method of statement ct's testing

Upload: madsam282729

Post on 03-Apr-2018

384 views

Category:

Documents


20 download

TRANSCRIPT

  • 7/28/2019 Method of Statement CT's Testing

    1/7

    Content

    1.Objective

    2.Test Equipment Required

    3.Test procedures1. Mechanical Check and Visual Inspection

    2. Insulation Resistance Test

    3. Polarity Test

    4. Secondary/Loop Resistance Test

    5. Burden Test (optional test)

    6. Magnetization Curve Test (optional test)

    7. Turns Ratio Test (optional test)

    8. Primary Injection Test

    9. High Voltage Test

    10.Commisioning Test

    4.Applicable Standards

    1. Objective

    To confirm the physical condition and electrical characteristics of current transformer installed in the

    installation. Ensure theCT is connected to system properlyin all respect (primary and secondary).

    2. Test Equipment Required

    Requi red equipm ent for test ing:

    1. Insulation tester

    2. Polarity tester

    3. Digital low ohmmeter

    4. Current source, multimeter

    5. Variac, step-up transformer (0-2kv)

    6. Primary current injection set

    3. Test Procedures

    3.1. Mechanical Check and Visual Inspection

    1. Verify nameplate ratings are in accordance with the approved drawings and specifications.

    2. Inspect for physical damage/ defects and mechanical condition.

    3. Verify correct connection of transformers with system requirements.

    http://electrical-engineering-portal.com/testing-commissioning-current-transformer#1http://electrical-engineering-portal.com/testing-commissioning-current-transformer#1http://electrical-engineering-portal.com/testing-commissioning-current-transformer#1http://electrical-engineering-portal.com/testing-commissioning-current-transformer#2http://electrical-engineering-portal.com/testing-commissioning-current-transformer#2http://electrical-engineering-portal.com/testing-commissioning-current-transformer#2http://electrical-engineering-portal.com/testing-commissioning-current-transformer#3http://electrical-engineering-portal.com/testing-commissioning-current-transformer#3http://electrical-engineering-portal.com/testing-commissioning-current-transformer#3http://electrical-engineering-portal.com/testing-commissioning-current-transformer#31http://electrical-engineering-portal.com/testing-commissioning-current-transformer#31http://electrical-engineering-portal.com/testing-commissioning-current-transformer#32http://electrical-engineering-portal.com/testing-commissioning-current-transformer#32http://electrical-engineering-portal.com/testing-commissioning-current-transformer#33http://electrical-engineering-portal.com/testing-commissioning-current-transformer#33http://electrical-engineering-portal.com/testing-commissioning-current-transformer#34http://electrical-engineering-portal.com/testing-commissioning-current-transformer#34http://electrical-engineering-portal.com/testing-commissioning-current-transformer#35http://electrical-engineering-portal.com/testing-commissioning-current-transformer#35http://electrical-engineering-portal.com/testing-commissioning-current-transformer#36http://electrical-engineering-portal.com/testing-commissioning-current-transformer#36http://electrical-engineering-portal.com/testing-commissioning-current-transformer#37http://electrical-engineering-portal.com/testing-commissioning-current-transformer#37http://electrical-engineering-portal.com/testing-commissioning-current-transformer#38http://electrical-engineering-portal.com/testing-commissioning-current-transformer#38http://electrical-engineering-portal.com/testing-commissioning-current-transformer#39http://electrical-engineering-portal.com/testing-commissioning-current-transformer#39http://electrical-engineering-portal.com/testing-commissioning-current-transformer#310http://electrical-engineering-portal.com/testing-commissioning-current-transformer#310http://electrical-engineering-portal.com/testing-commissioning-current-transformer#310http://electrical-engineering-portal.com/testing-commissioning-current-transformer#4http://electrical-engineering-portal.com/testing-commissioning-current-transformer#4http://electrical-engineering-portal.com/testing-commissioning-current-transformer#4http://electrical-engineering-portal.com/how-to-connect-current-transformershttp://electrical-engineering-portal.com/how-to-connect-current-transformershttp://electrical-engineering-portal.com/how-to-connect-current-transformershttp://electrical-engineering-portal.com/how-to-connect-current-transformershttp://electrical-engineering-portal.com/testing-commissioning-current-transformer#4http://electrical-engineering-portal.com/testing-commissioning-current-transformer#310http://electrical-engineering-portal.com/testing-commissioning-current-transformer#39http://electrical-engineering-portal.com/testing-commissioning-current-transformer#38http://electrical-engineering-portal.com/testing-commissioning-current-transformer#37http://electrical-engineering-portal.com/testing-commissioning-current-transformer#36http://electrical-engineering-portal.com/testing-commissioning-current-transformer#35http://electrical-engineering-portal.com/testing-commissioning-current-transformer#34http://electrical-engineering-portal.com/testing-commissioning-current-transformer#33http://electrical-engineering-portal.com/testing-commissioning-current-transformer#32http://electrical-engineering-portal.com/testing-commissioning-current-transformer#31http://electrical-engineering-portal.com/testing-commissioning-current-transformer#3http://electrical-engineering-portal.com/testing-commissioning-current-transformer#2http://electrical-engineering-portal.com/testing-commissioning-current-transformer#1
  • 7/28/2019 Method of Statement CT's Testing

    2/7

    4. Verify that adequate clearances exist between primary and secondary circuit wiring.

    5. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method.

    6. Verify that all required grounding and shorting connection provided.

    7. Verify all shorting blocks are in correct position, either grounding or open as required.

    8. Verify single point grounding of each core done properly. Grounding point shall be nearer to the

    CT location. However grounding shall be at relay point in case of several CT secondaries

    connected together like differential protection.

    3.2. Insulation Resistance Test

    The vol tage shal l be appl ied betw een:

    1. Primary to secondary plus ground (covered during switchgear test).

    2. Secondary to primary plus ground.

    3. Secondary core to core.

    Test voltage limits mentioned in table below. The ambient temperature shall be noted down during test.

    Table Test Vol tage Limi ts

    Rated voltage Test voltage

    100-1000V AC/DC 1000V DC

    >1000 to 5000V 5000V DC

    3.3. Polarity Test

    Polarity test is to confirm the polarity marking on the CT primary and secondary and verify it is matchingwith drawing. More ever it is giving an idea, how to connect the secondaries to make the protection ( like

    directional, differential) and metering function properly.

    Isolate CT secondary from the load and make circuit connection as shown in Figure 1.

    Close and open the battery switch connected on the primary. Observe the pointer is moving +v e

    di rect ion, while closing and ve di rect ionwhile opening for correct polarity.

    Figure 1 - CT Polarity Test

  • 7/28/2019 Method of Statement CT's Testing

    3/7

    3.4. Secondary / Loop Resistance Test (optional test)

    Secondary resistance test is to verify the CT secondary winding resistance with specified one and no

    discontinuity in the winding. This value can be used in other calculations.

    Loop resistance to ensure load is connected properly and circuits not left open. The circuit connectionshall be made as shown Figure 2for secondary resistance. Measure the dcresistance value and record.

    The same shall be done for all taps and cores. These values are influenced by temperature, so ambient

    temperature must be recorded during this test. The circuit connection shall be made as shown Figure

    2for loop resistance.

    Measure the dc resistance including CT and load, phase by phase and values can be compared between

    them.

    L im i ts :

    The value must be with in specified on nameplate after the effect of temperature taken in to account. If

    not factory test results shall be taken as reference.

    Figure 2 - CT resistance / Loop Resistance Test

    Notes:

    Ohmmeter connection for CT resistance excluding burden.

    Ohmmeter connection for CT loop resistance including burden.

  • 7/28/2019 Method of Statement CT's Testing

    4/7

    3.5 Burden Test (optional test)

    Burden tes tis to ensure the connected burden to CT is with in the rated burden, identified on the

    nameplate.

    Injected the rated secondary current of the CT, from CT terminals towards load side by isolating the CT

    secondary with all connected load and observe the voltage drop across the injection points. The burdenVA can be calculated as

    Burden VA = Voltage drop x rated CT sec. Current.

    L im i ts :

    The calculated burden should be less than rates CT burden.

    Note:

    Ammeter selector switch should be at respective phase during test.

    High impedance relays shall be shorted during the test.

    3.6. Magnetization Curve Test (optional test)

    Magnetization Curve test is to confirm the magnetization characteristics of CT with nameplate

    specification.

    This test shall be conducted before ratio test and after secondary resistance and polarity test, since

    residual magnetism left in the core due to DC test (polarity, resistance), which leads additional error in

    ratio test. The meters used for this test shall be having true RMS measurement.

    The circuit connection shall be made as shown Figure 3. The primary should be open during test.

    Demagnet isat ion

    Before start the test demagnetise the core by Inject voltage on secondary terminals and increase up to

    where considerable increment in current with small voltage increment. Now start decreasing the voltage

    to zero, the rate at which increased.

    Magnet isat ion test

    Now increase the voltage and monitor the excitation current up to the CT reaching near to saturation

    point. Record the reading of voltage and current at several points. Plot the curve and evaluate the Vk andImg from the graph.

    L im i ts :

    Class X CT:

    The obtained Vk should be greater than specified one; mag current should be less than specified one.

  • 7/28/2019 Method of Statement CT's Testing

    5/7

    Protection class CT:

    The secondary limiting voltage can be calculated as follow:

    Vslv = Is * ALF (Rct + (VA/Is*Is)) Where:

    Is rated secondary current

    Rct CT secondary resistance

    VA rated CT burden

    ALF Accuracy limit factor

    The mag current (Img) drawn at Vslv can be obtained from graph. The following criteria should be

    satisfied.

    Img < accuracy class * ALF * Is

    Meter ing Class CT:

    Accuracy can be ensured as follow:

    Img at Vs (= 1.2 * VA / Is) should be less than (accuracy class * Is)

    And instrument security factor to be verified.

    Figure 3 - Magnetisation Test

    3.7. Turns ratio Tests (optional test)

    This test is to ensure the turns ratio of CT at all taps. The circuit connection shall be made as

    shownFigure 4. The primary current of minimum of 25% rated pr imary c urrentto be injected on

    primary side of CT with secondaries shorted and the secondary current can be measured and recorded

    for all cores.

  • 7/28/2019 Method of Statement CT's Testing

    6/7

    L im i ts :

    The obtained turns ratio should match with rated nameplate ratio.

    3.8. Primary Injection Test

    This test is to ensure theCT circuitsare properly connected with respected cores and there is no mix up

    in the circuit (phase identification).

    The circuit connections shall be made as shown in Figure 4. Single point grounding shall be verified for

    CT circuits, before starting this test. Inject 25% of rated primary current between one phase and earth

    with all connected burden. Measure secondary current at all points of CT circuits. It shall be done for

    other phases.

    Core ident i f icat ion:

    When one CT is having several cores used for different purposes. The cores can be identified during

    primary injection test by shorting the one of the core at CT terminal itself and check there isno current

    only at relevant load. The same can be verified for other cores.

    Inject 25% of rated primary current between phase to phase with all connected burden. Measure

    secondary current at all points of CT circuits. It shall be done for other phases.

    L im i ts :

    Secondary current should only be observed at respective phase and neutral leads during Phase

    to earth injection.

    Secondary current should only be observed at respective phases and no current on neutral

    during Phase to phase injection.

    Figure 4 - Primary injection / Ratio test

    http://electrical-engineering-portal.com/download-center/books-and-guides/electrical-engineering/current-transformers-selection-guidehttp://electrical-engineering-portal.com/download-center/books-and-guides/electrical-engineering/current-transformers-selection-guidehttp://electrical-engineering-portal.com/download-center/books-and-guides/electrical-engineering/current-transformers-selection-guidehttp://electrical-engineering-portal.com/download-center/books-and-guides/electrical-engineering/current-transformers-selection-guide
  • 7/28/2019 Method of Statement CT's Testing

    7/7

    3.9. High Voltage Test

    This test is included with sw i tchgear h igh vo l tage.

    Objective of HV test is to determine the equipment is in proper condition to put in service, after installation

    for which it was designed and to give some basis for predicting whether or not that a healthy condition will

    remain or if deterioration is underway which can result in abnormally short life.

    Test Instruments Required for HV Test

    Calibrated AC hi-pot test set for switchgear with leakage current indicator and overload protection.

    Calibrated DC hi-pot test set for cables with leakage current indicator and overload protection.

    3.10. Commissioning Test

    After commissioning, secondary current measurement shall be carried out in CT circuits. Phase anglecheck shall be done for correct direction.

    4. Applicable Standards

    IEC 60044-1:Instrument transformers current transformer.

    IEC 60694:common specifications for HV switchgear.