material requirement planning - kocwcontents.kocw.net/kocw/document/2014/hanyang/... · •material...
TRANSCRIPT
Material Requirement Planning
Lecture-7Dr. Biswajit Sarkar
Dept. of Industrial & Management EngineeringHanyang University
South Korea
Books Reference
• 1. Analysis of Manufacturing Systems
by J. E. Rooda and J. Vervoort
• 2. Production/ Operations Management by William J. Stevenson, IRWIN publisher, ISBN 0-256-13900-8
Content
• Dependent versus Independent Demand
• MRP Inputs
• MRP Processing
• MRP Outputs
• Other Considerations
• Capacity Requirements Planning
• Benefits and Requirements of MRP
Dependent versus Independent Demand
When demand for items is derived from plans to make certain
products, it is with raw materials, parts, and subassemblies used in
producing a finished product, those items are said to have
dependent demand.
Independent demand is fairly stable once allowances are made for
seasonal variation; but dependent demand tends to be irregular or
"lumpy"; large quantities are used at specific points in time with
little or no usage at other times.
MRP Inputs• Material requirements planning (MRP) is a computer-based
information system designed to handle ordering and scheduling
of dependent-demand inventories (e.g. raw materials, component
parts, and subassemblies).
• A production plan for a specified number of finished products is
translated into requirements for component parts and raw
materials working backward, using lead time information to
determine when and how much to order.
• An MRP system has three major sources of information:
– a master schedule,
– a bill-of-materials file,
– an inventory record file
Master schedule
• The master schedule states which end items are to be
produced, when they are needed, and in what quantities.
Table illustrates a portion of a master schedule that shows
planned output for end item X for the planning horizon. The
schedule indicates that 100 units of X will be needed (e.g.,
for shipments to customers) at the start of week 4 and that
another 150 units will be needed at the start of week 8.
Table for a portion of master schedule
Item: X 1 2 3 4 5 6 7 8
Quantity 100 150
Although a master production schedule has no set time period
that it must cover, most managers like to plan enough into the
future so they have some general idea of probable upcoming
demands for the near term.
It is important, though, that the master schedule cover the
stacked or cumulative lead time necessary to produce the end
items. This amounts to the sum of lead times that sequential
phases of the production or assembly process require, as
illustrated in Figure, where the lead time is needed from
ordering parts and raw materials until final assembly is
completed.
Master schedule
Assembly
Subassembly
Fabrication
Procurement
1 2 3 4 5 6 7 8 9 10
Figure The planning horizon must cover the cumulative lead time
Master schedule
• A bill of materials (BOM) contains a listing of all of the
assemblies, subassemblies, and raw materials that are needed to
produce one unit of a finished product. Thus, each finished
product has its own bill of materials.
• A product structure tree is useful in illustrating how the bill of
materials is used to determine the quantities of each of the
ingredients (requirements) needed to obtain a desired number of
end items.
• Let's consider the product structure tree shown in Figure.
Bill-of-Materials (BOM) File
Chair
Leg Assembly
Legs Cross bar
Seat Back assembly
Side rails Cross bar Back support
Bill-of-Materials (BOM) File
Assembly diagram product structure tree for chair assembly
• The inventory records file is used to store information on
the status of each item by time period. This includes gross
requirements, scheduled receipts, and expected amount on
hand. It also includes other details for each item, such as
supplier, lead time, and lot size. Changes due to stock
receipts and withdrawals, canceled orders, and similar
events also are recorded in this file.
Inventory Records Files
• MRP processing takes the end-item requirements specified by the
master schedule ,: "explodes" them into time-phased requirements for
assemblies, parts, and raw materials using the bill of materials offset
by lead times.
• The quantities that are generated by exploding the bill of materials are
gross requirement. They do not take into account any inventory that is
currently on hand or due to the received.
• The materials that must actually be acquired to meet the demand
generated by the schedule are the net material requirements.
• Gross requirements: The total expected demand for an item or raw
material during each time period without regard to the amount on
hand. For end items, these quantities are shown in master schedule;
for components, these quantities are derived from the planned-order
releases of their immediate “parents”.
• Net requirements: The actual amount needed in each time period.
MRP Processing
• Scheduled receipts Open orders scheduled to arrive from
vendors in the pipeline by the beginning of a period.
• Projected on hand The expected amount of inventory that will
be on hand at the beginning of each time period: Scheduled
receipts plus available inventory from last period.
• Planned-order receipts The quantity expected to be received
by the beginning the period in which it is shown. Under lot-for-
lot ordering, this quantity will equal net requirements. Under lot
size ordering, this quantity may exceed net requirement. Any
excess is added to available inventory in the next time period.
• Planned-order releases It indicates an expected amount to order
in each time period; equals planned-order receipts offset by lead
time. This amount makes gross supplies at the next level in the
production chain. When an order is executed, it is removed from
planned-order releases and entered under scheduled receipts.
MRP Processing
• MRP systems have the ability to provide management with a fairly
broad range of outputs. These are often classified as primary reports,
which are the main reports, and secondary reports, which are optional
outputs.
• Production, inventory planning, and control are part of primary
reports. These reports normally include the following:
• Planned orders a schedule indicating the amount and timing of
future orders.
• Order releases authorizing the execution of planned orders.
• Changes to planned orders, including revisions of due dates or order
quantities and cancellations of orders.
MRP Outputs
• Secondary Reports Performance control, planning, and exceptions
belong to secondary reports.
• Performance-control reports are used to evaluate system operation.
They aid managers by measuring deviations from plans, including
missed deliveries and stock-outs, and by providing information that
can be used to assess cost performance.
• Planning reports are useful in forecasting future inventory
requirements. They include purchase commitments and other data
that can be used to assess future material requirements.
• Exception reports call attention to major discrepancies such as late
and overdue orders, excessive scrap rates, reporting errors, and
requirements for nonexistent parts. The wide range of outputs
generally permits users to adapt MRP to their particular need.
MRP Outputs
Others Considerations Safety StockTheoretically, inventory systems with dependent demand should not
require safety stock below the end-item level. This is one of the main
advantages of an MRP approach.
Apparently, safety stock is not needed because usage quantities can be
projected once the schedule has been established.
Practically, however, there may be exceptions. For example, a bottleneck
process or one with varying scrap rates can cause shortages in
downstream operations. Furthermore, shortages may occur if orders are
late or fabrication or assembly times are longer than expected. On the
surface, these conditions advance themselves to the rule of safety stock
to maintain smooth operations, but the problem becomes more
complicated when dealing with multi-echelon items because a shortage
of allow component will prevent manufacture of the final assembly.
However, a major advantage of MRP is lost by holding safety stock for
all lower-level item.
MRP systems deal with different problems in several ways. Manager's
first step to identify activities or operations that are subject to variability
and to determine the extent of that variability.
When lead times are variable, the concept of safety little instead of safety
stock is often used. This results in scheduling orders for arrival or
completion sufficient ahead of the time they are needed in order to
eliminate or substantially reduce the element of chance in waiting for
those items.
When quantities tend to vary, some safety stock may be called for, but
the manager must carefully consider the need and cost of carrying extra
stock. Frequently, managers elect to carry safety stock for end items,
which are subject to random demand, and for selected lower level
operations when safety time is not feasible.
Others Considerations Safety Stock
Choosing a lot size to order or for production is an important issue in
inventory management for both independent and dependent-demand
items. This is called lot sizing. For independent-demand items, economic
order sizes and economic run sizes are often used. For dependent-
demand systems, however, a much wider variety of plans is used to
determine lot sizes, mainly because no single plan has a clear advantage
over the others. Some of the most popular plans for lot sizing are
described in this section.
A primary goal of inventory management for both independent- and
dependent-demand systems is to minimize the sum of ordering cost (or
setup cost) and holding cost. With independent demand, that demand is
frequently distributed uniformly throughout the planning horizon (six
months, year). Demand tends to be much more lumpy for dependent
demand, and the planning horizon shorter (e.g., three months), so that
economic lot sizes are usually much more difficult to identify.
Others Considerations Lot Sizing
• Managers can realize economies by grouping order or run sizes. This
would be the case if the additional cost incurred by holding the extra
units until they were used led to a savings in setup or ordering cost.
This determination can be very complex at times, for several reasons.
• First, combining period demands into a single order, particularly for
middle-level or end items, has a cascading effect down through the
product tree; that is, in order to achieve this grouping, items at lower
levels in the tree must also be grouped, and their setup and holding
costs must also be incorporated into the decision.
• Second, the irregular period demand and the relatively short planning
horizon require a continual recalculation and updating of lot sizes. The
methods used to handle lot sizing range from the complex, which
attempt to include all relevant costs, to the very simple, which are
easy to use and understand. In certain cases, the simple models seem
to approach cost minimization although generalizations are difficult.
Let's consider some of these models:
Others Considerations Lot Sizing
Some Models LOT-FOR-LOT• Lot-for-Lot Ordering perhaps the simplest of all the methods is lot-
for-lot ordering. The order or run size for each period is set equal to
demand for that period.
• Not only is the order size obvious, but it also virtually eliminates
holding costs for parts carried over to other periods. Hence, lot-for-lot
ordering minimizes investment in inventory. Its two chief drawbacks
are that it usually involves many different order sizes and thus cannot
take advantage of the economies of fixed order size (e.g., standard
containers and other standardized procedures), and it involves a new
setup for each run. If setup costs can be significantly reduced, this
method may approximate a minimum-cost lot size.
Some Models EOQ• Sometimes economic order quantity models (EOQ) are used. They
can lead to minimum costs if usage is fairly uniform, This is
sometimes the case for lower-level items that are common to different
parents and for raw materials. However, the more lumpy demand is,
the less appropriate such an approach is. As demand
tends to be most lumpy at the end-item level, EOQ models tend to be
less useful for end items than for items and materials at the lowest
levels.
Some Models Fixed-Period Ordering • This type of ordering provides coverage for some predetermined
number of periods (e.g., two or three). In some instances, the span is
simply arbitrary; in other cases, a review of historical demand patterns
may lead to a more rational designation of a fixed period length. A
simple rule is: Order to cover a two-period interval. The rule can be
modified when common sense suggests a better way.
Some Models Part-Period Model • Another attempt to balance setup and holding costs is represented by
the part-period model. The term part period refers to holding a part or
parts over a number of periods.
• For instance, if 10 parts were held for two periods, this would be 10 X
2 = 20 part periods. The economic part period (EPP) can be computed
as the ratio of setup costs to the cost to hold a unit for one period.
• Thus, the formula for computing the EPP is
• EPP=Setup cost/Unit holding cost per period.
• In order to determine an order size that is consistent with the EPP,
various order sizes are examined for a planning horizon, and each
one's number of part periods is determined. The one that comes
closest to the EPP is selected as the best lot size. The order sizes that
are examined are based on cumulative demand.
Capacity Requirement Planning
• Capacity requirements planning is the process of determining short-
range capacity requirements. The necessary inputs include planned-
order releases for MRP, the current shop load, routing information,
and job times. Outputs include load reports for each work
center. When variances (underloads or overloads) are projected,
managers might consider remedies such as alternative routings,
changing or eliminating lot sizing or safety stock requirements, and lot
splitting. Moving production forward or backward can be extremely
challenging because of precedence requirements and the availability
of components.
Benefit and Requirement of MRP• 1. Low levels of in-process inventories.
• 2. The ability to keep track of material requirements.
• 3. The ability to evaluate capacity requirements generated by a given
master schedule.
• 4. A means of allocating production time.
• Production planners are obvious users of MRP Production managers,
who must balance work loads across departments and make decisions
about scheduling work, and plant foremen, who are responsible for
issuing work orders and maintaining production schedules, also rely
heavily on MRP output. Other users include customer service
representatives, who must be able to supply customers with projected
delivery dates, purchasing managers, and inventory managers. The
benefits of MRP depend in large measure on the use of a computer to
maintain up-to-date information on material requirements.
Benefit and Requirement of MRP• A computer and the necessary software programs to handle
computations and maintain records.
• Accurate and up-to-date:
• Master schedules
• Bills of materials
• Inventory records
• Integrity of file data
Benefit and Requirement of MRP• Accuracy is absolutely essential for a successful MRP system.
Inaccuracies in inventory record files or bills-of-material files can lead
to unpleasant surprises, ranging from missing parts, ordering many
of some items and too few of others, and failure to stay on schedule,
all of which contribute to inefficient use of resources, missed delivery
dates, and poor customer service. Moreover, implementing MRP can
be difficult and costly. Consequently, it is important for companies
considering an MRP system to be aware of this and to carefully
consider these factors against the benefits of MRP.
Benefit and Requirement of MRP• Unfortunately, some firms that have attempted to install an MRP
system have seriously underestimated the importance of these items.
In many cases, bills of materials are outdated because design changes
were not incorporated into the records, leading to parts lists that
did not correspond to actual requirements for assembly of the finished
product. It is not unusual for a firm to discover that the same part is
carried under different part numbers, making it difficult to develop
meaningful records.
• On the whole, the introduction of MRP has led to major improvements
in scheduling and inventory management, but it has not proved to be
the cure-all that many hoped. Consequently, manufacturers are
beginning to take a much broader approach to resource planning.
• One such approach is referred to as MRP II.
Q & A
Thanks For Your Kind Attention