megabolt shear testing program -...

34
Megabolt shear testing program Ron McKenzie Ben King Presentation to NUGS and BBUGS 25, 26 Feb 2015

Upload: doananh

Post on 30-Apr-2018

218 views

Category:

Documents


4 download

TRANSCRIPT

Megabolt shear testing program

Ron McKenzie

Ben King

Presentation to NUGS and BBUGS 25, 26 Feb 2015

Industry requested information on shear performance of cables in late 2013

Two recognised cable shear testing methods

Double shear test

British Standard (BS 7861-2) double embedment, single shear

Cable shear testing in industry

Costs of outside testing – $10k to $12k per test

Up to 36 different cables

We wanted to control certain variables

Wanted to replicate as close as possible what happens in a coal mine roof

Why do our own testing?

Rock (concrete)strength

Hole diameter

Grout strength

Cable pretension

Friction across the shear plane

Cable types

Embedment length

Factors affecting shear performance

Fixed factors

Rock (concrete)strength Originally 24 MPa

Settled on 40 MPa to align with UoW testing

Hole diameter – 42 mm, rifled holes

Grout strength – 60 MPa – aligns with UNSW pull test program

Friction across the shear plane – test rig designed to minimise effects of friction

Further tests are to be conducted to determine level of friction across the shear planes

Variable factors

Cable pretension

Tests conducted with 0 kN, 90 kN & 250 kN pretension

Cable types

Up to 36 possibilities when wire type, bulbing & cable capacity considered

Embedment length to a lesser degree – depended on the cable being tested

Cable types - wires

Smooth

Indented - four face (shown) or chevron

Spiral rib

Six different capacity cables available

49, 54, 58, 63, 70, 84 tonnes

Tests conducted on the commonly used 63 t MW9

Made from spiral wire

Can be bulbed or plain strand

Tests also carried out on 70 t MW10 megabolt

Made from smooth or indented wire

Same dia as MW9 – same collar fittings, tensioner, hole dia

Cable types - capacity

Cable geometry – 31 mm

MW9 spiral wire 63 t

MW10 smooth wire 70 t

Shear test rig

120 t max load

900 mm or 1,800 mm embedded length on either side

120 mm max displacement

252 mm dia samples

Initial lengths of 900 mm

Increased to 1,800 mm

Sample preparation

Tension applied via frame

No normal force applied across shear plane

Grouting using bottom-up grouting method

Grouting

Concrete cylinders were confined using cylindrical heavy steel clamps

Prevent radial cracking – in line with UNSW testing

Allows for handling of long lengths

Steel clamps

Friction between the steel faces of the rig is kept to a minimum

Eight roller bearings are the contact points

Friction across faces of the rig

Roller bearings

No pretension load across the shear faces

Concrete cylinders are contained within heavy steel clamps which are secured to faces of the rig – can’t move towards, or away from, the shear plane

Teflon film between faces of the anchor cylinders

Friction across shear faces

This cable pretensioned to 90 kN

Max shear load of 50.4 t

No scoring or signs of frictional wear between faces

Minimising the effects of friction is a major factor in achieving realistic results

Friction across shear faces

As a result of shearing an axial load is applied to the cable in the anchor cylinders

To obtain a realistic shear result the cable should not fully de-bond over the anchor length

The extent of de-bonding is determined by the bond strength of the cable

High bond strength cables have deformed wire & bulbs (MW9) & only require short embedment to fail the cable

When pull tested the standard MW9 will break with 450 mm embedment – hence the reason we started with anchor cylinders 900 mm long

Embedment length

The lower the bond strength the greater the de-bonding of the cable & hence the greater the shear displacement

Effects of bond strength

De-bonding propagates away from shear plane during loading

Displacement

The 900 mm anchor blocks did not provide sufficient embedment for smooth & indented wire cables without bulbs

Complete de-bonding occurred with the cable pulling through the cylinder

Decided to double up the anchor cylinders to provide 1,800 mm embedment

So far there has not been complete de-bonding in the longer anchor cylinders – partial de-bonding will always take place

Embedment length

A number of shear testing programs use end constraints to overcome the problem of full de-bonding along the length of the anchor cylinder or block

End constraints

B&W end constraint on an early test

End constraints do not exist in a mine roof

Exception can be when shearing takes place close to the collar of the cable & then only on one side of the shear plane

Tests on end constraints have shown that B&W draw-in contributes to displacement

Wedges can drawn in up to 16 mm

End constraints

Test Cable Wire Bulbs

per side Embedded

length (mm) Pretension

(kN) Max shear

load (t) Displacement at max load (mm)

1A*^ MW9 Spiral 2 900 90 50.4 94.5

1B MW9 Spiral 2 900 90 40.8 42.9

1C* MW9 Smooth 0 900 90 55.2# 118.6

1D MW9 Spiral 2 900 0 44.4 48.1

1E MW9 Spiral 2 900 250 38.4 34.3

1F* MW10 Smooth 0 900 90 61.2 88.5

1G* MW10 Indented 0 900 90 51.6 80.1

2A MW10 Indented 0 1,800 90 55.2 45.3

2B MW9 Smooth 4 1,800 90 49.2 50.2

2C MW10 Smooth 0 1,800 90 57.0 51.4

* End movement, complete debonding ^ Not fully grouted # Max load, no failure

Results summary

Effects of pre-tension

48 mm, 44 t 43 mm, 41 t

34 mm, 38 t

0

5

10

15

20

25

30

35

40

45

50

55

60

65

0 10 20 30 40 50 60 70 80 90 100 110 120

Shear load (t)

Shear displacement (mm)

MW9 0 kN pretension

MW9 90 kN pretension

MW9 250 kN pretension

Increase in cable tension causes a reduction in the maximum shear load

Also reduces the amount of displacement

Effects of pre-tension

Effect of wire type – 90 kN

0

5

10

15

20

25

30

35

40

45

50

55

60

65

0 10 20 30 40 50 60 70 80 90 100 110 120

Shear load (t)

Shear displacement (mm)

1B MW9, spiral, bulb

2A MW10, indented

2B MW9, smooth

2C MW10, smooth

Smooth wire, and to a lesser extent indented wire, allow for greater shear displacement due to reduced bond strength

Effect of wire type

All results

0

5

10

15

20

25

30

35

40

45

50

55

60

65

0 10 20 30 40 50 60 70 80 90 100 110 120

Shear load (t)

Shear displacement (mm)

1B MW9, spiral, bulb

1C MW9, smooth, no bulb

1D MW9, spiral, bulb, 0 kN

1E MW9, spiral, bulb, 250 kN

1G MW10, indented

2A MW10, indented

2B MW9, smooth

2C MW10, smooth

MW9, not grouted, ends free

Debonded

Debonded results

0

5

10

15

20

25

30

35

40

45

50

55

60

65

0 10 20 30 40 50 60 70 80 90 100 110 120

Shear load (t)

Shear displacement (mm)

1C MW9, smooth, no bulb

1G MW10, indented

MW9, not grouted, ends free

Debonded

Results embedment constrained

0

5

10

15

20

25

30

35

40

45

50

55

60

65

0 10 20 30 40 50 60 70 80 90 100 110 120

Shear load (t)

Shear displacement (mm)

1B MW9, spiral, bulb

1D MW9, spiral, bulb, 0 kN

1E MW9, spiral, bulb, 250 kN

2A MW10, indented

2B MW9, smooth

2C MW10, smooth

Either tensile cup & cone or

combination of axial tension & bending

Wire failure mode

Shear test on ungrouted, unconstrained MW9

Displacement went to the max of rig – 120 mm

Load was 15 t

Ends of cable progressively bent

Indicates differential loading on wires

Ungrouted, unconstrained test

Wires experience differential strain within the shear zone because of the lay of the wires

This in turn causes sequential failure of the wires

Hence you never reach the max capacity of cable

Ungrouted, unconstrained test

0

5

10

15

20

25

30

35

40

45

0 10 20 30 40 50 60

Shear load (t)

Shear displacement (mm)

The testing program has turned out to be far more involved than originally thought

Further testing is required

Initial results indicate that cable capacity, bond strength and pretension are the most import factors influencing cable shear behaviour

The higher the capacity of the cable the better, the lower the bond strength the better – debonding being the best!

Still require high bond strength in the anchor section at the top of the cable

Conclusions

Thanks for your attention