mgr philosophy
TRANSCRIPT
-
7/31/2019 Mgr Philosophy
1/56
24 May 2012 PMI Revision 00 1
MGR SYSTEM AN OVERVIEW
A CHATTERJEE , SS/MGR
-
7/31/2019 Mgr Philosophy
2/56
24 May 2012 PMI Revision 00 2
-
7/31/2019 Mgr Philosophy
3/56
24 May 2012 PMI Revision 00 3
COAL AVAILABILITY FROM MINESDaily an average of 30,000 MT Coal is required for a
typical 2000 MW Station & for 3260 Station like VSTPP , itis around 52,000 MT/day with 0.66 Sp Coal.Each super Thermal Power Project is linked with aparticular coal mine to meet its coal requirement. Thisparticular Mine is called Linked Mine.
i) For VSTPP, The Linked Mine is Nigahi Mine of NCL.
ii) The present capacity is 11milion Ton/year till dategoing to be 15 Million Ton by 2012)
The required coal for any power station is allotted
through SLC (Short Term Linkage Committee) allocationon quarterly basis i.e for 3 months . This allocation isdecided in periodic Quarterly meeting held at Delhi inconsultation with NTPC,COAL INDIA, CEA ,RAILWAYS,
OTHER POWER SECTORS etc.
-
7/31/2019 Mgr Philosophy
4/56
24 May 2012 PMI Revision 00 4
Grade Useful Heat Value(UHV) (Kcal/Kg)
Corresponding Ash%+ Moisture % at(60% RH & 40O C)
Gross Calorific ValueGCV (Kcal/ Kg) (at 5%moisture level)
A Exceeding 6200 Not exceeding 19.5 Exceeding 6454
B Exceeding 5600 but notexceeding 6200
19.6 to 23.8 Exceeding 6049 butnot exceeding 6454
C Exceeding 4940 but notexceeding 5600
23.9 to 28.6 Exceeding 5597 butnot exceeding. 6049
D Exceeding 4200 but notexceeding 4940
28.7 to 34.0 Exceeding 5089 butnot Exceeding 5597
E Exceeding 3360 but not
exceeding 4200
34.1 to 40.0 Exceeding 4324 but
not exceeding 5089
F Exceeding 2400 but notexceeding 3360
40.1 to 47.0 Exceeding 3865 butnot exceeding. 4324
G Exceeding 1300 but notexceeding 2400
47.1 to 55.0 Exceeding 3113 butnot exceeding 3865
Grades of Coal
-
7/31/2019 Mgr Philosophy
5/56
24 May 2012 PMI Revision 00 5
Merry Go Round (MGR) system is a NTPC owned, full fledgedRailway system used for hauling Coal from Min end to Thermalpower station.
For transportation of coal from Mine end, Coal Rakes are moved inthe dedicated MGR Circuit of NTPC.
Each coal rake consists of Bottom open Broad Gauge wagons(BOBR) hauled by one/two locomotive. The Rake Size is differentfor different project --for VSTPP the Rake Size is 50 Wagons.
MGR circuit consists of Broad Gauge Track ( i.e 1676 mm gauge)
MGR Track is laid on PRC (Pre reinforced Concrete) Sleepers.
For changing of Rake movement , from one Track to another,
Motor operated Point machine are provided which are operatedfrom different Control stations of MGR Circuit.
Multi Aspect Colour Light Signalling (MACLS) system , with panelInterlocking is provided for the safety of the rake movement fromone station to other.
Railway retired Loco drivers are engaged on Contract basis tooperate MGR Rakes for coal transportation purpose,
-
7/31/2019 Mgr Philosophy
6/56
24 May 2012 PMI Revision 00 6
MGR SYSTEM CONSISTS OF MAINLY
1) MGR OPERATING SYSTEM.
2) MAINTENANCE OF MGR ROLLING STOCK.
3) MAINTENCE OF TRACK & SIGNALLINGSYSTEM.
4) COAL CORDINATION & COAL BILLINGACTIVITY.
-
7/31/2019 Mgr Philosophy
7/56
24 May 2012 7
MGR OPERATING SYSTEM
Rake loading & Sampling
Loading system consists of a high-speed load- out station
at the mine end called SILO. The capacity of the silos forthe NTPC project varies between 3000 -- 4000 MT.The loading operation of the coal Rake takes place while itis moving under the silo at a speed of 0.8 - 1 k.m. per hr. It
takes appx 1 Min/wagon for loading. The silos are cylindrical and fed by twin belt conveyorsfrom Mine end through a Coal Handling System. For accurate weighing of coal to each wagon, Pre weigh
Hoppers are provided which weighs coal of individualwagons before it is discharged to wagon. After loading sampling is carried out , through randomsamples collected from couple of loaded wagons for
quality analysis.
-
7/31/2019 Mgr Philosophy
8/56
24 May 2012 PMI Revision 00 8
-
7/31/2019 Mgr Philosophy
9/56
24 May 2012 PMI Revision 00 9
-
7/31/2019 Mgr Philosophy
10/56
24 May 2012 PMI Revision 00 10
After loading & Sampling is over Loaded Rake comes to T/H for
unloading at power house end. Track Hopper is normally of 200-250 m length . Total Number of
Track Hopper varies as per coal handling quantity (For VSTPP,it is 3 nos).
In each placement appx 14-15 wagons are placed forsimultaneous unloading at T/H.
Wagons are provided with bottom discharge hoppers fitted withpneumatically operated automatic door actuating mechanism.
After placing the wagons on the hopper, electrical pulse isgiven to the pneumatic device for opening the bottom doors.
Coal rushes down due to its own weight. When the track hopper is empty, it takes only 20 seconds for
unloading one wagon i.e. 60 Tons. After unloading operation, individual wagon doors are closed,
checked for Proper setting of wagon doors & sent forsubsequent loading.
This coal falls on a T table, over which a paddle feeder runs
-
7/31/2019 Mgr Philosophy
11/56
24 May 2012 PMI Revision 00 11
-
7/31/2019 Mgr Philosophy
12/56
24 May 2012 PMI Revision 00 12
1) TOTAL MGR CIRCUIT IS DIVIDED IN 3 CONTROLSTATIONS.
2) MOVEMENT OF RAKE/LOCOMOTIVE , FROM ONESTATION TO ANOTHER , AFTER GETTING LINE
CLEARANCE THROUGH PRIVATE NUMBEREXCHANGE & RECEIVING SLOT.3) ALL MOVEMENTS DONE WITH SIGNALS ONLY
WHEREEVER PROVIDED.4) STATION WORKING RULE FRAMMED & DISPALYED
AT ALL CONTROL STATIONS.5) ABSOLUTE BLOCK WORKING FOLLOWED DURINGRAILWAY MOVEMENT THROUGH DUDHICHUACIRCUIT ,WHERE ONLY ONE PARTY OPERATES AT ATIME
-
7/31/2019 Mgr Philosophy
13/56
24 May 2012 PMI Revision 00 13
1) STRICT ADHERENCE OF STAION WORKING RULE &MOVEMENT THROUGH SIGNALS .
2) REGULAR BRAKE POWER TESTING OF RUNNINGRAKES , AT LEAST ONCE IN A WEEK.
3) SIGNAL OVERSHOOT PROTECTION SYSTEMPERIODICALLY TESTED.4) MONTHLY SAFETY AUDIT THROUGH VSTPP
SFAETY TEAM & TECHICAL AUDIT THROUGHCORPORATE CENTRE TEAM.
5) YEARLY SAFETY AUDIT IS PLANNED THROUGHRAILWAY EXPERTS.6) REGULAR FOOT PLATE INSPECTION BY
DEPARTMENTAL HEAD & OTHER SENIOR OFFICIALS
-
7/31/2019 Mgr Philosophy
14/56
24 May 2012 PMI Revision 00 14
WDM2A WDS6 WDG-3A Number 2 4 4
HP 2400 1200 3100
Speed 120 60 100
Tank Cap 5000 Lt 4000 6000
Weight 120 MT 126 MT 112MT
Cost 7Cr 6 Cr 8 Cr
-
7/31/2019 Mgr Philosophy
15/56
24 May 2012 PMI Revision 00 15
Type of Wagon BSCL CIMMCO TEXMACO
No of Wagons 43 67 39 +119
Total = 268 Nos
Year of Comg 88-89 90-91 00-01 & 05-06 DOM System Single Link Single Link Double link
Axle Load (Ton) 22.9 22.9 22.9
Length (M) 13.41 13.41 13.41
Carrying Capacity 60 MT 60 MT 60 MT Cost/Wagon Appx 25 Lacs
-
7/31/2019 Mgr Philosophy
16/56
24 May 2012 PMI Revision 00 16
LOCO MAINTENANCE
Light Schedule: T1,T2,M1,M2 includingtrouble shooting in MGR Work Shop.
Heavy Schedule: M4 &M6 including
Breakdown Maintenance in MGR WorkShop.
Major Schedule: M 24 & M 48 in Railway
Diesel Shed( like Patratu , E.C.Rly) POH:M 96 at Railway Workshops Golden
Rock(Trichy)
-
7/31/2019 Mgr Philosophy
17/56
24 May 2012 PMI Revision 00 17
DETAILS OF WAGON
MAINTENANCE Monthly Maintenance of 4 Rakes (50Wagons)
Maintenance of DOM Systems including
overhauling of Spool Valves.
Maintenance of Brake Systems includingoverhauling Distriubutor Valves.
Wheel Changing. Overhauling/Reclamation of Axle Bearings.
Reclamation of Wagon Doors.
-
7/31/2019 Mgr Philosophy
18/56
24 May 2012 PMI Revision 00 18
SIGNAL & TELECOM SYSTEM OF MGR Vulnerable areas of the track are electrically circuited
which are activated by the passage of trains forensuring maximum safety in train operation
Inter slotting system between the Cabins ensuresinvolvement of two Cabins for receiving & dispatchingof trains
Apart from the Signals, communication channelbetween the Control Rooms & Loco Driver isestablished thro Wireless & Walkie Talkie sets.
Signaling system with wireless communication is fullyoperational for safe train movement.
Multi-aspect Color light signaling with motorizedoperation of Points
System is operable from a interlocked Control Panelwith mimic diagrams located in Cabins.
Real time movement of trains are monitored thro Panel.
-
7/31/2019 Mgr Philosophy
19/56
24 May 2012 PMI Revision 00 19
ROUTINE S&T MNTCE Maintenance of Secondary cells numbering 300 Nos
Checking & adjustment of Point machines 33 Nos forcorrect setting in Normal & Reverse positions
Maintenance of 50 Nos Track Circuits
Adjustment of Voltage & correct focusing of Signals
Checking of interlocking circuits for propercorrespondence between Panel & Site,
Visual inspection of Relays
Maintenance of Wireless and Walkie Talkie sets
Maintenance of 2 Nos DG sets (for Standby Powersupply)
-
7/31/2019 Mgr Philosophy
20/56
24 May 2012 PMI Revision 00 20
SALIENT FEATURES OF MGR TRACK
Length of main MGR coal circuit 19.6 Km.
Total 52 Track Kilometer (including DCH & Non-coal track)
is maintained by MGR/VSTPP
Almost 40% i.e.7.8 Km of main MGR are in curvature
Steepest Gradient 1 in 125 Down in DCH Circuit.
52 Kg rail, short welded rail panel, T-12 rails for main line
and T-18 for yard lines in use.
No of Points & Crossings : 1 in 8 48 nos
1 in 12 03 nos Sleeper density M+7 in main line and M+4 in yard lines. PRC sleepers laid throughout main MGR track Total number of bridges & culverts - 34 Longest being 78 M steel girder bridge at DCH Track.
-
7/31/2019 Mgr Philosophy
21/56
24 May 2012 PMI Revision 00 21
-
7/31/2019 Mgr Philosophy
22/56
24 May 2012 PMI Revision 00 22
ROUTINE TRACK MNTCE
Daily patrolling of the entire track on foot by Key man. Packing of track at locations where slackness found.
Through packing of entire track once in a year.
Lifting of track at required locations.
Overhauling of track. Replacement of worn out rails and sleepers.
Maintenance of Hand lever operated points .
Re-alignment of curvature where distorted.
Lubrication of fish-plated joints yearly.
Greasing of gauge face of curvature track.
Removing spillage coal from track in W/Shop areas .
Drain cleaning & de-weeding along the track.
-
7/31/2019 Mgr Philosophy
23/56
24 May 2012 PMI Revision 00 23
MGR VSTPP AT A GLANCE1) TOTAL TRACK LENGTH MAINTAINED(INCLUDING BASKET MINE) =45 Km.
2) MAJOR BRIDGES IN CIRCUIT 2 STEEL GARDER(13 M)- NGH CIRCUIT-- 1 STEEL GARDER(26 M) DCH CIRCUIT-- 1 STEEL GARDER(72 M) DCH CIRCUIT
- 1 RCC GARDER BRIDGE(15 M) NGH CIRCUIT3) STEEPEST GRADIENT 1 IN 125 (IN DCH CIRCUIT)4) LOCOMOTIVES-- WDS6 =4 Nos. WDM2 =2 Nos WDG 3A= 04 NOS(1 ON LOAN BASIS FROM SIPAT)
TOTAL LOCO = 105) WAGONS BURN STANDARD =43 Nos
CIMMCO =67 Nos.
TEXMACO =158TOTALWAGONS =268
6) TOTAL NUMBER OF MOTORISED POINTS IN CIRCUIT = 33 NOS7) TOTAL NUMBER OF SIGNALS IN CIRCUIT = 21 NOS8) RAKE SIZE 50 WAGONS
-
7/31/2019 Mgr Philosophy
24/56
24 May 2012 PMI Revision 00 24
-
7/31/2019 Mgr Philosophy
25/56
24 May 2012 PMI Revision 00 25
MGR PERFORMANCE(07-08) AT A GLANCE
MAXIMUM COAL TRANSPORTED
1) IN A DAY = 70,138.94 MT(31/03/08)
2) IN A MONTH = 17.21 Lac MT(Mar- 08)
3) IN A YEAR = 173.91 Lac MT
(2007-08)
-
7/31/2019 Mgr Philosophy
26/56
24 May 2012 PMI Revision 00 26
COAL SUPPLY TO VSTPP DURING
THE YEAR 2007-08
Total Linkage 176.58 Lac MT
Total Receipt 173.91 Lac MT Total Consumption 171.43 Lac MT
-
7/31/2019 Mgr Philosophy
27/56
24 May 2012 PMI Revision 00 27
-
7/31/2019 Mgr Philosophy
28/56
24 May 2012 28
Coal handling system is the arrangement for transferring ofcoal from coal-wagons to coal-bunker or coal stock yard.
It also provide arrangement for separation of material
impurities, crushing of coals, Coal sampling etc.
In the coal handling system of NTPC stations, three coal paths are
normally available
Path A - direct conveying of coal from track hopper to boiler bunkers.
Path B - from track hopper to stockyardPath C - from stockyard to boiler bunkers.
The storage facilities at the stockyards have been provided only for
crushed coal.
-
7/31/2019 Mgr Philosophy
29/56
24 May 2012 PMI Revision 00 29
-
7/31/2019 Mgr Philosophy
30/56
24 May 2012 PMI Revision 00 30
The coal handling system is designed to provide100% standby for all the equipment and conveyors.
The capacity of the coal handling system for super
thermal stations varies from 1200 to 2000 t/h,normally, for a stage of 1000 MW,
-
7/31/2019 Mgr Philosophy
31/56
24 May 2012 PMI Revision 00 31
plough feeder/ paddle feeder vibrating screen
crushers,
Conveyor belt,
Idlers, Pulleys,
Drive Unit,
Take-ups,
Skirt board, Scrapper,
Stacker-cum-reclaimer,
Magnetic separators,
Motorized tripper.
-
7/31/2019 Mgr Philosophy
32/56
24 May 2012 PMI Revision 00 32
Below track hopper paddle feeder arrangement isprovided to unload coal to coal conveyors.
The 200mm coal as received at the track hopper isfed to the crusher house through 1A & 1Bconveyors.
-
7/31/2019 Mgr Philosophy
33/56
24 May 2012 PMI Revision 00 33
Vibrating Screen :The function of the vibratingscreen is: -
To send the coal having size of less than 20mm to
belt feeder through the bypass chute bypassing thecrusher and
To send the coal of more than 20mm size to thecrusher.
-
7/31/2019 Mgr Philosophy
34/56
24 May 2012 PMI Revision 00 34
CRUSHERS
To crush the coal from 200mmto 20mm size received
from vibrating screenCrusher hammer are made of MAGNEESE STEEL .
Hammer row -4(stage 1)
(a)Row-1 & 2 =18 hammer each
(b)Row-3&4=20 hammers each
No of hammer in each Crusher-
stage-1 = 76 hammers
stage-2 = 92 hammers
Weight of each hammer=18.5kg
Crushing motor rating -740kw/3.3kv
Life of hammer =4 lac MT of coal
Normal capacity=600 tons/hr
-
7/31/2019 Mgr Philosophy
35/56
24 May 2012 PMI Revision 00 35
Normally these crushers have a capacity of around 600
tons per hour.
-
7/31/2019 Mgr Philosophy
36/56
24 May 2012 PMI Revision 00 36
CONVEYOR BELTS
Made of diff. Layers or piles of fabric duck with rubber
protected by a rubber cover on both sides & edges.Fabric duck are designed to withstand tension created in
carrying the load .
Nylon rubber cover protect the fabric duck.
Material =fire resistant grade.
Belt Width=1600 mm.
Strength= 1000/1250 kN.
Belt speed=3.2-3 m/s.Belt length=20km.
-
7/31/2019 Mgr Philosophy
37/56
24 May 2012 PMI Revision 00 37
IDLERS
Idlers consists essentially of rolls made out of seamlesssteel tubes enclosed fully at each end fitted with
stationary shaft, antifriction bearing and laybrith sealing.
TYPES
TROUGHING IDLERS- shape the belt to support a
moving load without spillage or damage to the belt.
IMPACT IDLERS - absorb the shock of falling material
at loading and transfer points to protect belt from damage
-
7/31/2019 Mgr Philosophy
38/56
24 May 2012 PMI Revision 00 38
POSITIVE ACTION TROUGHING TRAINERS
automatically maintain troughing side alignment inone-way conveyors. A center pivot frame and offset
neutral guide rolls provide the troughing action.
RETURN IDLERS
support the empty belt during the return run.
POSITIVE ACTION RETURN TRAINERS automatically maintain return belt alignment on one-way
conveyors.
-
7/31/2019 Mgr Philosophy
39/56
24 May 2012 PMI Revision 00 39
PULLEYS
Made of mild steel.
Rubber coating is used to increase friction
factor between belt & pulley (rubber lagging
Shell dia-500mm.
Shaft dia-1400mm.
Pulley length-1800mm.
Shaft length-2350mm(bearing centre to
centre)
-
7/31/2019 Mgr Philosophy
40/56
24 May 2012 PMI Revision 00 40
DRIVE UNIT
Motors coupled to reduction gear with the help
of flexible/fluid coupling on the high speed shaft of theGear box
Flexible coupling on the input side
TAKE UPSTake up pulley to facilitates
Necessary tension for the drive to operate the belt
Sag at a point where requires horse power will be
at a minimum and load will move with least
disturbance over idlers
-
7/31/2019 Mgr Philosophy
41/56
24 May 2012 PMI Revision 00 41
SKIRT BOARD
Used with chutes at trail end.
Guides material centrally on the belt while loading
until it has settle down on the belt
SCRAPPERS
Placed at discharge pulley in order to clean the
carrying side of belt.It avoids the wear of return idlers due to build up
material.
-
7/31/2019 Mgr Philosophy
42/56
24 May 2012 PMI Revision 00 42
Pull Chord
Belt Sway
Zero Speed
Chute block
-
7/31/2019 Mgr Philosophy
43/56
24 May 2012 PMI Revision 00 43
This is used for stacking and reclaiming the coal fromstock yard. Generally two stacker claimers have beenprovided at each of the NTPC's projects. Their normalcapacity is 200 tons per hour and maximum design
capacity is 450 tons per hour. The stacker reclaimer generally consists of (a) bucket
wheel or digging wheel (b) boom conveyor. While thebelt conveyor carrying the coal for the stock yard is in thesame direction but the direction of the boom conveyor
with respect to stacking and reclaiming is opposite. Digging Wheel The digging wheel is use for cutting and
lifting the coal from the stock yard to the belt used fortransfering coal from the yard. The above transfer takesplace in case of reclaiming the coal only.
-
7/31/2019 Mgr Philosophy
44/56
24 May 2012 PMI Revision 00 44Stacker Reclaimer
-
7/31/2019 Mgr Philosophy
45/56
24 May 2012 PMI Revision 00 45
During stocking operation, the coal from the crusherhouse is diverted towards the stockyard conveyor at atransfer point TP2/ TP3. The above conveyor dischargescoal to the boom conveyor through a discharge chute.The boom conveyor, running in the forward direction,
creates coal stacks. During reclaiming, coal from the stock yard falls on the
boom conveyor with the help of the bucket wheel and theboom conveyor, during this period, rotates in backwarddirection. The coal from central chute falls on the
conveyor belts used for transferring the coal from thestock yard. By this way, the coal moves on theunderground conveyor belts connected to the main belts.
A 6.6 KV motor is used for running the stacker-cum-reclaimer and has a cable reeling drum on which flexiblecable is wrapped.
-
7/31/2019 Mgr Philosophy
46/56
24 May 2012 PMI Revision 00 46
-
7/31/2019 Mgr Philosophy
47/56
24 May 2012 PMI Revision 00 47
Coal to/from stock yard
Generally 2nos
Capacity ---200T/hrMaximum---400T/hr
Bucket wheel
Boom conveyor
-
7/31/2019 Mgr Philosophy
48/56
24 May 2012 PMI Revision 00 48
RECLAIMER IN OPERATIONSTACKER IN OPERATION
Bucket wheel
-
7/31/2019 Mgr Philosophy
49/56
24 May 2012 PMI Revision 00 49
MAGNETIC SEPARATOR
Any ferrous material onthe conveyor will be liftedfrom the moving conveyor.
No Tripping involved.
MS is interlocked withConveyor start up.
When ferrous Metal is
picked up, the MS ismoved from the Conveyor,de-magnatised and themetal piece is removed.
METAL DETECTORAny Metal with an area
of 100 Sq Cm will be
detected.Conveyor is trippedafter detection.
MD is not having
interlock with start up.A sandbag is droppednear the Metal piecefor easy location
-
7/31/2019 Mgr Philosophy
50/56
24 May 2012 50
TRIPPERS
To stack material at
desired bunker
Provided with wheels which moves on rails
parallel to conveyor.
Three types
motorized tripper
Belt propelled manually operated tripper
Winch driven tripper
-
7/31/2019 Mgr Philosophy
51/56
24 May 2012 PMI Revision 00 51
WEATHERING OF COAL
WHEN COAL IS EXPOSED TO ATMOSPHERE - IT
REACTS WITH OXYGEN - PRODUCTION OF
HEAT - RISE IN TEMPERATURE - OXIDATION
REACTION IS ACCELERATED - NUMBER OFCHANGES IN PHYSICAL AND CHEMICAL
PROPERTIES OF COAL TAKE PLACE - IT IS
CALLED WEATHERING OF COAL.
IMPORTANT FACTORS FOR
-
7/31/2019 Mgr Philosophy
52/56
24 May 2012 PMI Revision 00 52
IMPORTANT FACTORS FOR
STORAGE OF COAL
RANK OF COAL
SURFACE AREA
VENTILLATION
COMPACTION
AGE OF COAL
SIZE AND HEIGHT OF STOCK PILES
% LOSS I N CVSI ZE OF COAL
( MM) 1 YEAR 2 YEAR50 75 O. 11 0. 24
12 03 0. 5 1. 0
0. 3 0. 2 1. 0 2. 1
-
7/31/2019 Mgr Philosophy
53/56
24 May 2012 PMI Revision 00 53
PREDICTION OF SPONTANEOUS
COMBUSTION
B-M LIABILITY INDEX:
= 21.48M+ 0.98A- 0.62M
2
-0.58MA+ 0.08A
2
+ 10.2WHERE, M=% MOISTURE(AIR DRIED BASIS)
A=% ASH(AIR BASIS)
COALS HAVING B-M INDEX > 80 ARE HIGHLY
PRONE TO AUTO-OXIDATION.
-
7/31/2019 Mgr Philosophy
54/56
24 May 2012 PMI Revision 00 54
MANAGEMENT OF COAL STOCKYARD
Proper coal-air interaction to avoid auto- oxidation and
spontaneous combustion.
Close monitoring during march-june.
Design should ensure that for maximum duration of the year, air
strikes the width of the stockpile and not the length.
Freshly mined coals should be stacked and old coal should be used.
Freshly mined coals should not be stacked over old coal.
Stacking of coal layer by layer, with compaction of each layer.
-
7/31/2019 Mgr Philosophy
55/56
24 May 2012 PMI Revision 00 55
MANAGEMENT OF COAL STOCKYARD (CONTD.)
Stacking in trapezoidal shape, not in conical shape.Height of stockpile not more than 9-10m (indian coal).
Lumps and fines should be stacked together and compacted.
Before stacking coal should be visibly wet.
Segregation of stockpiles into various segments and relevent records
of period of stacking, quality of coal (cv) should be maintained.
Compaction of finer particles over the bigger particles.
-
7/31/2019 Mgr Philosophy
56/56