Submarine PipelineRepair Methodology
Presented By:
Yasir A. Al-Harbi
Terminal Department
January 25, 2016
![Page 2: MI-11 Submarine Pipeline Repair Methdology](https://reader036.vdocument.in/reader036/viewer/2022062317/577c81231a28abe054ab9f10/html5/thumbnails/2.jpg)
8/18/2019 MI-11 Submarine Pipeline Repair Methdology
http://slidepdf.com/reader/full/mi-11-submarine-pipeline-repair-methdology 2/15
Objective
To share with you Terminal Department’s efforts of
repairing the 56-inch submarine pipeline safely with
minimal environmental impact and highlight the steps
taken to ensure an uninterrupted supply of crude oilto the world.
![Page 3: MI-11 Submarine Pipeline Repair Methdology](https://reader036.vdocument.in/reader036/viewer/2022062317/577c81231a28abe054ab9f10/html5/thumbnails/3.jpg)
8/18/2019 MI-11 Submarine Pipeline Repair Methdology
http://slidepdf.com/reader/full/mi-11-submarine-pipeline-repair-methdology 3/15
Outline
System Operation Overview
Pipeline Damage Configuration
Challenges
Repair Methodology Options
Conclusion
![Page 4: MI-11 Submarine Pipeline Repair Methdology](https://reader036.vdocument.in/reader036/viewer/2022062317/577c81231a28abe054ab9f10/html5/thumbnails/4.jpg)
8/18/2019 MI-11 Submarine Pipeline Repair Methdology
http://slidepdf.com/reader/full/mi-11-submarine-pipeline-repair-methdology 4/15
7 miles (1.5 - 4) miles
WATER LEVEL
ShippersPumps
BoosterPumps
Juaymah Tank Farm
4 CLSs
12 CLSs
SP
M
Juaymah Offshore Platform
SEABED LEVEL
Operations System Overview
2.5 miles
![Page 5: MI-11 Submarine Pipeline Repair Methdology](https://reader036.vdocument.in/reader036/viewer/2022062317/577c81231a28abe054ab9f10/html5/thumbnails/5.jpg)
8/18/2019 MI-11 Submarine Pipeline Repair Methdology
http://slidepdf.com/reader/full/mi-11-submarine-pipeline-repair-methdology 5/15
Pipeline Damage Configuration
• The Dent Depth (6-inches)
• The Longitudinal Damage
Internal View
![Page 6: MI-11 Submarine Pipeline Repair Methdology](https://reader036.vdocument.in/reader036/viewer/2022062317/577c81231a28abe054ab9f10/html5/thumbnails/6.jpg)
8/18/2019 MI-11 Submarine Pipeline Repair Methdology
http://slidepdf.com/reader/full/mi-11-submarine-pipeline-repair-methdology 6/15
Challenges
• Environment protection
• Shallow area
• Hard and rocky seabed
• Customized material
• Heavy pipe weight
![Page 7: MI-11 Submarine Pipeline Repair Methdology](https://reader036.vdocument.in/reader036/viewer/2022062317/577c81231a28abe054ab9f10/html5/thumbnails/7.jpg)
8/18/2019 MI-11 Submarine Pipeline Repair Methdology
http://slidepdf.com/reader/full/mi-11-submarine-pipeline-repair-methdology 7/15
Repair Methodology Options
• Pressure Containing Sleeve
• Bolted Sleeve
• Patch Plate
• Flanged Spool
![Page 8: MI-11 Submarine Pipeline Repair Methdology](https://reader036.vdocument.in/reader036/viewer/2022062317/577c81231a28abe054ab9f10/html5/thumbnails/8.jpg)
8/18/2019 MI-11 Submarine Pipeline Repair Methdology
http://slidepdf.com/reader/full/mi-11-submarine-pipeline-repair-methdology 8/15
• Environmental
Precautions
• Material Availability
• Repair Barge
Repair Methodology OptionsFlanged Spool
![Page 9: MI-11 Submarine Pipeline Repair Methdology](https://reader036.vdocument.in/reader036/viewer/2022062317/577c81231a28abe054ab9f10/html5/thumbnails/9.jpg)
8/18/2019 MI-11 Submarine Pipeline Repair Methdology
http://slidepdf.com/reader/full/mi-11-submarine-pipeline-repair-methdology 9/15
56 inch Dia.New Spool
Swivel Flanges
56 inch Dia.
Incoming Pipeline
Repair ethodology Options
Flanged Spool Installation
![Page 10: MI-11 Submarine Pipeline Repair Methdology](https://reader036.vdocument.in/reader036/viewer/2022062317/577c81231a28abe054ab9f10/html5/thumbnails/10.jpg)
8/18/2019 MI-11 Submarine Pipeline Repair Methdology
http://slidepdf.com/reader/full/mi-11-submarine-pipeline-repair-methdology 10/15
Repair Methodology OptionsFlanged Spool
![Page 11: MI-11 Submarine Pipeline Repair Methdology](https://reader036.vdocument.in/reader036/viewer/2022062317/577c81231a28abe054ab9f10/html5/thumbnails/11.jpg)
8/18/2019 MI-11 Submarine Pipeline Repair Methdology
http://slidepdf.com/reader/full/mi-11-submarine-pipeline-repair-methdology 11/15
Repair Methodology OptionsFlanged Spool
![Page 12: MI-11 Submarine Pipeline Repair Methdology](https://reader036.vdocument.in/reader036/viewer/2022062317/577c81231a28abe054ab9f10/html5/thumbnails/12.jpg)
8/18/2019 MI-11 Submarine Pipeline Repair Methdology
http://slidepdf.com/reader/full/mi-11-submarine-pipeline-repair-methdology 12/15
Repair Methodology OptionsFlanged Spool
![Page 13: MI-11 Submarine Pipeline Repair Methdology](https://reader036.vdocument.in/reader036/viewer/2022062317/577c81231a28abe054ab9f10/html5/thumbnails/13.jpg)
8/18/2019 MI-11 Submarine Pipeline Repair Methdology
http://slidepdf.com/reader/full/mi-11-submarine-pipeline-repair-methdology 13/15
Repair ethodology Options
Pipeline Protection and Stabilization
![Page 14: MI-11 Submarine Pipeline Repair Methdology](https://reader036.vdocument.in/reader036/viewer/2022062317/577c81231a28abe054ab9f10/html5/thumbnails/14.jpg)
8/18/2019 MI-11 Submarine Pipeline Repair Methdology
http://slidepdf.com/reader/full/mi-11-submarine-pipeline-repair-methdology 14/15
Conclusion
• Reliable Execution
• Minimal Environment Impact
• Valuable Experience Gained.
![Page 15: MI-11 Submarine Pipeline Repair Methdology](https://reader036.vdocument.in/reader036/viewer/2022062317/577c81231a28abe054ab9f10/html5/thumbnails/15.jpg)
8/18/2019 MI-11 Submarine Pipeline Repair Methdology
http://slidepdf.com/reader/full/mi-11-submarine-pipeline-repair-methdology 15/15
Thanks