Page 1: MATERIALS ACCEPTANCE. LPA Construction chapter -2 paragraphs on -Materials Quality Control -Materials Finalization -andAppendix J -LPA materials acceptance

MATERIALS ACCEPTANCE

Page 2: MATERIALS ACCEPTANCE. LPA Construction chapter -2 paragraphs on -Materials Quality Control -Materials Finalization -andAppendix J -LPA materials acceptance

MATERIALS ACCEPTANCE

• LPA Construction chapter- 2 paragraphs on

- Materials Quality Control- Materials Finalization- and Appendix J

- LPA materials acceptance processes should match ODOTs BUT their issues - more manual work (No CMS/SM)- Unfamiliar - No planning

Page 3: MATERIALS ACCEPTANCE. LPA Construction chapter -2 paragraphs on -Materials Quality Control -Materials Finalization -andAppendix J -LPA materials acceptance

MATERIALS ACCEPTANCE

• Planning issues – before they sell the job – Who will do testing for asphalt and concrete– Who will be testing/inspecting Bridge Paint– Who will do fabrication inspection for steel or

prestressed– I have “As Per Plan or Specials” how are they

equal or better than ODOT specs?– How will I control – track materials to Bid items

Project Bill of Materials– Checklist - NEW

Page 4: MATERIALS ACCEPTANCE. LPA Construction chapter -2 paragraphs on -Materials Quality Control -Materials Finalization -andAppendix J -LPA materials acceptance

MATERIALS ACCEPTANCE• Understand Non-conformance Policy for

Materials– Specification 106.07– Proposal Note 8

• PN 008 - 01/15/2010 - SPECIFICATION AND SUPPLEMENTAL SPECIFICATIONS, POLICIES AND SPECIAL PROVISIONS INCORPORATED BY REFERENCE AS IF REWRITTEN HEREIN

• Policy 27-009 (P) Acceptance of Non-specification Material on Construction Projects

• Standard Procedures:510-009 (SP) Acceptance of Nonspecification Material on Construction Projects

Page 5: MATERIALS ACCEPTANCE. LPA Construction chapter -2 paragraphs on -Materials Quality Control -Materials Finalization -andAppendix J -LPA materials acceptance

MATERIALS ACCEPTANCE

• After Contract–Develop the Project Bill of Material – Require the Contractor supplier list?

(example)• Make sure the Contractor also provides a list of materials to

be used by all of the subcontractors, too.• Are the suppliers correct

–Documenting materials• Use C&MS Section 700 for documentation guidance • Temporary materials are to be documented in this manner

as well.

Page 6: MATERIALS ACCEPTANCE. LPA Construction chapter -2 paragraphs on -Materials Quality Control -Materials Finalization -andAppendix J -LPA materials acceptance

ACCEPTANCE OF WORK

Page 7: MATERIALS ACCEPTANCE. LPA Construction chapter -2 paragraphs on -Materials Quality Control -Materials Finalization -andAppendix J -LPA materials acceptance

MATERIALS ACCEPTANCE• Did they get the Contractor list of materials to you

at the preconstruction meeting per C&MS 108.02• Make sure the Contractor also provides a list of

materials to be used by all of the subcontractors, too.

• Documentation problems (No project Bill of Material)– Not having a system to track quantity of materials

accepted and needed• Notifying the CPE to require TE-24 and QPL

documentation

Page 8: MATERIALS ACCEPTANCE. LPA Construction chapter -2 paragraphs on -Materials Quality Control -Materials Finalization -andAppendix J -LPA materials acceptance

MATERIALS ACCEPTANCE• Typical Materials Problems – Asphalt

• No verification testing• No comparison of test results (producer to owner to JMF)• Delivery tickets with incorrect or no JMF

– Concrete• Use of correct aggregate in concrete pavement • Delivery tickets with incorrect or no JMF

– No tracking of approved materials to construction item

– Payment without materials approval

Page 9: MATERIALS ACCEPTANCE. LPA Construction chapter -2 paragraphs on -Materials Quality Control -Materials Finalization -andAppendix J -LPA materials acceptance

MATERIALS ACCEPTANCE

• If final Records do not have materials documentation FHWA funding cannot be used for payment