    Integrated Port Masterplanning

    43rd International Port Seminar, April 2007

    Prof. Han Ligteringen

  • 8/10/2019 Masterplanning Process

    2/29

    April 26, 2007 2

    Integral Port Planning

    Longterm: horizon 20 years

    Masterplan National/ Regional

    Individual port

    Medium term: 3-5 years

    Short term: 1 year

  • 8/10/2019 Masterplanning Process

    3/29

    April 26, 2007 3

    Rolling masterplan

  • 8/10/2019 Masterplanning Process

    4/29

    April 26, 2007 4

  • 8/10/2019 Masterplanning Process

    5/29

    April 26, 2007 5

    Lay-out design aspects

    Nautical requirements

    Hydraulic requirements

    Quay and Terminal dimensions

    Hinterland connections

    In addition: technical considerations

    environmental/ legal requirements

  • 8/10/2019 Masterplanning Process

    6/29

    April 26, 2007 6

    Technical considerations

    Balance of cut and fill

  • 8/10/2019 Masterplanning Process

    7/29

    April 26, 2007 7

  • 8/10/2019 Masterplanning Process

    8/29

    April 26, 2007 8

    Technical considerations

    Balance of cut and fill

    Angle between approach channel and mainwave direction

  • 8/10/2019 Masterplanning Process

    9/29

    April 26, 2007 9

  • 8/10/2019 Masterplanning Process

    10/29

    April 26, 2007 10

    Technical considerations

    Balance of cut and fill

    Angle between approach channel and main wavedirection

    Breakwater alignment

  • 8/10/2019 Masterplanning Process

    11/29

    April 26, 2007 11

  • 8/10/2019 Masterplanning Process

    12/29

    April 26, 2007 12

    Technical considerations

    Balance of cut and fill

    Angle between approach channel and main wavedirection

    Breakwater alignment

    Bends in the approach channel

  • 8/10/2019 Masterplanning Process

    13/29

    April 26, 2007 13

    Technical considerations

    Balance of cut and fill

    Angle between approach channel and main wavedirection

    Breakwater alignment

    Bends in the approach channel

    Morphological aspects

  • 8/10/2019 Masterplanning Process

    14/29

    April 26, 2007 14

    Technical considerations

    Balance of cut and fill

    Angle between approach channel and main wavedirection

    Breakwater alignment

    Bends in the approach channel

    Morphological effects

    Safety of berth locations

  • 8/10/2019 Masterplanning Process

    15/29

    April 26, 2007 15

    Environmental/ legal requirements

    Masterplan process (Fig. 4-2) shows only the

    technical side How does this fit in the overall process of planning,

    (political) decision making, financing and realisation?

    Example: Expansion Rotterdam port.

  • 8/10/2019 Masterplanning Process

    16/29

  • 8/10/2019 Masterplanning Process

    17/29

    April 26, 2007 17

    Realisation Basic Infrastructure

    Port Authority Government

    Finalisation Masterplan

    Phase 1

    Designs Permit appl.

    Detailed EIA Submit

    Tender Doc. Bid Process

    Selection Contract

    Construction - Completion

    Approval

  • 8/10/2019 Masterplanning Process

    18/29

    April 26, 2007 18

    Design Permit appl.

    Tender Doc. Bid Process

    Selection Contract

    Construction - Completion

    Operator Government

    Approval

    Realisation Terminal Facilities

  • 8/10/2019 Masterplanning Process

    19/29

    April 26, 2007 19

    Port of Rotterdam expansion project

    Maasvlakte 2

    History of the project

    Decision-making process

    Project studies

  • 8/10/2019 Masterplanning Process

    20/29

    April 26, 2007 20

    Western Europe

  • 8/10/2019 Masterplanning Process

    21/29

    April 26, 2007 21

    Existing Maasvlakte

  • 8/10/2019 Masterplanning Process

    22/29

    April 26, 2007 22

  • 8/10/2019 Masterplanning Process

    23/29

    April 26, 2007 23

    Evolvement port lay-out

    Plan Studies: 3 basic alternatives

    EIA for maximum area C/B only acceptable for minimum development

  • 8/10/2019 Masterplanning Process

    24/29

    April 26, 2007 24

    Basic Alt. A

  • 8/10/2019 Masterplanning Process

    25/29

    April 26, 2007 25

    Basic Alt. B

  • 8/10/2019 Masterplanning Process

    26/29

    April 26, 2007 26

    Basic Alt. C

  • 8/10/2019 Masterplanning Process

    27/29

    April 26, 2007 27

    Evolvement Port lay-out

    Plan Studies: 3 basic alternatives

    EIA for maximum area C/B only acceptable for minimum development

    Gov. Decision and Financing: revised minimum lay-out

    Finalisation Masterplan: ?

  • 8/10/2019 Masterplanning Process

    28/29

    April 26, 2007 28

    Present

    MasterplanLay-out

  • 8/10/2019 Masterplanning Process

    29/29

    April 26, 2007 29

    Environmental Requirements

    Gov. Decision end 1996: dual purpose (economic

    development and 750 ha nature) EIA procedure: compensation of lost sea area with

    sea reserve area.

    Governement finalapproval in 2003, but rejection inhighest legal body (State Council).

    Further EIA studies to refute objections,

    approval mid-2006, poject delay of about 1 year.