms ................................................................. a

    Figure A-2: RRSD Water Audit Reporting Worksheet ........................................... b

    Figure A-3: July 2007June 2008 RRSD Water Balance .................................... c

    Figure A-4: Water Loss Control Planning GuideWater Audit Data ValidityScore ............................................................................................................... e

    Figure A-5: Water Loss Control Planning GuideGeneral Guidelines for Settinga Target ILI ....................................................................................................... f

  • 8/10/2019 MasterPlan FinalReport Submitted

    10/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan ixH&S Project No. 31144-000

    TABLE OF TABLES

    Table 1-1: Existing Water Distribution System Pumps ....................................... 1-4

    Table 1-2: Existing Water Distribution System Tanks ........................................ 1-6

    Table 2-1: County Population Projections .......................................................... 2-3

    Table 2-2: Projected RRSD Populations ............................................................ 2-6

    Table 2-3: District ADD, MDD, and Peaking Factors 1998 to 2008 ................... 2-8

    Table 2-4: Projected Populations and Water Demands ................................... 2-21

    Table 3-1: Water Distribution System Storage Evaluation ................................. 3-2

    Table 3-2: Pump Capacity Evaluation ................................................................ 3-4

    Table 4-1: Needed Fire Flows for One- and Two-family Residences .............. 4-3

    Table 5-1: Master Meter Test ............................................................................. 5-3

    Table 5-2: Hydraulic Grade Line (HGL), Calibration Results ............................. 5-7

    Table 5-3: Summary of Loss of Head Tests ..................................................... 5-11

    Table 5-4: Fire Flow Test Results .................................................................... 5-16

    Table 5-5: Model Calibration with Fire Flow Test Results ................................ 5-16

    Table 8-1: Likelihood of Failure Weighting ......................................................... 8-3

    Table 8-2: Consequence of Failure Weighting ................................................... 8-4

    Table 9-1: Recommended Immediate Improvements (Phase 1) to ProvideAdequate Fire Flow ...................................................................................... 9-2

    Table 9-2: Recommended Phase 2 Improvements(to Supply Town of Weldon) ......................................................................... 9-5

    Table 9-3: Recommended Phase 3 Improvements(to Supply 2030 Demands) ........................................................................... 9-5

    Table 9-4: Rehabilitation Plan .......................................................................... 9-14

  • 8/10/2019 MasterPlan FinalReport Submitted

    11/163

  • 8/10/2019 MasterPlan FinalReport Submitted

    12/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 1-2H&S Project No. 31144-000

    4) Evaluate Storage and Pump Capacities

    a) Calculate storage needs and compare with existing tank capacities

    b) Determine pump requirements and compare with existing pump capacity

    c) Recommend additional storage and pump capacity if needed

    5) Model Critical Conditions

    a) Add new 12-inch pipe to Gaston and new booster pump station at Becker

    Village Tank

    b) Review model calibration

    c) Evaluate existing conditions

    d) Model supply to Weldon

    e) Identify improvements for deficient fire flows

    f) Model future conditions to check for deficiencies

    g) Evaluate alternatives for improvements

    h) Run extended period simulations to check pump and tank performance

    6) Model Water Quality

    a) Develop water age predictions

    b) Investigate methods of decreasing water age

    c) Evaluate water quality impacts of proposed improvements

    7) Develop Capital Improvement Plan

    a) Present preliminary recommendations to the District and respond to

    review comments

    b) Prioritize proposed improvements

    c) Organize construction projects and estimate costs

    d) Suggest funding opportunities

    e) Explore right of way and permit issues

    8) Prepare Final Report

    a) Write draft report

    b) QA/QC and technical review

    c) Respond to District review comments and submit final report

    d) Deliver hydraulic model to the District as an EPANET data file

  • 8/10/2019 MasterPlan FinalReport Submitted

    13/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 1-3H&S Project No. 31144-000

    1.2 Scope of Work - Water Audit

    1) Test water plants master meter

    2) Analyze production records and billing records

    3) Prepare audit as described in AWWA Manual M36 using AWWA software4) QA/QC and technical review

    5) Present the water audit results to the District

    1.3 Background Information

    Roanoke Rapids Sanitary District (RRSD or the District) is located along

    Interstate 95 in eastern North Carolina about five miles south of the Virginia

    border. The District comprises an area of approximately 15.6 square miles. The

    Districts water distribution system includes roughly 120 miles of pipe (6-inch

    diameter and larger), that supply more than 9,000 water customers. It includes

    parts of both Halifax County and Northampton County, all of the City of Roanoke

    Rapids and Town of Gaston, and parts of the Town of Weldon.

    Raw water is taken from Roanoke Rapids Lake which is an impoundment on the

    Roanoke River. Water flows by gravity (or is pumped under certain hydraulic

    conditions) to the water treatment plant (WTP) located west of NC Hwy 48 on the

    north side of the City of Roanoke Rapids.

    The water distribution system was originally built by Rosemary Manufacturing

    Company to supply the needs of its cloth and paper mills. RRSD was formed in

    1931 and in 1933 took over part of the water distribution system and expanded it.

    This included the construction of the 11 thStreet elevated tank. A second elevated

    tank was built on Rapids Street in 1951 and, according to a 1963 RRSD water

    distribution system study, the distribution system was greatly expanded to the

    east, south, and west in 1957. The District expanded to the north in 1977 when a

    12-inch transmission main was installed to supply the Town of Gaston. Further

    growth in the 1970s and 1980s included construction of the Becker Farm Tank

    in 1987.

  • 8/10/2019 MasterPlan FinalReport Submitted

    14/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 1-4H&S Project No. 31144-000

    Figure 1-1 shows the existing RRSD water distribution system with city and

    county boundaries.

    1.3.1 Tanks and Pump Stations

    The District has four pumps at the WTP as summarized inTable 1-1.A secondpump station located at the Becker Farm Tank was under construction at the

    start of this project and is discussed in detail in Chapter3.

    The District has two ground storage tanks used as clearwells at the WTP and

    four elevated storage tanks located throughout the distribution system as shown

    inFigure 1-1 and detailed inTable 1-2.Two additional tanks, the Roanoke-Davie

    tank and the I-95 tank are owned by Halifax County. However, these tanks are

    directly connected to RRSD pipes and directly influence the Districts operations.

    Table 1-1: Existing Water Distribution System Pumps

    PumpNo.

    PumpName

    PumpType

    WTPLocation

    RatedCapacity

    (gpm)

    RatedCapacity

    (mgd)

    TDH(ft)

    Power(hp)

    1PacoPump

    HorizontalSplit Case

    InsideFinished

    Water Pump

    Station

    3,000 4.3 250 250

    2Fairbanks

    MorsePump

    HorizontalSplit Case

    InsideFinished

    Water PumpStation

    2,200 3.2 320 250

    3Fairbanks

    Morse400

    VerticalTurbine

    OutsideFinished

    Water PumpStation

    4,400 6.3 273 400

    4

    Diesel

    Pump

    Vertical

    Turbine

    DieselEngine

    PumpStation

    3,000 4.3 200 630

    Note: Another vertical turbine pump (10 mgd, 310 TDH, 700 hp) was removed from service inJune,2009.

    Manufacturers pump curves for pumps 1, 2, and 3 are shown in Appendix C.

  • 8/10/2019 MasterPlan FinalReport Submitted

    15/163

  • 8/10/2019 MasterPlan FinalReport Submitted

    16/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 1-6H&S Project No. 31144-000

    Table 1-2: Existing Water Distribution System Tanks

    Tank Name Capacity (mg)Overflow

    Elevation (ft)Head Range

    (ft)

    Elevated

    Gaston 0.20 302 20Rapids Street 0.50 330 34.5

    11th Street 0.50 330 40

    Becker 0.50 320 37

    Roanoke / Davie* 0.50 325 30

    I-95* 0.25 325 26.5

    Ground

    Rectangular WTP Clearwell 1.25 97 12

    Circular WTP Clearwell 2.00 97 12

    Notes: * Owned by Halifax County, but directly connected to RRSD system

    1.3.2 Existin g Model Update

    The existing model was provided by RRSD. The model was updated and

    calibrated in 2007 by Highfill Infrastructure Engineering in a report titled Water

    Distribution System Model Update and Calibration.

    We updated the model by adjusting C-factors, pipe configurations, and minor

    losses at the WTP. We also added details showing the placement of pumps and

    pipes at the plant. Using aerial photographs and a yard drawing of the WTP, we

    arranged the pumps and piping to more clearly represent the system.

    Additionally, the 2007 model had very large minor losses for the piping at the

    WTP. We updated the minor losses for these pipes to reflect the actual valves

    and fittings shown on plant drawings.

    The Districts model did not include pipes with diameters smaller than 6 inches,

    as pipes that are smaller than 6-inches are often not included in hydraulic models

    to save computer memory and calculation time. In most cases, system hydraulics

    are not significantly affected by omitting small-diameter piping, however; to better

  • 8/10/2019 MasterPlan FinalReport Submitted

    17/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 1-7H&S Project No. 31144-000

    calibrate the model, we added some small-diameter pipes (more than 3 miles)

    where needed for this project.

    The total system demands in the model were also updated based on 2008 billing

    and production records. Domestic demand allocation, which is the placement ofeach individual residential and commercial demand based on detailed billing

    records, however, was not changed from the existing model.

    1.4 Purpose

    In this report, we have studied elements regarding the past and current public

    health, water use, water quality, and fire protection in the District and have made

    predictions about future water demands. Using the Districts hydraulic model, we

    identified current and future deficiencies in these elements associated with the

    distribution system and recommended corrective improvements.

    The purpose of the recommended improvements is to improve water

    conservation, water quality, and hydraulic capacity with the ultimate goal of

    protecting public health, safety, and the environment.

  • 8/10/2019 MasterPlan FinalReport Submitted

    18/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-1H&S Project No. 31144-000

    2 WATER REQUIREMENTS

    This chapter discusses Task 3 of the Water System Master Plan. The goal of

    Task 3 was to estimate future water requirements by projecting future population

    and water demands. The impacts of conservation were also evaluated. Ameeting with the District was held on September 17, 2009 to review preliminary

    projections and discuss fire flow requirements. Final projections were included in

    a January 21, 2010 technical memo and are summarized in this chapter.

    2.1 Population Projections

    As shown inFigure 1-1,the District falls within two North Carolina counties.

    Northampton County includes the Town of Gaston in the northern part of the

    District. The rest of the District is in Halifax County.

    2.1.1 Historic al Popu lation Record s

    Determining the population of the District based on census data is complicated

    because it falls in two counties and includes all or part of three municipalities

    (City of Roanoke Rapids, Town of Gaston, and Town of Weldon as shown in

    Figure 1-1).

    Historical county populations were relatively unchanged between 1980 and 2008,

    as shown inFigure 2-1.

    2.1.2 Distr ict Meter Coun t

    To obtain a more clear view of the population inside the District boundary, we

    reviewed water meter records.

    Meter records were examined to identify the trend over the last ten years as

    shown inFigure 2-2.The total population of Roanoke Rapids and Gaston, which

    cover much of the Districts area, is shown in comparison. These population

    estimates were provided by the state demographer.

    A linear regression of the meter data shows a trend of 49 new meters per year.

    This corresponds to supplying about 120 additional people per year assuming

    2.42 people per meter based on the average household size in the City of

    Roanoke Rapids from the 2000 census.

  • 8/10/2019 MasterPlan FinalReport Submitted

    19/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-2H&S Project No. 31144-000

    Figure 2-1: Historical County Populations

    Figure 2-2: Historical Meter Count

    -

    10,000

    20,000

    30,000

    40,000

    50,000

    60,000

    70,000

    1950 1960 1970 1980 1990 2000 2010 2020

    CountyPopulation

    Year

    Northampton Halifax

  • 8/10/2019 MasterPlan FinalReport Submitted

    20/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-3H&S Project No. 31144-000

    2.1.3 County Popu lat ion Project ions

    Projecting the population supplied by the District is also difficult because it falls

    within several political and planning boundaries. The state demographer makes

    County population projections starting from the last census (2000) as shown in

    Table 2-1.Projections for Halifax and Northampton Counties both decrease by a

    small percentage over the next twenty years.

    Table 2-1: County Population Projections

    Populations Halifax County Northampton County

    Census 2000 57,374 22,086

    2010 Projection 55,053 21,045

    2020 Projection 54,232 20,885

    2000 to 2020 % Decrease 5.5% 5.4%

    Annual % Decrease 0.3% 0.3%

    Current municipal populations are estimated by the state demographer, but

    municipal projections are not made. Some areas in North Carolina have

    projections for Traffic Analysis Zones (TAZ). TAZ data near the District is

    available through the Upper Coastal Plain Council of Governments. However, it

    only provides year 2000 and current population estimates. Population projections

    for the area are not currently available.

    TAZ data shows the location of existing population in the District more precisely,

    as shown by the population densities inFigure 2-3.TAZ data also includes

    population estimates which allow us to note the population growth between 2000

    and 2007 as shown inFigure 2-4.

  • 8/10/2019 MasterPlan FinalReport Submitted

    21/163

  • 8/10/2019 MasterPlan FinalReport Submitted

    22/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-5H&S Project No. 31144-000

    Figure 2-4: Population Growth between 2000 and 2007 (from TAZ Data)

  • 8/10/2019 MasterPlan FinalReport Submitted

    23/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-6H&S Project No. 31144-000

    2.1.4 Distr ict Popu lation Projection s

    Even though the state demographer predicts County populations will decrease,

    and municipal populations have declined by approximately 400 people in the past

    seven years, the number of water meters in the District has increased over the

    same time period (Figure 2-2). This implies that the population supplied by the

    District is increasing because the District service area has grown, or people are

    moving into areas of the District not within city limits. Part of the increase in the

    number of meters could be new meters used for irrigation, but the TAZ

    population estimates show an overall increase in population inside the District

    service area between 2000 and 2007 (Figure 2-4).

    Because of the population growth observed in the TAZ estimates, it is reasonable

    to assume that the increase in water meters denotes an increase in housing and

    growth in population. The meter trend corresponds to population growth of

    approximately 120 people per year, which is the basis forTable 2-2.

    Table 2-2: Projected RRSD Populations

    Year Population Projection

    2008 19,290

    2010 19,530

    2020 20,710

    2030 21,900

  • 8/10/2019 MasterPlan FinalReport Submitted

    24/163

  • 8/10/2019 MasterPlan FinalReport Submitted

    25/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-8H&S Project No. 31144-000

    Figure 2-5: District Average Day Demand and Maximum Day Demand 1998to 2009

    Table 2-3: District ADD, MDD, and Peaking Factors 1998 to 2008

    Year ADD MDD MDD/ADD

    1998 4.58 8.40 1.83

    1999 4.65 7.59 1.63

    2000 5.15 8.49 1.65

    2001 4.58 9.19 2.01

    2002 4.63 7.59 1.64

    2003 4.40 6.30 1.43

    2004 4.10 6.15 1.50

    2005 5.08 6.88 1.362006 5.34 7.81 1.46

    2007 5.53 7.66 1.38

    2008 5.13 8.08 1.57

    2009 5.18 7.11 1.37

    1.831.63

    1.65 2.01

    1.64

    1.43 1.50

    1.36

    1.46 1.381.57

    1.37

    0.0

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    8.0

    9.0

    10.0

    1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009

    WaterProduction(mgd)

    YearADD MDD MDD/ADD

  • 8/10/2019 MasterPlan FinalReport Submitted

    26/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-9H&S Project No. 31144-000

    Figure 2-5 also shows the ratio of MDD to ADD for each year. This ratio was

    especially high in 2001 due to usage by a textile mill. The mill, however, went out

    of business in early 2004, so such large peaks are not expected in the future.

    Since 2004, the largest ratio of MDD to ADD was 1.57 in 2008. This ratio was

    used to estimate future maximum day demands for domestic and wholesale

    customers.

    2.2.2 Needed Fire Flow s

    The water system master plan involves designing pipes and storage tanks to

    deliver fire flows. To do this, we estimated needed fire flows throughout the

    District. Zoning data from Halifax County, Northampton County, City of Roanoke

    Rapids, and Town of Weldon identified the type of land use in an area, and

    needed fire flows were estimated based on this information, as shown inFigure

    2-6.We assumed 3,500 gpm for industrial zones, 2,500 gpm for commercial

    zones, 1,500 for multi-family residential zones, 1,000 gpm for single-family

    residential zones, and 750 for agricultural residential zones. These fire flows are

    recommended by the International Conference of Building Officials (ICBO, 1997).

    2.2.3 Historic al Water Bil l ing

    Water billing records have remained relatively constant over the last few years as

    shown inFigure 2-7.Production records are shown for comparison. The

    prominent decline in water billing starting in about 2000 was due to large

    industrial customers curtailing their water use. Water billed has remained steady

    since 2003. These steady demands show that population growth was

    compensated by conservation. However, also important to note is the difference

    between water produced and water billed starting in 2005. This is likely due to

    water loss in the system such as leaks or other unbillable water use.

  • 8/10/2019 MasterPlan FinalReport Submitted

    27/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-10H&S Project No. 31144-000

    Figure 2-6: Estimated Needed Fire Flows Based on Zoning

  • 8/10/2019 MasterPlan FinalReport Submitted

    28/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-11H&S Project No. 31144-000

    Figure 2-7: Historical Water Billed and Produced by RRSD

    2.2.3.1 Historical Industrial Billing Records

    Roanoke Rapids has historically been home to paper and textile mills. Two large

    textile mills closed, one in 1997 and another in 2004. There has been a generaldecline in the textile industry in North Carolina in recent years. Free trade

    regulations and price competition from developing countries has triggered a

    steady relocation of the textile industry from the Carolinas to overseas

    production. However, the District still has three major industrial users (one textile,

    one paper, and one power supply industry). The historical water consumption of

    each large industrial user is shown inFigure 2-8.A steep drop in water used by

    two of the industries occurred in 1997.

    Industrial maximum day demands were based on the historical billing records

    shown inFigure 2-8.

    0.00

    1.00

    2.00

    3.00

    4.00

    5.00

    6.00

    7.00

    8.00

    0

    50,000

    100,000

    150,000

    200,000

    250,000

    Jan-97

    Jan-98

    Jan-99

    Jan-00

    Jan-01

    Jan-02

    Jan-03

    Jan-04

    Jan-05

    Jan-06

    Jan-07

    Jan-08

    Jan-09

    Jan-10

    Jan-11

    sage/Production(g

    d)

    Usage/Production(1000gallonspermonth)

    Month-Year

    Water Produced Water Billed

  • 8/10/2019 MasterPlan FinalReport Submitted

    29/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-12H&S Project No. 31144-000

    Figure 2-8: Historical Industrial Water Usage

    2.2.3.2 Historical Wholesale Billing Records

    The District sells water wholesale to Northampton and Halifax Counties. Water

    sold since 1990 is shown inFigure 2-9.Water sold wholesale is also commonly

    called exported water because it is used in another distribution system.

    The District has maintained purchase agreement contracts with Northampton and

    Halifax Counties since 1986 and 1981, respectively. Contract limits are shown

    onFigure 2-9.Northampton Countys purchase agreement was amended in

    2002. Since that time, the average annual volume sold has more than doubled.

    The average amount of water purchased by both counties has continued to

    slowly increase as shown inFigure 2-9.

    0.00

    0.25

    0.50

    0.75

    1.00

    1.25

    1.50

    1.75

    2.00

    2.25

    Jan-9

    0

    Jun-9

    1

    Oct-9

    2

    Mar-9

    4

    Jul-9

    5

    Dec-9

    6

    Apr-9

    8

    Aug-9

    9

    Jan-0

    1

    May-0

    2

    Oct-0

    3

    Feb-0

    5

    Jul-0

    6

    Nov-0

    7

    Mar-0

    9

    Aug-1

    0

    Dec-1

    1

    Usage(mgd)

    Month-Year

    Dominion Co-Gen

    Halifax Linen

    Kapstone Paper

  • 8/10/2019 MasterPlan FinalReport Submitted

    30/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-13H&S Project No. 31144-000

    Figure 2-9: Historical Wholesale Water Sold and Contractual Agreement Ranges

    Current Contract Min

    Current Contract Max

    Current Contract Min

    Current Contract Max

    Original Contract Range

    Original Contract Range

    0.0

    0.5

    1.0

    1.5

    2.0

    2.5

    3.0

    3.5

    Jan-9

    0

    Jan-9

    1

    Jan-9

    2

    Jan-9

    3

    Jan-9

    4

    Jan-9

    5

    Jan-9

    6

    Jan-9

    7

    Jan-9

    8

    Jan-9

    9

    Jan-0

    0

    Jan-0

    1

    Jan-0

    2

    Jan-0

    3

    Jan-0

    4

    Jan-0

    5

    Jan-0

    6

    Jan-0

    7

    Jan-0

    8

    Jan-0

    9

    Jan-1

    0

    Jan-1

    1

    Jan-1

    2

    Usage(mgd)

    Month-Year

    Historical Wholesale Demand

    Halifax County

    Northampton County

  • 8/10/2019 MasterPlan FinalReport Submitted

    31/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-14H&S Project No. 31144-000

    2.2.3.3 Historical Domestic Demand

    We analyzed domestic demand by determining per capita water use. We

    calculated per capita use by dividing total domestic use by the population

    supplied. We determined the total domestic use from historical billing records.

    We estimated the population supplied by multiplying the number of meters by the

    Census 2000 official estimate of 2.42 persons per household for the City of

    Roanoke Rapids. The calculated gallons per capita per day (gpcd) are shown in

    Figure 2-10 for years 2003 to 2008. The per capita demand decreased

    significantly in 2004 because of conservation, which is discussed in the next

    section. Since 2004, annual per capita demand has averaged 82 gpcd.

    The per capita demand shown in the chart includes small commercial users such

    as restaurants, car washes, etc. but not non-revenue water.

    Figure 2-10: Recent Per Capita Demand

    93

    8382

    80

    85

    79

    70

    75

    80

    85

    90

    95

    2003 2004 2005 2006 2007 2008

    GallonsPerCapitaPe

    rDay

    Year

  • 8/10/2019 MasterPlan FinalReport Submitted

    32/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-15H&S Project No. 31144-000

    2.2.4 Cons ervation Measures

    House Bill 1215 was ratified by the North Carolina General Assembly in 2002.

    The Bill contains a number of provisions related to water conservation and water

    supply planning, motivated by North Carolinas experience with the extreme

    drought of 2002 and a heightened awareness to focus more attention on

    assuring adequate water supply for future needs.

    House Bill 1215 dealt with two types of water conservation. The first type was

    conservation necessary on a short-term basis during droughts or other

    emergency situations. The second type was year-round water use efficiency. The

    bill directed the Department of Environment and Natural Resources (DENR) to

    pursue voluntary measures and incentives that increase long-range water useefficiency.

    Roanoke Rapids Sanitary District responded by adopting a set of Water Shortage

    Regulations in 2003 that addressed both conservation measures necessary on a

    short-term basis during droughts and year-round water use efficiency guidelines

    for its customers.

    Conservation is evident from per capita demand trend.Figure 2-10 shows a clear

    decrease in per capita demand between 2003 and 2004.

    AsFigure 2-10 shows, per capital demand has stabilized since 2004 varying from

    85 to 79 gpd. This report assumes conservation will continue in the future.

  • 8/10/2019 MasterPlan FinalReport Submitted

    33/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-16H&S Project No. 31144-000

    2.2.5 Recen t Water Use

    The percentage of water produced for each type of consumption is shown in

    Figure 2-11 for 2009.

    Figure 2-11: Percentage of Domestic, Wholesale, and Industrial WaterProduced in 2009

    Domestic

    (Residential and

    Commercial

    Customers)

    29%

    Dominion Co-Gen

    (Industrial)

    3%

    Halifax Linen

    (Industrial)

    2%

    Kapstone Paper

    (Industrial)

    5%

    Halifax County

    (Wholesale)

    31%

    Northampton

    County (Wholesale)

    7%

    Unmetered

    23%

    2009

  • 8/10/2019 MasterPlan FinalReport Submitted

    34/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-17H&S Project No. 31144-000

    2.3 Demand Projections and Water Requirements

    After examining historical production and billing trends as described above, this

    section describes demand projections and future water requirements.

    2.3.1 Ass ump tions for Project ions

    In order to project water use, we made assumptions based on our study of

    historical trends. Assumptions for projections are summarized below.

    a) Domestic water use of 85 gallons per person per day

    b) Population increase of approximately 120 people per year based on metertrend

    c) Domestic growth areas are shown inFigure 2-12,based on discussions withDistrict staff

    d) Halifax County maximum day demand for the design year is equal to theircurrent contractual maximum.

    e) Northampton County maximum day demand increases to 0.75 mgd by designyear

    f) The Town of Weldon will receive a maximum of 2.0 mgd by 2010 and willincrease its supply from the District by 10% by the design year

    g) For domestic, industrial, and wholesale demand, a maximum day peakingfactor of 1.57 was used

    h) Industrial consumption will increase by 10 percent by the design year for each

    of the three existing industrial customers

    i) Water demand for new industries will increase the total industrial demand by10 percent by the design year

    j) Industrial growth will occur in areas outside Roanoke Rapids city limits, butinside the District boundary as shown inFigure 2-13.This was based ondiscussions with District staff

    k) Peak hour demand multiplier is 1.3 for domestic, wholesale, and industrialwater users based on diurnal measurements made for the Districts InitialDistribution System Evaluation in 2007

    l) Design fire flow is 3,500 gpm, which is equivalent to 5.04 mgd

  • 8/10/2019 MasterPlan FinalReport Submitted

    35/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-18H&S Project No. 31144-000

    Figure 2-12: Anticipated Population Growth Areas for Residential andCommercial Customers in RRSD

  • 8/10/2019 MasterPlan FinalReport Submitted

    36/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-19H&S Project No. 31144-000

    Figure 2-13: Areas for Industrial Growth

  • 8/10/2019 MasterPlan FinalReport Submitted

    37/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-20H&S Project No. 31144-000

    2.3.2 Water Requirements Summary

    A summary of projected water requirements is shown inTable 2-4.

    A water audit (Appendix A) was part of the Water Distribution System Master

    Plan. Because the water audit revealed a notable amount of non-revenue water,a percentage for water loss was added to estimate total system demands. For

    future years, we assumed that the percent of water loss would decrease over

    time as infrastructure is renewed or repaired.

    Maximum day plus fire was the critical (largest) design flow for RRSD (15.9 mgd

    in 2030). Maximum day demands by 2030, 10.9 mgd, do not exceed the water

    treatment plants rated capacity of 12.5 mgd. However, District staff indicates that

    the plant cannot currently achieve the rated capacity and estimate a maximum

    treatment rate of 10 mgd.

    The limitations on plant capacity need to be addressed before the maximum day

    supply to the Town of Weldon can begin as shown inFigure 2-14. Figure 2-14

    shows historical and predicted average and maximum day demands compared to

    plant capacity.

  • 8/10/2019 MasterPlan FinalReport Submitted

    38/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 2-21H&S Project No. 31144-000

    Table 2-4: Projected Populations and Water Demands

    Water Requirement 2010 2020 2030

    Population Supplied 19,530 20,710 21,900

    Domestic Consumption (mgd) 1.66 1.76 1.86

    Industrial Use (mgd) 0.55 0.60 0.65

    Wholesale Demand (mgd) 3.10 3.44 3.78

    Non-Revenue Water (%) 20% 15% 10%

    Non-Revenue Water (mgd) 1.06 0.87 0.63

    Total Average Day Demand (mgd) 6.37 6.67 6.92

    Maximum Day Demand (mgd) 10.0 10.5 10.9

    Maximum Day Plus Fire (mgd) 15.0 15.5 15.9

    Peak Hour Demand (mgd) 13.0 13.7 14.2

    Note: See Section 3.1 for water requirement assumptions

    Figure 2-14: Water Requirements and WTP Capacity

    WTP Rated

    Capacity

    Average Day

    Historical

    Maximum Day

    Historical

    WTP ExistingEstimated Capacity

    Predicted

    Average Day

    Predicted

    Maximum Day

    0

    2

    4

    6

    8

    10

    12

    14

    1995 2000 2005 2010 2015 2020 2025 2030

    WaterProduction(mgd)

    Year

    Begin to Export

    Water to Town

    of Weldon

  • 8/10/2019 MasterPlan FinalReport Submitted

    39/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 3-1H&S Project No. 31144-000

    3 STORAGE AND PUMP EVALUATION

    Two important components of RRSDs water distribution system are storage and

    pumping. The storage and pumping capacities must be adequate for existing and

    future water requirements. Storage and pumping capacities were evaluated forexisting and future conditions as described in this chapter.

    3.1 Storage Requirements

    Storage serves three purposes in a water system: it supplements production

    during fires, equalizes demand on a daily basis, and supplies the system during

    emergencies (for a limited period of time).

    3.1.1 Elevated Sto rage

    Fire storage provides fire flows while the WTP supplies maximum day demand.

    For the worse case, we assumed a fire flow of 3,500 gpm for which the American

    Water Works Association (AWWA) recommends a design duration of 3 hours.

    Assuming a 3,500 gpm fire flow for 3 hours, the corresponding volume is 0.63

    million gallons for the fire storage requirement.

    Equalizing storage allows water to be pumped at a constant rate. Storage

    depletes when demand is above average and fills when below average. The

    amount of storage required depends on how much the demand varies. The

    variation in demand over a 24-hour period is called the diurnal curve. A diurnal

    curve was previously calculated from tank level data in a 2007 report titled

    Water Distribution System Model Update and Calibration by Highfill

    Infrastructure Engineering. This diurnal curve was examined, and the calculated

    equalizing requirement was 8 percent of the total water used in a day. The

    equalizing requirement is therefore 0.85 mg currently, 0.90 mg for 2020 and 0.94

    mg for 2030 as shown in Table 3-1.

    Equalizing storage and fire storage are usually combined to evaluate elevated

    storage. The elevated storage requirement was compared with existing elevated

    storage capacity to determine if more storage is needed.

  • 8/10/2019 MasterPlan FinalReport Submitted

    40/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 3-2H&S Project No. 31144-000

    Table 3-1: Water Distribution System Storage Evaluation

    Units 2008 2010 2020 2030

    Equalizing Storage

    Percent from diurnal curve 8% 8% 8% 8%

    Maximum Day mgd 8.08 10.03 10.51 10.90

    Storage Needed mg 0.64 0.79 0.83 0.86

    Fire Storage

    Design Fire Flow gpm 3,500 3,500 3,500 3,500

    Duration hrs 3 3 3 3

    Storage Needed mg 0.63 0.63 0.63 0.63

    Emergency Storage

    Percent to Meet State Regulations 50% 50% 50% 50%

    Average Day mgd 5.13 6.37 6.67 6.92

    Storage Needed mg 2.57 3.18 3.34 3.46

    Total Storage Requirement

    Elevated Storage mg 1.27 1.42 1.46 1.49Emergency Storage mg 2.57 3.18 3.34 3.46

    Existing Storage Capacity

    Gaston mg 0.15*

    Rapids Street mg 0.50

    11th Street mg 0.50

    Becker mg 0.50

    Rectangular WTP clearwell mg 1.25 (0)

    Circular WTP clearwell mg 2.00

    Roanoke / Davie mg 0.50

    I-95 mg 0.25

    Total mg 5.65 (4.4)

    Elevated Storage Summary

    Required (Fire plus Equalizing) mg 1.27 1.42 1.46 1.49

    Existing Capacity mg 1.65 1.65 1.65 1.65

    Surplus Storage mg 0.38 0.23 0.19 0.16

    Emergency Storage Summary

    Required (by State) mg 2.6 3.2 3.3 3.5

    Existing Capacity mg 5.65 5.65 5.65 (4.4) 5.65 (4.4)

    Surplus Storage mg 3.08 2.47 2.31 (1.1) 2.19 (0.9)

    Notes:WTP clearwells and County-owned tanks were not relied upon for equalizing or fire storage,

    but could be used in an emergency. The District is considering removing the rectangularWTP clearwell from operation due to its aging condition. Surplus emergency storagewould be 0.9 mg by 2030 in this case, as shown above in parentheses.

    * Gaston tank rated at 200,000 gallons but operating capacity closer to 0.15 mg

  • 8/10/2019 MasterPlan FinalReport Submitted

    41/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 3-3H&S Project No. 31144-000

    As shown in Table 3-1, there is sufficient elevated storage both now and for 2030

    (surplus of 0.16 mg and 2.19 mg, respectively).

    3.1.2 Emergency Storage

    Emergency storage supplies water when the normal sources are interrupted.Emergency storage requirements are typically compared to the total elevated

    and ground storage available in a system.

    According to the Rules of Governing Public Water System published by the North

    Carolina Department of the Environment, Health and Natural Resources,

    combined elevated and ground storage of finished water shall be a minimum of

    one-half a days supply of the average annual daily demand. This would be 3.18

    mg for 2010 and 3.46 mg for 2030 as shown in Table 3-1.

    Existing elevated and ground storage is 5.65 mg in total, or 4.4 mg if the

    rectangular clearwell is taken out of service. In either case, there is sufficient

    emergency storage currently and for 2030 projected demands. Therefore, RRSD

    meets the current and the future requirements for emergency storage.

    3.2 Pumping Evaluation

    The firm capacity of the pumps at the water plant must meet maximum day

    demands.Table 3-2 appears to show the existing pumps are adequate for

    current and future conditions. Firm capacity is defined as the rated capacity with

    the largest pump out of service (the Fairbanks Morse 400 hp pump in this case).

    All pumps need to be taken offline occasionally for repairs and/or maintenance,

    which means the remaining pumps in service must have enough capacity to

    meet demand.

    However, the diesel pump is not intended for regular use but as an emergency

    pump, should power be lost at the WTP. Excluding the diesel pump, the firm

    capacity is only 7.5 mgd, which is deficient.

  • 8/10/2019 MasterPlan FinalReport Submitted

    42/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 3-4H&S Project No. 31144-000

    Table 3-2: Pump Capacity Evaluation

    million gallons per day (mgd) 2008 2010 2020 2030

    Maximum Day Demand 8.08 10.03 10.51 10.90

    Total Pump Capacity 17.4 17.4 17.4 17.4

    Firm Pump Capacity 11.1 11.1 11.1 11.1

    Pump Capacity Deficit - - - -

    *Firm Pump CapacityNo Diesel 7.5 7.5 7.5 7.5

    *Pump Capacity DeficitNo Diesel 0.60 2.5 3.0 3.4

    *Assumes: Diesel pump (No. 4) is for emergency and short-term use only. Both inside pumpstation pumps cannot be operating at the same time.

    3.2.1 WTP Pump Recomm endat ions

    We recommend a new pump with the same rated flow as Pump 3 (4,400 gpm or

    6.34 mgd). The required head of a new pump was estimated by running the

    model under various demand conditions. Based on these results, we recommend

    a pump that is efficient in the range of 235 to 255 feet of total dynamic head.

    We also recommend testing Pump 2 (inside Fairbanks Morse) to determine the

    wire-to-water efficiency for evaluating its replacement. This pump is nearly 60

    years old and was designed for a TDH nearly 100 feet higher than existing

    conditions. This pump may be operating at low efficiencies. Measuring its

    efficiency would allow calculation of the time it would take to recover replacement

    costs through reduced power costs.

    3.2.2 Beck er Pump Station

    There is a new duplex pump station (completed November 2009) at the Becker

    Tank. The pumps were originally designed to pump 1,050 gpm at 70 TDH, but

    during factory testing each was able to pump 1,400 gpm. However; variable

    frequency drives (VFDs) will automatically limit flow to 1,200 gpm.

    There are two main purposes for the Becker Pump station. The main goal is to

    pull water out of the Becker Tank, because this tank is 10 feet lower than the

    Rapids Street and 11thStreet Tanks, and the altitude valve closes to prevent

  • 8/10/2019 MasterPlan FinalReport Submitted

    43/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 3-5H&S Project No. 31144-000

    overflows. Consequently, the Becker Farms tank historically has gone for weeks

    with little change in water level (little tank turnover). Inadequate tank turnover can

    cause water quality problems. The second objective of this pump station is to

    help deliver water south to Halifax County if demands rise with a new industrial

    park currently under development.

    District staff controls the pump station at the WTP, at the operator's discretion,

    with flow rate as an adjustable parameter. VFDs are programmed to allow pumps

    to run between 350 and 1200 gpm. There will be an automatic shut-off when the

    tank level drops to half full, thus maintaining a reserve for fire protection. The

    altitude valve on Becker tank can be controlled remotely enabling the operators

    to postpone filling the tank until system demands have dropped.

  • 8/10/2019 MasterPlan FinalReport Submitted

    44/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 4-1H&S Project No. 31144-000

    4 HYDRAULIC MODELING

    The hydraulic model was used for condition assessment by showing existing

    hydraulic conditions, and for examining the future conditions. Deficiencies were

    identified and the model was used to design improvements by studyingalternatives to correct existing problems and meet future demands. This chapter

    explains the way in which the model was used and the criteria for assessing

    modeling results. Results and recommendations are presented in the following

    chapters.

    4.1 Modeling Scenarios

    First, we modeled existing conditions for average day, maximum day, and peak

    hour demands to identify existing problems. Future demand scenario pressure

    problems and fire flow deficiencies were identified and alternatives were tested in

    the model to find the most efficient improvements that met design criteria. Peak

    hourly demands were used to evaluate system pressures because these

    demands represent the worst-case condition, with respect to pressure, that

    customers would experience. Maximum day demand plus fire demands could

    result in lower pressures, but fires are less common and the locations that would

    experience low pressure are highly dependent on the location and size of the fire.Average day conditions were used to examine water age as a surrogate for water

    quality. Average day demand conditions were used to evaluate water age

    because these demands represent the worst-case condition for water quality as

    velocities are lower and therefore water age higher.

    This hydraulic model used two types of simulations. The first type, steady state,

    analyzed one moment in time. Steady state simulations were used to help size

    pipes and pumps. The second type, extended period simulations, evaluate pumpand tank performance over time as well as water age.

  • 8/10/2019 MasterPlan FinalReport Submitted

    45/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 4-2H&S Project No. 31144-000

    4.2 Design Criteria

    We compared the models predicted performance with design criteria for :

    1. Pressures at the nodes

    2. Head losses and velocities in the pipes

    3. Fire flows

    4. Tank and pump performance

    4.2.1 Pressure

    There are generally three design criteria for pressures: maximum pressure,

    minimum pressure during peak hour, and minimum pressure during a fire flow.

    Generally, maximum pressures should be no greater than 150 psi which is the

    nominal pressure rating of some distribution system piping and fittings. Some

    utilities require pressure-reducing valves on the service lines to individual

    customers when pressures exceed 80 psi.

    The minimum pressure during peak hour refers to minimum pressure at

    customers taps during the highest demand. This value is typically in the range of

    30-50 psi and ensures that there is adequate pressure to second story fixtures.

    The minimum pressure during fire flows, as recommended by the National Fire

    Protection Association (NFPA), is 20 psi. This pressure is the minimum pressure

    anywhere in the distribution system. The value of 20 psi is used because it

    prevents backflow or groundwater contamination and provides head for

    overcoming the friction losses in the hydrant branch, hydrant, and suction hoses

    to the pumper truck during a fire.

    4.2.2 Head Lo ss and Velocit ies

    In general, a distribution system is considered to be deficient if the following

    conditions are predicted:

    1. Velocities greater than 5 ft/sec

    2. Head losses greater than 5 ft/1,000 ft (about 10 psi per mile)

  • 8/10/2019 MasterPlan FinalReport Submitted

    46/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 4-3H&S Project No. 31144-000

    When designing larger pipes (16-inch or greater) the goal is to keep head losses

    less than 2 ft/1,000 feet (about 5 psi per mile).

    Head losses and velocities exceeding the criteria can indicate excessive loss of

    energy, which might require additional pumping. They are not absolute limits,because even though the operating costs can be substantial over the life of the

    pipe, it must be compared to the capital cost of new pipes to correct the deficient

    piping. It is important to note that as velocity increases, pipe head losses

    increase exponentially. As velocities approach 10 ft/sec, the potential exists for

    other problems, such as water hammer, to emerge.

    4.2.3 Fire Flow s

    Table 4-1 summarizes needed fire flows for one-and two-family residences as

    recommended in the AWWA Manual of Practice on Distribution System

    Requirements for Fire Protection.

    Table 4-1: Needed Fire Flows for One- and Two-family Residences

    Distance Between Buildings (ft) Needed Fire Flow (gpm)

    More than 100 500

    31-100 750

    11-30 1,000

    Less than 11 1,400

    At 20 psi

    In the model, nodes on pipes with diameters less than 6 inches were not

    considered for fire flow analysis because fire hydrants are only allowed on

    pipelines that are 6-inches or larger, according to the Rules Governing Public

    Water Systems by the NC Department of Environment and Natural Resources.

  • 8/10/2019 MasterPlan FinalReport Submitted

    47/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 4-4H&S Project No. 31144-000

    4.2.4 Tank and Pump Performance

    Elevated storage tanks supply water for short periods of peak demand and

    should remain at least half full to maintain a reserve for fire protection or other

    emergencies.

    Tanks by themselves do not produce water to supply a distribution system

    because the net flow over 24 hours is zero. The 24-hour average demand must

    be supplied by the WTP and purchased supplies. WTP capacity plus purchased

    water must be equal to or greater than the maximum day demand of a water

    distribution system.

    Pump operations must ensure that the tanks cycle (fill and empty) enough to

    prevent excessive water age and thus ensure good water quality. General criteriafor pump operations is to allow the tank levels to drop as much as possible while

    still providing adequate fire flow and emergency storage. The larger the range in

    water level for each tank, the lower water age will be.

  • 8/10/2019 MasterPlan FinalReport Submitted

    48/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 5-1H&S Project No. 31144-000

    5 CONDITION ASSESSMENT

    The condition of the distribution system was assessed in three ways. The first

    was by performing field tests. The second was by examining RRSD records and

    interviewing District staff to deduce the age and condition of the pipes. The thirdwas running the hydraulic model under existing demands and operations to

    determine pressures and available fire flows system-wide.

    5.1 Field Tests

    Field tests help show the general condition of the existing piping system. These

    tests serve three purposes:

    1. Produce input data needed for the hydraulic model

    2. Obtain information for calibrating the model

    3. Check for unusual conditions such as closed valves or mapping errors

    Four types of tests were performed for this master plan. They included a master

    meter test, hydraulic gradient tests, C-factor or loss of head tests, and fire flow

    tests. These tests were used to further validate the model, which was last

    calibrated in 2007, and check for any unusual conditions as discussed below.

    5.1.1 Master Meter TestA meter test compares master meter registration to flow rates measured by

    another instrument. Our meter tests compare meter registration to pitot tube

    measurements of the flow in a pipe, rather than simply checking electronic

    calibration of a transducer. Many meters, including the D istricts master meter at

    the WTP, have a primary device (a Venturi tube in this case), and a secondary

    element, such as a differential pressure transducer, which converts the physical

    output to an electronic signal. An inaccurate primary device causes meter error

    even if the secondary element is calibrated correctly.

    The master meter test was conducted on September 15, 2009. It compared the

    meter totalizer for the 20-inch pipe leaving the WTP to pitometer flow

    measurements. Pitometers are pitot tubes that are inserted into a pipe through a

    corporation tap which the District installed prior to testing. Flowing water

  • 8/10/2019 MasterPlan FinalReport Submitted

    49/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 5-2H&S Project No. 31144-000

    produced a differential pressure between the upstream and downstream orifices

    of the pitot tube. Water velocities were calculated from the measured differential

    pressures. The average velocity was determined by conducting a velocity profile

    along the vertical diameter of the 20-inch pipe, as shown byFigure 5-1. The

    profile has a typical bullet shape for velocities within a pipe. The inside diameter

    was measured with a pipe caliper. The area of the pipe was calculated from the

    diameter, and the flow rate was determined by multiplying the area of the pipe by

    the average velocity.

    Figure 5-1: Velocity Profile for 20-inch Pipe

    Table 5-1 shows the results of the meter test. The 20-inch meter was tested for

    five different flow rates. The different flow rates were achieved by running

    various pump combinations.

    0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    20

    0.5 1.5 2.5 3.5 4.5

    Distanc

    efromBottom-inches

    Velocity - feet per second

    Average Maximum Minimum

  • 8/10/2019 MasterPlan FinalReport Submitted

    50/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 5-3H&S Project No. 31144-000

    Table 5-1: Master Meter Test

    Description Results

    Location Roanoke Rapids WTP

    Name BIF Series 41969Meter Size 20 X 13.318Multiplier 1,000,000

    Gauging Point DataPipe Size - inches 20

    Inside Diameter - inches 20.250Velocity Factor 0.706

    Test Date - 2009 September 15

    Test Number: 1

    2 3 4 5Totalizer Registration- gal 0.062 0.078 0.145 0.087 0.117*Elapsed Time - minutes 29.71 29.97 30.43 16.05 19.86Pump(s) In Use:

    No. 1: PACO X X XNo. 2: Inside FM XNo. 3: Outside 400 HP X X X

    Pitometer Flow - mgd 2.87 4.03 7.44 8.57 9.35Master Meter Flow - mgd 3.01 3.75 6.86 7.81 8.48

    Totalizer Error 4.6% -7.0% -7.8% -8.9% -9.2%

    Notes: * Control valve to Gaston closed during test. Negative sign indicates meter is under-registering flow

    Flow outside design range of meter. Test disregarded.

    The lowest flow showed the meter was over-registering. This flow was outside

    the design range of the meter, so the result was disregarded. The next four flow

    rates consistently indicated the meter was under-registering between 7.0% and

    9.2%. This is a significant inaccuracy.

    We recommend contacting the master meter manufacturer or supplier to adjust

    the primary and/or secondary metering element to agree with measured flows.

    We also recommend that all system master meters have their primary devices

    tested annually to verify their performance.

  • 8/10/2019 MasterPlan FinalReport Submitted

    51/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 5-4H&S Project No. 31144-000

    Remaining field tests and the water audit (Appendix A) accounted for the under-

    registering meter when flow rates were used in calculations.

    5.1.2 Hydrau l ic Gradient Tests

    Hydraulic gradient is the change in hydraulic grade line (HGL) with distance.The HGL is the ground elevation plus water pressure expressed in feet.

    Hydraulic gradient tests consist of simultaneous flow and pressure

    measurements along trunk mains between the water plant and tanks. Plotting

    measured HGLs versus distance shows where head loss occurs along

    important trunk mains. Comparing measured HGLs and flows with model

    predictions is a method of calibrating the model.

    Two hydraulic gradient tests were performed for this study. Test 1 traced the

    hydraulic gradient from the WTP to Rapids Street Tank. The test also

    measured HGLs at two sites along the 20-inch pipe in Henry Street. The test

    was conducted for two conditions: with a large flow from the water plant

    (HGL 1-A) and with a fire hydrant flowing at 11 thStreet (HGL 1-B) as shown in

    Figure 5-2.Test 2 traced the hydraulic gradient from the WTP to Becker Farm

    Tank with large flow from the water plant as shown inFigure 5-3.

    TheTable 5-2 shows the results from the HGL field tests compared to the

    model results. The locations of the measurements are shown inFigure 5-2

    andFigure 5-3 for reference.

    To match the model to the measurements for HGL 1, we had to assume

    several valves were closed as shown inFigure 5-4.For HGL 1-A, the model

    calibration indicates that a 12-inch valve is closed on 8 thStreet between

    Wilson Street and Rapids Street Tank. Valve status records indicate a broken

    valve in that area. Due to the age of the system, valves that are broken in the

    closed position are not surprising. We recommend locating the closed valve

    and repairing or replacing it as soon as possible to improve fire flow

    availability.

  • 8/10/2019 MasterPlan FinalReport Submitted

    52/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 5-5H&S Project No. 31144-000

    Figure 5-2: Hydraulic Grade Line Test 1, WTP to Rapids Tank

  • 8/10/2019 MasterPlan FinalReport Submitted

    53/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 5-6H&S Project No. 31144-000

    Figure 5-3: Hydraulic Grade Line Test 2, WTP to Becker Farm Tank

  • 8/10/2019 MasterPlan FinalReport Submitted

    54/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 5-7H&S Project No. 31144-000

    Table 5-2: Hydraulic Grade Line (HGL), Calibration Results

    Location Distance (ft)MeasuredHGL (ft)

    CalibratedModel HGL (ft)

    HGL 1-A

    WTP - 350 352

    Henry Street & 1st Street 3,500 345 345Franklin Street & 5th Street 6,400 340 340

    Bolling Road & Wilson Street 8,300 340 340

    Rapids Street Tank 10,500 327 327

    HGL 1-B

    WTP - 335 333

    Henry Street & 1st Street 3,500 330 330

    Franklin Street & 5th Street 6,400 327 327

    Henry Street & 8th Street 8,800 325 327

    Franklin Street & 11th Street 11,100 304 305

    HGL 2

    WTP - 354 353311 Carolina Street 5,300 339 339

    Carolina Street & 8tStreet 8,200 335 335

    11th Street Tank 10,800 322 322Kelly Street & Long Circle 15,600 313 312

    Old Farm Road 20,900 306 306

    Becker Farm Tank 22,100 305 305

    Notes

    The Gaston control valve was open during all HGL tests. Pumps 1 and 3 operating. Measured = 8.49 mgd, model = 8.37 mgd (1.4 % difference).Pump 3 operating, hydrant flow on 11thStreet was 460 gpm (measured and model)Pumps 1 and 3 operating. Measured = 8.68 mgd, model = 8.57mgd (1.3% difference).

    For HGL 1-B, the model calibration indicates that two valves are closed near

    the location of the flowing hydrant on 11thStreet (near the ball park).Figure

    5-5 shows the most likely locations of these closed valves. Again, we

    recommend locating the closed valves and repairing or replacing them as

    soon as possible to improve fire flow availability.

    For HGL 2, only minor modifications to the modelsroughness coefficients

    and elevations were made to calibrate the predicted HGLs with the field

    measurements. Results are shown inTable 5-2 andFigure 5-6.Notable is the

    steep loss in head between 8thStreet and 11thStreet. This loss is due to a

    restriction in the system as water flows through 16-inch pipes until it reaches

    10thStreet where the pipe sizes reduce to 8-inches until reaching the 11th

    Street Tank.

  • 8/10/2019 MasterPlan FinalReport Submitted

    55/163

  • 8/10/2019 MasterPlan FinalReport Submitted

    56/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 5-9H&S Project No. 31144-000

    Figure 5-5: Pipes with Possible Closed Valves near 11 thStreet Ball Park

    Figure 5-6: HGL 2, Calibration Results

    WTP

    11thStreet

    Tank

    KellySt&Long

    Circle

    BeckerFarmTank

    280

    290

    300

    310

    320

    330

    340

    350

    360

    0 5,000 10,000 15,000 20,000 25,000

    HGL-feet

    Distance - feet

    Calibrated Model Measured

  • 8/10/2019 MasterPlan FinalReport Submitted

    57/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 5-10H&S Project No. 31144-000

    District staff notes that the Roanoke Rapids Fire Department, approximately ten

    years ago, had inadequate fire flow in the area during a fire at the Heilig-Meyers

    Furniture Store, likely due to the hydraulic constriction.

    5.1.3 C-Facto r TestsC-factor tests, also called loss of head tests, determine the friction coefficient C

    in the Hazen-Williams equation. This equation relates head loss to the flow in a

    pipe with the coefficient, a smoothness indicator. A typical coefficient of a new

    pipe is 140. Computer models need accurate C-factor data to simulate hydraulic

    performance.

    Each test consisted of measuring flow, head loss and pipe length, and calculating

    the coefficient for a known pipe diameter. Flow was measured using a hydrant

    pitot blade or a meter at the water plant. Head loss was measured using digital

    pressure gauges connected to hydrants on the upstream and downstream ends

    of the test section. The length of the test section was measured using a

    measuring wheel or scaled from the hydraulic model

    Table 5-3 shows the results of the loss of head tests. Not surprisingly for an

    unlined pipe installed before 1935, the C factor along Roanoke Avenue was low

    (43) indicating the interior of the pipe is tuberculated and head losses are high.

    The pipe segments tested along 2ndStreet and 10thStreet were installed around

    1947 based on available maps of the distribution system and hydrant dates.

    Lined pipe did not become predominant for most water distribution systems until

    after World War II. Although these pipes were installed around 1947, shortly after

    World War II ended, the results of the C-factor test make it clear that the two test

    segments were unlined cast iron based on their low C-factors (Table 5-3). The

    low C-factor indicates significant tuberculation and high head losses. We

    assumed other pipes installed in 1947 were also unlined.

    We attempted to conduct a C-factor test on one of the pipes near the WTP. This

    was not possible because the valves in the yard of the WTP were inoperable.

    Therefore, the test was cancelled.

  • 8/10/2019 MasterPlan FinalReport Submitted

    58/163

  • 8/10/2019 MasterPlan FinalReport Submitted

    59/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 5-12H&S Project No. 31144-000

    Figure 5-7: Hydraulic Grade Line, WTP to Craige Street

    This pipe is most likely lined ductile iron and a C-factor of at least 120 was

    expected. A photograph of 45-degree bend removed in 2008 confirms that the

    interior of the pipe is fairly smooth as shown inFigure 5-8. Figure 5-8,however,also shows an expansion coupling from the same pipeline removed in the same

    year. The coupling was highly tuberculated indicating the C factor could be much

    lower. The pipe condition was inconsistent from these photographs. We

    recommend investigating this section of pipe by installing taps for pressure and

    flow measurements.

    GastonMeter

    SouthSideofBridge

    HydrantonCraige

    295

    300

    305

    310

    315

    320

    325

    330

    335

    340

    0 1,000 2,000 3,000 4,000 5,000 6,000

    Head(elevation+pressurein

    feet)

    Distrance from Gaston Meter (ft)

    Model

    Measured (+)

    Measured

    Measured (-)

    Calculated C-factor

    ranges from 13 to 44

    Calculated C-factor ranges

    from 33 to 113

    Assumed C-factor of 120

  • 8/10/2019 MasterPlan FinalReport Submitted

    60/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 5-13H&S Project No. 31144-000

    Figure 5-8: Gaston Road 12-Inch Pipe Fittings Removed in 2008

    45-Degree Bend

    Expansion Coupling

  • 8/10/2019 MasterPlan FinalReport Submitted

    61/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 5-14H&S Project No. 31144-000

    5.1.4 Fire Flow Tests

    Fire flow tests show the strengths and weaknesses of the system at particular

    test locations and the test measurements can be used to calibrate models.

    Figure 5-9 shows the location of fire flow tests we performed for the District.

    A fire flow test consists of measuring the static pressure with the hydrants closed,

    then opening a nearby hydrant and measuring the residual pressure and the flow

    rate.

    Table 5-4 summarizes the fire flow test results. The table shows the location of

    the test, and static and residual pressures of the test hydrant. The table also

    shows the flow during the test and the available flow at 20 psi, which is the

    lowest acceptable pressure in a water system.

    Estimated needed fire flows, which depend on land use (types and sizes of

    buildings) are shown inFigure 2-6 and are also included inTable 5-4. Only one

    location was deficient because the needed flow exceeded the available flow.

    Improvements to reinforce these areas are discussed in a later chapter.

    The fire flow tests were also used for further model calibration as shown in Table

    5-5.Minor model adjustments were made to elevations and C-factors in most

    cases. All fire flow tests were within 3 psi of model predictions except for one.Fire flow tests which indicated unexpected conditions are discussed in detail

    below.

  • 8/10/2019 MasterPlan FinalReport Submitted

    62/163

    Roanoke Rapids Sanitary DistrictDistribution System Master Plan 5-15H&S Project No. 31144-000

    Figure 5-9: Fi