may 2021 enotek bulletin
TRANSCRIPT
ENOTEK BULLETIN
As a commitment and highly awareness onCovid-19 spread, Enotek Top Managementcommitted to held in-house weekly RTKCovid-19 swab test to al staff and frontlineron every week during this Covid-19Pandemic. This session been conducted byMedical Officer from Poliklinik Putra Care,Kajang. As of end of May 2021, Enotekmanagement had conducted 7 session ofRTK swab test.
This weekly swab test session beenconducted to ensure the health status of allstaff are well known and if any positivecases present, immediate action will betaken effectively in order to eliminate Covid-19 spread in organization. As cumulativeresult for May weekly basis swab testsession, no positive cases for Enotek staffand frontliner.
Health Safety Security Environmental & Quality Control
May 2021
HOUSEKEEPING
DOCUMENTATION
POOR ISOLATION
6
4
3
5113 247NMPIAUDITHOURS
YTD YTD YTD
43,615 51 245
HSSE – 3
PROJECT – 0
QAQC - 4
HSSE – 24
PROJECT – 6
QAQC - 21
May 2021ENOTEK BULLETIN
RANDOM DRUG TEST – MAY 202112 LSR COMPLIANCES - ENOTEK
Lead Site Engineer, Abdul Karim and Shahrul Hirzuan were attended the AGTES training at NIOSH
Bangi
AUTHORISED GAS TESTER & ENTRY SUPERVISORCOMPETENCY TRAINING – NIOSH BANGI
Eagerness from Enotek
Management level to comply and ensure
work site execute in safe condition, 2 staff
which is Lead Site Engineer, Abdul Karim
and Shahrul Hirzuan been sent for
Authorised Gas Tester and Entry Supervisr
Competency Training at National Institute of
Safety and Health (NIOSH) on physical
training session which is on 3 & 4 May 2021.
The purpose of the training is to entitle a
person to be a competent person to conduct
gas testing prior AESP enter confine space
area according to Industrial Code of Practice
(ICOP2010).
Commitment to comply with Shell 12
Life Saving Rules, NGC Probina – Enotek
Contractor had conducted Random Drug-
Urine Test to their workers to ensure all their
worker are free from any drug consuming
post advice by Enotek management. This
test were been agreed by contractor to
conduct randomly to their worker for May
2021 in assurance with respective result.
Next, the result for the drug test for NGC
Probina – Enotek contractor are negative.
Tubiono - Negative
Jumari - Negative
May 2021ENOTEK BULLETIN
SAFETY CORNER – MYSEJAHTERA DAILY UPDATE – COVID-19 STATUS
PH – Kamarul Alam conducted LFI sharing at worksite SH NTI SLE East during morning TBT.
CUMULATIVE LFI SHARING WORKSITE LFI SHARING – ENOTEK
On end of May 2021, Enotek PH had
conducted LFI Sharing to all frontliner at work site
related to Driver Crashed into C-Store, Driver runs
overs Service Champion and Armed Robbery of
Security Office. Consequences and severity of an
incident been highlighted to all frontliner to ensure
no repeated incident been occur especially at
Enotek site as per LFI. The conclusion of the
sharing is any possible of unsafe act and unsafe
condition are probably lead to disaster or harm to
human and assets, without concrete control
measure towards any possible hazard may lead
to an incident. At end of the sharing, all frontliner
understand on the input of the sharing
SH NTI JALAN KAPAR. SH BATU BERENDAM SH CHAAH
COVID-19 MY SEJAHTERA APPS1. Always to update Daily health declaration
in Covid-19 status2. Ensure the date of declaration are updated
at Profile section.
-------------- SYAMIL ZAKWAN BIN AHMAD TAJUDDIN
MAY 2021ENOTEK BULLETIN
Quality
QAQC REWARDS AND RECOGNITIONS
SHARING WITH SITE ENGINEER & FRONTLINER
In May 2021, ENOTEK QAQC Department running
an awareness and sharing program about QLASSIC to Site
Engineer. The Aims of this program is to increase the
knowledge about how to conduct inspection using the
correct tools which is construction full fill criteria and meet
the standard. Beside that ,QLASSIC is to measure and
evaluate the workmanship quality of a building construction
which is the information collected can be use for
improvement.
To motivated the Site Engineer & site front liner to construct
and deliver good quality of project construction, ENOTEK
Engineering Sdn. Bhd. will introduced the Rewards &
Recognition system which is QAQC department will conduct
Internal audit and evaluate the site performance . This
program planning to be start in June 2021.
The R&R (Rewards and Recognitions) will be carried out
together with cooperation ENOTEK Project and Safety
Department. QAQC R&R initiative is as appreciation to the
site front liner .
QLASSIC TOOLS
QLASSIC TOOLSSHARING QLASSIC WITH SITE ENGINEER FOR NTI KAPAR
SHARING QLASSICWITH SITE ENGINEER FOR NTI SLE EAST
MAY 2021ENOTEK BULLETIN
STEEL FIBRE REINFORCEMENT CONCRETEINNOVATION FOR SHELL PROGRAM
WHAT IS STEEL FIBRE REINFORCEMENT
CONCRETE?Steel fiber is a metal reinforcement. Steel fiber for
reinforcing concrete is defined as short, discrete
lengths of steel fibers with an aspect ratio (ratio of
length to diameter) from about 20 to 100, with
different cross-sections, and that are sufficiently
small to be randomly dispersed in an unhardened
concrete mixture using the usual mixing
procedures.
FORECOURT SLAB
Steel Fibre Reinforcement concrete had applied at
ENOTEK site at NTI Shell Jln Kapar, Klang. The
element apply for using the SFRC is forecourt
element which mean replace conventional method
casting concrete from using BRC as reinforcement
to use Steel Fibre for reinforcement.Steel Fibre
Cross section for concrete SFRC method Quality control on Slump test Casting work with direct pour
SHARING BY
--- HANAFI ROSLAN & FIRDAUS RAMLAN
BENEFIT USING SFRC
Significant productivity improvements. Time Saving. (Save time on both
preparation & construction stages)
Cost saving together with reduced material volume (no BRC), more rapid
construction (direct discharge) and reduced labor costs (eliminate labor for
machine handling). Average cost saving:
Suspended slab (on pile) - 20%
Non-suspended slab (on ground) - 30%
For NTI application, the steel fiber dosage is ranging from 15-30kg/m³. Subject to
design loading determined by principal consultant.
No DESCRIPTION SFRC CONVENTIONAL
1 Reinforcement Strength
1100MPa (HVMIX® 80/60)
510 Mpa (BRC)
2 Placement Method Steel fiber mixed inconcrete truck (on-site)
BRC to receive concrete
3 Concrete Discharge Direct Pour,concrete pump & mobile crane
Concrete pump & mobile crane.