mclaughlin road and spine road municipal class ... · ultimately construction of the project. the...
TRANSCRIPT
Prepared for:
Town of Caledon
6311 Old Church Road, Caledon, ON L7C 1J6 6/19/2019
McLaughlin Road and Spine Road Municipal
Class Environmental Assessment –
Environmental Study Report
Widening of McLaughlin Road and Construction of the
New East-West Spine Road (Mayfield West Phase 2)
Project No. TPB166090
McLaughlin Road and Spine Road Municipal Class
Environmental Assessment – Environmental
Study Report
Town of Caledon
Widening of McLaughlin Road and Construction of new East-West
Spine Road (Mayfield West Phase 2)
Project No. TPB166090
Prepared for:
Town of Caledon
6311 Old Church Road, Caledon, ON L7C 1J6
Prepared by:
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited
3450 Harvester Road, Suite 100
Burlington, ON L7N 3W5 Canada
T: 905-335-2353
6/19/2019
Copyright and non-disclosure notice
The contents and layout of this report are subject to copyright owned by Wood (© Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited). save to the extent that copyright has been legally assigned by us to another party or is used by
Wood under license. To the extent that we own the copyright in this report, it may not be copied or used without our prior written
agreement for any purpose other than the purpose indicated in this report. The methodology (if any) contained in this report is
provided to you in confidence and must not be disclosed or copied to third parties without the prior written agreement of Wood.
Disclosure of that information may constitute an actionable breach of confidence or may otherwise prejudice our commercial interests.
Any third party who obtains access to this report by any means will, in any event, be subject to the Third Party Disclaimer set out below.
Third-party disclaimer
Any disclosure of this report to a third party is subject to this disclaimer. The report was prepared by Wood at the instruction of, and
for use by, our client named on the front of the report. It does not in any way constitute advice to any third party who is able to access
it by any means. Wood excludes to the fullest extent lawfully permitted all liability whatsoever for any loss or damage howsoever
arising from reliance on the contents of this report. We do not however exclude our liability (if any) for personal injury or death
resulting from our negligence, for fraud or any other matter in relation to which we cannot legally exclude liability.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page i
Executive Summary
Wood Environment & Infrastructure Solutions (Wood) was retained by the Town of Caledon to undertake
a Schedule “C” Environmental Assessment (EA) for the widening of McLaughlin Road and the construction
of the new Spine Road, including connection of the Spine Road to the Highway 410 interchange. The
project is necessary to service the Mayfield West Phase 2 (MW2) development, which is anticipated to
accommodate 18,000 residents and 4,700 jobs. The Class EA was undertaken to fulfill Phases 3 and 4 of
the Municipal Class EA process, to provide a preferred preliminary design and environmental
commitments to guide completion of the detailed design and contract package preparation, and
ultimately construction of the project.
The Town of Caledon completed the Mayfield West Phase 2 Transportation Master Plan (MW2-TMP) in
2016, which fulfilled Phase 1 (Problem or Opportunity Statement) and Phase 2 (Alternative Solutions) of
the Municipal Engineers Association (MEA) Municipal Class Environmental Assessment (Class EA) process.
The purpose of the MW2-TMP was to provide a comprehensive transportation strategy accommodating
both vehicular traffic and provisions for the pedestrian / cyclist communities and to service the new MW2
development. In the MW2 development, Spine Road was proposed to connect to Hurontario Street /
Valleywood Boulevard immediately south of the interchange with Highway 410, however, through
consultation with MTO, further modifications to the interchange of Highway 410 / Valleywood Boulevard /
Hurontario Street were considered and determined to be preferred.
The problems and opportunities to be addressed as part of this project are as follows:
• Future traffic operations, safety, travel demand, transit and active transportation;
• Geometric deficiencies;
• Pavement condition; and
• Drainage deficiencies and opportunities for stormwater management.
Consultation
A Public Information Centre was held in July 2018 and provided information regarding the evaluation of
alternative design concepts and identification of the recommended design concept. Regular meetings
were held with the Ministry of Transportation and the Landowners Group to provide updates and to seek
input on the study. Indigenous communities were also consulted throughout the study, including a
meeting with the Mississaugas of the Credit First Nation to review the project.
Policies / Plan Review
This Environmental Study Report (ESR) examined the various background reports / policies / regulations
and related studies for consistency in the recommendations and guidelines. The study proceeds in
conformance with the various policies.
Planning Alternatives
The planning alternatives from the MW2-TMP were further assessed in order to validate and determine
the correct solution. A full set of planning alternatives were evaluated to determine the preferred planning
solution. Seven alternatives were explored using a common set of criteria in the areas of transportation,
conformity with existing Town policies and plans, the socio- economic environment, the natural
environment and capital costs.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page ii
After careful consideration of the alternatives based on the evaluation criteria and in consultation with
agencies and stakeholders, Alternative 7 was selected as the preferred planning solution.
Alternative 7: Combination of - Improved transit services, improved active transportation, travel demand
management and widening of McLaughlin Road, construction of Spine Road and
interchange improvements.
Alternative Design Concepts
The study investigated alternative design concepts for achieving Alternative 7. Several different
alternatives were considered for horizontal alignments, structural alternatives and interchange
modifications. For each option chosen, with proper environmental constraint avoidance and mitigation
planning measures employed, the benefits of the preferred alternatives outweigh their potential impacts
to the natural and cultural environment.
The horizontal alignment chosen for McLaughlin Road was Alternative 1 (widen to a four-lane urban
cross section).
The horizontal alignment chosen for Spine Road was Alternative 3 (Revised alignment, based on input
from agencies and Town of Caledon).
The alternative chosen for the connection of the Spine Road to Hurontario Street and Highway 410 was
Alternative 2 (Connect Spine Road to Valleywood Boulevard, with Hurontario Street ending at the
intersection with Spine Road and reconfiguration of the interchange). To accommodate this alternative, a
new flyover structure is required to support the new northbound on-ramp from Hurontario Street /
Valleywood Boulevard / Spine Road to Highway 410. This flyover will consist of a two-span structure, with
abutments on either side of Highway 410 and a centre pier in the median of the highway. The
approximate total span of the flyover will be 78.5m. Several alternatives were explored to identify the
chosen structural cross section. Alternative 3 (slab on steel box girders) was recommended.
Design Criteria
The ESR outlines the proposed design criteria for the preliminary design of McLaughlin Road, Spine Road
and the interchange modifications based on the TAC Geometric Design Guide for Canadian Roads (2017),
the MTO Design Supplement (June 2017) and the Town of Caledon standards. Additionally, intersection
designs have been developed to provide an acceptable level of service at each intersection and storage
lengths were calculated based on 95th percentile queue lengths.
Property Requirements
Property purchase required has been minimized to the degree possible, however, some additional
property will be required from both private and public landowners at various locations. During detailed
design, property requirements (including permission to enter requirements) will be confirmed.
Active Transportation
Active transportation facilities will be included along McLaughlin Road and Spine Road, as well as through
the interchange. During the detailed design phase, designers will confirm that the design meets the
minimum requirements as defined by the Accessibility for Ontarians with Disabilities Act (AODA).
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page iii
Pavement Design
A preliminary pavement design was completed for McLaughlin Road and Spine Road as part of the
geotechnical investigation. The pavement structure for the roads within the interchange was not
determined as part of this study and will need to be determined as part of the detailed design.
Hydrogeology
A preliminary Hydrogeology Assessment has been completed for this study, which concluded that the
dewatering effort is expected to be low, and neither a Permit to Take Water nor an Environmental Activity
and Sector Registry will be required if the excavations of subsurface infrastructure are limited to
excavations of up to 30 metres (m) at a time. The report recommended that a private well survey
completed to establish the number of active wells that are present nearby, and the quality and quantity of
the water produced by these wells, as well as an assessment of the conditions of these wells.
Stormwater Management
A Stormwater Management Report has been completed for this study, which recommends the following
stormwater management strategies and hydraulic improvements:
• Neither the subject segment of McLaughlin Road nor the Spine Road traverse regulated watercourses,
hence no permanent hydraulic structures (i.e. bridges or open footing culverts) are required;
• It is recommended that the stormwater management plan for the future expansion of McLaughlin
Road and the Spine Road be incorporated into the drainage and stormwater management plan for
the adjacent development areas, in accordance with the recommendations of the MW2 Area
Comprehensive Environmental Impact Study and Management Plan and the MW2 Functional
Servicing Plan;
• Low Impact Development Best Management Practices (LID BMP’s) are recommended to mitigate
thermal enrichment of storm runoff, as well as to manage water budget;
• The proposed works are anticipated to coincide with the urbanization within the adjacent
developments, hence no interim works are anticipated to be required;
• Provide an enhanced level of stormwater quality control for the proposed works, as well as to address
conveyance capacity constraints of existing drainage infrastructure;
• The existing wet pond within the limits of the interchange should be expanded to address both
additional quality and quantity control; and
• Detailed design will include supporting hydrologic and hydraulic analyses, establish storage
requirements for the stormwater management facility and verify the conveyance capacity and
hydraulic grade line.
Utilities
Based on a preliminary review, relocation or protection of various utilities will be required during the
detailed design phase, including but not limited to Bell Canada, Enbridge, Alectra Hydro and Region of
Peel watermain.
Illumination
Full illumination will be installed along McLaughlin Road, Spine Road and within the interchange as part
of the construction works. Any existing lighting will remain operational at all times during construction.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page iv
Structural
The structural design of the Highway 410 northbound flyover will consist of a two-span structure, with
abutments on either side of Highway 410 and a centre pier in the median of the highway. Additionally, in
order to facilitate the new north to east on-ramp, portions of the existing overpass will need to be
modified.
Construction Staging
A detailed staging plan will be completed as part of the detailed design process, which will provide for
maintenance of traffic on all existing roadways and ramps.
Environmental Issues and Commitments
A number of potential impacts and mitigation measures have been identified in relation to land use,
noise, archaeology, built and cultural heritage and natural environment. In terms of land use, the following
impacts to property have been documented within the study area and will be reviewed during the
detailed design process:
• Property purchase along both sides of McLaughlin Road, Spine Road and adjacent to the interchange
- Purchase will be completed in accordance with Town policy;
• Driveway reconstruction / grading (both asphalt and gravel) - Driveways will be reconstructed to
match existing materials;
• Impact to landscape features (fencing, gates and retaining walls) - Landscape features will be
modified and / or reconstructed as indicated on the preliminary design drawings;
• Impact to or removal of trees and residential landscape plantings at various properties - A tree
preservation plan and landscape planting plan will be prepared in detailed design; and
• Coordination with development plans.
No permanent noise impacts requiring mitigation have been identified. The contract documents will
identify the contractor’s responsibilities with respect to controlling temporary construction noise. The
contract documents will also explicitly state that compliance with all applicable law is an expectation of
the contract including adherence to the Town of Caledon Noise By-Law 86-110 [2] and MOECC
Publication NPC-115.
Some areas within the limits of the interchange improvements have been identified for a Stage 2
Archaeological Assessment and will be carried out as part of the detailed design phase.
Similarly, a number of cultural heritage resources were identified and will be further investigated as part of
the detailed design phase.
Numerous aquatic and terrestrial issues are identified with corresponding mitigation measures to protect
species, such as birds, bats and fish. Erosion and sediment control (ESC) measures are proposed to
prevent sedimentation, ensure vegetation is reestablished and all disturbed grounds are stabilized.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page v
Table of Contents
1.0 Introduction and Background ......................................................................................................................................... 1
1.1 Introduction ........................................................................................................................................................... 1
1.2 Study Organization ............................................................................................................................................. 2
1.3 Study Background and Purpose .................................................................................................................... 2
1.4 Environmental Assessment ............................................................................................................................. 2
1.4.1 Class Environmental Assessment Process................................................................................. 3
1.4.2 Environmental Study Report .......................................................................................................... 4
1.4.3 Filing of the ESR .................................................................................................................................. 4
1.4.4 Part II Order Request ........................................................................................................................ 6
1.5 Previous Studies and Adjacent Projects ..................................................................................................... 6
2.0 Stakeholder and Agency Consultation ........................................................................................................................ 6
2.1 Consultation .......................................................................................................................................................... 6
2.1.1 Mailing List ............................................................................................................................................ 7
2.2 Indigenous Engagement .................................................................................................................................. 7
2.2.1 Identification of Indigenous Communities ............................................................................... 7
2.3 Agency Consultation .......................................................................................................................................... 8
2.3.1 Meetings ................................................................................................................................................ 8
2.3.2 Ministry of Transportation Consultation ................................................................................... 9
2.3.3 Utilities Consultation .......................................................................................................................10
2.4 Public and Landowner Consultation ..........................................................................................................10
2.4.1 Public Information Centre .............................................................................................................11
3.0 Existing Conditions ............................................................................................................................................................17
3.1 Study Area ............................................................................................................................................................17
3.2 Land Use and Development Plans .............................................................................................................17
3.2.1 Town of Caledon Official Plan (2016) .......................................................................................17
3.2.2 Region of Peel Official Plan (2016) ............................................................................................18
3.2.3 Mayfield West Phase 2 – Secondary Plan Transportation Master Plan (2015) ........18
3.2.4 Caledon Transportation Needs Study Update – Town of Caledon and Region of
Peel (2009) ...........................................................................................................................................18
3.2.5 Region of Peel Sustainable Transportation Strategy (2018) ...........................................19
3.2.6 Region of Peel Long Range Transportation Plan (2012) ...................................................19
3.2.7 Region of Peel Road Characterization Study (2013) ..........................................................19
3.3 Provincial Land Use Planning Initiatives ...................................................................................................20
3.3.1 Provincial Policy Statement (2014) ............................................................................................20
3.3.2 Growth Plan for the Greater Golden Horseshoe (2017) ....................................................20
3.3.3 The Greenbelt Plan (2017) ............................................................................................................21
3.4 Existing Land Use ..............................................................................................................................................21
3.4.1 Proposed Development .................................................................................................................22
3.5 Transportation ....................................................................................................................................................23
3.5.1 Existing Roadway Network ...........................................................................................................23
3.5.2 Existing Railway Network ..............................................................................................................23
3.5.3 Existing Traffic Conditions ............................................................................................................23
3.5.4 Future Traffic Conditions ...............................................................................................................24
3.5.5 Existing Transit and Active Transportation Network ..........................................................24
3.6 Natural Environment ........................................................................................................................................24
3.6.1 Terrestrial Resources .......................................................................................................................25
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page vi
3.6.2 Aquatic Resources ............................................................................................................................25
3.7 Cultural Heritage Report ................................................................................................................................25
3.8 Stormwater Management Assessment .....................................................................................................26
3.9 Archaeological Assessment ...........................................................................................................................27
3.10 Geotechnical Investigation ............................................................................................................................27
3.10.1 Visual Pavement Condition Survey............................................................................................27
3.10.2 Subsurface Conditions....................................................................................................................27
3.10.3 Environmental Chemical Analysis ..............................................................................................28
3.11 Hydrogeological Assessment .......................................................................................................................28
4.0 Development and Evaluation of Alternative Planning Solutions ....................................................................29
4.1 Problem and Opportunity Statement .......................................................................................................29
4.2 Evaluation Criteria .............................................................................................................................................29
4.3 Identification of Alternatives ........................................................................................................................30
5.0 Development and Evaluation of Alternative Design Concepts .......................................................................31
5.1 Horizontal Alignment Alternatives .............................................................................................................31
5.1.1 McLaughlin Road ..............................................................................................................................31
5.1.2 Spine Road ..........................................................................................................................................33
5.1.3 Interchange Modifications ............................................................................................................35
5.2 Structural Alternatives .....................................................................................................................................35
5.3 Stormwater Management Alternative Assessment .............................................................................35
5.3.1 General Stormwater Management Opportunities...............................................................35
5.3.2 Alternative Stormwater Management Practices ...................................................................36
5.3.3 General Assessment ........................................................................................................................37
6.0 Description of Preferred Design ..................................................................................................................................39
6.1 Major Features of the Recommended Plan ............................................................................................39
6.1.1 Design Criteria ...................................................................................................................................39
6.1.2 Vertical Alignment............................................................................................................................44
6.1.3 Typical Cross Section ......................................................................................................................44
6.1.4 Intersection and Sideroads ...........................................................................................................49
6.1.5 Transit....................................................................................................................................................51
6.1.6 Private Entrances ..............................................................................................................................52
6.1.7 Property Requirements ..................................................................................................................52
6.1.8 Active Transportation......................................................................................................................54
6.1.9 Accessibility for Ontarians with Disabilities Act Measures ...............................................56
6.1.10 Pavement Design ..............................................................................................................................56
6.1.11 Utilities ..................................................................................................................................................57
6.1.12 Agency Approvals ............................................................................................................................58
6.1.13 Illumination .........................................................................................................................................58
6.1.14 Preferred Design Impacts on Local Air Quality Conditions .............................................58
6.1.15 Structural Design ..............................................................................................................................59
6.1.16 Construction Staging ......................................................................................................................60
6.1.17 Preliminary Cost Estimate .............................................................................................................61
6.2 Potential Impacts and Mitigation Measures .........................................................................................61
6.2.1 Land Use ..............................................................................................................................................61
6.2.2 Air Quality ............................................................................................................................................61
6.2.3 Noise Assessment ............................................................................................................................62
6.2.4 Archaeological Assessment ..........................................................................................................63
6.2.5 Built and Cultural Heritage ...........................................................................................................63
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page vii
6.2.6 Natural Environment .......................................................................................................................64
6.2.7 Hydrogeology ....................................................................................................................................67
6.2.8 Stormwater Management .............................................................................................................68
6.2.9 Monitoring ..........................................................................................................................................69
6.2.10 Source Water Protection ...............................................................................................................69
6.2.11 Climate Change .................................................................................................................................69
7.0 Summary of Environmental Issues and Commitments to Environmental Impacts and Mitigation
Measures ...............................................................................................................................................................................70
8.0 References ............................................................................................................................................................................74
List of Figures
Figure 1-1 Key Plan .............................................................................................................................................................................. 1
Figure 1-2 Municipal Class Environmental Assessment Process ....................................................................................... 5
Figure 3-1 Existing Land Use ........................................................................................................................................................ 22
Figure 6-1 McLaughlin Road Cross Section ............................................................................................................................ 46
Figure 6-2 Spine Road Cross Section ........................................................................................................................................ 47
Figure 6-3 Spine Road Cross Section ........................................................................................................................................ 48
Figure 6-4 Preliminary Property Requirements ..................................................................................................................... 53
Figure 6-5 Proposed Bus Stop Locations and Active Transportation Facilities……………………………………………55
List of Tables
Table 2-1 Consultation Schedule ................................................................................................................................................... 7
Table 2-2 TAC Meeting Invitation and Attendees ................................................................................................................... 9
Table 2-3 MTO Consultation Summary ....................................................................................................................................... 9
Table 2-4 PIC Comment Summary ............................................................................................................................................. 11
Table 4-1 Evaluation Criteria for Alternatives ........................................................................................................................ 29
Table 5-1 McLaughlin Road Alternative Alignment Assessment ................................................................................... 32
Table 5-2 Spine Road Alternative Alignment Assessment ................................................................................................ 34
Table 6-1 Design Criteria – McLaughlin Road ....................................................................................................................... 39
Table 6-2 Design Criteria – Spine Road .................................................................................................................................... 40
Table 6-3 Design Criteria – Valleywood Boulevard.............................................................................................................. 40
Table 6-4 Design Criteria – Hurontario Street ....................................................................................................................... 41
Table 6-5 Design Criteria – N-E/W/S Ramp ............................................................................................................................ 41
Table 6-6 Design Criteria – S/E-N Ramp .................................................................................................................................. 42
Table 6-7 Design Criteria – N-E Ramp ...................................................................................................................................... 43
Table 6-8 Design Criteria – S-E Ramp ....................................................................................................................................... 43
Table 6-10 Recommended Minimum Structural Pavement Design for McLaughlin Road .................................. 56
Table 6-11 Recommended Minimum Structural Pavement Design for Spine Road .............................................. 57
Table 6-12 Required Agency Approvals / Permitting Requirements ............................................................................ 58
Table 7-1 Summary of Environmental Issues and Commitments to Environmental Impacts and Mitigation
Measures ........................................................................................................................................................................... 70
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page viii
List of Appendices
Appendix A - Notice of Study Commencement
Appendix B - Indigenous Consultation
Appendix C - Agency and Landowner Meeting Minutes and Comments
Appendix D - Transportation and Traffic Study
Appendix E - Natural Environment Report
Appendix F - Cultural Heritage Report
Appendix G - Stormwater Management Assessment
Appendix H - Active Transportation Review
Appendix I - Archaeological Assessment
Appendix J - Public Consultation
Appendix K - Geotechnical Investigation Report
Appendix L - Preliminary Cost Estimate
Appendix M - Noise Impact Report
Appendix N - Traffic Safety Assessment
Appendix O - Hydrogeological Assessment
Appendix P - Structural Overpass Design Report
Appendix Q - Utilities Consultation
Appendix R - Climate Change Review
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page ix
List of Acronyms
AASHTO American Association of State Highway and Transportation Officials
AODA Accessibility for Ontarians with Disabilities Act
CHER Cultural Heritage Evaluation Reports
Class EA Municipal Class Environmental Assessment
CVCA Credit Valley Conservation Authority
EA Environmental Assessment
EASR Environmental Activity and Sector Registry
ECCC Environment and Climate Change Canada
ESA Endangered Species Act, 2007
ESC Erosion and Sediment Control
ESR Environmental Study Report GEV Generalized Extreme Value
ha hectare
LID BMP Low Impact Development Best Management Practices
LOS Level of Service
LRTP Long Range Transportation Plan (Region of Peel)
m metres
MBCA Migratory Birds Convention Act
MCFN Mississaugas of the Credit First Nation
MECP Ministry of Environment, Conservation and Parks
MNO Métis Nation of Ontario
MNRF Ministry of Natural Resources and Forestry
MTO Ministry of Transportation
MW2 Mayfield West Phase 2
MW2-TMP Mayfield West Phase 2 Transportation Master Plan
OLA Outdoor Living Area
OPSS Ontario Provincial Standards and Specifications
PIC Public Information Centres
PPS Provincial Policy Statement
PSW Provincially Significant Wetlands
PTTW Permit to Take Water
RCS Road Characterization Study (Region of Peel Road)
ROW Right-of-way
SAR Species at Risk
SCS Soil Conservation Service
SHR Shoulder Rounding
SWH Significant Wildlife Habitat
SWM Stormwater Management
SWMP Stormwater Management Practices
TAC Technical Agency Meeting
TRCA Toronto and Region Conservation Authority
VRA Valleywood Residents Association
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 1
1.0 Introduction and Background
1.1 Introduction
The Town of Caledon (Town) has completed a Municipal Class Environmental Assessment (Class EA) for
the widening of McLaughlin Road and construction of the new Spine Road which are contained within the
Mayfield West Phase 2 (MW2) development area (Figure 1-1). This study was initiated in September 2016
and originally consisted of constructing the new east-west Spine Road from Hurontario Street to
Chinguacousy Road. However, based on input provided by key stakeholders, an additional study area was
identified at the Highway 410 interchange with Hurontario Street / Valleywood Boulevard (labelled as
extended study area on Figure 1-1). Modifications to the interchange are necessary to accommodate the
projected traffic volumes generated by Mayfield West Phase 2 development area. Overall, the
improvements are required to meet the Town’s development needs considering satisfactory level of
service (LOS) and safe driving conditions within the Study Area.
Wood Environment & Infrastructure Solutions (Wood), was retained by the Town to complete the study.
Figure 1-1 Key Plan
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 2
1.2 Study Organization
The Study Team consisted of staff from the following organizations:
Proponent: Town of Caledon
Kant Chawla, Project Manager
Prime Consultant: Wood Environment & Infrastructure Solutions
David Sinke, Project Manager
Jason Stahl, Transportation Engineer
Ravi Bhim, Traffic Engineer
Aniqa Shams, Environmental Planner
Aaron Farrell, Water Resources Engineer
Erin Hellinga, Environmental Specialist
Daryl Rideout, Fisheries Biologist
Jeff Balsdon, Terrestrial Ecologist
Shaun Austin, Senior Archaeologist
Shami Malla, Geotechnical Engineer
Buddy Ledger, Noise and Vibration Engineer
Kim Gilder, Hydrogeological Assessment
1.3 Study Background and Purpose
The intent of this Study is to widen McLaughlin Road, construct the new Spine Road and modify the
Highway 410 interchange to allow connection to the new Spine Road. The requirement for the EA Study
has been triggered by the network requirements set out in the approved Mayfield West Phase 2
Transportation Master Plan (MW2-TMP) which fulfilled the requirements of Phases 1 and 2 of the Class EA
process. The MW2-TMP was a comprehensive transportation strategy accommodating both vehicular
traffic and provisions for the pedestrian / cyclist communities and to service the new MW2 development,
which is anticipated to accommodate 18,000 residents and 4,700 jobs. In the MW2-TMP, Spine Road was
proposed to connect to Hurontario Street / Valleywood Boulevard immediately south of the interchange
with Highway 410. In 2016, this Class EA study was initiated by the Town of Caledon to fulfill Phases 3 and
4 of the Class EA process. Phase 2, which consists of evaluating the alternative planning solutions was
investigated in further detail as part of this Class EA, in order to validate the preferred solution and move
on to examine the various design concepts in Phase 3. Section 2 provides an overview of the consultation
undertaken to support the evaluation process and section 5 will outline the evaluation process.
As mentioned previously, the study area was modified in July 2018 to include the Highway 410
interchange, based on input provided by key stakeholders. The Highway 410 interchange falls under the
Ministry of Transportation (MTO) jurisdiction. As a result of this change, the study required significant
involvement from the Ministry of Transportation (MTO) to review and accept the proposed changes to the
interchange. The MTO Class EA process is similar to the Municipal Class EA process and as such the Town
of Caledon required MTO approval to extend this Class EA study area to include the interchange. MTO
accepted this change and agreed to continue with the Municipal Class EA process.
1.4 Environmental Assessment
The Ontario Environmental Assessment Act (R.S.O. 1990, c. E.18; EA Act) was put into place to provide for
the protection, conservation and wise management of the environment within the province. The Act
applies to all projects being undertaken by provincial, municipal or other public bodies within the
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 3
province (unless explicitly exempt). It defines the environmental assessment works that must be
completed prior to commencement of any undertaking, as well as the proponent’s duty to consult with all
affected and / or interested parties.
No undertaking that falls under the scope of the EA Act can proceed until the Minister of the Environment,
Conservation and Parks (MECP) provides approval of the submitted EA documentation. This includes
resolution of public appeals made in accordance with section 7.2(3) of the Act.
1.4.1 Class Environmental Assessment Process
The Class EA process is a mechanism by which planning, and approval of municipal servicing is provided
in an efficient, timely, economical and environmentally responsible manner. It represents a consistent,
streamlined and easily understood process for planning and implementing municipal infrastructure
projects. This study, the widening of McLaughlin Road and the construction of the Spine Road, is classified
as being subject to the Class EA process. It is being conducted according to the requirements outlined in
the Municipal Engineers Association document titled Municipal Class Environmental Assessment (October
2000, as amended in 2007, 2011 & 2015).
Consistent with the Class EA process, the study approach has been designed to meet the following
objectives:
i. Protection of the environment, including natural, social and economic components of the
environment.
ii. Participation of a broad range of stakeholders in the study process to allow for sharing of ideas,
education, testing of creative solutions and developing alternatives.
iii. Documentation of the study process in compliance with all phases of the Class EA process.
The Class EA process classifies projects according to their level of complexity and potential environmental
impacts. These are termed “Schedules” and are summarized below:
Schedule A and A+ includes projects that involve minor modifications to existing facilities.
Environmental effects of these projects are generally small; therefore, the projects are considered
pre-approved.
Schedule B includes projects that involve improvements and minor expansion to existing
facilities. There is a potential for some adverse environmental impacts and, therefore, the
proponent is required to proceed through a screening process, including consultation with those
affected. Schedule B projects are required to proceed through Phases 1, 2 and 5 of the Class EA
process.
Schedule C includes projects that involve construction of new facilities and major expansion of
existing facilities. These projects proceed through the environmental assessment planning process
outlined in the Class EA document. These projects are required to fulfill the requirements of all
five phases of the Class EA process.
This study is being completed under the requirements of a Schedule “C” Municipal Class EA. The
following Schedule C triggers, as noted in the Municipal Engineers Association’s Municipal Class EA
Document (October 2000, as amended in 2007, 2011 & 2015), apply to this study:
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 4
• Construction of new roads or other linear paved facilities (e.g. HOV lanes) with an estimated capital
cost to be greater than 2.4 million (Adjusted for inflation in 2019 to $2.6 million).
The following Class EA planning phases apply:
• Phase 1 – Identify the problem (deficiency) or opportunity.
• Phase 2 – Identify and evaluate alternative solutions to address the problem or opportunity by taking
into consideration the existing environment and establish the preferred solution considering public
and review agency input.
• Phase 3 – identify alternative design concepts for the preferred solution implementation by taking
into consideration the existing environment and establish the preferred design concept by
considering public and review agency input.
• Phase 4 – Document the EA including the design and consultation process in an Environmental Study
Report (ESR) for public review.
• Phase 5 – Complete contract drawings and documents and proceed to construction and operation.
Monitor construction for adherence to environmental provisions and commitments. Where special
conditions dictate, monitor the operation of the completed facility.
The phases of the Class EA process for this Study are illustrated below in Figure 1-2.
1.4.2 Environmental Study Report
This ESR documents the rationale for the Study, the background to the study, existing and future
conditions within the Study Area, the planning, design and consultation process leading to the preferred
alternative, anticipated positive and negative impacts and proposed mitigation measures.
1.4.3 Filing of the ESR
All parties having expressed an interest in the Study will be notified by letter, regarding the completion of
the Study and filing of the ESR. In addition, a Notice of Study Completion will be placed in the local
newspaper, the Caledon Citizen Newsletter, in accordance with the requirements of the Class EA process.
Copies of the ESR will be made available at the following locations:
Caledon Town Hall
6311 Old Church Road
Caledon, ON L7C 1J6
Phone: 905-584-2272
Hours:
Monday - Friday: 8:30 am to 4:30 pm
Caledon Public Library – Margaret Dunn
Valleywood Branch
20 Snelcrest Drive
Caledon, ON L7C 1B5
Hours:
Monday, Tuesday and Thursday: 2:00 pm to 8:30 pm
Wednesday and Friday: 10:00 am to 6:00 pm
Saturday: 10:00 am to 4:00 pm
Town of Caledon Website:
http://www.town.caledon.on.ca/en/townhall/mayfieldwestsecondaryplanphase2.asp
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 5
Phase 1
Identify and Describe the Problem(s)
Identify Problems and Opportunities
Addressed through the Mayfield West Phase 2 Transportation Master
Plan (October 2015)
Phase 2
Alternative Planning Solutions Identify Reasonable Alternative Planning Solutions to the Problem(s)
Evaluate the Alternative Solutions taking into consideration the
environmental and technical factors.
Addressed through the Mayfield West Phase 2 Transportation Master
Plan (October 2015)
Phase 3
Alternative Design Concepts for the Preferred Solution
Issue Notice of Study Commencement: September 2016
Identify Alternative Designs to Implement the Preferred Solution
Inventory Natural, Social / Cultural and Economic Environments
Identify the Impacts of the Alternative Designs after Mitigation
Evaluate Alternative Designs with Consideration of the Impacts
Identify a Preferred Design
Phase 4
Environmental Study Report
Complete an ESR
Place ESR on Public Record for 30 Calendar Days for Review
Notify the Public and Government Agencies of Completion of the Study
Issue Notice of Study Completion: June 2019
Phase 5
Implementation
Complete Detail Design and Contract Administration
Proceed to Construction of the Project
Monitor Environmental Provisions and Commitments
PUBLIC INFORMATION
CENTRE
July 5, 2018
Figure 1-2 Municipal Class Environmental Assessment Process
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 6
A review period of not less than thirty (30) days will be provided, during which comments will be received
from stakeholders and agencies. If members of the public, interest groups and / or government agencies
feel that their concerns have not been addressed through the Class EA study process, a person or party
may request the MECP to make an order for the Study to comply with Part II of the EA Act (referred to as a
Part II Order). More information on Part II Order requests is provided in Section 1.2.4; however, it is
anticipated that all concerns will be resolved through discussion between the Town and the concerned
party or parties.
1.4.4 Part II Order Request
The Class EA process provides an opportunity for the public and other stakeholders to appeal the Class EA
process undertaken by the Study Team. Under the provisions of subsection 16 of the amended EA Act,
there is an opportunity under the Class EA process for the Minister to review the status of a Study.
Members of the public, interest groups and review agencies may request the Minister to require a
proponent to comply with Part II of the EA Act, before proceeding with a proposed undertaking. This is
known as a “Part II Order” (formerly called “Bump-Up Request”). The procedure for dealing with concerns
that may result in the Minister, by order, requiring the proponent to comply with Part II of the EA Act is
outlined in the Class EA document. It is anticipated that all concerns will be resolved through discussion
between the Town and the concerned individual(s) or group(s).
As of July 1, 2018, a Part II Order Request Form must be used to request a Part II Order. The Part II Order
Request Form is available online on the Forms Repository website (http://www.forms.ssb.gov.on.ca/) by
searching “Part II Order” or “012-2206E” (the form ID number).
1.5 Previous Studies and Adjacent Projects
The Study Team reviewed the following planning documents, guidelines and other reports relevant to the
McLaughlin Road and Spine Road corridor. The list below presents some of the key documents being
referenced by the study and is not inclusive.
• Active Transportation Study, Region of Peel (2011);
• Caledon Transportation Needs Study Update, Town of Caledon and Region of Peel (2009);
• MTO Class Environmental Assessment for Provincial Transportation Facilities (2000);
• Mayfield West Phase 2 – Secondary Plan Transportation Master Plan (2015);
• Official Plan, Region of Peel (2016);
• Official Plan, Town of Caledon (2016); and
• Transportation Impact Studies, Town of Caledon Terms of Reference and Guidelines (2017).
2.0 Stakeholder and Agency Consultation
2.1 Consultation
A Notice of Study Commencement, detailing the study area, summarizing the study’s objectives and
requesting comments, was submitted to relevant stakeholders, property owners and agencies by mail, in
September 2016. The Notice of Study Commencement was published in the Caledon Citizen on
September 22, 2016 and October 6, 2016.
A Notice of Study Area Revision, as shown in Figure 1-1 (Section labelled extended study area) was
distributed in association with the Notice of Public Information Centre. The Study Area was revised to
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 7
include the Highway 410 interchange with Hurontario Street / Valleywood Boulevard based on the input
received from key stakeholders. It was determined that modifications to the interchange are critical to
maintain and accommodate the operation of the proposed Spine Road intersection with Hurontario Street
/ Highway 410.
Responses to this notice were received from several stakeholders and agencies. Copies of the newspaper
advertisement, letters from and to stakeholders and agencies as well as copies of all comments and
responses are contained in Appendix A.
Consultation with agencies and public stakeholders was completed in Phase 3. The following table
presents an overview of the agency and public stakeholder consultation activities.
Table 2-1 Consultation Schedule
Type Date
Project Team Meeting #1 with Town of Caledon August 15, 2016
Notice of Commencement, published in newspaper and mailed
to study Mailing List
Newspaper Advertisement: September 22, 2016
and October 6, 2016
Mail-out: September 2016
Technical Agency Committee Meeting May 24, 2018
Notice of Public Information Centre and Notice of Study Area
Revisions published in newspaper and mailed to study Mailing
List
Newspaper Advertisement: June 21, 2018 and
July 5, 2018
Mail-out: June 2018
Public Information Centre July 5, 2018
Notice of Completion June 20, 2019
Details regarding the consultation with agencies and public stakeholders are further detailed in the
following sections.
2.1.1 Mailing List
A Study Mailing List was generated from Town records, which included all residents living on streets
bordering the Study Area. Additional contacts were added by request, including through completion of
Comment Forms at the Public Information Centre. The agency mailing list can be found in Appendix A.
2.2 Indigenous Engagement
Indigenous engagement is a key component of the Class EA process. The MECP delegated the procedural
aspects of the Duty to Consult to the Town of Caledon in its response to the Notice of Commencement.
Copies of all Indigenous engagement documents can be found in Appendix B.
2.2.1 Identification of Indigenous Communities
In consultation with the MECP, the Town sought direction on the identification of Indigenous
communities that may have an interest in the study. The MECP confirmed on November 10, 2016 that the
Mississaugas of the Credit First Nation (MCFN) and Métis Nation of Ontario (MNO) should be engaged.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 8
Both the MCFN and MNO were circulated the Notice of Commencement and the Notice of Study Area
Revision. Neither group responded directly to the notifications. Wood subsequently contacted both
groups to ensure the specifics of the study were understood. Documentation of this correspondence can
be found in Appendix B.
2.2.1.1 Mississaugas of the Credit First Nation
The Town followed up with MCFN on March 7, 2019 by email to re-share the Notice of Commencement
and Notice of Study Area Revision and to share the Stage 1 Archaeological Assessment Report. A phone
conversation was held on March 14, 2019 during which MCFN noted that they had an interest in meeting
with the Town to discuss the study and next steps. A meeting was completed on May 2, 2019. The
purpose of the meeting was to provide an overview of the McLaughlin Road and Spine Road Municipal
Class Environmental Assessment (Class EA), with a focus on the archaeological assessments, cultural
heritage assessments and natural heritage. During the meeting, MCFN expressed interest in attending any
site visits for archeological and natural heritage concerns. The Stage 2 Archaeological Assessment will be
occurring during detailed design and MCFN would like confirmation that they will be involved. The
following commitment was agreed to be included in the ESR.
The Town of Caledon and specifically this Study Area falls within Traditional Territory of Mississaugas of the
Credit First Nation. As such, the Ministry of the Environment, Conservation and Parks has delegated
procedural aspects of the duty to consult to the Town of Caledon as part of the Class EA. Based on the
Town’s relationship with MCFN, the Town is committed to ensuring involvement of MCFN’s Field Liaisons
Representatives in any fieldwork associated with future stages of this Project. The Town will work with the
Proponent responsible for the detailed design stage to ensure that this involvement occurs during detailed
design activities, such as Stage 2 Archaeological Assessment and further natural environment assessments.
Meeting minutes can be found in Appendix B.
Further consultation will occur with MCFN during detailed design.
2.2.1.2 Métis Nation of Ontario
The Town followed up with MNO by phone on March 7, 2019 to determine the appropriate lines of
communication since the original contact had left MNO since the original Notice of Commencement.
During the conversation with MNO’s Manager of Lands, Resources and Consultation, the appropriate
communication process was identified. The Notice of Commencement, Notice of Study Area Revision and
the Stage 1 Archaeological Assessment Report were shared by email on March 7, 2019. Response was
received the same day identifying that the information had been forwarded to the Regional Consultation
Committee and that if additional information was required, the representative would make a request to
the Town.
2.3 Agency Consultation
2.3.1 Meetings
2.3.1.1 Technical Agency Committee Meeting
As part of Phase 3 consultation activities, a Technical Agency Meeting (TAC) meeting was held on
May 24, 2018 at the Town of Caledon Town Hall (6311 Old Church Road Committee Room), from 2:00 pm
to 4:30 pm. The purpose of this meeting was to review alternative design concepts for the proposed Spine
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 9
Road, McLaughlin Road and the Highway 410 interchange. Meeting agenda and minutes can be found in
Appendix C.
A meeting invite was sent out on March 27, 2018 to the following agencies (with the number of attendees
that participated in brackets):
Table 2-2 TAC Meeting Invitation and Attendees
Type Agency
Utilities
Bell Canada Municipal Operations Centre
Enbridge Gas Distribution Inc.
Hydro One Brampton
Zayo Group Holdings Inc. (Formerly MTS Allstream)
Rogers Cable (Brampton)
Telus Network
Conservation Authorities Credit Valley Conservation Authority (3)
Toronto Region Conservation Authority (3)
Federal Government Department of Fisheries and Oceans Canada
Provincial Government
Ministry of Environmental, Conservation and Parks
Ministry of Transportation
Ministry of Natural Resources and Forestry
Region Region of Peel (3)
Municipality City of Brampton (1)
Emergency Services Caledon Fire (2)
Ontario Provincial Police (1)
The TAC reviewed materials to be presented at the Public Information Centre, to identify and address
natural environment constraints, and provide input to the evaluation of the planning alternatives and
preferred design. Other components of evaluation included the technical aspects, cost, and compatibility
with Region of Peel, Town of Caledon, Toronto and Region Conservation Authority (TRCA) and Credit
Valley Conservation Authority (CVCA) plans and policies.
2.3.2 Ministry of Transportation Consultation
The Study Team met with the Ministry of Transportation (MTO) several times during the course of the
study. Further consultation with MTO will occur during the detailed design phase.
Table 2-3 MTO Consultation Summary
Date Meeting Summary
November
15, 2016
The purpose of the meeting was to discuss the approach of the Spine Road connection to the
Hurontario Street / Valleywood Boulevard interchange with Highway 410.
Topics covered:
• Background summary of the study to date;
• Town’s objective for the Spine Road connection and the importance of the Hurontario Street
/ Valleywood Boulevard connection; and
• MTO issues, constraints and requirements.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 10
Date Meeting Summary
January 11,
2017
The purpose of the meeting was to discuss the status of the Spine Road connection to the Hurontario
Street / Valleywood Boulevard interchange with Highway 410 and present conceptual connection
alternatives.
Topics covered:
• Study update;
• GTA West update;
• Review of the connection alternatives and the MTO terms of reference for traffic assessment;
and
• The importance of the Hurontario Street / Valleywood Boulevard connection.
April 11,
2017
The purpose of the meeting was to discuss the status of the Spine Road connection to the Hurontario
Street / Valleywood Boulevard interchange with Highway 410.
Topics covered:
• Review of planning studies; and
• Review of alternatives.
June 20,
2017
The purpose of the meeting was to discuss the approach to the traffic modelling methodologies of
the proposed improvements to the Highway 410 / Hurontario Street / Valleywood Boulevard
interchange to accommodate the connection of the Spine Road.
November
16, 2017
The purpose of the meeting was to review the transportation analysis and the public consultation
requirements as per the Class EA.
February
16, 2018
The purpose of the meeting was to discuss the progress of the study to date.
Topics covered:
• Review of study to date;
• Review of the work plan; and
• Schedule.
May 7,
2018
The purpose of the meeting was to summarize the study to date, recommend interchange
modifications, review MTO comments received to date and discuss next steps.
November
27, 2018
The purpose of the meeting was to review traffic modelling, review all submitted material and discuss
forthcoming reports.
December
10, 2018
The purpose of the meeting was to summarize the study to date.
Topics covered:
• Review of Study to date;
• Review of Study timeline;
• Preferred design; and
• Review technical and environmental studies.
2.3.3 Utilities Consultation
Utility companies were contacted during the Notice of Commencement and invited to participate in the
TAC. There are various utilities present within the Study Area and further consultation will be required
through detailed design to confirm conflicts and determine any required relocations. Further details
regarding utility relocation can be found in Section 6.1.14.
Information received from utilities can be found in Appendix Q.
2.4 Public and Landowner Consultation
Effective consultation is an important part of the Class EA process. Feedback from the public is significant
as it helps identify gaps and allows the Study Team to understand the design preference. Public
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 11
Information Centres (PIC’s) provide a transparency to the EA process and gives individuals an outlet to
express their concerns. As detailed below, one PIC was held to provide information on progress with the
study and present the alternatives.
Throughout the study, several meetings were held with the various landowners and their representatives.
The following groups were involved in these discussions:
• Brook Valley;
• Cedar City Development;
• Conservatory Group;
• Fieldgate Homes;
• Glen Schnarr & Associates;
• GSAI;
• Laurier Homes;
• LEA Group;
• Mattamy;
• Melrose Investments;
• P. Becker Consulting; and
• Urbantech.
2.4.1 Public Information Centre
The Town held a PIC on July 5, 2018 from 5:00 pm to 8:30 pm at Caledon Public Library - Margaret Dunn
Valleywood Branch (20 Snelcrest Drive, Caledon, ON L7C 1B5). A joint Notice of PIC and Notice of Study
Area Revision was advertised through the newspaper (Caledon Citizen) and mailed to the individuals on
the Study Mailing List in June 2018.
The session included a series of 31 poster boards displayed around the room to share information on
progress of the study, proposed design, alternative preferred solutions being considered and next steps in
the study. Study Team members were on hand to guide attendees through the information, discuss the
study and answer questions. Attendees were encouraged to sign-in and complete a Comment Form.
There were 80 attendees that signed into the PIC and 5 completed Comment Forms returned and 13
emails received.
Details of this PIC are presented in Appendix J and a summary of comments received are presented in
Table 2-4.
2.4.1.1 Summary of PIC Comments Received
All comments received via email, letter and PIC comment forms were formally responded by letter or
email on March 20, 2018. All letters and comments received are found in Appendix J. The following table
presents a summary of the comments received and how these comments were addressed.
Table 2-4 PIC Comment Summary
Stakeholder
Type Comment Received Response
Resident (Summarized)
• Noise Levels
As part of this study, a Noise Impact Study was completed to
determine if the future interchange modifications would impact
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 12
Stakeholder
Type Comment Received Response
the Valleywood community. The study found that the increase in
traffic noise would be under the threshold requiring additional
noise mitigation measures, based on the MTO Environmental
Guide for Noise (2006).
Resident (Summarized)
• Concerns with
reconfiguration of
interchange
• Signalized
intersection
As part of this study, a Traffic Assessment was completed, which
simulated the vehicle movements on a system wide basis, with
full development constructed. This study confirmed that from a
traffic operations perspective, the right turn northbound
movement west of the bridge is preferred to the existing left turn
movement east of the bridge.
Resident Continue Etobicoke
Creek Trail as it already
was to Lake Ontario.
Need safe cycling
infrastructure to allow
safe connection.
The proposed interchange modifications will not affect the
existing connection between the Valleywood community and the
Etobicoke Creek Trail.
As noted on the active transportation slide presented at the PIC,
this study has recommended a new dedicated overpass of
Highway 410 for pedestrians and cyclists, ultimately connecting
the Valleywood community to the new MW2 development.
Additional on-road and off-road infrastructure, as well as the
new pedestrian / cyclist overpass is also proposed, as presented
at the PIC.
Brampton
Christian School
The north end of
Hutchinson Farm Lane
must remain open to
allow access to our
existing front of building
parking lot for access for
11 school buses and 70
cars morning and night
to drop off and pick up
students at start and
end of school day, plus
35 staff at school.
Access to Brampton Christian School will be maintained at all
times. Depending on the relative timing of construction of the
proposed interchange modifications and adjacent development,
temporary realignment of Hutchinson Farm Lane and its
connection to Hurontario Street may be required. Under fully
developed conditions, access to the school will be from the new
road network that will be constructed for the adjacent
development.
Brampton
Christian School
It is essential to
maintain current access
to Brampton Christian
School via Hutchinson
Farm Lane until an
efficient alternate route
is available.
Access to Brampton Christian School will be maintained at all
times. Depending on the relative timing of construction of the
proposed interchange modifications and adjacent development,
temporary realignment of Hutchinson Farm Lane and its
connection to Hurontario Street may be required. Under fully
developed conditions, access to the school will be from the new
road network that will be constructed for the adjacent
development.
TRCA (Summarized)
TRCA has a series of
comments, as outlined
in their letter dated July
4th, 2018.
The Study Team will continue to work with TRCA directly to
address their concerns. Consultation with TRCA will be ongoing as
part of detailed design.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 13
Stakeholder
Type Comment Received Response
Resident (Summarized)
• Install lights at 410
north off-ramps
immediately
• In interim, install no
u-turn signs
• Access in and out of
Valleywood during
construction
• Noise levels
• Better notification
of public meetings
• Build proposed
modifications
immediately
As part of this study, a Noise Impact Study was completed to
determine if the future interchange modifications would impact
the Valleywood community. The study found that the increase in
traffic noise would be under the threshold requiring additional
noise mitigation measures, based on the MTO Environmental
Guide for Noise (2006).
In regard to comments about u-turn signs, the Town’s By-Law
office has been advised of your concern, and representatives from
the Town will contact you directly to discuss further.
Regarding access to the Valleywood community during
construction, the Town commits to ensuring full access is
maintained at all times during construction. Specifics on the
traffic staging plan will be determined in the detailed design
phase.
Moving forward, your contact information will be added to the
study’s contact list and future communications will be sent
directly to you.
We appreciate your wish to advance the works as quickly as
possible. The Town is moving forward with completion of the
Class EA. Following completion of this study, detailed design will
commence. Progress updates will be provided by the Town as
the study progresses.
Resident (Summarized)
• How will access be
provided to new
MW2 subdivision?
For traffic movements to / from the new MW2 development west
of Highway 410 / 10, access to Highway 410 will be provided by
the proposed interchange modifications presented at the recent
public meeting. U-turns for vehicles entering and exiting the
development will not be allowed.
Resident (Summarized)
• Request for PIC
material for review
PIC material was sent via email on July 10, 2018.
Resident (Summarized)
• Proposed signal at
Highway 410 off-
ramp cannot handle
the large volume of
traffic projected
• Add a new loop
ramp for direct
access to
Hurontario Street /
Valleywood
Boulevard
As part of this study, a Traffic Assessment was completed which
simulates future vehicle movements on a system wide basis, with
full development constructed. Based on this study, the proposed
signal and intersection improvements, including a second left turn
lane, can accommodate the projected turning movements to the
level-of-service required by MTO and an additional off-ramp is
not required.
Resident
(Valleywood
Residents
Association (VRA)
(Summarized)
• Better notification
and response
Copies of presentation material, staff report, and Council minutes
were sent via email on July 6, 2018.
As part of the Class EA process, a formal public consultation
process, with defined timelines, is required. Once the study is
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 14
Stakeholder
Type Comment Received Response
letter dated
November 22,
2016
timelines for
comment periods
• Proposed two lanes
on overpass in each
direction does not
allow for space for
emergency vehicles
• Second access in /
out is required
• View showing
height of new
flyover compared
to the homes in the
Valleywood
community
• Requested Council
records which
indicated initiation
of study
filed, we also encourage you to remain involved through the
subsequent detailed design and construction phase of this study.
In response to significant concerns expressed regarding
emergency vehicle access, the Town intends to investigate this
issue as part of a separate overall transportation network review,
conducted in conjunction with a review of the Town’s Official
Plan.
Although the VRA letter is not specific to this study, the letter will
be included as part of the final study documentation, which will
be placed on the public record. This letter reinforces the position
of the VRA that a second access is required. However, some of
the other specifics relating to jurisdictional changes, road
classification and MTO’s future plans for the Highway 410 / GTA
West cannot be answered as part of this study. Please discuss the
other items of concern with Town Council and / or the MTO
directly.
The new flyover will be approximately 7 metres (m) above
Highway 410 and will consist of one lane with paved shoulders
and concrete barrier. The top of this flyover structure will be
approximately the same elevation as the top of the existing
earthen berm between Highway 410 and the Valleywood
Community.
Resident (Summarized)
• Only one entrance /
exit and proposed
modifications does
not address this
• Move traffic exiting
Highway 410
northbound to new
intersection with
Spine Road
• Likes idea of
moving Highway
410 southbound
off-ramp to
signalized
intersection
• Terminate Highway
410 at the new
intersection with
Spine Road and
provide access to
Highway 10 via the
new intersection
• Rerouting of traffic
away from
Valleywood
Regarding vehicle access, the town intends to investigate this
issue as part of a separate overall transportation network review,
conducted in conjunction with a review off the Town’s Official
Plan. Members of the Valleywood community will be invited to
participate in this study.
In response to traffic concerns, a Traffic Assessment was
completed which simulates future vehicle movements on a
system wide basis, with full development constructed. Based on
this assessment, a direct connection between northbound
Highway 410 and the new intersection is not needed, and the
existing intersection with an additional left turn lane and new
traffic signal will be sufficient to accommodate the anticipated
flow of traffic.
Additionally, shifting the ramp to the new intersection is
necessary, as left turn movements throughout the new
interchange will be limited to signalized intersections only. Your
support of this aspect of the proposed design is noted.
As part of this study, a Noise Impact Study was completed to
determine if the future interchange modifications would impact
the Valleywood community. The study found that the increase in
traffic noise would be under the threshold requiring additional
noise mitigation measures, based on the MTO Environmental
Guide for Noise (2006).
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 15
Stakeholder
Type Comment Received Response
(vehicles not from
the area do not
know that
Valleywood
Boulevard does not
continue north)
In terms of road closures, with the proposed modifications, all
northbound traffic on Hurontario Street will have direct access to
Highway 410 via the new flyover. This is expected to reduce the
occurrence of vehicles mistakenly entering the Valleywood
community due to wayfinding issues.
Resident (Summarized)
• Access concerns
have not been
addressed with
current proposal
• Traffic lights will
further limit access
to / from the
community
• Traffic noise
In terms of vehicle access, the Town intends to investigate this
issue as part of a separate overall transportation network review,
conducted in conjunction with a review of the Town’s Official
Plan. Members of the Valleywood community will be invited to
participate in this study.
In terms of traffic lights, a traffic assessment was completed
which simulates the vehicle movements on a system wide basis,
with full development constructed. The assessment has found
that no significant delays are anticipated at this intersection and
issues with access / egress to the Valleywood community are not
anticipated.
As part of this study, a noise impact study was completed to
determine if the future interchange modifications would impact
the Valleywood community. The study found that the increase in
traffic noise would be under the threshold requiring additional
noise mitigation measures, based on the MTO Environmental
Guide for Noise (2006).
Resident (Summarized)
• Noise concerns
As part of this study, a Noise Impact Study was completed to
determine if the future interchange modifications would impact
the Valleywood community. The study found that the increase in
traffic noise would be under the threshold requiring additional
noise mitigation measures, based on the MTO Environmental
Guide for Noise (2006).
Resident (Summarized)
• Removal of
Hutchinson Farm
Lane
• Rename another
new roadway within
the MW2
subdivision to
acknowledge
history associated
with Hutchinson
family
The Study Team will coordinate with the appropriate Town staff
members to review and address your request to ensure that we
follow the protocols / bylaws.
Resident (Summarized)
• Noise concerns
As part of this study, a Noise Impact Study was completed to
determine if the future interchange modifications would impact
the Valleywood community. The Study found that the increase in
traffic noise would be under the threshold requiring additional
noise mitigation measures, based on the MTO Environmental
Guide for Noise (2006).
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 16
Stakeholder
Type Comment Received Response
Resident (Summarized)
• Noise concerns
(videos included)
As part of this study, a Noise Impact Study was completed to
determine if the future interchange modifications would impact
the Valleywood community. The study found that the increase in
traffic noise would be under the threshold requiring additional
noise mitigation measures, based on the MTO Environmental
Guide for Noise (2006).
Fieldgate 410
Developments
(Summarized)
• Impact to property
based on proposed
interchange
modifications is
significant
• Wants to explore
refinements to the
design to keep
modifications
within the existing
property line
The Study Team will continue to work with Fieldgate directly to
address their concerns. No formal response will be provided.
Resident (Summarized)
• Noise concerns
• Pollution concerns
• Property value
impacts
• Environmental
impacts
• Future addition /
expansion of Spine
Road
• Communication
procedures (both
during study and
after)
• Relocate off-ramp
away from
Valleywood
Community
As part of this study, a Noise Impact Study was completed to
determine if the future interchange modifications would impact
the Valleywood community. The study found that the increase in
traffic noise would be under the threshold requiring additional
noise mitigation measures, based on the MTO Environmental
Guide for Noise (2006).
In terms of pollution concerns, development of Mayfield West is
included in the approved Town of Caledon Official Plan. This
planned development will generate additional traffic. A primary
objective of this study is to accommodate this additional traffic
efficiently, minimizing congestion and idling. Since idling is a
contributor to air pollution, the proposed roadway network
improvements will reduce air pollution compared with the
scenario in which development proceeds without roadway
network improvements.
In terms of property value impacts, a property value analysis is not
typically completed as part of the Class EA assessment. As a result,
the Town does not have any specific plans to complete this type
of assessment.
In terms of environmental impacts, as part of this study, a Natural
Environmental Assessment will be completed, which identifies the
wildlife, vegetation, and significant natural features within the
Study Area. Any impacts to the natural environment are identified
and series of mitigation measures are recommended. Upon
completion of the study, a copy of this report can be provided for
your review.
In terms of expansion and addition of Spine Road, a Traffic
Assessment was completed which simulates the vehicle
movements on a system wide basis, based on the MW2
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 17
Stakeholder
Type Comment Received Response
development being fully constructed. As part of this assessment,
a projection of traffic to 2031 was completed and additional
widening of the Spine Road post-construction was not identified.
Beyond the horizon year of 2031, future expansion of the
surrounding road network is subject to further study.
In terms of communication procedure, after construction is
completed, any issues / concerns should be expressed to the Town
directly, which will be addressed on an as-needed basis.
Lastly, questions regarding the off-ramp relocation, currently the
recommendation made by this study is to maintain the location of
this intersection.
3.0 Existing Conditions
3.1 Study Area
The Study Area is located within the Town of Caledon, approximately 1700 m north of Mayfield Road on
McLaughlin Road, and the construction of the new east-west Spine Road from Hurontario Street to
Chinguacousy Road. The Study Area includes the Highway 410 interchange with Hurontario Street /
Valleywood Boulevard (Figure 1-1).
3.2 Land Use and Development Plans
The following land use and development plans were reviewed to determine their applicability to the Study
Area:
• Town of Caledon Official Plan (2016);
• Region of Peel Official Plan (2016);
• Mayfield West Phase 2 – Secondary Plan Transportation Master Plan (2015);
• Caledon Transportation Needs Study Update – Town of Caledon and Region of Peel (2009);
• Region of Peel Active Transportation Study (2011);
• Region of Peel Long Range Transportation Plan (2012); and
• Region of Peel Road Characterization Study.
These policies were reviewed to ensure the study is in line with the policies contained within them.
3.2.1 Town of Caledon Official Plan (2016)
The Official Plan indicates the commitment to implement sustainable development patterns and urban
design throughout the Town.
The Study Area falls within the MW2 Secondary Planning Area. Mayfield West is designated as a Rural
Service Centre, with major educational, recreational and commercial facilities. The Plan states that
Mayfield West should be planned as a compact community with a focus on land use, housing and
economic development opportunities. Development of Mayfield West is projected to result in a major
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 18
increase in population. By 2021, the population is projected to be 18,179 and by 2031 it is projected to
grow to 26,744.
3.2.2 Region of Peel Official Plan (2016)
The Regional Official Plan provides direction to the Region of Peel in terms of land use policies,
sustainable development framework and long-term regional strategic policy framework for growth. The
goals of the plan are the following:
• “To create healthy and sustainable regional communities for those living and working in Peel which is
characterized by physical, mental, economic and social well-being; minimized crime, hunger and
homelessness; a recognition and preservation of the region's natural and cultural heritage; and an
emphasis on the importance of Peel's future as a caring community”;
• “To recognize, respect, preserve, restore and enhance the importance of ecosystem features, functions
and linkages, and enhance the environmental well-being of air, water, land resources and living
organisms”;
• “To recognize the importance of a vital, competitive and diverse economy and a sound tax base, and
manage and stage growth and development in accordance with the financial goals and overall fiscal
sustainability of the Region”; and
• “To support growth and development which takes place in a sustainable manner, and which
integrates the environmental, social, economic and cultural responsibilities of the Region and the
Province”.
The widening of McLaughlin Road and the construction of Spine Road is consistent with the Region of
Peel Official Plan as the road improvements will not be occurring in a key natural heritage feature area or
hydrologically sensitive area. The improvements will also protect any existing natural features and will not
negatively impact the environment.
3.2.3 Mayfield West Phase 2 – Secondary Plan Transportation Master Plan (2015)
The MW2-TMP was “undertaken to identify and assess the transportation requirements necessary to
support the growth and development of MW2 while considering the long-range transportation needs of
the community in relation to land use planning”. This study has guidance and directives for the
transportation network specific to the MW2 community, including traffic modelling, high-level road
network plan, cross-section requirements for arterial roads, rail crossing requirements, traffic calming,
transit planning, pedestrian and cycling planning, parking policies and phasing of development and roads.
The MW2-TMP was used as a building block to determine the design criteria for the preferred design of
McLaughlin Road and Spine Road and fulfilled Phases 1 and 2 of the Class EA process. The design criteria
and preferred design are discussed in more detail in Chapters 6 and 7.
3.2.4 Caledon Transportation Needs Study Update – Town of Caledon and
Region of Peel (2009)
The Caledon Transportation Needs Study Update was undertaken to determine the potential
transportation improvements to accommodate future traffic demand. This document is an update from
the original 2004 Caledon Transportation Needs Study.
The following are the changes that prompted the update:
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 19
• “The most current plan for the Provincial Highway 427 extension has the highway ending in the
vicinity of Major Mackenzie Drive”;
• “To meet Provincial growth guidelines, Caledon is now planning for substantial additional growth with
a target population of 108,000 persons by year 2031”;
• “The new Provincial Metrolinx agency is actively planning new transportation directions for the Great
Toronto and Hamilton area, including improved public transit services to communities such as
Caledon”; and
• “Several other new transportation studies have recently been initiated that will have future
implications on Caledon. This study helps provide a basis on which the Town can respond to these
studies”.
The improvements to the Study Area are consistent with the Caledon Transportation Needs Study Update
as the EA is determining the need to improve transportation infrastructure in anticipation of the future
growth of MW2.
3.2.5 Region of Peel Sustainable Transportation Strategy (2018)
The purpose of this study is to increase active transportation within the Region by creating a regional
vision and long-term goals for improvement. The study provides suggested policies, guidelines and
programs to achieve the goals. The Region of Peel has committed to 50% of sustainable mode share by
2041, which includes increasing the current 37% of the trips by walking, cycling, transit, carpooling and
telework to 50%. The strategy also aims to create a framework to:
• “Accommodate growth in a way that prioritizes environmental, societal and economic sustainability,
and”
• “Contribute to a Regional transportation system that is safe, convenient, efficient, multi-modal, well-
integrated and sustainable.”
This framework is based on the 2011 Active Transportation Study and includes input from the City of
Brampton, City of Mississauga, Town of Caledon, surrounding municipalities and other agencies, The
Region of Peel will be designing a multi-use trail along Mayfield Road, from Chinguacousy Road to
Hurontario Street between 2018-2022, which meets the objectives of this strategy and is within close
proximity to the Study Area. This study and the previous Active Transportation Study (2018) has defined
the MW2 development as a candidate area for the extension of the Etobicoke Creek Trail and an
extension of the Brampton ZUM service.
3.2.6 Region of Peel Long Range Transportation Plan (2012)
The purpose of the Region of Peel Long Range Transportation Plan (LRTP) is to identify the projected
regional transportation challenges and issues that will rise over the next 20 years. The Plan discusses
various appropriate policies, strategies and road improvement plans to help solve future challenges. This
document was used as a guide for this Class EA study.
3.2.7 Region of Peel Road Characterization Study (2013)
The Region of Peel Road Characterization Study (RCS) was a result of the recommendations from the
LRTP. The RCS is an implementation measure with the goal of identifying the objectives, needs and
respective function of the arterial roads owned by the Region. This included recognizing the competing
uses and users of the road, including goods movement, transit, pedestrian usage and active
transportation. The product of the study was a characterization of the road based on functionality and
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 20
adjacent land use. The study also aimed to consider intensification and future development impacts on
the road network. This study did not specifically characterize McLaughlin Road or Spine Road. However,
Mayfield Road (which is immediately south of the Study Area) is characterized as an Industrial Connector.
3.3 Provincial Land Use Planning Initiatives
The following provincial planning documents were reviewed to determine their applicability to the Study
Area:
• Provincial Policy Statement (2014);
• The Growth Plan for the Greater Golden Horseshoe (2017); and
• The Greenbelt Plan (2017).
These policies were reviewed to ensure the study is in line with the policies contained within them.
3.3.1 Provincial Policy Statement (2014)
The Provincial Policy Statement (PPS) provides for appropriate development while protecting resources of
provincial interest, public health and safety, and the quality of the natural and built environment. The PPS
supports improved land use planning and management, which contributes to a more effective and
efficient land use planning system.
The following policies within the PPS support potential improvements to the McLaughlin Road and Spine
Road Study Area:
Healthy, livable and safe communities are sustained by (Section 1.1, subsection 1.1.1, (g)):
“Ensuring that necessary infrastructure, electricity generation facilities and transmission and distribution
systems, and public service facilities are or will be available to meet current and projected needs.”
Infrastructure and Public Service Facilities (Section 1.6, subsection 1.6.1):
“Infrastructure, electricity generation facilities and transmission and distribution systems, and public
service facilities shall be provided in a coordinated, efficient and cost-effective manner that considers
impacts from climate change while accommodating projected needs.”
The proposed improvements discussed in this report are consistent with policies included in the PPS.
3.3.2 Growth Plan for the Greater Golden Horseshoe (2017)
The Growth Plan for the Greater Golden Horseshoe – Places to Grow, was adopted in July 2017, replacing
the former Growth Plan for the Greater Golden Horseshoe (2006), under the provisions of the Places to
Grow Act, 2005. The plan provides the framework for implementing the Provincial Government’s vision for
building strong, prosperous communities by better managing growth to the year 2041 in the expanding
Greater Toronto and Hamilton Area. Since implementation, the plan has been amended to provide
population and employment forecasts to the year 2041.
The Growth Plan contains specific policies and directions regarding transportation infrastructure, land use
planning, urban form, housing, natural heritage and resource protection to be considered by
municipalities in their planning activities. Of particular interest, the Growth Plan provides direction on
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 21
where growth can occur, the form of future development and future population and employment
forecasts.
The proposed improvements discussed in this report are consistent with policies included in the Growth
Plan for the Greater Golden Horseshoe (2017).
3.3.3 The Greenbelt Plan (2017)
The Greenbelt Plan was amended in July 2017 and is an overarching document that serves to protect the
Greenbelt Area from urbanization that would cause harm to its agricultural and ecological features. The
Greenbelt Plan is supported by The Growth Plan for the Greater Golden Horseshoe and the Niagara
Escarpment Plan. The Study Area does not fall within the Niagara Escarpment Plan designation; however, a
small portion of the Study Area falls within the Greenbelt Plan Protected Countryside designation.
The Protected Countryside designation permits the appropriate infrastructure to connect urban centres in
areas of growth and economic development. This includes the widening of existing roads and
construction of new roads. Nevertheless, the policies also state the need to minimize any possible
negative impacts or disturbances on the landscape, in terms of light intrusion, noise and road salt. The
Class EA study has assessed and will strive to minimize impacts wherever possible.
3.4 Existing Land Use
The land use adjacent and within the Study Area is predominantly rural in nature. The following is a
breakdown of the major land uses within and / or adjacent to the study Area:
• The majority of the east side of Highway 410 is residential;
• North and south of the proposed Spine Road is prime agricultural; and
• Significant environmental features include: Etobicoke Creek Headwater Wetland Complex, Upper
Fletchers Creek Wetland Complex and a small portion of the Greenbelt Area.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 22
3.4.1 Proposed Development
Figure 3-1 Existing Land Use
The proposed residential development, MW2 will be located immediately adjacent to the Study Area. The
MW2 development is anticipated to accommodate 18,000 residents and 4,700 jobs. The 207.5 hectares
(ha) development aims to support a range of housing types (apartments, townhouses, stacked
townhouses, back-to-back townhouses, single and semi-detached dwellings) and incorporate active
transportation and public transportation opportunities. This development achieves the density target of
80 people and jobs per ha as stated in the Growth Plan for the Greater Golden Horseshoe.
Employment in the Study Area includes a new elementary school, work from home and no fixed location
jobs (McDonald, 2017). The area immediately west of Highway 10 will be developed as a business / office
park, which will include low to mid-rise commercial properties. A transit hub will also be developed
adjacent to the employment area, which will encourage transit usage on the Hurontario Street corridor.
The widening of McLaughlin Road and construction of the new Spine Road is critical for supporting this
development as it provides an east-west corridor for the new residents and employers in the area and to
provide transit connections.
Study Area
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 23
3.5 Transportation
Wood has completed a Traffic Study to investigate existing and future traffic conditions within the study
area. The study assessed the need for improvements to accommodate traffic in a safe and efficient
manner. This study is included in Appendix D.
3.5.1 Existing Roadway Network
The main connecting roadways within or in the vicinity of the Study Area include:
• McLaughlin Road is a north-south arterial road that extends from Caledon in the north, through the
City of Brampton, to the City of Mississauga in the south. Within the Study Area, McLaughlin Road has
a posted speed of 80 km / h, features a rural cross section, 1 travel lane per direction and only
intersects with Mayfield Road.
• Chinguacousy Road is a north-south arterial road that extends from Caledon in the north, through
the City of Brampton, to the City of Mississauga in the south. Within the Study Area, Chinguacousy
Road has a posted speed of 80 km / h, features a rural cross section, 1 travel lane per direction and
only intersects with Mayfield Road.
• Mayfield Road is an east-west Regional arterial road that extends from Winston Churchill Boulevard
to the west and Highway 50 to the east. Within the Study Area, Mayfield Road has a posted speed of
60 km / h, features an urban and rural cross section and provides 1 travel lane per direction with
auxiliary lanes at many intersections.
• Hurontario Street is a north-south Regional arterial road that extends from Highway 410 in the north
to the City of Mississauga in the south. Within the Study Area, Hurontario Street has a posted speed
of 70 km / h, features an urban and rural cross section and provides 2 travel lanes per direction with
auxiliary lanes at many intersections. Hurontario Street becomes Highway 10, past the Highway 410
interchange.
• Highway 410 is a provincial freeway that extends from Highway 10 (also known as Hurontario Street)
in the north to Highway 401 in the south. Within the Study Area, Highway 410 is transitioning from a
freeway configuration to a highway configuration where it connects with Highway 10. Highway 410
has a posted speed of 80 km / h, has full access control and provides 2 travel lanes per direction with
speed change lanes / ramps at the interchange with Valleywood Boulevard and Hurontario Street.
3.5.2 Existing Railway Network
The Orangeville Brampton Railway crosses the study area once at the proposed Spine Road 520 metres
east of McLaughlin Road. The rail traffic is minor, consisting of four scheduled freight trips between
Orangeville and Mississauga per week. There are occasional increases in freight trains for customer needs
and occasional scheduled maintenance.
3.5.3 Existing Traffic Conditions
The intersections within the Study Area are operating with an overall acceptable LOS for both the AM and
PM peak hours. All movements are operating with a LOS of “D” or better with the exception of the
westbound left turn movement on the stop-controlled intersection of the Highway 410 WB Off-ramp at
Valleywood Boulevard, which shows LOS “F” during the PM peak hour, on account of considerably high
turning volume demand (454 volume per hour ) and limited gaps in the north-south (N / S) traffic along
Valleywood Boulevard.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 24
3.5.4 Future Traffic Conditions
The following summarized the results of the traffic analysis for future conditions (2031).
• The intersections within the Study Area are expected to operate with an overall acceptable LOS “D” or
better during the PM peak hour;
• All turning movements will operate at a LOS “D” or better;
• Delays and 95th percentile queues are acceptable for all movements and most notably, queues on the
Highway 410 westbound off-ramp do not spill onto the mainline, and
• Signalized intersections are required at the following locations for the system to operate as modelled:
o Valleywood Boulevard at Snelcrest Drive / Royal Valley Drive;
o Valleywood Boulevard at Highway 410 westbound / northbound off-ramp;
o Spine Road at Valleywood Boulevard / Hurontario Street;
o Hurontario Street at Collingwood Avenue / Highwood Road; and
o Hurontario Street at Mayfield Road.
3.5.5 Existing Transit and Active Transportation Network
Transit: The City of Brampton (Brampton Transit) currently operates one bus route that extends just south
of the Study Area, Route 24 Van Kirk. This route approaches the Study Area at Hurontario Street and
Collingwood Avenue, where it continues south away from the Study Area.
Active Transportation: Within the Study Area, active transportation varies depending on location due to
differences in the road cross-section along the various roads. Pedestrian infrastructure consisting of
sidewalks is provided within the footprint of the interchange. A linkage is provided through the
Valleywood subdivision to the Etobicoke Creek Trail. For the balance of the study corridor, there are no
existing active transportation facilities.
3.6 Natural Environment
The following sections will provide a summary of the existing terrestrial and aquatic resources. For the full
report, please refer to Appendix E.
Four of the six woodlands within the Study Area contain areas of wetland which have been evaluated and
designated as Provincially Significant Wetlands (PSW). The PSWs are part of the Upper Fletchers Creek
Wetland Complex and the Etobicoke Creek Headwater Wetland Complex. A small section of the Study
Area falls within the Greenbelt Area which tracks part of Etobicoke Creek in this location. Several
candidate Significant Wildlife Habitats (SWH) are present within the Study Area, including raptor wintering
areas, bat maternity colonies, turtle wintering areas, colonially nesting bird breeding habitat (trees /
shrubs), water fowl nesting areas, amphibian woodland breeding habitats, special concern and rare
wildlife species habitats and amphibian movement corridor habitat.
More information regarding the Features Based Water Balance summary can be found in the approved
Mayfield West Phase 2, Stage 1 Environmental Impact Study and Environmental Implementation Report
(EIS/EIR). Information regarding the Southeast Wetland under the jurisdiction of TRCA can also be found
in the EIS/EIR.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 25
3.6.1 Terrestrial Resources
Wildlife and vegetation surveys were completed and one rare plant species, Butternut, was observed. This
species is listed as an Endangered species under the Endangered Species Act, 2007 (ESA). The majority of
the bird species recorded within the vicinity of the Study Area are provincially common with the exception
of Barn Swallow, which is listed as a Threatened species under the ESA and Eastern Wood-Pewee and
Wood Thrush which are listed as Special Concern under the ESA. Rare mammals which may occur in the
Study Area are the bat species; Eastern Small-footed Myotis, Little Brown Myotis, Northern Long-eared
Myotis, and Tri-colored Bat, all Endangered under the ESA. No evidence of rare mammals was observed
within the Study Area during field investigations though targeted bat surveys were not conducted.
Suitable amphibian and reptile habitat is limited within the proposed footprint and primarily located
along vegetated drainage features. Rare reptile species potentially occurring in the Study Area include
Blanding’s Turtle (Threatened under the ESA), Common Snapping Turtle and Northern Map Turtle (both
Special Concern under the ESA). No rare reptiles or amphibians were observed within the Study Area
during field investigations.
3.6.2 Aquatic Resources
Aquatic investigations within the Study Area found that all drainage features are ephemeral, dry at the
time of investigation and do not provide direct fish habitat. Roadside drainage features were found to
have standing water but no flow. These were also found to not provide direct fish habitat. With respect to
fish and fish habitat, the primary concern is associated with Redside Dace within Fletchers Creek
downstream of the Study Area. However, no direct Redside Dace habitat was identified within the Study
Area. No other rare or endangered fish were noted or observed within the Study Area during field
investigations.
3.7 Cultural Heritage Report
Two related Cultural Heritage Evaluation Reports (CHER) completed for the Town of Caledon prior to this
report were carefully reviewed. They are entitled: Cultural Heritage Landscapes Assessment & Built
Heritage Resources Assessment for the Mayfield West Phase 2 Secondary Plan and Cultural Heritage
Resource Assessment Review Update of the Mayfield West Phase 2 Secondary Plan. As the Mayfield West
Phase 2 Secondary Plan area extends beyond the Class EA Study Area, not all of the heritage resources
identified in these reports are pertinent to the present study.
The 2008 study identified 14 properties and a railway as having cultural heritage resource significance.
The 2017 study identified four properties and the railway. The current CHER identifies 10 cultural heritage
resources pertinent to the proposed roadway development.
The heritage context of all properties and landscapes within the present study has been somewhat altered
through years of land use. Visual alterations of cultural heritage landscapes have been caused by both
subtractive and additive modifications through neglect and reuse. All of the heritage resources within the
Study Area are evocative vestiges of historical land uses over time.
A range of effects are anticipated within the Study Area, mostly as a result of impacts on vegetation,
fences, farmsteads and viewscapes. The impacts are characterized from low to high, based primarily on
the distance of resources and vegetation from the right-of-way (ROW) or impact zone.
Property encroachment along the roadways should be sensitive to the rural character of the identified
heritage resources, and post-construction landscaping along the two corridors should employ heritage
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 26
plantings and heritage themes to help conserve and enhance the cultural heritage character near the
heritage resources.
Four of the five built heritage properties listed in the Town of Caledon Heritage Register are far enough
away from the existing McLaughlin Road and the proposed Spine Road that effects on them should be
low. This includes: 12259 Chinguacousy Road, and 12461, 12700 and 12711 McLaughlin Road. With regard
to the listed property at 12502 McLaughlin Road, there is a laneway lined with mature trees that could be
impacted closer to McLaughlin Road. This CHER report was completed in January 2018 and the site
conditions may have altered since then.
In addition, the property at 12324 McLaughlin Road also has a very significant row of mature oak trees
along the laneway that could be impacted by the building of the Spine Road. And lastly, the historic Credit
Valley Railway corridor will be impacted by the building of the Spine Road in the area where the new
roadway is proposed to cross the rail corridor.
For the full report, please refer to Appendix F.
3.8 Stormwater Management Assessment
The Study Area encompasses portions of the Fletcher’s Creek Subwatershed and the Etobicoke Creek
Watershed. The subject segment of McLaughlin Road lies within the Fletcher’s Creek Subwatershed of the
Credit River Watershed and a segment of Spine Road straddles the boundary of the Etobicoke Creek
Watershed and the Fletcher’s Creek Subwatershed of the Credit River Watershed. The existing interchange
is contained within the Etobicoke Creek Watershed.
Existing land use conditions within the Study Area are primarily agricultural, with some woodlots in the
vicinity of the proposed alignment of the Spine Road. The surficial soils within the Study Area are primarily
Chinguacousy clay loam, which is classified as soil conservation service (SCS) Soil Type ‘C’ (i.e. exhibits
moderate to low infiltration rates), with small pockets of Jeddo Clay Loam, which is classified as SCS Soil
Type ‘D’ (i.e. exhibits low infiltration rates). Surficial slopes within the Fletcher’s Creek Subwatershed have
been characterized as typically low, with only the creek and valley features downstream of the Study Area
having slopes that are steeper. The slopes within the Etobicoke Creek Watershed portion of the Study
Area tend to be steeper, with the steepest slopes located along the watercourses through the area. The
drainage along McLaughlin Road is currently provided by roadside ditches, which convey runoff from
north to south; drainage within the limits of the future Spine Road is currently conveyed in the form of
sheet flow with minor headwater drainage features in the vicinity of the terrestrial woodlots.
The existing drainage system within the interchange is comprised of roadside ditches, culverts and storm
sewer systems. The drainage system conveys all runoff toward the existing wet pond stormwater
management (SWM) facility, which discharges to the Etobicoke Creek via a 1200 millimetre (mm) diameter
sewer (approximately 750 m in length). The total drainage area to the existing SWM facility is
approximately 31 ha, with an impervious coverage of 21%. Although no information has been provided
regarding the design criteria for the SWM facility, it is anticipated that the existing facility provides
stormwater quality control to an enhanced (i.e. 80% TSS removal) standard of treatment, based upon the
vintage of the SWM facility and Wood’s experience within the Etobicoke Creek Watershed as part of other
studies. Furthermore, it is anticipated that the existing SWM facility provides some form of stormwater
quantity control, likely associated with the conveyance capacity of the 1200 mm diameter storm sewer at
the SWM facility outlet.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 27
For the full report, please refer to Appendix G.
3.9 Archaeological Assessment
Wood completed a Stage 1 Archaeological Assessment for the limits of the Study Area specific to the
interchange area. The balance of the Study Area was contained within the MW2 development area, and
various archaeological studies were completed by the various landowners, as such a Stage 1 Study was
not required at these locations.
The Stage 1 Archaeological Assessment concluded that portions of the Study Area not previously
disturbed have archaeological potential and warrant Stage 2 Archaeological Assessment, primarily
because of the proximity to, or presence of:
1. 19 previously registered pre-contact and post-contact sites;
2. Numerous water sources;
3. Early transportation routes; and
4. Historically documented structures from at least as early as 1859.
The Stage 2 Archaeological Assessment is limited to the study area of the interchange, Hurontario Street
and a small portion of the proposed Spine Road. Appendix A, Figure 6 of the Stage 1 Archeological
Report (Appendix I of the ESR) identifies the findings of the study.
For the full report, please refer to Appendix I
3.10 Geotechnical Investigation
Wood completed a geotechnical investigation, visual pavement condition survey and environmental
chemical analysis of the Study Area. The following is a brief summary of the investigation.
For the full report, please refer to Appendix K.
3.10.1 Visual Pavement Condition Survey
Wood completed a visual pavement condition survey of McLaughlin Road within the Study Area to
identify any distresses. The identification and classification of the pavement distresses were carried out in
accordance with MTO’s “Flexible Pavement Condition Rating Manual – Guidelines for Municipalities”, SP-
022. Generally, the existing asphaltic concrete surface condition was rated ‘Fair’ to ‘Poor’ condition.
3.10.2 Subsurface Conditions
The sub-surface conditions for boreholes drilled in the mid driving lane typically consisted of asphaltic
concrete overlaying a granular base, with a layer of gravelly sand fill underlain by native silty clay / clayey
silt till which are predominant at the 1.5 m depth below grade. Boreholes drilled in the shoulder rounding
typically consisted of a granular material or topsoil overlaying a layer of fill, which commonly consisted of
silty sand and gravel and was underlain by native silty clay / clayey silt till.
The geotechnical investigation for Spine Road included boreholes placed at the centreline and toe-of-
slope of the proposed road. All boreholes were advanced to a depth of 1.5 m. The sub-surface conditions
for the boreholes drilled on the Spine Road alignment typically consisted of a layer of topsoil underlain by
a layer of silty sand which is overlaying native clayey silt. The thickness of the topsoil measured ranged
between 180 mm and 400 mm with an average thickness of approximately 265 mm.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 28
The sub-surface conditions in the widening area of McLaughlin Road were investigated though the
drilling of 17 boreholes at the SHR. 10 of the 17 shoulder boreholes contained a layer of granular at the
surface with an average granular thickness of 500 mm which ranged from 250 mm to 850 mm.
Within the interchange, sub-surface conditions consisted of surficial cover (i.e. asphaltic concrete or
topsoil) and / or sand and gravel / gravelly sand fill underlain by clayey silt / silty clay fill overlying native
soils (in descending order - stiff to hard clayey silt / silty clay till, compact to very dense sandy silt / sand
and silt / silt and very dense sandy silt till). The inferred groundwater level, based on change is soil colour
(brown to grey), varied at depths from about 4.1 m to 7.8 m (elevations 255.5 m to 253.8 m) below grade.
3.10.3 Environmental Chemical Analysis
Aside from fill material (i.e., silty sand and gravel) in select boreholes, no other evidence (i.e., visual /
olfactory) of environmental impacts were observed in any of the soil samples collected from this Study
Area. The RKI Eagle 2 was used to measure soil vapour readings in all boreholes. The readings were non-
detectable for combustible organic vapour) and ranged from non-detectable to 5 ppm for total organic
vapour.
Additionally, four samples were found to exceed the provincial standards for sodium absorption ratio, 2
samples exceeded provincial standards for electrical conductivity likely indicating impacted soil from the
application of road salt and one sample was found to exceed provincial standards for PHC F4, a likely
impact from a minor spill of fuel or motor oil.
3.11 Hydrogeological Assessment
From a review of available secondary source material, the following is a summary of hydrogeological
existing conditions within the Study Area:
• The available physiographic and surficial geology mapping, as well as geotechnical borehole logs
completed across the Study Area suggests that the subsurface soils consist of fine grained, relatively
cohesive till or till-like soils.
• Due to the nature of the subsurface soils and the available groundwater levels, the dewatering effort
is expected to be small and based on findings from a previous Study completed by WSP
(Geotechnical Investigation, Sanitary Trunk Sewer on MW2, Caledon, Ontario, Final (version 1), WSP
Canada Inc., August 31, 2016), neither a Permit to Take Water (PTTW) nor an Environmental Activity
and Sector Registry (EASR) would be required if the excavations of subsurface infrastructure across
the Study Area were limited to excavations of up to 30 m at a time.
• There are no creek crossings (no existing culverts) or surface water features that are in the immediate
vicinity of the Study Area and as such, no impacts to surface water would be expected during the
completion of construction activities.
• Local wells found as a result of a water well record search are not expected to be active supply wells,
as most local properties are connected to municipal water and sewer, or will be upon the completion
of construction. Remaining wells that may be private supplies are located upgradient and are not
expected to be impacted by the construction activities.
• The local groundwater has not been tested and therefore the local groundwater quality has not been
confirmed. The upgradient land use is primarily agricultural so the presence of contaminants
associated with industrial activities is expected to be low.
• Unconfined groundwater flow generally follows the topography, indicating a regional flow direction
towards the south. The local groundwater flow direction will be towards the nearby streams, which
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 29
serves as the local groundwater discharge zone. These generally consist of tributaries of Etobicoke
Creek and the Credit River, resulting in local flow towards the north northwest and south-southeast,
respectively, towards the creek channels.
For the full report, please refer to Appendix O.
4.0 Development and Evaluation of Alternative Planning Solutions
4.1 Problem and Opportunity Statement
The problem and opportunity statement has not been changed since completion of the MW2-TMP. The
MW2 planning area currently lacks a transportation system that will be capable of accommodating
anticipated future travel needs generated by the planned new community in an efficient, effective and
sustainable manner. The specific problems and opportunities to be addressed are as follows:
• Future traffic operations, safety, travel demand, transit and active transportation;
• Geometric deficiencies;
• Pavement condition;
• Drainage deficiencies and opportunities for stormwater management; and
4.2 Evaluation Criteria
As part of the initial phases of this Study, the following preliminary evaluation criteria were developed to
reflect the concerns of various stakeholders, as communicated through preliminary consultation. Table 4-1
provides a description of the evaluation criteria being applied to assess the planning alternatives:
Table 4.1 Evaluation Criteria for Alternatives
Component Evaluation Criteria Description
Social / Land
Use / Cultural
Environment
Impacts to Existing
Property
Potential impact to existing properties within the Study Area (i.e.
property value impacts)
Compatibility with Future
Land Use and Block Plans
Presence, number and characteristics of residences, community
facilities, public parks, institutions or businesses within or adjacent
to the Study Area.
Archaeological and
Cultural Heritage Impacts
Potential adverse effects on archaeological and cultural heritage
features.
Noise Impacts Impact on noise levels at noise sensitive receivers during
construction and during operation.
Air Quality Ability to reduce emissions associated with transportation within
the Study Area.
Natural
Environment
Vegetation Community Potential adverse effects on terrestrial species and habitats.
Wildlife Potential adverse effects on existing wildlife due to disturbance or
loss of habitat.
Fish and Aquatic Habitat Potential to minimize impact on aquatic features.
Surface Water Quality and
Quantity
Potential adverse effect on surface water quality and flood
potential.
Transportation
and Technical
Accommodation of
Existing and Future
Ability to accommodate the existing traffic volume as well as
future traffic volume.
Travel Demand Potential to address existing and future capacity and operational
needs.
Geometrics & Safety Ability to improve vehicular and active transportation safety.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 30
Component Evaluation Criteria Description
Alternative Modes of
Transportation
Ability to contribute to the active transportation network
throughout the corridor including consideration of active
transportation type and design and access to destinations along
the corridor.
Utility Relocation Ability to minimize effects on existing and proposed utilities.
Costs Capital Cost Capital costs of the proposed improvements and maintenance
costs.
Property Acquisition Costs Costs of expropriation.
4.3 Identification of Alternatives
Based on Phase 2 of the MW2-TMP, the following planning alternatives have been identified for
consideration in addressing the problems and opportunities discussed above:
Alternative 1: Do Nothing - Maintain McLaughlin Road, Spine Road, and the interchange in their
present condition with no improvements.
Alternative 2: Improve other Roads - Add capacity to adjacent parallel roads to accommodate traffic.
Alternative 3: Transit Infrastructure Improvements - Improve transit infrastructure to support Brampton
Transit Service and address capacity requirements.
Alternative 4: Active Transportation Infrastructure Improvements - Improve active transportation
infrastructure to support the growth initiatives of the Town.
Alternative 5: Travel Demand Management - Encourage and support change in travel behavior to
reduce peak travel demand by; promoting carpooling and possible High-Occupancy
Vehicle (HOV) lanes, promoting flexible work hours, increase active transportation trips.
Alternative 6: Widen McLaughlin Road, construct Spine Road, and complete interchange improvements
- Addition of traffic lanes including interchange improvements to increase traffic capacity
of the corridor.
Alternative 7: Combination - Combination of; improved transit services, improved active transportation,
travel demand management and widening of McLaughlin Road / construction of Spine
Road / complete interchange improvements.
Alternative 1 and 2 were eliminated as they did not fulfill the recommendations of the MW2-TMP and the
Town of Caledon Official Plan.
After careful consideration of the alternatives considering the evaluation criteria above and in consultation
with agencies and stakeholders, Alternative 7 – Combination was selected as the preferred planning
solution.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 31
5.0 Development and Evaluation of Alternative Design Concepts
Based on the preferred planning alternative as described above, a series of alternative design concepts
have been considered, and are discussed below.
5.1 Horizontal Alignment Alternatives
5.1.1 McLaughlin Road
The following horizontal alignment alternatives were considered for McLaughlin Road:
Alternative 1: Widen to a four-lane urban cross section.
Alternative 2: Widen to a four-lane urban cross section shifting the road to the west.
Alternative 3: Widen to a four-lane urban cross section shifting the road to the east.
Alternative 4: A hybrid approach (A combination of Alternatives 1, 2 and 3).
The assessment of the horizontal alignment alternatives for McLaughlin Road is provided in Table 5-1.
Based on the review of existing and future conditions, the assessment of alternatives, as well as
consultation with stakeholders, the Study Team has selected Alternative 1 as the preferred alternative.
With proper environmental constraint avoidance and mitigation planning, the benefits of the preferred
alternative outweigh its potential impacts to the natural and cultural environment.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 32
Table 5-1 McLaughlin Road Alternative Alignment Assessment
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 33
5.1.2 Spine Road
The following horizontal alignment alternatives were considered for the Spine Road:
Alternative 1: Caledon endorsed framework plan alignment.
Alternative 2: Landowners group framework plan alignment.
Alternative 3: Revised alignment (based on input from agencies and Town).
The assessment of the horizontal alignment alternatives for Spine Road is provided in Table 5-2.
Based on the review of existing and future conditions, the assessment of alternatives, as well as
consultation with stakeholders, the Study Team has selected Alternative 3 as the preferred alternative.
With proper environmental constraint avoidance and mitigation planning, the benefits of the Preferred
Alternative outweigh its potential impacts to the natural and cultural environment.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 34
Table 5-2 Spine Road Alternative Alignment Assessment
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 35
5.1.3 Interchange Modifications
The following alternatives were considered for the connection of the Spine Road to Hurontario Street:
Alternative 1: ‘T’ intersection immediately south of the interchange with a roundabout at the
intersection of Spine Road with Hurontario Street.
Alternative 2: Connect Spine Road to Valleywood Boulevard, with Hurontario Street ending at the
intersection with Spine Road and reconfiguration of the interchange.
Alternative 3: Same as Alternative 2, but with a roundabout at the intersection of Spine Road /
Hurontario Street / Valleywood Boulevard.
Alternative 4: Connect Spine Road to Valleywood Boulevard but shift connection to Hurontario Street
westerly and maintain current interchange configuration.
Alternative 5: Same as Alternative 4, but with a roundabout at the intersection of Spine Road /
Hurontario Street / Valleywood Boulevard.
Based on a review of existing and future conditions, an assessment of alternatives, as well as consultation
with the MTO, the Study Team has selected Alternative 2.
5.2 Structural Alternatives
With the new interchange configuration described in Section 5.1.3, a new flyover is required to support
the new northbound on-ramp from Hurontario Street / Valleywood Boulevard / Spine Road to Highway
410. A number of alternative structural cross sections were considered for this new structure, as follows:
Alternative 1: Cast-in-place post-tensioned deck.
Alternative 2: Slab on Steel Plate Girders.
Alternative 3: Slab on Steel Box Girders.
Alternative 4: Slab on Precast Concrete Girders.
A detailed assessment of alternatives is included in Appendix P. Based on this assessment, Alternative 3:
Slab on Steel Box Girders is recommended. The box girder structure will utilize uncoated weathering
steel except the end 3.0 m under the expansion joint, which will be coated. The vertical clearance provided
is approximately 5.2 m and is controlled by the future widening of Highway 410 and the right shoulder of
the northbound lane.
5.3 Stormwater Management Alternative Assessment
Stormwater Management (SWM) will be provided for the road improvements to satisfy the applicable
criteria. Based on the increase in pavement for the ultimate ROW and the removal of the existing ditch
system for the proposed urbanized roadway(s), stormwater controls are required, in accordance with the
applicable Region of Peel, the CVCA, the TRCA, the MTO, the Ministry of Natural Resources and Forestry
(MNRF) and the MECP criteria.
5.3.1 General Stormwater Management Opportunities
Stormwater Management practices (SWMPs) for the management of roadway runoff generally fall into
two categories: those that address water quantity and those that manage quality of surface runoff. Water
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 36
quantity management issues relate to properly sizing watercourse crossings, as well as the conveyance of
roadway runoff along the roadway corridor for minor and major storm events. In addition, water quantity
management strategies can include the need for facilities to address downstream flood and erosion
potential resulting from the expansion of the roadway ROW. Typically, the flood and erosion protection
standards are defined in the watershed or subwatershed planning study, which are dependent on the
hydrologic function and watercourse sensitivity of the receiving stream system.
In terms of water quality, the SWMPs relate to the treatment of new pavement, and where possible, the
treatment of existing pavement; however, current legislation solely relates to the former. Typically, the
treatment level is related to the standards defined in the watershed or subwatershed planning study,
which are dependent on the quality and sensitivity of the receiving stream system (i.e. Level 1, Level 2,
etc.).
Various Low-Impact Development Best Management Practices (LID BMPs) or SWMPs are available to
address the quality of runoff from roadways. Due to the linear nature of roadway corridors, the full
spectrum of SWM practices is typically not appropriate.
5.3.2 Alternative Stormwater Management Practices
For watercourse crossings of roadway corridors, typical management opportunities include:
i. Controlling or reducing upstream flows to the capacity of existing crossings.
ii. Increasing the capacity of the existing crossing to the appropriate runoff standard.
iii. Developing optimized diversions between sub-catchments to facilitate and / or reduce hydraulic
crossings.
The decision process to select a management opportunity largely relates to environmental impacts,
economics, timing and future required gradients. Given that McLaughlin Road roadway is planned for
reconstruction and Spine Road for new construction, the need or warrant for upgrading hydraulic capacity
of crossings needs to be coordinated with the structural assessment of the respective crossings.
Quality Management
There are numerous SWMPs, which can be used to treat contaminated stormwater runoff from roadway
surfaces. These include the following:
i. Wet ponds / wetlands / hybrids (generally linear facilities);
ii. Enhanced grass swales;
iii. Filter strips;
iv. Bioretention systems;
v. Oil and grit separators;
vi. Off-site SWM facilities; and
vii. Cash-in-lieu of on-site treatment.
The respective characteristics, advantages and disadvantages of the foregoing have been well
documented in previous municipal and provincial literature and hence this information has not been
repeated within this document. Some brief advantages and disadvantages, though, are discussed in the
following section.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 37
5.3.3 General Assessment
The advantages and disadvantages of the various Best Management Practices associated with both
quantity and quality control measures are as follows:
Stormwater Infrastructure Monitoring and Maintenance
One of the highest contributors to the failure of stormwater systems is the lack of monitoring and
maintenance to ensure the systems continue to perform as they were originally designed and constructed.
Debris, sedimentation and erosion can significantly impact the ability of stormwater infrastructure to
handle quantity and quality aspects of future storm events.
Quantity and Erosion Control
Controlling runoff in SWM facilities upstream of crossings requires land and future management /
maintenance by municipal forces. The advantages relate to maintaining existing sizing of drainage
infrastructure or smaller infrastructure across the roadway, as well as downstream.
Disadvantages include the cost of land, infrastructure and maintenance. Increasing the size of drainage
infrastructure, while somewhat costlier to the roadway authority, reduces the need for future maintenance
and eliminates the need for the dedication of stand-alone land for surface controls. Inter-subcatchment
diversions can be effective on a minor scale in optimizing and / or reducing the number of crossings and
are typically followed to address both major and minor runoff conditions.
Quality Control
Wet ponds, Wetlands, Hybrids
These systems generally require the dedication of land that most often is not available in linear corridors
for roadway projects. Most often when applied to roadway runoff, these SWMP’s are located adjacent to
creek crossings. For this Study, this particular opportunity is considered extremely limited. These systems
typically provide an excellent level of treatment and as end-of-pipe systems are more visible, hence less
prone to failure.
Enhanced Grassed Swales
Grassed swales designed with a trapezoidal geometry and flat longitudinal profiles with largely un-
maintained turf can provide excellent filtration and treatment for storm runoff from roadways. It is
generally conceded that treatment levels are at a minimum, normal (formerly Level 2) treatment, and
when combined with other practices can provide enhanced treatment. Their application in linear corridors
is also particularly appropriate and can be further enhanced through the introduction of check dams to
provide additional on-line storage. The application in urbanized roadway cross-sections (i.e. curb and
gutter) often requires alternative grading and roadway configurations which can compromise the function
of the roadway itself and are therefore typically not preferred. Notwithstanding, gutter outlets along
outside lanes have functioned effectively in the past where the ROW can accommodate the design.
Filter Strips
Filter strips typically are designed for small drainage areas less than 2 ha and are applied as part of a
treatment train. Filter strips require flat areas with slopes ranging from 1 to 5% and are usually in the
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 38
range of 10 to 20 m in length in the direction of flow. Flow leaving filter strips should be a maximum of
0.10 m depth, based on a 10 mm storm event.
Bioretention Systems
Bioretention systems are used in the treatment train process to provide water quality control and
infiltration. Bioretention systems should be situated within flat areas with slopes ranging from 1 to 5%.
Bioretention systems require 5 to 10% of the contributing drainage area and as such cannot typically
service large drainage areas. Where groundwater contamination could be an issue, bioretention systems
should be lined to prevent infiltration.
Infiltrative Trenches
Infiltrative trenches are similar to bioretention systems, however are typically located below the ground
surface. By installing the trenches below ground surface, the trenches are not required to follow the slope
of the roadway and can be implemented in steeper roadway sections. Infiltrative trenches can be
implemented beneath other roadway features such as multi-use paths, which saves on the dedication of
land and preserves the function of the roadway. Where groundwater levels are located near the ground
surface, the feasibility of their application significantly reduces.
Oil and Grit Separators
These systems tend to serve limited drainage areas and provide levels of treatment (less than enhanced,
formerly Level 1). They are typically encouraged as part of a “treatment train” approach. Disadvantages
include the need for frequent maintenance, as well as relatively high capital costs and the ability to serve
small drainage areas.
Off-Site Stormwater Management Facilities
While facilities can often not be constructed within roadway ROW lands, roadway runoff can be directed
towards subdivisions, which would have their runoff managed by future SWM facilities. A number of
future SWM facilities are planned adjacent to McLaughlin Road and Spine Road. As such, discharge to off-
site SWM facilities should be utilized as much as possible.
Cash-in-Lieu of On-Site Treatment
Often, due to the sensitivity of downstream systems (i.e. low habitat potential) and the difficulty of
providing affordable and effective SWM on-site, roadway authorities have proposed the contribution of
cash-in-lieu of on-site stormwater management, to be directed towards other environmental
enhancement projects. These can either be identified in subwatershed planning studies or addressed on a
site-specific basis. The priority of application usually relates first to improving watershed conditions in the
directly affected watershed. This approach is supported by both Provincial and Municipal policy.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 39
6.0 Description of Preferred Design
6.1 Major Features of the Recommended Plan
6.1.1 Design Criteria
The proposed design criteria for the preliminary design of McLaughlin Road, Spine Road and the
interchange modifications are outlined below. All preliminary design drawings are located at the end of
Section 7.0. The criteria are based on the TAC Geometric Design Guide for Canadian Roads (2017), the
MTO Design Supplement (June 2017) and the Town of Caledon standards.
Table 6-1 Design Criteria – McLaughlin Road
Present Conditions Design Standards Proposed
HIGHWAY CLASSIFICATION RAU UAU UAU
NUMBER OF THROUGH LANES 2 4 4
POSTED SPEED (KM / H) 80 60 60
DESIGN SPEED (KM / H) 100 70 70
MIN STOPPING SIGHT
DISTANCE (m) 185 105 105
MIN ‘K’ FACTOR N/A CREST – 17
SAG – 12
CREST – 21
SAG – 21
GRADES MAXIMUM 1.5% 5% 2.7%
MIN RADIUS (m) N/A 200 N/A
LANE WIDTH (m) 3.00 3.50 3.25 – INSIDE
3.50 – CURB
MEDIAN WIDTH (m) N/A 5.00 5.00
RIGHT-OF-WAY (m) VARIES 28.0 – 35.0 35.0
Notes
(1) Assumed McLaughlin Road will be illuminated
(2) Lane widths based on MW2-TMP
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 40
Table 6-2 Design Criteria – Spine Road
Present Conditions Design Standards Proposed
HIGHWAY CLASSIFICATION
SPINE ROAD DOES
NOT CURRENTLY EXIST
UAU UAU
NUMBER OF THROUGH LANES 2 - 4 2 – 4
POSTED SPEED (KM / H) 60 60
DESIGN SPEED (KM / H) 70 70
MIN STOPPING SIGHT
DISTANCE (m) 105 105
MIN ‘K’ FACTOR CREST – 17
SAG – 12
CREST – 31
SAG – 31
GRADES MAXIMUM 5% 2%
MIN RADIUS (m) 200 320
LANE WIDTH (m) 3.50 3.25 – INSIDE
3.50 – CURB
MEDIAN WIDTH (m) 5.00 4.00 – 5.00
RIGHT-OF-WAY (m) 28.0 – 35.0 27.0 – 35.0
Notes
(1) Assumed McLaughlin Road will be illuminated
(2) Lane widths based on MW2-TMP
Table 6-3 Design Criteria – Valleywood Boulevard
Present Conditions Design Standards Proposed
HIGHWAY CLASSIFICATION UAU UAU UAU
NUMBER OF THROUGH LANES 2 2 – 4 2 – 4
POSTED SPEED (KM/H) 60 60 60
DESIGN SPEED (KM/H) 70 70 70
MIN STOPPING SIGHT
DISTANCE (m) N/A 105 105
MIN ‘K’ FACTOR CREST – 20
SAG – N/A
CREST – 17
SAG – 12
CREST – 24
SAG – 25
GRADES MAXIMUM 3.25% 6% 3.25%
MIN RADIUS (m) N/A 200 250
LANE WIDTH (m) 2 X 3.65 2 X 3.5 4 X 3.75
MEDIAN WIDTH (m) VARIES VARIES VARIES
0 – 5.5
RIGHT-OF-WAY (m) N/A N/A 35.0
Notes
(1) Assumed Valleywood Boulevard will be illuminated
(2) Lane widths based on MTO standards
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 41
Table 6-4 Design Criteria – Hurontario Street
Present Conditions Design Standards Proposed
HIGHWAY CLASSIFICATION UAU UAU UAU
NUMBER OF THROUGH LANES 4 4 4
POSTED SPEED (KM/H) 70 70 70
DESIGN SPEED (KM/H) 80 80 80
MIN STOPPING SIGHT
DISTANCE (m) >130 130 >130
MIN ‘K’ FACTOR CREST – N/A
SAG – N/A
CREST – 26
SAG – 16
CREST – N/A
SAG – N/A
GRADES MAXIMUM 0.86% 6% 0.86%
MIN RADIUS (m) N/A 250 500
LANE WIDTH (m) 4 X 3.65 4 X 3.5 4 X 3.75
MEDIAN WIDTH (m) 0 – 3.8 N/A 2.5 – 5.5
RIGHT-OF-WAY (m) 43.0 N/A 43.0
Notes
(1) Assumed Hurontario Street will be illuminated
(2) Lane widths based on Region of Peel standards
Table 6-5 Design Criteria – N-E/W/S Ramp
Design Standards Proposed
CROSSING ROAD DESIGN SPEED (KM/H) 70 70
RAMP DESIGN SPEED (KM/H) 60 60
SIGHT DISTANCE REQUIREMENT FOR STOPPING,
CROSSING, AND TURNING MOVEMENTS AT THE
CROSSING ROAD
N/A N/A
MIN ‘K’ FACTOR CREST – 11
SAG – 9
CREST – 150
SAG – N/A
GRADES MAXIMUM 6% 0.85%
MIN RADIUS (m) 120 130
LANE WIDTH (m) 2 X 3.75 2 X 3.75
SHOULDER WIDTH (m) 1.0 LT
2.5 RT
1.0 LT
2.5 RT
SHOULDER ROUNDING (m) 0.5 0.5
SUPERELEVATION MAX RATE (m/m) 0.06 0.06
SIGHT DISTANCE AT EXIT TERMINAL (m) EXIST EXIST
EXIT TERMINAL SPEED-CHANGE LANE LENGTH (m) EXIST EXIST
Notes
(1) Assumed ramp will be illuminated
(2) Shoulder rounding to increase to 1.0m where steel beam guide rail is required
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 42
Table 6-6 Design Criteria – S/E-N Ramp
Design Standards Proposed
CROSSING ROAD DESIGN SPEED (KM/H) 100 100
RAMP DESIGN SPEED (KM/H) 60 60
SIGHT DISTANCE REQUIREMENT FOR STOPPING,
CROSSING, AND TURNING MOVEMENTS AT THE
CROSSING ROAD
N/A N/A
MIN ‘K’ FACTOR CREST – 11
SAG – 9
CREST – 20
SAG – 20
GRADES MAXIMUM 6% 5.4%
MIN RADIUS (m) 120 130
LANE WIDTH (m) 4.75 4.75
SHOULDER WIDTH (m) 1.0 LT
2.5 RT
1.0 / 2.5 LT
1.0 / 2.5 RT
SHOULDER ROUNDING (m) 0.5 0.5
SUPERELEVATION MAX RATE (m/m) 0.06 0.06
SIGHT DISTANCE AT ENTRANCE TERMINAL (m) 205 >205
ENTRANCE TERMINAL SPEED-CHANGE LANE LENGTH
(m) 140 - 325 430
Notes
(1) Assumed ramp will be illuminated
(2) Shoulder rounding to increase to 1.0m where steel beam guide rail is required
(3) Entrance terminal speed-change lane length from TAC GDG (2017) – Table 10.6.5
(4) Wider left (inside) shoulder to ensure sight distance is achieved (only for flyover)
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 43
Table 6-7 Design Criteria – N-E Ramp
Design Standards Proposed
CROSSING ROAD DESIGN SPEED (KM/H) 100 100
RAMP DESIGN SPEED (KM / H) 40 40
SIGHT DISTANCE REQUIREMENT FOR STOPPING,
CROSSING, AND TURNING MOVEMENTS AT THE
CROSSING ROAD
N/A N/A
MIN ‘K’ FACTOR CREST – 4
SAG – 6
CREST – N/A
SAG – 50
GRADES MAXIMUM 6% 2.55%
MIN RADIUS (m) 50 50
LANE WIDTH (m) 4.75 4.75
SHOULDER WIDTH (m) 1.0 LT
2.5 RT
1.0 LT
2.5 RT
SHOULDER ROUNDING (m) 0.5 0.5
SUPERELEVATION MAX RATE (m / m) 0.06 0.06
SIGHT DISTANCE AT ENTRANCE TERMINAL (m) 205 >205
ENTRANCE TERMINAL SPEED-CHANGE LANE LENGTH
(m) 225 - 405 275
Notes
(1) Assumed ramp will be illuminated
(2) Shoulder rounding to increase to 1.0m where steel beam guide rail is required
(3) Entrance terminal speed-change lane length from TAC GDG (2017) – Table 10.6.5
Table 6-8 Design Criteria – S-E Ramp
Design Standards Proposed
CROSSING ROAD DESIGN SPEED (KM / H) 80 80
RAMP DESIGN SPEED (KM / H) 60 60
SIGHT DISTANCE REQUIREMENT FOR STOPPING,
CROSSING, AND TURNING MOVEMENTS AT THE
CROSSING ROAD
N/A N/A
MIN ‘K’ FACTOR CREST – 11
SAG – 9
CREST – 35
SAG – 25
GRADES MAXIMUM 6% 2.3%
MIN RADIUS (m) 120 130
LANE WIDTH (m) 4.75 4.75
SHOULDER WIDTH (m) 1.0 LT
2.5 RT
1.0 LT
2.5 RT
SHOULDER ROUNDING (m) 0.5 0.5
SUPERELEVATION MAX RATE (m/m) 0.06 0.06
SIGHT DISTANCE AT ENTRANCE TERMINAL (m) 205 >205
ENTRANCE TERMINAL SPEED-CHANGE LANE LENGTH (m) 40 - 100 265
Notes
(1) Assumed ramp will be illuminated
(2) Shoulder rounding to increase to 1.0m where steel beam guide rail is required
(3) Entrance terminal speed-change lane length from TAC GDG (2017) – Table 10.6.5
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 44
6.1.2 Vertical Alignment
The vertical alignment for McLaughlin Road, Spine Road and the interchange modifications are shown in
detail on the preliminary design drawing sheets. The vertical alignment will be refined in detailed design
based on the following criteria:
• Meet the design criteria for the vertical alignment specified above;
• Match the existing centerline profile at key locations;
• Match elevations where interfacing with existing / future development;
• Match existing boulevards, commercial properties, entrances and sideroads as closely as possible; and
• Minimize property purchase requirements.
6.1.3 Typical Cross Section
The typical cross sections for McLaughlin Road and Spine Road are illustrated in Figures 6-1, 6-2 and 6-3.
Key elements of the proposed cross section include the following:
McLaughlin Road
• Concrete curb and gutter;
• Four (4) through lanes (3.25m lanes + 3.50m adjacent to curb);
• Minimum 2.0m raised median at all intersections;
• 5.0m flush median island;
• 1.80m bike lanes;
• 4.0m planting strip;
• 1.5m sidewalk (both sides);
• 3.0m left turn lanes as required at all intersections; and
• Illumination on both sides.
Spine Road (from Chinguacousy Road to 350m east of McLaughlin Road)
• Concrete curb and gutter;
• Two (2) – 3.50m through lanes;
• Minimum 2.0m raised median at all intersections;
• 5.0m median two-way left turn lane;
• 2.0m bike lanes;
• Lay-by parking where required by urban development;
• 4.0m planting strip;
• 1.5m sidewalk (both sides);
• 3.0m left turn lanes as required at all intersections; and
• Illumination on both sides.
Spine Road (from 350m east of McLaughlin Road to Hurontario Street)
• Concrete curb and gutter;
• Four (4) through lanes (3.25m lanes + 3.50m adjacent to curb);
• Minimum 2.0m raised median at all intersections;
• 5.0m flush median island;
• 2.0m bike lanes;
• 4.0m planting strip;
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 45
• 1.5m sidewalk (both sides);
• 3.0m left turn lanes as required at all intersections; and
• Illumination on both sides.
For the roadways within the footprint of the interchange modifications, a variety of cross sections will be
applied. Key elements of these roadways are as follows:
N-E/W/S Ramp, S/E-N Ramp, E-N/S Ramp, N-E Ramp and S-E Ramp
• Rural cross-section and open ditches;
• One (1) 4.75m through lane (additional lanes at intersections where required);
• 1.0m L / 2.5m R paved shoulders;
• 3.5m left and right turn lanes as required at all intersections; and
• Illumination (either with high mast lighting or localized overhead illumination).
Valleywood Boulevard
• Concrete curb and gutter;
• Four (4) – 3.75m through lanes;
• Minimum 2.0m raised median at all intersections;
• Flush median island of varying widths;
• 2.5m boulevard
• 1.5m sidewalk (both sides);
• 3.5m left and right turn lanes as required at all intersections; and
• Illumination on both sides.
During the Class EA process, it was identified that an important element of the preferred design is to
ensure the curb lane northbound continues directly onto the existing S-N Ramp. This will ensure that
traffic heading northbound are not inadvertently directed into the Valleywood subdivision, which does
not have any roads that continue northerly across Etobicoke Creek.
Hurontario Street
• Concrete curb and gutter;
• Four (4) – 3.75m through lanes;
• Minimum 2.0m raised median at all intersections;
• 1.5m boulevard;
• 1.5m sidewalk (both sides);
• 3.5m left and right turn lanes as required at all intersections; and
• Illumination on both sides.
Highway 410
The proposed modifications will shift the freeway to highway transition north. Extension of the existing
median barrier is required. Further details on the extension of the median barrier will be determined as
part of the detailed design phase.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 46
Figure 6-1 McLaughlin Road Cross Section
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 47
Notes
From Chinguacousy Road to 350 m east of McLaughlin Road
Figure 6-2 Spine Road Cross Section
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 48
Notes
From 350 m east of McLaughlin Road to Hurontario Street
Figure 6-3 Spine Road Cross Section
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 49
6.1.4 Intersection and Sideroads
Intersection designs have been developed to provide an acceptable LOS at each intersection. Storage
lengths were calculated based on 95th percentile queue lengths. Required turning lanes and
corresponding storage lengths are shown on the preliminary design drawings.
Refer to the Traffic and Transportation Report (Appendix D) for more details regarding intersections and
signal coordination and timing.
The following summarizes the key characteristics of each intersection:
McLaughlin Road at Mayfield Road
Modification to this intersection is required to fulfill the requirements of the proposed design. For the
south leg, the City of Brampton is planning to widen McLaughlin Road south of the intersection. In
addition, the Region of Peel is planning on widening Mayfield Road both west and east of McLaughlin
Road. During detailed design, discussions with the City of Brampton and Region of Peel should be
undertaken to ensure coordination of designs.
The north leg of the intersection will be modified to the configuration shown on the preliminary design.
The traffic signals will need to be modified to accommodate the proposed works.
McLaughlin Road at Collector Roads
As part of future development, several new roadways will be constructed, which will intersect with
McLaughlin Road at various locations. During detailed design, coordination with the developers and
municipal officials will be required to ensure the works are coordinated. Confirmation on locations of
signalized intersections or stop control should also be completed as part of the detailed design.
McLaughlin Road at Spine Road
Left turn lanes have been identified for all four legs of the intersection. Additionally, bike lanes will cross
this intersection both north-south and east-west.
It is anticipated that the intersection will need to accommodate many pedestrians. As such, ladder
crosswalks should be painted to ensure the crossing locations are well marked for both the pedestrians
and vehicles crossing the intersection.
Spine Road at Chinguacousy Road
This intersection will consist of a new stop-controlled connection from the Spine Road and Chinguacousy
Road. Planning studies have not identified this intersection to warrant signalization. As part of the detailed
design process, signal warrants should be completed to verify that signalization is not required.
Spine Road at Collector Roads
Similar to McLaughlin Road, the Spine Road will intersect with various collector roads as they are
constructed with development. During detailed design, coordination with the developers and municipal
officials will be required to ensure the works are coordinated. Confirmation on locations of signalized
intersections or stop control should also be completed as part of the detailed design.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 50
Hutchinson Farm Lane at Hurontario Street
As part of the interchange modifications, the intersection of Hutchinson Farm Lane and Hurontario Street,
along with the majority of Hutchinson Farm Lane, will be closed. In order to maintain access to properties
which utilize this roadway, the following will be implemented:
Development occurs before interchange modifications: A new access will be constructed connecting the
properties to the developer constructed road network.
Development occurs after interchange modifications: A temporary roadway will be constructed, which
connects to the Spine Road. After development occurs, the access will be reconfigured, connecting to the
developer constructed road network.
Specifics will be determined as part of the detailed design.
Hurontario Street at Collingwood Avenue / Highwood Road
This intersection will match existing conditions except for the north leg, where Hurontario Street will be
realigned to the west. The existing signal may need to be modified to address the realignment of the
north leg. Also, just north of the intersection will be the entrance taper for the new S-E Ramp. Signage in
advance of the intersection will be required to direct traffic heading to Highway 410 southbound. The left
and right turn lanes southbound will also be reinstated to match existing conditions.
Hurontario Street at Spine Road / N-E / W / S Ramp / S / E-N Ramp / Valleywood Boulevard
A new intersection with these roads is required as per the preferred design. Left and right turn lanes will
be provided as shown on the preferred design. A left turn for the eastbound to northbound direction is
not provided. All eastbound traffic heading north onto Highway 410 will enter the highway via. the
existing S-N Ramp.
This intersection will be signalized, and a number of key operational elements were identified by MTO,
which will need to be implemented during the detailed design process, as follows:
• Over 80% of the green time per cycle will need to be dedicated to the westbound to southbound dual
left turn lanes;
• Overlap signal phasing for the northbound to eastbound right turn lane with the westbound to
southbound dual left turn lanes to allow both movements to operate concurrently; and
• Addition of a ‘no right on red’ for the northbound to eastbound right turn lane is required to prevent
merging issues and improve operations and efficiency.
Valleywood Boulevard at E-N / S Ramp
As part of the works, an additional left turn lane will be added to the existing E-N/S Ramp. Modifications
to Valleywood Boulevard will also be completed and the southbound left turn to the existing loop ramp
will be removed.
Similar to the above, several key operational elements were identified by MTO, which will need to be
implemented during detailed design, as follows:
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 51
• Signal must be coordinated with the Hurontario Street and Spine Road / N-E / W / S Ramp / S/ E-N
Ramp / Valleywood Boulevard intersection; and
• Over 80% of the green time per cycle will need to be dedicated to the movement from dual left-turns
from the ramp to Valleywood Boulevard (southbound).
This existing stop-controlled intersection is currently scheduled to be signalized by MTO and has
considered the preliminary design outlined by this report. As part of detailed design, the designer will
confirm the layout of the signals to ensure the new configuration of this intersection does not affect the
operations of the new signals.
Valleywood Boulevard at Snelcrest Drive / Royal Valley Drive
This intersection will match existing conditions, with the exception of the following:
• Raised median treatment for the south leg will be removed and replaced with a smaller 2.0 m wide
median;
• An additional southbound through lane will be added; and
• A traffic signal will be installed as required by the Transportation and Traffic Study (Appendix D).
Emergency Access from Highway 410 to Snelcrest Drive
As part of this study, a review was completed of the existing emergency access from Highway 410 to
Snelcrest Drive. Both MTO and the Town of Caledon Fire and Emergency Services identified emergency
access to be an important issue. The review concluded that the existing emergency access is to connect to
the future northbound on-ramp. However, MTO has noted that under current conditions, the freeway to
highway transition creates a lower speed environment for emergency vehicles to use the access during
emergency situations. However, given the proposed modifications, the transition area between freeway
and highway will move north. As such, the MTO cannot commit to reinstatement of this access as part of
this study. Further discussion on this topic is deferred to detailed design.
Spine Road and Collector Road ‘F’
As part of the consultation process, MTO has noted that the distance between their new ramps at the
intersection with Hurontario Street / Spine Road and any intersection within the Mayfield West Phase 2
development must be a minimum of 400m. Currently the land use plan provided by the development
group identifies Collector Road ‘F’ only 200m west of the new ramps. As part of detailed design, the
spacing between the new intersection/ramps and Collector Road ‘F’ will be confirmed in consultation with
the MTO.
6.1.5 Transit
As the surrounding areas continue to develop and expand, it is anticipated that demand for transit will
increase. The MW2-TMP identifies a ‘major transit node’ to be constructed on the Spine Road just west of
Hurontario Street. This transit node is anticipated to service local bus routes, bus rapid transit and GO
transit.
During detailed design, coordination should be completed with Brampton Transit and Metrolinx to
confirm the specifics for the future transit node, along with any local transit requirements (i.e. stops,
shelters and bus bays).
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 52
6.1.6 Private Entrances
As of writing of this report, it is anticipated that some existing homes along McLaughlin Road will remain
for the foreseeable future. Where necessary, these existing entrances will be reconstructed based on the
following criteria:
• Asphalt aprons between the curb and sidewalk;
• Match original driveway material at the property line;
• Driveway grades in accordance with municipal standards; and
• Permission to enter required for re-grading of driveways beyond the limit of the ROW.
In addition, gaps in the raised median will be provided based on current land uses to allow for full
vehicular movements only where it is deemed safe.
Within the interchange area, a few access constraints were identified which need to be considered during
detailed design, as follows:
• 12571 Hurontario Street, 12581 Hurontario Street and 12591 Hurontario Street access the highway
immediately north of the interchange. With the addition of the new northbound on-ramp, access to
these properties will need to be restricted. Further consideration to permanent closure of these access
points will need to be completed as part of detailed design;
• Access to Hurontario Street from the undeveloped property on the northeast corner of Hurontario
Street and Highwood Road will need to be closed; and
• Access from the Region’s lands on the northwest corner of Hurontario Street and Collingwood
Avenue will need to be limited to right-in right-out.
6.1.7 Property Requirements
The MW2-TMP has designated ROW widths for both McLaughlin Road and the Spine Road. These
property requirements were carried forward and are identified on the preliminary design drawings.
For the interchange, most of the modifications are contained within the existing Highway 410 ROW.
Property taking has been minimized to the degree possible, however, there will be additional property
required from both private and public land owners at various locations. During detailed design, property
requirements (including permission to enter requirements) will be confirmed. Figure 6.4 shows the
preliminary property requirements for the interchange improvements, which are also to be confirmed
during detailed design.
Any surplus lands generated from the removal of Hutchinson Farm Lane can be transferred to the Region
of Peel. Further review of this transfer will need to be completed as part of the detailed design process.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 53
Figure 6.4 Preliminary Property Requirements
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 54
6.1.8 Active Transportation
The recommended pedestrian and cycling facilities (i.e. active transportation) for McLaughlin Road and
Spine Road are as follows:
• 1.8 m wide on-road bike lanes along McLaughlin Road;
• 2.0 m wide on-road bike lanes along Spine Road; and
• 1.5 m / 2.0 m wide sidewalk for pedestrians on either side of McLaughlin Road and Spine Road.
Within the limits of the interchange, active transportation will be provided in the following manner:
• 1.5 m sidewalk on both sides of Valleywood Boulevard between Snelcrest Drive and Hurontario Street;
• 3.0 m multi-use trail on both sides of Spine Road between Hurontario Street and Collector Road ‘F’;
and
• Transition to bike lane (on-road) and sidewalk (off-road) along the Spine Road at Collector Road ‘F’.
As part of the MW2-TMP, a pedestrian / cyclist structure is proposed to cross over Highway 410,
connecting the west limit of Snelcrest Drive to the MW2 development. At this time, the specifics of the
proposed pedestrian / cyclist structure are not known, and further study is deferred to a later date.
Additionally, the Town has initiated the process to determine the approximate location of bus stops and
active transportation facilities along McLaughlin Road and Spine Road. A plan showing the various
aspects noted are identified on Figure 6.5.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 55
Figure 6.5 Proposed Bus Stop Locations and Active Transportation Facilities
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 56
6.1.9 Accessibility for Ontarians with Disabilities Act Measures
The Accessibility for Ontarians with Disabilities Act (AODA) requires that all barriers in the built
environment (public spaces and buildings) be removed. The Integrated Accessibility Standards Regulation
identifies the specific requirements that must be implemented for public spaces and the associated
timelines. During the detailed design phase, the designers will need to confirm that the design for
McLaughlin Road, Spine Road and the interchange meets the minimum requirements as defined by the
AODA.
6.1.10 Pavement Design
A preliminary pavement design was completed for McLaughlin Road and Spine Road as part of the
geotechnical investigation. The following is a brief summary of the pavement design recommendations.
For the full report, please refer to Appendix K.
Rehabilitation
For McLaughlin Road, two (2) selected rehabilitation strategies were selected for investigation and
analysis, as follows:
Partial Depth Reconstruction and Resurface: This option involves removal of total asphalt (70 mm) and
further excavating to a total depth of 250 mm of granular materials, proof-rolling, completing base repair
where needed, re-grading and compaction, addition of 100 mm of new granular A and compaction and
resurfacing with 150 mm of hot mix. This option will improve drainage and the structural capacity of the
pavement and will have lower maintenance cost over the pavement service life than the existing
pavement. In addition, it will not change the existing vertical profiles and will yield a structure number of
123 mm. Partial depth reconstruction is an option if raising the grade is not feasible.
In-place Pulverization, Remixing, and Resurfacing: This option will involves pulverizing the remaining
asphalt to a total depth of 120 mm. The resulting mixture of asphalt concrete materials and granular is
then graded to cross fall and compacted and used as a base. The advantages of this option include the
elimination of surface defects and reflection cracking and the reuse of the existing material efficiently.
Typically, the GBE for Bituminous crushed recovered material is in the order of 1.0. In-place pulverization
should be graded and compacted and resurfaced with 120 mm of HMA. This will raise the vertical profile
by 120 mm and will yield SN of 128 mm. Pulverization is cost-effective if raising the grade is feasible.
Widening of McLaughlin Road
A wider roadway platform is required to accommodate the preferred design alternative for McLaughlin
Road. The minimum pavement structural design for widening McLaughlin Road is presented below in
Table 6-10 and was designed in accordance with the 1993 American Association of State Highway and
Transportation Officials (AASHTO) Guide for the Design of Pavement Structures.
Table 6-10 Recommended Minimum Structural Pavement Design for McLaughlin Road
Material Description AASHTO’93 Pavement Design for 20 years
Hot Mix Asphalt Concrete Surface HL3 or HL1 or SP12.5 50mm / PGAC 58-28
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 57
Binder Course HDBC of HL8 or SP19.0 50+50mm / PGAC 58-28
Granular ‘A’ Base 150mm
Granular ‘B’ Subbase (Type II) 300mm
Total Pavement Thickness 600mm
New Construction for Spine Road
A new roadway platform is required to accommodate the preferred design for Spine Road. The minimum
pavement structural design for the Spine Road is presented below in Table 6-11 and was designed in
accordance with the 1993 AASHTO Guide for the Design of Pavement Structures.
Table 6-11 Recommended Minimum Structural Pavement Design for Spine Road
Material Description AASHTO’93 Pavement Design for 20 years
Hot Mix Asphalt Concrete Surface HL3 or HL1 or SP12.5 50mm / PGAC 58-28
Binder Course HDBC of HL8 or SP19.0 50+50mm / PGAC 58-28
Granular ‘A’ Base 150mm
Granular ‘B’ Subbase (Type II) 400mm
Total Pavement Thickness 700mm
Pavement structure for Interchange Modifications
The pavement structure for the roads within the footprint of the interchange were not determined as part
of this study and will need to be determined as part of the detailed design.
6.1.11 Utilities
Utility companies were contacted at the commencement of the Study and were invited to participate.
Based on a preliminary review, relocation or protection of various utilities will be required during the
detailed design phase, as follows:
Bell Canada
• Relocation is anticipated for most of the corridor; and
• Some of the existing infrastructure can be protected, depending on the results of the utility conflict
analysis completed by the detailed design team.
Enbridge
• Relocation of Enbridge gas main is anticipated for the corridor. Further coordination is recommended
for the detailed design team.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 58
Alectra Hydro (formerly Hydro One Brampton)
• All existing hydro poles within the Study Area are in conflict with the proposed widening. Further
coordination is required by the detailed design team to determine the specifics of the relocation
works.
Region of Peel Watermain
• The existing watermains are not anticipated to be significantly impacted. Further review is required by
the detailed design team to determine the impacts (if any) to the existing watermain; and
• The watermain appurtenances (such as hydrants and valve chambers) will need to be adjusted /
relocated. Further review is required by the detailed design team.
A comprehensive utility investigation should be conducted in the detailed design phase, to locate and
determine conflicts with the proposed works.
6.1.12 Agency Approvals
Agency approvals are required as part of detailed design and before construction can begin. Approval
requirements are summarized in Table 6-12.
Table 6-12 Required Agency Approvals / Permitting Requirements
Agency Approval / Permit Required Comments
Ministry of the Environment,
Conservation and Parks
EASR - Self Registration of Water
Taking Activity
For road construction and
construction site dewatering.
Department of Fisheries and Oceans Fisheries Act N/A
Toronto Region Conservation
Authority
Permit under O. Reg. 166 / 06 Required to develop in areas
within regulated limit
Credit Valley Conservation Permit under O. Reg. 166 / 06 Required to develop in areas
within regulated limit
Ministry of Natural Resources and
Forestry
ESA Section 17 (c) Permit for Approval for Activities
that may affect Species or Habitat
protected under the ESA (17C)
Town of Caledon Woodlands By-law 2000-100 Required for the removal of trees
during construction.
Ministry of Transportation Highway Corridor Management
Permit
Required if Town is proponent of
project.
6.1.13 Illumination
Full illumination will be installed along McLaughlin Road, Spine Road, and within the interchange as part
of the construction works. The detailed design team will notify the appropriate system operators before
making changes to the existing lighting system.
6.1.14 Preferred Design Impacts on Local Air Quality Conditions
An air quality impact assessment was not deemed to be required for this Class EA. Qualitatively, the
existing air quality conditions in the area, which are currently agricultural lands, will change as the MW2
Secondary Plan for the area is implemented. The potential air quality impacts that could arise during both
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 59
construction and operation of the roads, when weighted against the need for the Town to grow in
accordance with the Provincial Growth Plan is low.
The MW2 area is being designed with the following considerations:
• Protection of natural heritage features (i.e., wetlands);
• Traffic Demand Management is an important implementation measure;
• New road capacity to carry automobiles, cyclists, pedestrians and transit in the MW2 area; and
• Accommodation of active transportation and future public transit.
The Highway 410 portion is located adjacent to the study area with revisions to the interchange part of
the project. Currently and in the future some of the air quality impacts in the area will be from operation
of this highway.
Implementation of the MW2 Secondary Plan will result in air quality impacts but this is part of the
development process. Typical of the development process, the major roads (widening of McLaughlin Road
and construction of the new East-West Spine Road) will be developed first and will result in air quality
impacts. However these roads are necessary to support the residential, commercial and institutional
components of the MW2 Secondary Plan. The current and future impacts to air quality were always
anticipated to occur by permitting development in an area that is currently agricultural land. This
development is necessary to meet planning commitments by the Town, including meeting the Provincial
Growth Plan.
While air quality impacts will occur in the area from the municipal roads, development and Highway 410,
additional air quality studies will be undertaken during detailed design to ascertain the potential impact
on any sensitive receptors proposed in the MW2 area. Potential air quality impacts to present and future
sensitive receptors will be minimized as much as possible in the operation of a widened existing
McLaughlin Road, Spine Road, and the interchange modifications.
6.1.15 Structural Design
Highway 410 northbound flyover
As noted in Section 5, a new flyover of Highway 410 is proposed for northbound traffic. This flyover will
consist of a two-span structure, with abutments on either side of Highway 410 and a centre pier in the
median of the highway. The approximate total span of the flyover will be 78.5m.
The new flyover will be subject to review and approval by the MTO. Conversations with MTO should begin
early in the design process to ensure all design requirements are met.
The MTO has indicated that there are no plans to widen Highway 410 at the Study Area. However, in
order to ensure the new flyover can accommodate future widening without significant modification to the
superstructure / substructure, it has been assumed that one additional lane in each direction will be
constructed. The future lanes are identified on the general arrangement drawing accordingly.
Modification of the existing Highway 410 / Valleywood Boulevard Overpass
In order to facilitate the new N-E on-ramp, portions of the existing overpass will need to be modified, as
follows:
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 60
• Removal of a portion of the slope paving and replaced with a concrete barrier / retaining wall; and
• Consideration for future widening of Highway 410 when modifying the slope paving.
Additional consideration for the following is to be completed during detailed design:
• Installation of shoring in order to modify the slope paving may be limited by vertical clearances under
the structure;
• Removal of a portion of the slope paving may decrease cover on the existing foundation; and
additional frost protection should be considered; and
• The RSS abutment walls have shown signs of settlement at this location, which should be considered
as part of the detailed design phase.
Other Structural Works
Within the limits of the McLaughlin Road, there are no drainage features crossings supporting direct or
indirect habitat or watercourses. As such, no structural culverts are noted as required.
For the Spine Road, only intermittent watercourses cross the Study Area. With the planned
redevelopment, these intermittent features will be redirected to the proposed SWM facilitates. As such,
there are no structural culverts anticipated for the Spine Road.
Within the interchange, there are a number of open ditches which ultimately drain to the existing wet
pond via a number of culverts. These culverts vary in size from small corrugated steel pipes to longer span
box culverts. As part of detailed design, these culverts will need to be removed / replaced / extended to
facilitate the new interchange configuration. The detailed design team will need to facilitate modification
of these elements as part of the design.
Additionally, modification to the Etobicoke Creek crossing north of the interchange will be required to
facilitate the construction of the new northbound Highway 410 on-ramp. The detailed design team is to
consider either installation of a headwall over the existing structure or an extension matching the existing
configuration of the culvert.
6.1.16 Construction Staging
At some locations, widening of McLaughlin Road can be completed with traffic on the existing portion of
the roadway. Traffic would then shift to the new platform, allowing rehabilitation for the existing road
platform. For those locations where a grade change is proposed between existing and proposed, more
significant staging will be required, with temporary shoring required as necessary. More specifics for the
construction staging and phasing will be determined as part of the detailed design phase.
Critical to the staging process of the interchange will be to ensure that access to the Valleywood
subdivision is maintained at all times during construction. As part of the detailed design process, a
detailed staging plan will be completed, which will not only identify roads to be maintained, but also any
temporary road construction that will be required to maintain access to the Valleywood subdivision.
Consideration for both emergency access and for residents will be made as part of the detailed staging
plan.
During consultation with the MTO, it was identified that the Etobicoke Creek crossing of Highway 410 / 10
is scheduled to be completed in 2020. As part of the interchange modifications, a new northbound ramp
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 61
will need to cross over this culvert. Coordination will be completed as part of the detailed design phase to
ensure conflicts between the two projects are minimized.
6.1.17 Preliminary Cost Estimate
A copy of the preliminary cost estimate for the road improvements can be found in Appendix L.
6.2 Potential Impacts and Mitigation Measures
6.2.1 Land Use
The proposed work within the Study Area will result in the roadway and associated traffic being brought
closer to existing residential and rural land uses. The following impacts to property have been
documented within the Study limits, and will be reviewed during the detailed design phase:
• Property purchase along both sides of McLaughlin Road, Spine Road and within the interchange:
Purchase will be completed in accordance with Town policy;
• Driveway reconstruction / grading (both asphalt and gravel): Driveways will be reconstructed to match
existing materials;
• Impact to landscape features (fencing, gates and retaining walls): Landscape features will be modified
and / or reconstructed as indicated on the preliminary design drawings;
• Impact to or removal of trees and residential landscape plantings at various properties: A tree
preservation plan and landscape planting plan will be prepared in detailed design; and
• Coordination with development plans.
6.2.2 Air Quality
Highway 410, Hurontario Street and Mayfield Road are adjacent to the study area and would be the main
sources of air quality impacts. The widening of McLaughlin Road and the Spine Road are local municipal
roads and would contribute less to the air quality than the existing roads and Highway 410.
6.2.2.1 Sensitive Receptors
The following are the types of land uses which are defined as sensitive receptors for potential air quality
effects:
• Health care facilities;
• Senior citizens’ residences or long-term care facilities;
• Child care facilities;
• Educational facilities;
• Places of worship; and
• Residential dwellings.
Highway 410 and existing housing developments are located adjacent to the east side of the study area.
On the south side of the study area is Mayfield Road and existing housing developments with residences
located on the southern edge closest to the proposed roadways and development.
6.2.2.2 Construction Impacts and Mitigation Measures
In addition to the community and road configuration minimizing idling and other traffic related air quality
impacts, best management practices to mitigate any air quality impacts caused by construction dust (i.e.,
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 62
use of non-chloride dust suppressants) will be undertaken in the construction phase. Extensive vegetation
and tree planting will ensure that impacts by the new roads on sensitive receptors will be minimized.
Increases in particulate matter above ambient conditions may occur at distances from a few metres to 300
metres in areas of traffic stagnation due to congestion The roads will be designed to operate at a LOS to
minimize congestion and the potential for a reduction in air quality contaminants produced by stagnated
traffic. Construction related air emissions can also be expected, including dust from various material
handling operations and combustion emissions from construction equipment, which is typically powered
by diesel engines. Such emissions will be of a temporary nature and the impact is not predicted to move
far from the immediate vicinity of the construction activities along the major roads.
Typical mitigation measures include the control of air quality impacts from dust releases around the
construction sites and construction equipment and includes the following:
• During construction, vehicles / machinery and equipment will be in good repair, equipped with
emission controls, as applicable, properly maintained and operated within regulatory requirements.
• A minimal number of machines operating in any one area shall be carefully considered during
construction activities.
• Water and dust suppressants (non-chloride) will be applied during construction to protect air quality
due to dust.
The Air Quality Impact Assessment will be completed during detailed design and provided to MECP for
their review and approval. The assessment will include the following consideration:
• Assess impacts at existing and future sensitive receptors;
• Emissions and modelling impacts will be compared against the Ontario Ambient Air Quality Criteria
and the Canadian Ambient Air Quality Standards;
• The assessment will include cumulative impacts based on background air quality data and additional
impacts from the MW2 development;
• At least two modelling scenarios will be conducted comparing current versus future build; and
• Dust mitigation measures during construction and other applicable mitigation measures will be
included.
6.2.3 Noise Assessment
As part of this Study, a Noise Assessment was completed to determine the noise impacts of the proposed
improvements to the Highway 410 interchange, Valleywood Boulevard and the proposed Spine Road
(Appendix M). The recommendations of this report are summarized as follows:
The guideline applicable to this Study is the MTO Environmental Noise Guide (2006), which was applied to
complete this Study.
The results of the assessment indicate that the predicted noise is below the 5 dBA criterion as defined by
the MTO Noise Guide but the overall Future “build” sound levels at five receivers (R071, R128, R133, R135
and R143) are above the 65 dBA criterion. These exceedances of the 65 dBA criterion represent the values
at the most exposed façade. However, according to the MTO Noise Guide the need for mitigation must be
determined based on the outdoor living area (OLA) sound levels. In each case for R071, R128, R133, R135
and R143 the OLA sound levels are expected to be below the 65 dBA criterion. Therefore, based on the
noise modelling results, consideration for noise mitigation is not a requirement for the project.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 63
As noted by the local residents, noise levels are an existing problem that will not be improved as part of
the proposed works. During detailed design, the Town will consult with the local residents further and
determine if any noise mitigation beyond the standards outlined by the MTO Environment Noise Guide
(2006) is required.
Construction noise impacts are temporary and largely unavoidable. However, the contract documents
should identify the contractor’s responsibilities with respect to controlling noise, as well as recording,
investigating and if possible addressing complaints. The contract documents should also explicitly state
that compliance with all applicable law is an expectation of the contract including adherence to the Town
of Caledon Noise By-Law 86-110 [2] and MOECC Publication NPC-115.
6.2.4 Archaeological Assessment
As noted in Section 3, some areas within the limits of the interchange improvements have been identified
for a Stage 2 Archaeological Assessment. As part of the detailed design, a Stage 2 Archaeological
Assessment should be carried out by means of hand-shovel test pits at 5-m intervals (while avoiding
buried utilities) and the screening of test-pit soils for artifacts through 6-mm mesh. All areas of
disturbance should be documented to determine their spatial limits.
No grading or other activities that may result in the destruction or disturbance to the Study Area is
permitted until notice of the Ministry of Tourism, Culture and Sport approval has been received.
6.2.5 Built and Cultural Heritage
As noted in Section 3, a number of built and cultural heritage resources were identified. As part of
detailed design, the proposed works in and around each heritage resource must ensure that the heritage
character of the buildings and landscapes on these properties is not unduly obscured or impacted.
Given the above, the following mitigation measures are recommended:
• Encroachment onto former Credit Valley Railway lands should be minimized in order to preserve the
historic appearance of the railway corridor. The crossing at the new Spine Road should be designed to
be sympathetic to the rural nature of the area;
• The mature oak trees that are along the laneway at 12324 McLaughlin should be protected from the
construction of the new Spine Road. In the current design of the Spine Road, the oak trees will be
separated from the road by about 30 m;
• Construction fencing and tree hoarding should be installed around and in front of those heritage
resources which are closer to the roadway, at a sufficient distance to ensure that there will be no
direct construction impacts as a result of the movement of construction equipment or machinery;
• Standard road construction techniques should be used where possible, excluding all avoidable
construction techniques (such as deep foundation work or piling) that could cause structural damage
to heritage resources;
• All trees that cannot be saved should be replaced with large caliper nursery stock that are appropriate
for roadside use (i.e. salt resistant). Replacement trees should replicate as closely as possible the
heritage appearance, assortment and placement of the current trees;
• Wherever possible, the roadway should be engineered to ensure that the heritage character of the
buildings and landscapes are not unduly impacted or obscured; and
• All outstanding Heritage Impact Assessments for heritage resources within the Study Area (including
the Cultural Heritage Landscape of the former Credit Valley Railway) should be completed. By doing
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 64
so it can be determined whether any of these resources should be designated under the Ontario
Heritage Act.
6.2.6 Natural Environment
An aquatic and terrestrial impact assessment memo (Appendix E) was completed to document any
impacts associated with the proposed design and to recommend any necessary mitigation measures to
minimize the impacts. The following summarizes the anticipated impacts and the proposed mitigation.
6.2.6.1 Aquatic Impacts
Impacts associated with the construction in the McLaughlin Road and Spine Road alignment will include
the installation of culverts at intermittent tributaries along Spine Road and the extension of culverts at
McLaughlin Road. Disturbances with these activities will include loss of riparian habitat and temporary
disturbance during construction activity.
The proposed works at the Highway 410 and Highway 10 interchange include the installation of a
headwall, proposed to avoid having to extend the existing culvert. The proposed headwall construction
would entail no in-water work. Impacts would include the removal of limited woody vegetation which
could be mitigated through revegetation with native riparian species per conservation authority planting
guidelines. Construction activity can also result in erosion and sedimentation originating from the work
area.
6.2.6.2 Terrestrial Impacts
Wetlands
All of the wetland vegetation communities, including portions of the PSW Complex, which is located
beyond the limits of the proposed works, will not be impacted.
Vegetation Impacts
An assessment of the Preliminary Design indicates that the footprint of the proposed road widening will
primarily impact lands that consist of agricultural and residential land uses. A total projected loss of
58,648 m2 of natural and semi-natural habitats are expected from the proposed works.
Loss of natural woody vegetation is projected to occur in only one small area of White Pine Hardwood
(mixed) Forest. Based on local protocols, a 10 m buffer is required beyond the forest dripline and only
selective removal is expected within the forest habitat and its buffer. Planted trees in many other parts of
the Study Area are also projected to be removed. A tree inventory has been completed of specimens with
a diameter at breast height of greater than 10 centimeters within the impact areas identified in the
preliminary design. Correspondence with the CVCA and TRCA will be necessary during the detailed design
phase to determine compensation and revegetation requirements for vegetation removals and
disturbances occurring in the Conservation Authority regulated limits. Conservation authority
requirements typically include replacement ratios for woody vegetation removals, planting of native
species and include delineation of sensitive habitat and / or tree preservation areas.
Vehicles associated with the construction works and the subsequent increased traffic once the roads are
constructed and in use may result in impacts to existing vegetation communities. These disturbances can
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 65
include the spread of exotic and invasive species and increased dust generation which may result in
deposition on vegetation, potentially effecting photosynthesis, respiration and transpiration.
Terrestrial Wildlife Impacts
All the species observed within the Study Area are provincially ranked secure, apparently secure or not
suitable for conservation activities (generally non-native species), with exception of the Species at Risk
(SAR) discussed below. Most species present are typical of agricultural and urban settings and
anthropogenically influenced natural areas. The habitats for species which rely on woodlands areas are
not expected to be affected, as such a small area of forest is within the zone of impact.
Direct impacts on wildlife can include disturbance, physical harm or mortality. The removal of vegetation
and trees within both the natural and anthropogenic habitats has the potential to disturb nesting birds.
This disturbance can cause destruction or abandonment of nests. As well, wildlife can attempt to move
into or through construction zones to breed, nest or forage, which can result in potential harm or
mortality. An active construction zone has the potential to produce increased noise and light disturbance
to wildlife adjacent to the Study Area.
Vegetation communities within the Study Area have the potential to support three types of SWH. The
forests onsite could potentially support Bat Maternity Colonies. Although no suitable habitat was
observed during field investigations, extensive targeted surveys for bats and / or maternity colonies have
not been undertaken to date. The combination of woodlands and open foraging areas could provide
Raptor Wintering Areas. These SWH are not expected to be impacted by the Study work due to minimal
removal of both woodland and open habitats, and the presence of such suitable habitat in the
surrounding area. The third type of SWH which has the potential to be present is Habitat for Species of
Conservation Concern, which are those species designated Special Concern under the ESA. These species
and their probabilities of occurrence are discussed further below.
The woodlands and hedgerows within the Study Area function as linkages and corridors between
vegetated communities and wildlife habitats. The Study could result in the loss of wildlife corridor
functionality between vegetated communities in an already fragmented landscape. Wildlife may cross the
road regularly to travel between nearby suitable habitats. Expansion of the road and associated increases
in traffic volumes may increase the risk of road mortality.
Species at Risk and Provincially Rare Species
Based on background information derived from secondary sources and field investigations, Study works
have the potential to impact several SAR. Species observed during field investigations include Barn
Swallow (Hirundo rustica), Eastern Wood-pewee (Contopus virens), Wood Thrush (Hylocichla mustelina)
and Butternut (Juglans cinerea). Other potentially impacted species include four species of bats, Red-
headed Woodpecker (Melanerpes erythrocephalus), Monarch butterfly (Danaus plexippus), Bobolink
(Dolichonyx oryzivorus) and Eastern Meadowlark (Sturnella magna).
Additional SAR and provincially rare species reported within the 10 km2 grid encompassing the Study
Area and those which have a reported range including the Study Area are reported in Amec Foster
Wheeler’s Widening of McLaughlin Road and Construction of East-West Spine Road (MW2) Natural
Environment Existing Conditions Report. Based on the last observed date, habitat requirements and
habitat available within the Study Area, these additional SAR have low or no probability of occurring
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 66
within the Study Area. As such, these species or their habitat are not expected to be impacted by Study
works.
Barn Swallow is listed as Threatened under the ESA. This species was observed frequently throughout the
Study Area which consists of abundant suitable foraging habitats. There are limited bridge or culvert
nesting sites present; however, there are potential nesting sites on various buildings. At the detailed
design phase, avian nesting investigations should be conducted at any relevant structures or buildings to
confirm the absence or presence of Barn Swallows and nests.
Two Eastern Wood-pewee and one Wood Thrush were identified within the Study Area during field
investigations. Both of these species are listed as Special Concern under the ESA. All three individuals were
in Woodland 1 which is the only woodland currently within the impact zone. All individuals were detected
singing within the woodlot, not from the periphery. Therefore, it is likely the minimal effects to the
woodland based on anticipated zones of impact would not interfere with these species or their habitat.
Butternut is classified as Endangered under the ESA. One Butternut was observed at the northeast of the
Study Area (adjacent to Woodland 6). It is possible other individuals exists within the Study Area as
woodlots were not surveyed extensively. Based on the proposed preliminary design, and the required
buffer of 25 m around individual trees, this species will not be affected as the recorded individual is
outside the zone of impact and woodlots are minimally impacted.
Four species of bat are classified as Endangered under the ESA in Ontario (Tri-colored Bat, Little Brown
Myotis, Northern Myotis, and Eastern Small-footed Myotis). All four species have the potential to occur
within the deciduous forest habitats within the Study Area. No deciduous forest habitats are anticipated
to be impacted. The only woodland within the zone of impact is a mixed forest which is dominated by
White Pine which will not support bat maternity colonies and therefore impacts to these species are not
expected.
Two species (Red-headed Woodpecker and Monarch) classified as Special Concern in Ontario were
determined to have moderate potential to be present and utilizing habitats within the Study Area. These
species were not observed during field investigations and the impacts to suitable habitats are expected to
be very limited. It is unlikely that these species or important associated habitats will be impacted.
Bobolink and Eastern Meadowlark, both classified as Threatened in Ontario, are considered to have a low
potential to occur within the Study Area based on 2017 land uses. However, MNRF correspondence
indicates the Study Area has supported these species in the past, presumably when suitable nesting
habitats, such as hay crops, were planted. At the detailed design phase, agricultural land use
investigations should be conducted to confirm the absence or presence of suitable habitats and these
species.
Animal Movement Corridors
The Significant Wildlife Habitat Criterion Schedules for Ecoregion 6E outlines two wildlife habitats meeting
the criteria for animal movement corridor habitat. Based on a review of ecosites and wildlife present,
amphibian movement corridor habitat is considered potentially present in the Project study area.
Amphibian movement corridors may be present within the study area. These corridors are found in all
ecosites that potentially support significant amphibian breeding habitat. Given the Project study area has
a section of Etobicoke Creek, watercourses, swamps, and moist forests with vernal pools (SWDM2-2,
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 67
SWDM3-3, FODM7-2, FODM7-7, and FODM9-4 ecosites) which may provide breeding habitat for
amphibians, there are likely linkages between these areas on site.
6.2.6.3 Mitigation
Birds
Barn Swallow is provincially-designated as Threatened and is therefore protected under the provincial SAR
legislation, which prohibits destroying critical or essential habitat for Threatened and Endangered SAR. In
order to avoid adverse effects to Barn Swallow and their habitat, mitigation measures should be applied,
including adhering to breeding bird season restrictions. Creation of an artificial nest structure nearby will
be required to compensate for the loss of Barn Swallow nesting habitat. Replacement nests are required
to be installed prior to the beginning of the breeding bird season (April 1 to August 31).
The Migratory Birds Convention Act (MBCA 1994) makes it unlawful to pursue, hunt, take, capture, kill or
sell birds listed therein ("migratory birds”). Compliance with the MBCA regulations and guidelines for
vegetation clearing or demolition, as recommended by Environment Canada, will be considered during
the project’s construction phase. In order to minimize the potential risk of any nesting migratory birds,
clearing of vegetation and any proposed work activities in migratory bird habitat must be undertaken
outside of the active breeding season (mid-May to August 1 for Southern Ontario). In the event that
clearing (or other work) is required during the nesting season, a nest survey must be conducted by a
qualified avian biologist within 2 days prior to commencement of the works to identify and locate active
nests of species covered by the MBCA.
Bats
If bat SAR are detected within the Study Area during detailed design, further mitigation measures such as
bat boxes may be necessary. Any vegetation clearing should take place outside the active period for bats
(April 1 to September 30), or at least the maternity period (June 1 to July 31).
Fish
It is recommended that “in-the-dry’ and in-water works occur between July 1 to March 31 to protect both
warm and cool-water species. Furthermore, fish rescue will be required in order to move fish from the
work areas to areas upstream prior to beginning the dewatering process that is required to complete
construction “in-the-dry”.
Erosion and Sediment Control (ESC)
Prior to the commencement of construction, standard ESC measures should be designed and
implemented and should meet or exceed Ontario Provincial Standards and Specifications (OPSS). The
control measures shall be implemented prior to work and be maintained through all phases of the Study
until vegetation is re-established, and all disturbed ground is permanently stabilized.
6.2.7 Hydrogeology
A preliminary hydrogeology Study has been completed for this Study (Appendix O). As noted by this
report, the dewatering effort is expected to be small and as such, neither a PTTW nor an EASR will be
required if the excavations of subsurface infrastructure are limited to excavations of up to 30 m at a time.
Local wells found as a result of a water well record search are not expected to be active supply wells, as
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 68
most local properties are connected to municipal water and sewer, or will be upon the completion of
construction. Remaining wells that may be private supplies are located upgradient and are not expected
to be impacted by the construction activities.
Also, for the new northbound flyover, dewatering effort is expected to be relatively low and may remain
below 50,000 L / day, but once the detailed design is determined, the dewatering effort required should
be calculated to confirm whether some form of permitting with the MECP will be required, whether it be a
registration on the EASR or whether a PTTW will be required.
As a due diligence measure, a private well survey should be completed within a 500 m radius pre-
construction to establish the number of active wells that are present nearby, and the quality and quantity
of the water produced by these wells, as well as an assessment of the conditions of these wells. Any well
complaints received during the course of the construction should be investigated by a qualified
professional and recommendations generated on the potential source of the well complaint and
recommendations on how to address the issue (if required).
6.2.8 Stormwater Management
A Stormwater Management Report has been completed for this Study (Appendix G). To meet the
standards of the Town of Caledon, the CVCA, the MTO, the TRCA, the MNRF and the MECP, the report
recommends the following SWM strategies and hydraulic improvements for McLaughlin Road and Spine
Road:
• Neither the subject segment of McLaughlin Road nor the Spine Road traverse regulated watercourses,
hence no permanent hydraulic structures (i.e. bridges or open footing culverts) are required.
• It is recommended that the SWM plan for the future expansion of McLaughlin Road and the Spine
Road be incorporated into the drainage and SWM plan for the adjacent development areas, in
accordance with the recommendations of the MW2 Area Comprehensive Environmental Impact Study
and Management Plan and the MW2 Functional Servicing Plan.
• LID BMP’s are recommended to mitigate thermal enrichment of storm runoff, as well as to manage
water budget in accordance with the requirements provided in The Guidance for Development
Activities in Redside Dace Protected Habitat.
• The proposed works are anticipated to coincide with the urbanization within the adjacent
developments, hence no interim works are anticipated to be required.
The report also recommends the following SWM strategies and hydraulic improvements for the
interchange modifications:
• The proposed works associated with the Spine Road / Highway 410 Interchange would result in an
additional 16,156 m2 of paved surface (i.e. 5% increase in imperviousness).
• SWM for the proposed works would be required to provide an enhanced level of stormwater quality
control for the proposed works, as well as to address conveyance capacity constraints of existing
drainage infrastructure.
• The existing wet pond within the limits of the interchange should be expanded to address both
additional quality and quantity control.
• That supporting hydrologic and hydraulic analyses be completed as part of detailed design for the
interchange, to establish the storage requirements for the SWM facility, as well as to verify the
conveyance capacity and hydraulic grade line of the 1200 mm diameter pipe at the outlet under
existing and proposed conditions.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 69
• The detailed design assessment should necessarily include supporting hydrologic and hydraulic
analyses for the swales and culverts, to verify that all hydraulic structures satisfy current criteria for
freeboard and flood protection of the roadways.
6.2.9 Monitoring
The Town will review the implementation of mitigation measures and key design features, to confirm that
they are consistent with the contract and with commitments made. All Town construction projects are
subject to daily on-site inspection. Additionally, any environmental features constructed to facilitate
wildlife movement will be monitored post-construction. Further remediation may be required if steps
taken to direct wildlife towards the crossing are not successful.
6.2.10 Source Water Protection
Based on the Source Water Protection Information Atlas by MECP, Source Protection Plan for the CTC
(Credit Valley, Toronto and Region and Central Lake Ontario) Source Protection Region, Credit Valley
Source Protection Area Assessment Report and the Approved Updated Assessment Report: Toronto and
Region Source Protection Area, the Study Area is not within the Wellhead Protection Area, Intake
Protection Zone, Issue Contributing Area, Significant Groundwater Recharge Area, Highly Vulnerable
Aquifer or Significant Groundwater Quality Threat Area. Additionally, none of the activities in the study
area will result in drinking water threats.
6.2.11 Climate Change
The climate change review is based on the development of climate change influenced rainfall scenarios
that can be used to support modelling and design of drainage features associated with the subject
roadway at the detailed design stage. These rainfall estimates have been developed to align with relevant
modelling completed to date for the project and, as such, the focus events have been identified as the 25-
year return period event for 6-hour and 12-hour durations. The future timeframes for this analysis have
been identified as 2050 and 2080. Further details can be found in Appendix R.
The following recommendations stem from the foregoing assessment of climate change influenced
rainfall:
• It is recommended that the project maintain reliance on the Gumbel based estimates for assessment
and design, given the direction adopted by Environment and Climate Change Canada (ECCC) and the
differences between the Gumbel and Generalized Extreme Value (GEV) based estimates.
• It is recommended that the project give consideration to using rainfall estimates based on a GEV
approach for design stress testing purposes.
• It is recommended that additional consultation be completed to determine the appropriate rainfall
scenario to use for detailed design of drainage works associated with the roadway.
It is anticipated that the above recommendations will be considered during detailed design.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment – Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 70
7.0 Summary of Environmental Issues and Commitments to Environmental Impacts and
Mitigation Measures
Table 7-1 Summary of Environmental Issues and Commitments to Environmental Impacts and Mitigation Measures
Potential
Environmental
Effects
Expressed By Mitigation Measures and Work Commitments
Aquatic
Resources
(Fisheries/
Watercourse)
MECP,
TRCA, CVCA &
MNRF
Installation of culverts at intermittent tributaries along Spine Road and the extension of culverts at McLaughlin Road.
It is recommended that “in-the-dry’ and in-water works occur between July 1 to March 31 to protect both warm and cool-water
species. Furthermore, fish rescue will be required in order to move fish from the work areas to areas upstream prior to beginning
the dewatering process that is required to complete construction “in-the-dry”.
Modification to the Etobicoke Creek crossing north of the interchange will be required to facilitate the construction of the new
northbound Highway 410 on-ramp. The detailed design team is to consider either installation of a headwall over the existing
structure or an extension matching the existing configuration of the culvert.
The intermittent watercourses crossing Spine Road will be redirected to the proposed SWM facilitates.
Within the interchange culverts will need to be removed / replaced / extended to facilitate the new interchange configuration. The
detailed design team will need to facilitate modification of these elements as part of the design.
Landscaping and
Vegetation
TRCA, CVCA &
MNRF
Loss of natural woody vegetation is projected to occur in only one small area of White Pine Hardwood (mixed) Forest. Based on
local protocols, a 10 m buffer is required beyond the forest dripline and only selective removal is expected within the forest
habitat and its buffer.
Correspondence with the CVCA and TRCA will be necessary during the detailed design phase to determine compensation and
revegetation requirements for vegetation removals and disturbances occurring in the Conservation Authority regulated limits.
Conservation authority requirements typically include replacement ratios for woody vegetation removals, planting of native
species, and include delineation of sensitive habitat and/or tree preservation areas.
Prior to the commencement of construction, standard ESC measures should be designed and implemented and should meet or
exceed OPSS. The control measures shall be implemented prior to work and be maintained through all phases of the Study until
vegetation is re-established, and all disturbed ground is permanently stabilized.
Traffic and
Access Residents
A traffic management and construction staging plan will be prepared at the detailed design phase. The staging plan will identify
roads to be maintained and any temporary road construction that will be required to maintain access to the Valleywood
subdivision. Consideration for both emergency access and for residents will be made as part of the detailed staging plan.
Transit Brampton Transit
& Metrolinx
During detailed design, coordination should be completed with Brampton Transit and Metrolinx to confirm the specifics for the
future transit node, along with any local transit requirements (i.e. stops, shelters and bus bays).
Utilities Utility Companies Required utility relocations will be coordinated with relevant companies during the detailed design phase.
Illumination Town of Caledon
Full illumination will be installed along McLaughlin Road, Spine Road and within the interchange as part of the construction
works. the detailed design team will notify the appropriate system operators before making changes to the existing lighting
system.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment – Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 71
Potential
Environmental
Effects
Expressed By Mitigation Measures and Work Commitments
Property
Requirements
and Impacts
Residents
Property purchase along both sides of McLaughlin Road, Spine Road, and within the interchange. Purchase will be completed in
accordance with Town policy.
Driveway reconstruction / grading (both asphalt and gravel). Driveways will be reconstructed to match existing materials.
Impact to landscape features (fencing, gates and retaining walls). Landscape features will be modified and / or reconstructed as
indicated on the preliminary design drawings.
Impact to or removal of trees and residential landscape plantings at various properties. A tree preservation plan and landscape
planting plan will be prepared in the detailed design phase.
During detailed design, there may be a need for an archeological assessment to satisfy the TRCA property section standards and
protocols.
Coordination with development plans during detailed design is required.
Built and
Cultural
Heritage
Ministry of
Tourism, Culture
and Sport
Encroachment onto former Credit Valley Railway lands should be minimized in order to preserve the historic appearance of the
railway corridor. The crossing at the new Spine Road should be designed to be sympathetic to the rural nature of the area.
The mature oak trees that are along the laneway at 12324 McLaughlin should be protected from the construction of the new
Spine Road. In the current design of the Spine Road, the oak trees will be separated from the road by about 30m.
Construction fencing and tree hoarding should be installed around and in front of those heritage resources which are closer to
the roadway, at a sufficient distance to ensure that there will be no direct construction impacts as a result of the movement of
construction equipment or machinery.
Standard road construction techniques should be used where possible, excluding all avoidable construction techniques (such as
deep foundation work or piling) that could cause structural damage to heritage resources.
All trees that cannot be saved should be replaced with large caliper nursery stock that are appropriate for roadside use (i.e. salt
resistant). Replacement trees should replicate as closely as possible the heritage appearance, assortment and placement of the
current trees.
Wherever possible, the roadway should be engineered to ensure that the heritage character of the buildings and landscapes are
not unduly impacted or obscured.
All outstanding Heritage Impact Assessments for heritage resources within the Study Area (including the Cultural Heritage
Landscape of the former Credit Valley Railway) should be completed. By doing so it can be determined whether any of these
resources should be designated under the Ontario Heritage Act.
Archaeology
Ministry of
Tourism, Culture
and Sport
As part of the detailed design, a Stage 2 should be carried out by means of hand-shovel test pits at 5-m intervals (while avoiding
buried utilities) and the screening of test-pit soils for artifacts through 6-mm mesh. All areas of disturbance should be
documented to determine their spatial limits.
No grading or other activities that may result in the destruction or disturbance to the Study Area is permitted until notice of the
Ministry of Tourism, Culture and Sport approval has been received.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment – Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 72
Potential
Environmental
Effects
Expressed By Mitigation Measures and Work Commitments
Wildlife MNRF
At the detailed design phase, avian nesting investigations should be conducted at any relevant structures or buildings to confirm
the absence or presence of Barn Swallows and nests.
At the detailed design phase, agricultural land use investigations should be conducted to confirm the absence or presence of
suitable habitats and these species (Bobolink and Eastern Meadowlark).
Creation of an artificial nest structure nearby will be required to compensate for the loss of Barn Swallow nesting habitat.
Replacement nests for Barn Swallow are required to be installed prior to the beginning of the breeding bird season (April 1 to
August 31).
The MBCA (1994) makes it unlawful to pursue, hunt, take, capture, kill or sell birds listed therein ("migratory birds”). Compliance
with the MBCA regulations and guidelines for vegetation clearing or demolition, as recommended by Environment Canada, will be
considered during the project’s construction phase.
In order to minimize the potential risk of any nesting migratory birds, clearing of vegetation and any proposed work activities in
migratory bird habitat must be undertaken outside of the active breeding season (mid-May to August 1 for Southern Ontario).
In the event that clearing (or other work) is required during the nesting season, a nest survey must be conducted by a qualified
avian biologist within 2 days prior to commencement of the works to identify and locate active nests of species covered by the
MBCA.
If bat SAR are detected within the Study Area during detailed design, further mitigation measures such as bat boxes may be
necessary.
Any vegetation clearing should take place outside the active period for bats (April 1 to September 30), or at least the maternity
period (June 1 to July 31).
Noise Town of Caledon
Construction noise impacts are temporary and largely unavoidable. However, the contract documents should identify the
contractor’s responsibilities with respect to controlling noise, as well as recording, investigating and if possible addressing
complaints. The contract documents should also explicitly state that compliance with all applicable law is an expectation of the
contract including adherence to the Town of Caledon Noise By-Law 86-110 [2] and MOECC Publication NPC-115.
Stormwater
Management MECP
It is recommended that the SWM plan for the future expansion of McLaughlin Road and the Spine Road be incorporated into the
drainage and SWM plan for the adjacent development areas, in accordance with the recommendations of the MW2 Area
Comprehensive Environmental Impact Study and Management Plan and the MW2 Functional Servicing Plan.
LID BMP’s are recommended to mitigate thermal enrichment of storm runoff, as well as to manage water budget in accordance
with the requirements provided in The Guidance for Development Activities in Redside Dace Protected Habitat.
SWM for the proposed works would be required to provide an enhanced level of stormwater quality control for the proposed
works, as well as to address conveyance capacity constraints of existing drainage infrastructure.
The existing wet pond within the limits of the interchange should be expanded to address both additional quality and quantity
control.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment – Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 73
Potential
Environmental
Effects
Expressed By Mitigation Measures and Work Commitments
That supporting hydrologic and hydraulic analyses be completed as part of detailed design for the interchange, to establish the
storage requirements for the SWM facility, as well as to verify the conveyance capacity and hydraulic grade line of the 1200 mm
diameter pipe at the outlet under existing and proposed conditions.
The detailed design assessment should necessarily include supporting hydrologic and hydraulic analyses for the swales and
culverts, to verify that all hydraulic structures satisfy current criteria for freeboard and flood protection of the roadways.
Groundwater
MECP, TRCA,
CVCA, Town of
Caledon
As a due diligence measure, a private well survey should be completed within a 500 m radius pre-construction to establish the
number of active wells that are present nearby, and the quality and quantity of the water produced by these wells, as well as an
assessment of the conditions of these wells. Any well complaints received during the course of the construction should be
investigated by a qualified professional and recommendations generated on the potential source of the well complaint and
recommendations on how to address the issue (if required).
Surface Water
Quality
MECP, TRCA,
CVCA, Town of
Caledon
Dewatering methods will be reviewed during detailed design. At such time, a permit be obtained if required.
AODA Town of Caledon During the detailed design phase, the designers will need to confirm that the design for McLaughlin Road, Spine Road, and the
interchange meets the minimum requirements as defined by the AODA.
Consultation MCFN
The Town of Caledon and specifically this Study Area falls within Traditional Territory of Mississaugas of the Credit First Nation. As
such, the Ministry of the Environment, Conservation and Parks has delegated procedural aspects of the duty to consult to the
Town of Caledon as part of the Class EA. Based on the Town’s relationship with MCFN, the Town is committed to ensuring
involvement of MCFN’s Field Liaisons Representatives in any fieldwork associated with future stages of this Project. The Town will
work with the Proponent responsible for the detailed design stage to ensure that this involvement occurs during detailed design
activities, such as Stage 2 Archaeological Assessment and further natural environment assessments.
Air Quality MECP
During construction, vehicles / machinery and equipment will be in good repair, equipped with emission controls, as applicable,
properly maintained and operated within regulatory requirements.
A minimal number of machines operating in any one area shall be carefully considered during construction activities.
Water and dust suppressants (non-chloride) will be applied during construction to protect air quality due to dust.
The Air Quality Impact Assessment will be completed during detailed design and provided to MECP for their review and approval.
- Assess impacts at existing and future sensitive receptors;
- Emissions and modelling impacts will be compared against the Ontario Ambient Air Quality Criteria and the Canadian Ambient
Air Quality Standards;
- The assessment will include cumulative impacts based on background air quality data and additional impacts from the MW2
development;
- At least two modelling scenarios will be conducted comparing current versus future build; and
- Dust mitigation measures during construction and other applicable mitigation measures will be included.
McLaughlin Road and Spine Road Municipal Class Environmental Assessment –
Environmental Study Report
Town of Caledon
Project No. TPB166090 | 6/19/2019 Page 74
8.0 References
McDonald, N. (2017). MW Phase 2 stage 2 Planning Justification Report for Settlement Area Expansion.
Meridian Planning. Available from:
https://www.peelregion.ca/planning/officialplan/pdfs/ropa/ninth/Appendix-VI-Caledon-MW-PJR-
Sep-27-V5-reduced.pdf
Region of Peel. (N.d). Proposed Expansion of Mayfield West Phase 2 Stage 2. Available from:
https://www.peelregion.ca/planning/officialplan/mayfield-west-stage-2.htm
Town of Caledon. (2015). Mayfield West Phase 2 Secondary Plan Transportation Master Plan Final Report.
Appendix A
Notice of Study Commencement
Appendix B
Indigenous Consultation
Appendix C
Agency and Landowner Meeting Minutes
and Comments
Appendix D
Transportation and Traffic Study
Appendix E
Natural Environment Report
Appendix F
Cultural Heritage Report
Appendix G
Stormwater Management
Assessment Report
Appendix H
Environmental Impact
Assessment Report
Appendix I
Archaeological Assessment
Appendix J
Public Information Centre
Appendix K
Geotechnical Investigation Report
Appendix L
Preliminary Cost Estimate
Appendix M
Noise Impact Study
Appendix N
Utilities Consultation
Appendix O
Hydrogeological Assessment
Appendix P
Structural Overpass Design Report
Appendix Q
Utilities Consultation
Appendix R
Preliminary Road Design Drawings