mgr philosophy

Upload: sam

Post on 05-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Mgr Philosophy

    1/56

    24 May 2012 PMI Revision 00 1

    MGR SYSTEM AN OVERVIEW

    A CHATTERJEE , SS/MGR

  • 7/31/2019 Mgr Philosophy

    2/56

    24 May 2012 PMI Revision 00 2

  • 7/31/2019 Mgr Philosophy

    3/56

    24 May 2012 PMI Revision 00 3

    COAL AVAILABILITY FROM MINESDaily an average of 30,000 MT Coal is required for a

    typical 2000 MW Station & for 3260 Station like VSTPP , itis around 52,000 MT/day with 0.66 Sp Coal.Each super Thermal Power Project is linked with aparticular coal mine to meet its coal requirement. Thisparticular Mine is called Linked Mine.

    i) For VSTPP, The Linked Mine is Nigahi Mine of NCL.

    ii) The present capacity is 11milion Ton/year till dategoing to be 15 Million Ton by 2012)

    The required coal for any power station is allotted

    through SLC (Short Term Linkage Committee) allocationon quarterly basis i.e for 3 months . This allocation isdecided in periodic Quarterly meeting held at Delhi inconsultation with NTPC,COAL INDIA, CEA ,RAILWAYS,

    OTHER POWER SECTORS etc.

  • 7/31/2019 Mgr Philosophy

    4/56

    24 May 2012 PMI Revision 00 4

    Grade Useful Heat Value(UHV) (Kcal/Kg)

    Corresponding Ash%+ Moisture % at(60% RH & 40O C)

    Gross Calorific ValueGCV (Kcal/ Kg) (at 5%moisture level)

    A Exceeding 6200 Not exceeding 19.5 Exceeding 6454

    B Exceeding 5600 but notexceeding 6200

    19.6 to 23.8 Exceeding 6049 butnot exceeding 6454

    C Exceeding 4940 but notexceeding 5600

    23.9 to 28.6 Exceeding 5597 butnot exceeding. 6049

    D Exceeding 4200 but notexceeding 4940

    28.7 to 34.0 Exceeding 5089 butnot Exceeding 5597

    E Exceeding 3360 but not

    exceeding 4200

    34.1 to 40.0 Exceeding 4324 but

    not exceeding 5089

    F Exceeding 2400 but notexceeding 3360

    40.1 to 47.0 Exceeding 3865 butnot exceeding. 4324

    G Exceeding 1300 but notexceeding 2400

    47.1 to 55.0 Exceeding 3113 butnot exceeding 3865

    Grades of Coal

  • 7/31/2019 Mgr Philosophy

    5/56

    24 May 2012 PMI Revision 00 5

    Merry Go Round (MGR) system is a NTPC owned, full fledgedRailway system used for hauling Coal from Min end to Thermalpower station.

    For transportation of coal from Mine end, Coal Rakes are moved inthe dedicated MGR Circuit of NTPC.

    Each coal rake consists of Bottom open Broad Gauge wagons(BOBR) hauled by one/two locomotive. The Rake Size is differentfor different project --for VSTPP the Rake Size is 50 Wagons.

    MGR circuit consists of Broad Gauge Track ( i.e 1676 mm gauge)

    MGR Track is laid on PRC (Pre reinforced Concrete) Sleepers.

    For changing of Rake movement , from one Track to another,

    Motor operated Point machine are provided which are operatedfrom different Control stations of MGR Circuit.

    Multi Aspect Colour Light Signalling (MACLS) system , with panelInterlocking is provided for the safety of the rake movement fromone station to other.

    Railway retired Loco drivers are engaged on Contract basis tooperate MGR Rakes for coal transportation purpose,

  • 7/31/2019 Mgr Philosophy

    6/56

    24 May 2012 PMI Revision 00 6

    MGR SYSTEM CONSISTS OF MAINLY

    1) MGR OPERATING SYSTEM.

    2) MAINTENANCE OF MGR ROLLING STOCK.

    3) MAINTENCE OF TRACK & SIGNALLINGSYSTEM.

    4) COAL CORDINATION & COAL BILLINGACTIVITY.

  • 7/31/2019 Mgr Philosophy

    7/56

    24 May 2012 7

    MGR OPERATING SYSTEM

    Rake loading & Sampling

    Loading system consists of a high-speed load- out station

    at the mine end called SILO. The capacity of the silos forthe NTPC project varies between 3000 -- 4000 MT.The loading operation of the coal Rake takes place while itis moving under the silo at a speed of 0.8 - 1 k.m. per hr. It

    takes appx 1 Min/wagon for loading. The silos are cylindrical and fed by twin belt conveyorsfrom Mine end through a Coal Handling System. For accurate weighing of coal to each wagon, Pre weigh

    Hoppers are provided which weighs coal of individualwagons before it is discharged to wagon. After loading sampling is carried out , through randomsamples collected from couple of loaded wagons for

    quality analysis.

  • 7/31/2019 Mgr Philosophy

    8/56

    24 May 2012 PMI Revision 00 8

  • 7/31/2019 Mgr Philosophy

    9/56

    24 May 2012 PMI Revision 00 9

  • 7/31/2019 Mgr Philosophy

    10/56

    24 May 2012 PMI Revision 00 10

    After loading & Sampling is over Loaded Rake comes to T/H for

    unloading at power house end. Track Hopper is normally of 200-250 m length . Total Number of

    Track Hopper varies as per coal handling quantity (For VSTPP,it is 3 nos).

    In each placement appx 14-15 wagons are placed forsimultaneous unloading at T/H.

    Wagons are provided with bottom discharge hoppers fitted withpneumatically operated automatic door actuating mechanism.

    After placing the wagons on the hopper, electrical pulse isgiven to the pneumatic device for opening the bottom doors.

    Coal rushes down due to its own weight. When the track hopper is empty, it takes only 20 seconds for

    unloading one wagon i.e. 60 Tons. After unloading operation, individual wagon doors are closed,

    checked for Proper setting of wagon doors & sent forsubsequent loading.

    This coal falls on a T table, over which a paddle feeder runs

  • 7/31/2019 Mgr Philosophy

    11/56

    24 May 2012 PMI Revision 00 11

  • 7/31/2019 Mgr Philosophy

    12/56

    24 May 2012 PMI Revision 00 12

    1) TOTAL MGR CIRCUIT IS DIVIDED IN 3 CONTROLSTATIONS.

    2) MOVEMENT OF RAKE/LOCOMOTIVE , FROM ONESTATION TO ANOTHER , AFTER GETTING LINE

    CLEARANCE THROUGH PRIVATE NUMBEREXCHANGE & RECEIVING SLOT.3) ALL MOVEMENTS DONE WITH SIGNALS ONLY

    WHEREEVER PROVIDED.4) STATION WORKING RULE FRAMMED & DISPALYED

    AT ALL CONTROL STATIONS.5) ABSOLUTE BLOCK WORKING FOLLOWED DURINGRAILWAY MOVEMENT THROUGH DUDHICHUACIRCUIT ,WHERE ONLY ONE PARTY OPERATES AT ATIME

  • 7/31/2019 Mgr Philosophy

    13/56

    24 May 2012 PMI Revision 00 13

    1) STRICT ADHERENCE OF STAION WORKING RULE &MOVEMENT THROUGH SIGNALS .

    2) REGULAR BRAKE POWER TESTING OF RUNNINGRAKES , AT LEAST ONCE IN A WEEK.

    3) SIGNAL OVERSHOOT PROTECTION SYSTEMPERIODICALLY TESTED.4) MONTHLY SAFETY AUDIT THROUGH VSTPP

    SFAETY TEAM & TECHICAL AUDIT THROUGHCORPORATE CENTRE TEAM.

    5) YEARLY SAFETY AUDIT IS PLANNED THROUGHRAILWAY EXPERTS.6) REGULAR FOOT PLATE INSPECTION BY

    DEPARTMENTAL HEAD & OTHER SENIOR OFFICIALS

  • 7/31/2019 Mgr Philosophy

    14/56

    24 May 2012 PMI Revision 00 14

    WDM2A WDS6 WDG-3A Number 2 4 4

    HP 2400 1200 3100

    Speed 120 60 100

    Tank Cap 5000 Lt 4000 6000

    Weight 120 MT 126 MT 112MT

    Cost 7Cr 6 Cr 8 Cr

  • 7/31/2019 Mgr Philosophy

    15/56

    24 May 2012 PMI Revision 00 15

    Type of Wagon BSCL CIMMCO TEXMACO

    No of Wagons 43 67 39 +119

    Total = 268 Nos

    Year of Comg 88-89 90-91 00-01 & 05-06 DOM System Single Link Single Link Double link

    Axle Load (Ton) 22.9 22.9 22.9

    Length (M) 13.41 13.41 13.41

    Carrying Capacity 60 MT 60 MT 60 MT Cost/Wagon Appx 25 Lacs

  • 7/31/2019 Mgr Philosophy

    16/56

    24 May 2012 PMI Revision 00 16

    LOCO MAINTENANCE

    Light Schedule: T1,T2,M1,M2 includingtrouble shooting in MGR Work Shop.

    Heavy Schedule: M4 &M6 including

    Breakdown Maintenance in MGR WorkShop.

    Major Schedule: M 24 & M 48 in Railway

    Diesel Shed( like Patratu , E.C.Rly) POH:M 96 at Railway Workshops Golden

    Rock(Trichy)

  • 7/31/2019 Mgr Philosophy

    17/56

    24 May 2012 PMI Revision 00 17

    DETAILS OF WAGON

    MAINTENANCE Monthly Maintenance of 4 Rakes (50Wagons)

    Maintenance of DOM Systems including

    overhauling of Spool Valves.

    Maintenance of Brake Systems includingoverhauling Distriubutor Valves.

    Wheel Changing. Overhauling/Reclamation of Axle Bearings.

    Reclamation of Wagon Doors.

  • 7/31/2019 Mgr Philosophy

    18/56

    24 May 2012 PMI Revision 00 18

    SIGNAL & TELECOM SYSTEM OF MGR Vulnerable areas of the track are electrically circuited

    which are activated by the passage of trains forensuring maximum safety in train operation

    Inter slotting system between the Cabins ensuresinvolvement of two Cabins for receiving & dispatchingof trains

    Apart from the Signals, communication channelbetween the Control Rooms & Loco Driver isestablished thro Wireless & Walkie Talkie sets.

    Signaling system with wireless communication is fullyoperational for safe train movement.

    Multi-aspect Color light signaling with motorizedoperation of Points

    System is operable from a interlocked Control Panelwith mimic diagrams located in Cabins.

    Real time movement of trains are monitored thro Panel.

  • 7/31/2019 Mgr Philosophy

    19/56

    24 May 2012 PMI Revision 00 19

    ROUTINE S&T MNTCE Maintenance of Secondary cells numbering 300 Nos

    Checking & adjustment of Point machines 33 Nos forcorrect setting in Normal & Reverse positions

    Maintenance of 50 Nos Track Circuits

    Adjustment of Voltage & correct focusing of Signals

    Checking of interlocking circuits for propercorrespondence between Panel & Site,

    Visual inspection of Relays

    Maintenance of Wireless and Walkie Talkie sets

    Maintenance of 2 Nos DG sets (for Standby Powersupply)

  • 7/31/2019 Mgr Philosophy

    20/56

    24 May 2012 PMI Revision 00 20

    SALIENT FEATURES OF MGR TRACK

    Length of main MGR coal circuit 19.6 Km.

    Total 52 Track Kilometer (including DCH & Non-coal track)

    is maintained by MGR/VSTPP

    Almost 40% i.e.7.8 Km of main MGR are in curvature

    Steepest Gradient 1 in 125 Down in DCH Circuit.

    52 Kg rail, short welded rail panel, T-12 rails for main line

    and T-18 for yard lines in use.

    No of Points & Crossings : 1 in 8 48 nos

    1 in 12 03 nos Sleeper density M+7 in main line and M+4 in yard lines. PRC sleepers laid throughout main MGR track Total number of bridges & culverts - 34 Longest being 78 M steel girder bridge at DCH Track.

  • 7/31/2019 Mgr Philosophy

    21/56

    24 May 2012 PMI Revision 00 21

  • 7/31/2019 Mgr Philosophy

    22/56

    24 May 2012 PMI Revision 00 22

    ROUTINE TRACK MNTCE

    Daily patrolling of the entire track on foot by Key man. Packing of track at locations where slackness found.

    Through packing of entire track once in a year.

    Lifting of track at required locations.

    Overhauling of track. Replacement of worn out rails and sleepers.

    Maintenance of Hand lever operated points .

    Re-alignment of curvature where distorted.

    Lubrication of fish-plated joints yearly.

    Greasing of gauge face of curvature track.

    Removing spillage coal from track in W/Shop areas .

    Drain cleaning & de-weeding along the track.

  • 7/31/2019 Mgr Philosophy

    23/56

    24 May 2012 PMI Revision 00 23

    MGR VSTPP AT A GLANCE1) TOTAL TRACK LENGTH MAINTAINED(INCLUDING BASKET MINE) =45 Km.

    2) MAJOR BRIDGES IN CIRCUIT 2 STEEL GARDER(13 M)- NGH CIRCUIT-- 1 STEEL GARDER(26 M) DCH CIRCUIT-- 1 STEEL GARDER(72 M) DCH CIRCUIT

    - 1 RCC GARDER BRIDGE(15 M) NGH CIRCUIT3) STEEPEST GRADIENT 1 IN 125 (IN DCH CIRCUIT)4) LOCOMOTIVES-- WDS6 =4 Nos. WDM2 =2 Nos WDG 3A= 04 NOS(1 ON LOAN BASIS FROM SIPAT)

    TOTAL LOCO = 105) WAGONS BURN STANDARD =43 Nos

    CIMMCO =67 Nos.

    TEXMACO =158TOTALWAGONS =268

    6) TOTAL NUMBER OF MOTORISED POINTS IN CIRCUIT = 33 NOS7) TOTAL NUMBER OF SIGNALS IN CIRCUIT = 21 NOS8) RAKE SIZE 50 WAGONS

  • 7/31/2019 Mgr Philosophy

    24/56

    24 May 2012 PMI Revision 00 24

  • 7/31/2019 Mgr Philosophy

    25/56

    24 May 2012 PMI Revision 00 25

    MGR PERFORMANCE(07-08) AT A GLANCE

    MAXIMUM COAL TRANSPORTED

    1) IN A DAY = 70,138.94 MT(31/03/08)

    2) IN A MONTH = 17.21 Lac MT(Mar- 08)

    3) IN A YEAR = 173.91 Lac MT

    (2007-08)

  • 7/31/2019 Mgr Philosophy

    26/56

    24 May 2012 PMI Revision 00 26

    COAL SUPPLY TO VSTPP DURING

    THE YEAR 2007-08

    Total Linkage 176.58 Lac MT

    Total Receipt 173.91 Lac MT Total Consumption 171.43 Lac MT

  • 7/31/2019 Mgr Philosophy

    27/56

    24 May 2012 PMI Revision 00 27

  • 7/31/2019 Mgr Philosophy

    28/56

    24 May 2012 28

    Coal handling system is the arrangement for transferring ofcoal from coal-wagons to coal-bunker or coal stock yard.

    It also provide arrangement for separation of material

    impurities, crushing of coals, Coal sampling etc.

    In the coal handling system of NTPC stations, three coal paths are

    normally available

    Path A - direct conveying of coal from track hopper to boiler bunkers.

    Path B - from track hopper to stockyardPath C - from stockyard to boiler bunkers.

    The storage facilities at the stockyards have been provided only for

    crushed coal.

  • 7/31/2019 Mgr Philosophy

    29/56

    24 May 2012 PMI Revision 00 29

  • 7/31/2019 Mgr Philosophy

    30/56

    24 May 2012 PMI Revision 00 30

    The coal handling system is designed to provide100% standby for all the equipment and conveyors.

    The capacity of the coal handling system for super

    thermal stations varies from 1200 to 2000 t/h,normally, for a stage of 1000 MW,

  • 7/31/2019 Mgr Philosophy

    31/56

    24 May 2012 PMI Revision 00 31

    plough feeder/ paddle feeder vibrating screen

    crushers,

    Conveyor belt,

    Idlers, Pulleys,

    Drive Unit,

    Take-ups,

    Skirt board, Scrapper,

    Stacker-cum-reclaimer,

    Magnetic separators,

    Motorized tripper.

  • 7/31/2019 Mgr Philosophy

    32/56

    24 May 2012 PMI Revision 00 32

    Below track hopper paddle feeder arrangement isprovided to unload coal to coal conveyors.

    The 200mm coal as received at the track hopper isfed to the crusher house through 1A & 1Bconveyors.

  • 7/31/2019 Mgr Philosophy

    33/56

    24 May 2012 PMI Revision 00 33

    Vibrating Screen :The function of the vibratingscreen is: -

    To send the coal having size of less than 20mm to

    belt feeder through the bypass chute bypassing thecrusher and

    To send the coal of more than 20mm size to thecrusher.

  • 7/31/2019 Mgr Philosophy

    34/56

    24 May 2012 PMI Revision 00 34

    CRUSHERS

    To crush the coal from 200mmto 20mm size received

    from vibrating screenCrusher hammer are made of MAGNEESE STEEL .

    Hammer row -4(stage 1)

    (a)Row-1 & 2 =18 hammer each

    (b)Row-3&4=20 hammers each

    No of hammer in each Crusher-

    stage-1 = 76 hammers

    stage-2 = 92 hammers

    Weight of each hammer=18.5kg

    Crushing motor rating -740kw/3.3kv

    Life of hammer =4 lac MT of coal

    Normal capacity=600 tons/hr

  • 7/31/2019 Mgr Philosophy

    35/56

    24 May 2012 PMI Revision 00 35

    Normally these crushers have a capacity of around 600

    tons per hour.

  • 7/31/2019 Mgr Philosophy

    36/56

    24 May 2012 PMI Revision 00 36

    CONVEYOR BELTS

    Made of diff. Layers or piles of fabric duck with rubber

    protected by a rubber cover on both sides & edges.Fabric duck are designed to withstand tension created in

    carrying the load .

    Nylon rubber cover protect the fabric duck.

    Material =fire resistant grade.

    Belt Width=1600 mm.

    Strength= 1000/1250 kN.

    Belt speed=3.2-3 m/s.Belt length=20km.

  • 7/31/2019 Mgr Philosophy

    37/56

    24 May 2012 PMI Revision 00 37

    IDLERS

    Idlers consists essentially of rolls made out of seamlesssteel tubes enclosed fully at each end fitted with

    stationary shaft, antifriction bearing and laybrith sealing.

    TYPES

    TROUGHING IDLERS- shape the belt to support a

    moving load without spillage or damage to the belt.

    IMPACT IDLERS - absorb the shock of falling material

    at loading and transfer points to protect belt from damage

  • 7/31/2019 Mgr Philosophy

    38/56

    24 May 2012 PMI Revision 00 38

    POSITIVE ACTION TROUGHING TRAINERS

    automatically maintain troughing side alignment inone-way conveyors. A center pivot frame and offset

    neutral guide rolls provide the troughing action.

    RETURN IDLERS

    support the empty belt during the return run.

    POSITIVE ACTION RETURN TRAINERS automatically maintain return belt alignment on one-way

    conveyors.

  • 7/31/2019 Mgr Philosophy

    39/56

    24 May 2012 PMI Revision 00 39

    PULLEYS

    Made of mild steel.

    Rubber coating is used to increase friction

    factor between belt & pulley (rubber lagging

    Shell dia-500mm.

    Shaft dia-1400mm.

    Pulley length-1800mm.

    Shaft length-2350mm(bearing centre to

    centre)

  • 7/31/2019 Mgr Philosophy

    40/56

    24 May 2012 PMI Revision 00 40

    DRIVE UNIT

    Motors coupled to reduction gear with the help

    of flexible/fluid coupling on the high speed shaft of theGear box

    Flexible coupling on the input side

    TAKE UPSTake up pulley to facilitates

    Necessary tension for the drive to operate the belt

    Sag at a point where requires horse power will be

    at a minimum and load will move with least

    disturbance over idlers

  • 7/31/2019 Mgr Philosophy

    41/56

    24 May 2012 PMI Revision 00 41

    SKIRT BOARD

    Used with chutes at trail end.

    Guides material centrally on the belt while loading

    until it has settle down on the belt

    SCRAPPERS

    Placed at discharge pulley in order to clean the

    carrying side of belt.It avoids the wear of return idlers due to build up

    material.

  • 7/31/2019 Mgr Philosophy

    42/56

    24 May 2012 PMI Revision 00 42

    Pull Chord

    Belt Sway

    Zero Speed

    Chute block

  • 7/31/2019 Mgr Philosophy

    43/56

    24 May 2012 PMI Revision 00 43

    This is used for stacking and reclaiming the coal fromstock yard. Generally two stacker claimers have beenprovided at each of the NTPC's projects. Their normalcapacity is 200 tons per hour and maximum design

    capacity is 450 tons per hour. The stacker reclaimer generally consists of (a) bucket

    wheel or digging wheel (b) boom conveyor. While thebelt conveyor carrying the coal for the stock yard is in thesame direction but the direction of the boom conveyor

    with respect to stacking and reclaiming is opposite. Digging Wheel The digging wheel is use for cutting and

    lifting the coal from the stock yard to the belt used fortransfering coal from the yard. The above transfer takesplace in case of reclaiming the coal only.

  • 7/31/2019 Mgr Philosophy

    44/56

    24 May 2012 PMI Revision 00 44Stacker Reclaimer

  • 7/31/2019 Mgr Philosophy

    45/56

    24 May 2012 PMI Revision 00 45

    During stocking operation, the coal from the crusherhouse is diverted towards the stockyard conveyor at atransfer point TP2/ TP3. The above conveyor dischargescoal to the boom conveyor through a discharge chute.The boom conveyor, running in the forward direction,

    creates coal stacks. During reclaiming, coal from the stock yard falls on the

    boom conveyor with the help of the bucket wheel and theboom conveyor, during this period, rotates in backwarddirection. The coal from central chute falls on the

    conveyor belts used for transferring the coal from thestock yard. By this way, the coal moves on theunderground conveyor belts connected to the main belts.

    A 6.6 KV motor is used for running the stacker-cum-reclaimer and has a cable reeling drum on which flexiblecable is wrapped.

  • 7/31/2019 Mgr Philosophy

    46/56

    24 May 2012 PMI Revision 00 46

  • 7/31/2019 Mgr Philosophy

    47/56

    24 May 2012 PMI Revision 00 47

    Coal to/from stock yard

    Generally 2nos

    Capacity ---200T/hrMaximum---400T/hr

    Bucket wheel

    Boom conveyor

  • 7/31/2019 Mgr Philosophy

    48/56

    24 May 2012 PMI Revision 00 48

    RECLAIMER IN OPERATIONSTACKER IN OPERATION

    Bucket wheel

  • 7/31/2019 Mgr Philosophy

    49/56

    24 May 2012 PMI Revision 00 49

    MAGNETIC SEPARATOR

    Any ferrous material onthe conveyor will be liftedfrom the moving conveyor.

    No Tripping involved.

    MS is interlocked withConveyor start up.

    When ferrous Metal is

    picked up, the MS ismoved from the Conveyor,de-magnatised and themetal piece is removed.

    METAL DETECTORAny Metal with an area

    of 100 Sq Cm will be

    detected.Conveyor is trippedafter detection.

    MD is not having

    interlock with start up.A sandbag is droppednear the Metal piecefor easy location

  • 7/31/2019 Mgr Philosophy

    50/56

    24 May 2012 50

    TRIPPERS

    To stack material at

    desired bunker

    Provided with wheels which moves on rails

    parallel to conveyor.

    Three types

    motorized tripper

    Belt propelled manually operated tripper

    Winch driven tripper

  • 7/31/2019 Mgr Philosophy

    51/56

    24 May 2012 PMI Revision 00 51

    WEATHERING OF COAL

    WHEN COAL IS EXPOSED TO ATMOSPHERE - IT

    REACTS WITH OXYGEN - PRODUCTION OF

    HEAT - RISE IN TEMPERATURE - OXIDATION

    REACTION IS ACCELERATED - NUMBER OFCHANGES IN PHYSICAL AND CHEMICAL

    PROPERTIES OF COAL TAKE PLACE - IT IS

    CALLED WEATHERING OF COAL.

    IMPORTANT FACTORS FOR

  • 7/31/2019 Mgr Philosophy

    52/56

    24 May 2012 PMI Revision 00 52

    IMPORTANT FACTORS FOR

    STORAGE OF COAL

    RANK OF COAL

    SURFACE AREA

    VENTILLATION

    COMPACTION

    AGE OF COAL

    SIZE AND HEIGHT OF STOCK PILES

    % LOSS I N CVSI ZE OF COAL

    ( MM) 1 YEAR 2 YEAR50 75 O. 11 0. 24

    12 03 0. 5 1. 0

    0. 3 0. 2 1. 0 2. 1

  • 7/31/2019 Mgr Philosophy

    53/56

    24 May 2012 PMI Revision 00 53

    PREDICTION OF SPONTANEOUS

    COMBUSTION

    B-M LIABILITY INDEX:

    = 21.48M+ 0.98A- 0.62M

    2

    -0.58MA+ 0.08A

    2

    + 10.2WHERE, M=% MOISTURE(AIR DRIED BASIS)

    A=% ASH(AIR BASIS)

    COALS HAVING B-M INDEX > 80 ARE HIGHLY

    PRONE TO AUTO-OXIDATION.

  • 7/31/2019 Mgr Philosophy

    54/56

    24 May 2012 PMI Revision 00 54

    MANAGEMENT OF COAL STOCKYARD

    Proper coal-air interaction to avoid auto- oxidation and

    spontaneous combustion.

    Close monitoring during march-june.

    Design should ensure that for maximum duration of the year, air

    strikes the width of the stockpile and not the length.

    Freshly mined coals should be stacked and old coal should be used.

    Freshly mined coals should not be stacked over old coal.

    Stacking of coal layer by layer, with compaction of each layer.

  • 7/31/2019 Mgr Philosophy

    55/56

    24 May 2012 PMI Revision 00 55

    MANAGEMENT OF COAL STOCKYARD (CONTD.)

    Stacking in trapezoidal shape, not in conical shape.Height of stockpile not more than 9-10m (indian coal).

    Lumps and fines should be stacked together and compacted.

    Before stacking coal should be visibly wet.

    Segregation of stockpiles into various segments and relevent records

    of period of stacking, quality of coal (cv) should be maintained.

    Compaction of finer particles over the bigger particles.

  • 7/31/2019 Mgr Philosophy

    56/56