meygen tidal energy project phase 1a – progress update

33
MeyGen Tidal Energy Project Phase 1a – Progress Update All Energy 2016 Practical experience in tidal array developments 05 th May 2016 David Taaffe Project Manager

Upload: trinhduong

Post on 14-Feb-2017

221 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Tidal Energy Project

Phase 1a – Progress Update

All Energy 2016

Practical experience in tidal array developments

05th May 2016

David Taaffe Project Manager

Page 2: MeyGen Tidal Energy Project Phase 1a – Progress Update

Project Overview

Page 3: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen ProjectArtists Impression

Atlantis Resources: May 2016

Page 4: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Site Location

MeyGen: Inner Sound,

Pentland Firth, Scotland

Strategic location;

• Exceptionally fast currents;

• Sufficient water depth;

• Close connection to UK grid;

Atlantis Resources: May 2016

Page 5: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen ProjectInstallation, Grid & Consents Sequence

Demonstration tidal array Phase 1a 6 MW

Commercial tidal array Phase 1b 6 MW

Phase 1c & d 74 MW

Phase 2 312 MW

6MW

12MW

86 MW

398 MW

Consenting Phase 186MW

Consenting Phase 2312MW

33kV DNO14.9 MW

132kV Grid

Connected237MW

TBD Grid 141 MW

Cumulative MW

Installed

Grid Connection

TypeConsents

Atlantis Resources: May 2016

Page 6: MeyGen Tidal Energy Project Phase 1a – Progress Update

Installation Site Layout

Atlantis Resources: May 2016

Page 7: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Project Phase 1ASystem Diagram - 6MW Tidal Energy Array

7

1 x ARL + 3 x AHH 1.5MW TTG’s generating at 4.1kV

4No Subsea cables

4.1kV frequency converters (turbine control)

4.1kV frequency converters (grid connection compliance control)

4.1kV to 33kV transformers

33kV switchgear 33kW 14.9MW grid

connection

Atlantis Resources: May 2016

Page 8: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1ASupply Contract Structure

MeyGen(Project Company)

SHEPD(GRID CONNECTION)

NGET(Grid Compliances)

ANDRITZ(3 x TTG)

(Supply Only)

ATLANTIS(1 x TTG)

(Supply Only)

FISHERCable/TTG/GBS

(Installation)

JDRSUB-CABLES

(Supply)

GLOBAL ENERGYGBS

(Manufacture)ABB(ONSHORE WORKS)

EPC

O’Connor UtilitiesHDD

(Design/Execute)

JGCGBS Ballast

(Manufacture)

Robert Bird GroupGBS

(Design)

FIDIC

FIDIC

FIDIC

FIDIC

FID

ICFI

DIC

Gri

d A

gFI

DIC

FID

IC

Co

nsu

ltant

Atlantis Resources: May 2016

Page 9: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1AMajor Contracts

Grid

Subsea

cables

Directional

drilling

Grid Connection

Onshore Works

Offshore Installation

AHH Turbines

Atlantis Turbine

Turbine Support Structures

Submarine Cables

Directional Drilling

Page 10: MeyGen Tidal Energy Project Phase 1a – Progress Update

Progress to Date

Page 11: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1AProject Progress Highlights

September 2014

Financial closeis achieved for£51.3 millionfunding for6MW MeyGenPhase1A

January 2015ConstructionWorks commenceat the MeyGenOnshore Site tobuild access road

March 2015HDD Drilling Commences

&5800 Tonnes ofSteel deliveredto Scrabster forBallast Blocks

April 2015

First HDD bore

completed

July 2015HDD Drillingcompleted –four HDDbores totallength over2km

August 2015Manufacture of

11.5km of subsea cable completed

Sept 201511.5km of

Subsea Cable

Installed successfully

Oct 2015Environmental monitoring test

equipment successfully

deployed

Dec 2015Onshore building

steelwork erection

completed

Feb/Mar 2016Onshore building

floor slab pour completed

& electrical fit-out commences

April 2016SSE Grid

connection works ready for

commissioning

Atlantis Resources: May 2016

Page 12: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1A15MW Grid Connection – Project Status

1212

Existing 33kV Line Thurso to Laurel

33kV Line from Laurel to HastigrowConductor Upgrade

Hastigrow 33kV substation upgrades

COMPLETE

18km of 33kV cable installed

14.9MW 33kV connection at Ness of Quoys –Substation built and switchgear installed

Atlantis Resources: May 2016

Page 13: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1A15MW Grid Connection – SHEPD

• MeyGen Connection Agreement in place since 2010 – early investment crucial

• Classified as “Large Power Station” and required to meet Grid Code –electrical interface with Onshore Works Contract

• Dedicated room within building designed and built to house SHEPD substation – physical interface with Onshore Works Contract

Onshore Building, SHEPD Room – 33kV Switchgear Installed

17km of Onshore 33kV Onshore Cabling completed

Page 14: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1AOnshore Works – ABB

• Onshore Civil Works Completed

• SHEPD room completed and Handed Over for Grid Connection

• Electrical Fit out work commenced

• Building designed to minimise noise and visual impact

• Designed to reliably dissipate heat from electrical conversion equipment

Onshore Building – South and West Elevations

Atlantis Resources: May 2016

Page 15: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1AOnshore Works – ABB

Onshore Building – Power Conversion Units (PCU) Installed. The PCUs provide torque control to the turbines (Interface with both Turbine Contracts) and convert power to Grid Code compliant quality (Interface with Grid)

Onshore Building – Overhead Cable Management System

Atlantis Resources: May 2016

Page 16: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1AOnshore Works – ABB

Control Building – Installation of 33kVtransformers (left) and LVAC switch board(above)

Atlantis Resources: May 2016

Page 17: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1AHorizontal Directional Drilling - OCU

Horizontal Directional Drilling – 4 x 570m Bores completed (Interfaces with Cable Supply, Onshore Works and Offshore Works Contracts)

Atlantis Resources: May 2016

Page 18: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1ASubsea Cable Design and Manufacture - JDR

Cable Supply Contract –Completed Design andManufacture of 11.5km ofsubsea cable (Interfaces withTurbines, Offshore Works andOnshore Works)

Page 19: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1AOffshore Cable Installation - JFMS

Mobilisation of Offshore Construction Vessel (Siem Daya) at Hartlepool

Atlantis Resources: May 2016

Page 20: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1AOffshore Cable Installation - JFMS

Installation of 11.5km of Cable Offshore

• Offshore Cable Installation Works Completed

• Bespoke cable laying operation - specific neap tide selected and one 2.5 km cable installed every 12 hours

• Total operation at MeyGen Site completed in 2.5 days

• Interfaces with Cable supply Contract and HDD ContractAtlantis Resources: May 2016

Page 21: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1ACable Installation - JFMS

Subsea cable being pulled through HDD to Onshore Site

• Cables pulled through HDD bores with enough length to connect directly to building

• 24 hour operation co-ordinated with Offshore Lay

• Post-Installation cables tested from Onshore to confirm successful install

Atlantis Resources: May 2016

Page 22: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1ACable Installation - JFMS

22As- Built Cable Routes

Image of Subsea Cable on the seabed

Atlantis Resources: May 2016

Page 23: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1ATurbine Support Structure (TSS) Detailed Design- RBG

23

Detailed design of TSS completed

Tank Testing of TSS

Ballast Block Detailed Design

• Design Life of 25 Years

• Two different TSS designs – design interface with both turbine supply contracts

• Turbine and Substructure is one dynamic system

Page 24: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1ATurbine Support Structure (TSS) Ballast Blocks- JGC

24

• 16 of 24 Ballast Blocks completed

• Each Ballast Block weighs 200 Tonnes

• Each Substructure has 6 Ballast Blocks – total Ballast weight 1200 Tonnes

• Most cost effective design uses steel plates “as cast” and bolted together.

• Design life of 25 years required steel plates to be cladded to prevent water ingress. Ballast Blocks at JGC Fabrication Facility in

Janetstown, Thurso.

Page 25: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1ATurbine Support Structure Fabrication - GEG

• All fabricated steel forfour TSS has beenprocured and deliveredto Nigg

• Inner Sections of allfour TSS substantiallycompleted

• In the process ofassembling the outerlegs

• Interfaces with bothTurbine Suppliers forstructural stabs andcable managementsystems

TSS pylons for AHH Turbines attached to inner leg sections at NiggAtlantis Resources: May 2016

Page 26: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1ATurbine Support Structure Fabrication – GEG

TSS pylons for ARL Turbine attached to inner leg section at Nigg

Atlantis Resources: May 2016

Page 27: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1ATidal Turbine Generator Supply – ARL and AHH

1 X Atlantis AR1500 1.5MW Turbine 3 X Andritz Hydro Hammerfest 1.5MW HS1000 Mk1 TurbinesAtlantis Resources: May 2016

Page 28: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1ATurbine Technology Comparison– ARL and AHH

Area Atlantis - AR1500 Andritz - HS1000 MK1

Rotor Diameter 18m 18m

Rated Power 1.5MW 1.5MW

Inspection period (MTBO) 6.25 years 5 years

Blade Material Carbon Fibre Carbon Steel

Cut Out Velocity 5m/s 4.5m/s

Pitch System Collective Hydraulic Independent, Electrical

Gearbox 2 Stage 3 Stage

Generator Permanent Magnet Induction Machine

Yaw Mechanism Electrical Electrical

Connection Offered Wetmate Drymate

Turbine Controller (and Converter)

Onshore Onshore

Atlantis Resources: May 2016

Page 29: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1ATurbine System – Atlantis Resources

1.5MW AR1500 TTG – Nacelle AssemblyAtlantis Resources: May 2016

Page 30: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1ATurbine System – Andritz Hydro Hammerfest

1.5MW HS1000 MK1 TTG – Nacelle and Drive Train Assembly

Atlantis Resources: May 2016

Page 31: MeyGen Tidal Energy Project Phase 1a – Progress Update

Path to Completion

Page 32: MeyGen Tidal Energy Project Phase 1a – Progress Update

MeyGen Phase 1AFinal Steps to Project Completion

July 2016Turbine Final

Pre-deployment Assembly at Nigg

June 2016Energise Grid

Connection and Onshore Equipment

Ready for Export

Sept 2016First two Turbine

Installations completed

Nov 2016Final two Turbine

Installations completed

Feb 2017Commissioning

Completed

March 2017Project Completion

and commercial operation

commences

August 2016Installation of

TSS

Atlantis Resources: May 2016

Page 33: MeyGen Tidal Energy Project Phase 1a – Progress Update

May-16

Confidential and not for distribution 33

THANK YOU