ministry of local government and rural …...furthermore, about seven (7) agricultural extension...
TRANSCRIPT
MINISTRY OF LOCAL GOVERNMENT
AND RURAL DEVELOPMENT
KWAHU AFRAM PLAINS NORTH DISTRICT
ASSEMBLY
MEDIUM -TERM DEVELOPMENT PLAN 2014-2017
ANNUAL PROGRESS REPORT, 2016
Prepared by
DISTRICT PLANNING CO-ORDINATING UNIT
K.A.P.N.D.A
FEBRUARY,2017
ii
TABLE OF CONTENT
Contents
LIST OF FIGURES ................................................................................................................. iii
CHAPTER ONE: INTRODUCTION ........................................................................................ 1
CHAPTER: TWO: MONITORING AND EVALUATION ACTIVITIES............................... 2
2.0 PROGRAMME AND PROJECT STATUS FOR THE YEAR ....................................... 2
2.1 Enhancing Competitiveness of Ghana’s Private Sector............................................... 2
2.2 Accelerated Agricultural Modernisation and Sustainable Natural Resource
Management ......................................................................................................................... 7
2.2.1 Status of Selected Indicators, 2016 ........................................................................... 8
2.3 Infrastructure and Human Settlements Development .................................................... 10
2.3.1. Status of Selected Indicators, 2016 ........................................................................ 12
2.4 Human Development, Productivity and Employment. .................................................. 12
GHANA SOCIAL OPPORTUNITIES PROJECT (GSOP) ...................................... 14
The labour intensive project which started was implemented in the District in 2015,
introduced its Climate Change component in the second quarter of the year under
review. .............................................................................................................................. 14
2.5 Transparent and Accountable Governance............................................................... 17
2.6 Update on Critical Development and Poverty Issues ................................................... 18
2.6.1 Water and Sanitation ............................................................................................... 18
2.6.2 Teenage Pregnancy ................................................................................................. 19
2.6.3 Maternal Mortality .................................................................................................. 19
2.6.9 School Feeding Programme .................................................................................... 21
2.8 Update on Physical Projects ........................................................................................ 22
CHAPTER THREE: ................................................................................................................ 23
CONCLUSION AND RECOMMENDATIONS .................................................................... 23
3.1 Summary and Conclusion .............................................................................................. 23
iii
3.2 Recommendation.......................................................................................................... 24
APPENDICES ......................................................................................................................... 25
Appendix 1: Update of indicators .................................................................................... 25
LIST OF FIGURES
Fig.1: Achievement of indicators for Agricultural Modernisation and Sustainable Natural Resource
Management .......................................................................................................................................... 8
Fig.2: Achievement of indicators for Infrastructure and Human Settlement Development ............................ 12
1
CHAPTER ONE: INTRODUCTION
The 2016 Annual Progress Report provides an assessment of the implementation of policies
and strategies outlined in the Ghana Shared Growth and Development Agenda (GSGDA II),
2014–2017. It is the tenth assessment of the progress of implementation of the GSGDA.
The overall goal of the GSGDA is to accelerate the growth of the economy with the view to
creating more jobs, generating more incomes, and reducing poverty.
Policy measures identified to achieve this overall goal are prioritized in five thematic areas,
namely:
Enhanced competitiveness of Ghana’s private sector;
Accelerated agricultural modernisation and sustainable natural resource management;
Infrastructure and human settlements development;
Human development, productivity and employment; and
Transparent and Accountable governance
The report presents the results of the assessment of the status of indicators and targets
adopted for monitoring the progress of key policy and programme interventions earmarked to
be undertaken in 2017. It also documents key policy measures and strategies implemented
during the year to bring about the expected changes in these indicators.
Out of a total of seventy five (80) indicators assessed, only eight (8) achieved their targets,
sixteen (16) of the targets were exceeded. Twenty five (24) of the targets were not met. Data
was not readily available for twenty two (22) of the indicators. The number of indicators that
were yet to be implemented was ten (10).
2
CHAPTER: TWO: MONITORING AND EVALUATION
ACTIVITIES
2.0 PROGRAMME AND PROJECT STATUS FOR THE YEAR
2.1 Enhancing Competitiveness of Ghana’s Private Sector
The private sector has been identified as pivotal to accelerated growth, job creation and
transformation of the economy. In order to position it to play its role in Ghana’s economic
growth and transformation, the competitiveness of the sector has to be enhanced, through the
removal of core constraints inhibiting its growth. Priority medium-term policies and
programmes under the GSGDA aims at removing constraints in the value chain and
enhancing productivity, efficiency, and reliability in the following key areas:
The Assembly had planned a number of activities for the year. A total of Seventy Six (85)
people in the District were trained. Among them, eighteen (18) participants consisting of two
(2) men and sixteen (16) women were taken through the process of transforming groundnut to
groundnut oil and packaging and also how to keep proper records. The activity was
implemented in the Second quarter at Amankwa. The participants were equipped with
requisite knowledge and skills in groundnut processing.
Twenty-Six (26) people were also trained in rearing Grass cutter / rabbit in the second quarter
at Adeemra. The participants consisted of Twenty three (23) men and Three (3) women.
The participants were taken through the various types of grass cutter /rabbit, importance of
rearing grass cutter/rabbit and how to handle them and also the equipment used.
Another training was held on the processing of cassava in the third quarter at Amankwa
Tornu. Eighteen (18) participants consisting of eighteen (18) women were trained in the
proper knowledge and skills in cassava processing and packaging.
In the fourth quarter, a training on Business Management was held at Donkorkrom where
Twenty-Nine (29) participants all being women were trained on how to manage their small
Business and finances.
3
Agricultural Commodity Processing Infrastructure Development (ACPID)
The Agricultural Commodity Processing Infrastructure Development (ACPID) component is
mainly focused in the development and manufacture of agro- processing equipment, Cassava
processing machines and others. The Rural Technology Facility (RTF) trained nine (9)
technical apprentices.
The RTF was also able to manufacture a Soap Mixture and a Soap cutting Machine for its
clients and also presented start up kits to fourteen (14) graduate apprentices in the fourth
quarter.
Table 2.1: Agro processing machines manufactured by the RFT in Donkokrom in 2016
Description Quantity
Soap cutting machine 2
Soap mixer 1
Artisans presented with start-up kits Training on groundnut processing
Participants at Grass cutter rearing training Business Management training
4
Training on Cassava Processing
Status of some selected indicators, 2016
There were four indicators measured under this area. One of the targets set for the year was
not achieved due to inadequate funding while three other indicators could not be measured
due to a difficulties in acquiring data.
UPDATE ON FUNDING AND DISBURSEMENT
Update on Funding by Sources
ITEMS 2014 (GH¢) 2015 (GH¢) 2016 (GH¢) TOTAL (GH¢)
0
0.5
1
1.5
2
2.5
3
3.5
TARGET NOT ACHIEVED LACK OF DATA
INDICATORS
5
DACF 828,549.10 2,144,611.84 1,951,077.26 4,924,238.20
MPs DACF 66,097.76 114,861.72 46,182.03 227,141.51
IGF 393,323.00 304,494.61 371,742.79 1,069,560.40
OTHER DONOR
FUNDS
0.00 14,148.00 0.00 14,148.00
GOG GRANTS 12,880,544.70 499,855.50 450,492.00 13,830,892.20
DDF 822,787.86 514,892.00 738,861.00 2,076,540.86
TOTAL REVENUE
14,991,302.42
3,592,863.67
3,558,355.08
22,142,521.17
From the chart above it is evident that the District Assembly Common Fund is the largest
funding source of revenue for the Assembly to implement its activities and the trend over the
three years shows that the amount released from DACF increased significantly from 2014 to
2015, (GHS 828,549.10 to GHS 2,144,611.84) while it decreased (GHS 1,951,077.26) in
2016. This is as a result of more releases in 2015 than the other two years hence the
Assembly had implemented more activities in 2015 than the other years.
The Internally Generated funds is the third lowest source of revenue for the District. It is
evident from the chart that the Assembly generated more revenue from the District in 2014 as
DACF
MPs DACFIGF
OTHER DONOR FUNDSGOG GRANTS
DDFTOTAL REVENUE
0.00
2,000,000.00
4,000,000.00
6,000,000.00
8,000,000.00
10,000,000.00
12,000,000.00
14,000,000.00
16,000,000.00
2014
(GH¢)2015
(GH¢)2016
(GH¢)
LINE CHART TREND SHOWING FUNDING
SOURCES
DACF MPs DACF IGF OTHER DONOR FUNDS GOG GRANTS DDF TOTAL REVENUE
6
economic activities were higher and dwindled in 2015 when the ferry at Agordeke was not
operational and this affected the influx of goods into the market especially from Volta region
but appreciated significantly in 2016 when the Donkorkrom market was completed while the
capacity building training for the revenue collectors had a massive effect in revenue
generation.
The releases from the District Development Facility (DDF) depreciated from 2014 to 2015
but appreciated in 2016, hence the Assembly’s implementation of projects under DDF was
higher in 2015 than the other years as it had higher releases that year.
The chart shows that the District’s total had dwindled over the three years hence the
Assembly had to roll over projects and programmes or reduce the number of projects to be
implemented.
Update on Disbursements
ITEMS 2014 (GH¢) 2015 (GH¢) 2016 (GH¢) Total (GH¢)
ADMINISTRATION 384,309.76 270,802.78 318,581.04 973,693.58
SERVICE 0.00 0.00 0.00 0.00
SPECIAL PROJECTS 14,557,089.21 2,740,790.84 3,658,969.86 20,956,849.91
TOTAL EXPENDITURE 14,941,398.97 3,011,593.62 3,977,550.90 21,068,201.14
ADMINISTRATION
SERVICE
SPECIAL PROJECTS
TOTAL EXPENDITURE
0
5000000
10000000
15000000
2014 (GH¢)2015 (GH¢)
2016 (GH¢)
LINE CHART SHOWING THE TREND OF
DISBURSEMENT
ADMINISTRATION SERVICE SPECIAL PROJECTS TOTAL EXPENDITURE
7
From the chart above it is evident that the Assembly disbursed more funds in 2014 than the
other years due to the Assembly gaining a significantly higher source of funding in 2014 than
the other years under review. While the Assembly expended major proportion of its revenue
of special projects, it expended a significantly lower amount on administrative costs.
CHALLENGES:
Delay in the flow of the common fund and other central Government funds.
Funds not sufficient due to the unknown deductions from the Common Fund
secretariat.
IGF:
Even though the Assembly educates the tax payers, challenges are still encountered
in payment such as low capability of the collectors even though they have been
trained.
Low IGF based due to the morphology of the area has made it difficult to track the
goods especially on island.
2.2 Accelerated Agricultural Modernisation and Sustainable Natural Resource
Management
The focus of agricultural development strategy under the GSGDA is to accelerate the
modernisation of agriculture to contribute significantly to the structural transformation of the
economy through an effective linkage of agriculture to industry, associated by job creation,
food security, and supply of raw materials for value addition.
The strategies are also aimed at providing a major impetus to change the lives and fortunes of
the citizenry, particularly those in rural communities. The strategies adopted will transform
agriculture to ensure domestic food and nutrition security, support agro-processing, and
energise the rural economy in order to reduce poverty and inequality in all its forms.
The modernization of agriculture entails significant improvements in productivity enhancing
measures along the value chain, including the adoption of high yielding crop varieties;
mechanization services; improved extension services; upgrading skills of operators; and
access to inputs, markets and finance.
8
A total of One Thousand Four Hundred and Seventy-Nine (1,479) farm and home visits were
made by seven (7) Agricultural Extension Agents in 82 communities’ District wide. 60% of
the households were females while 40% were males.
Besides this, Six (6) field demonstrations were conducted at Memchemfre, New Kyease,
Donkorkrom, Adiemmra, Apeabra and Amankwatornu. The crops demonstrated include
cowpea, Maize, Yam, Cassava, Ground nuts and pepper production respectively. 324 farmers
were involved consisting of One Hundred and Ninety Eight (198) males and One Hundred
and Twenty Six (126) females. The demonstration was successful and the crops were
harvested in December.
Furthermore, about seven (7) Agricultural Extension Agents (males), four (4) Agricultural
Development Officers were trained in post-harvest management of cereals, roots and tubers.
The training enhanced the capacity of the officers to reduce the rate of post-harvest losses in
the District.
2.2.1 Status of Selected Indicators, 2016
A total of thirteen (13) indicators were earmarked for the year, however, very little progress
was made in terms of achieving targets. Only two (2) of the indicators had their targets
achieved. There were however, difficulties in acquiring data on most of the indicators hence
the reason for the inability to report on many of the indicators.
Fig.1: Achievement of indicators for Agricultural Modernisation and Sustainable Natural
Resource Management
9
Figure 2 indicates that out of a total of thirteen (13) indicators, three (3) of the targets were
exceeded while five (5) targets were not achieved and the five (5) remaining indicators lacked
data.
From the chart above it is evident that out thirteen indicators assessed only three exceeded
their targets, while four targets were not achieved we had difficulties in assessing six
indicators.
0
1
2
3
4
5
6
TARGET EXCEEDED TARGET NOT ACHIEVED LACK OF DATA
INDICATORS
0
1
2
3
4
5
6
7
TARGET EXCEEDED TARGET NOT
ACHIEVED
LACK OF DATA
INDICATORS
10
2.3 Infrastructure and Human Settlements Development
The GSGDA recognizes the need to expand existing social and economic infrastructure as a
means to propel economic growth and sustainable poverty reduction. The overall objective
for the sector therefore, is to ensure that infrastructural services are provided reliably and
efficiently.
A number of infrastructural developments took place within the year. Developments were
focused on road construction, Completion of Community centre complex, Completion of the
3.8km Feeder road from Memchemfre to Catapillar Tornu, Completion of the Six- Unit
Classroom block at Kedekope, the Community Day School at Memchemfre as well as the
Assembly’s Guest House at Donkorkrom.
Improving access to safe drinking water in rural and urban communities continues to pose a
challenge to the Government and stakeholders in the water and sanitation sector. To address
the challenge, the Assembly in collaboration with Water Aid drilled two boreholes at Salepe
and Meyikpor.
Improving access to education in the District especially on areas on the island, the Assembly
completed the six (6)-unit classroom block with ancillary facilities at Kadekope on the Dwarf
Island
DRILLED BOREHOLE AT SALEPE
.
11
COMPLETED 6-UNIT CLASSROOM BLOCK WITH ANCILLARY AT KEDEKOPE
COMPLETED COMMUNITY DAY SENIOR HIGH SCHOOL AT MEMCHEMFRE
COMPLETED COMMUNITY CENTRE COMPLEX AT DONKORKROM
12
2.3.1. Status of Selected Indicators, 2016
Fig.2: Achievement of indicators for Infrastructure and Human Settlement Development
Figure 3 indicates that out of a total of sixteen (17) indicators, eight (8) had their targets not
achieved while five (3) indicators had targets exceeded. Four (4) indicators were not
implemented. Some indicators were though not achieving targets however, activities were in
progress to ensure that the Assembly meet those targets in the next period. The high
percentage of indicators which activities were not implemented was attributed to inadequate
funding alternatives to finance them while one (1) other indicators had no data available.
2.4 Human Development, Productivity and Employment.
The policies and programmes outlined in the Ghana Shared Growth and Development
Agenda (GSGDA), under the Human Development, Productivity and Employment thematic
0
1
2
3
4
5
6
7
8
9
TARGET EXCEEDED TARGET NOT
ACHIEVED
LACK OF DATA NOT IMPLEMENTED
INDICATORS
13
area, are aimed at producing well educated and skilled population capable of transforming the
key sectors of the economy for wealth creation and poverty reduction. The focus areas in this
thematic area are:
Education;
Health;
HIV and AIDS/STI/TB;
Population Management;
Productivity And Employment;
Social Policy and Social Protection;
Poverty And Income Inequalities Reduction; and
Sports Development
This section of the report assesses progress made in 2016 towards the achievement of the
objectives in the above focus areas, using specific indicators and targets adopted to track
progress of implementation, as well as key policy measures and strategies implemented to
enhance human development, productivity and employment.
Several interventions were implemented in the education sector to improve on the educational
sector of the District. The Assembly received support from relevant Organisations to
facilitate its activities. Some of the activities carried out were; the construction of institutional
latrines, provision of dual and mono desks and the supply of School uniforms and chalk to
Schools.
Two (2) new Circuit Supervisors were trained in Management Skills to strengthen school
supervision in the District. This was organised to build the capacity of the Circuit Supervisors
in their activities.
Inclusive Educational programmes were conducted in five (5) communities to increase
awareness on the importance of Girls education. The communities are Abotanso, Mem-
chemfre, Bridge Ano, Nton- Aboma and Mafe-Abiwu kope. This was done to increase the
enrolment of Girls in school.
Three Hundred and sixty-six (366) girls received sanitary pads under the Girls Participation
Approach for Students Success programme (GPASS). This was done to improve on the
enrolment and retention of girl-child through the provision of sanitary facilities.
The formation of gender clubs is to improve on the enrolment, retention and performance of
the Girl-child in schools. Currently, thirteen (13) girls clubs are active in schools within the
District.
14
The annual Inter schools and District sporting competition was held in the third quarter with
the 16 athletes who participated in the Under-15 inter- district competition also qualified to
join the regional team for the national competition.
Thirty two students from sixteen (16) basic schools and three (3) second cycle institutions
were presented with footballs and some jerseys for participation in the 6th March celebration.
The National Youth Employment Programme
The National Youth Employment was carried out successfully in the district, the Programme
Co-coordinator was supported with adequate logistic to carry out programme .The youth
were engaged for employment on all Proposed Modules, the detailed of number of youth
employed
The table below shows the number of active workers for each module.
S/N MODULE MALE FEMALE TOTAL
1. FIRE SERVICE ASSISTANTS 8 2 10
2. PRISON SERVICE ASSISTANTS 9 2 11
3. COMMUNITY POLICE ASSISTANTS 11 3 14
4. COMMUNITY HEALTH WORKERS 37 63 100
5. COMMUNITY EDUCATION
TEACHING ASSISTANTS
52 40 92
Source: District Youth Employment Agency, 2016
GHANA SOCIAL OPPORTUNITIES PROJECT (GSOP)
The labour intensive project which started was implemented in the District in 2015,
introduced its Climate Change component in the second quarter of the year under review.
The Rehabilitation of Degraded land through Climate Change activities specifically by
planting Mango trees through the Ghana Social Opportunities Project (GSOP) in the year
under review has had a tremendous influence in the lives of beneficiary communities in the
District. So far, the labour-intensive project which covers ten hectare land in three (3)
communities namely Amankwah, Ntonaboma and Mem-chemfre had been running from the
second quarter and provided employment opportunities to people from all walks of life
thereby reducing poverty levels in the District. Moreover, their knowledge in farming has
15
also been enhanced as they are guided by Agricultural Extension Agents to use simple tools
for the project.
A 2.2km feeder road from Agordeke to Wodidada was also under rehabilitation in the fourth
quarter under the said project. One Hundred and six (106) beneficiaries from the two
communities consisting of forty- five (45) females and Sixty-one (61) males were employed
to man the project.
However, delay in the payment of wages to the workers and the supply of tools is a challenge
that deters the project as it derails the zeal and passion of the workers due to the effect on
their livelihood.
The table below shows the number of people recruited in each community.
S/N COMMUNITY MALE FEMALE TOTAL
1. AMANKWAH 19 15 34
2. NTONABOMA 13 35 48
3. MEM-CHEMFRE 16 34 50
4. AGORDEKE/ WODIDIADA 61 45 106
5 Total 109 129 238
Source: District Assembly, 2016
It is evident from the table above that, Two Hundred and Thirty Eight (238) beneficiaries
from four communities have been offered employment on a minimum wage with One
Hundred Twenty Nine (129) being females and One Hundred and Nine being males.
16
GSOP MANGO PLANTATION AT NTONABOMA
Table 2.2: Status of District indicators under Human Development, Productivity,
Employment for 2016.
The chart above shows that out thirty indicators assessed, five (5) of the targets were
exceeded while the four (4) targets were not implemented. As many as eleven (11) of the
targets were not achieved. The number of targets achieved were eight (8) while eleven (11)
targets could not be assessed due to difficulties in assessing data.
0
2
4
6
8
10
12
TARGET
EXCEEDED
TARGET NOT
ACHIEVED
LACK OF DATA NOT
IMPLEMENTED
TARGET
ACHIEVED
INDICATORS
17
2.5 Transparent and Accountable Governance
Ghana continues to make significant progress in deepening and expanding the frontiers of
democratic governance. The practice of democracy and transparent and accountable
governance has made tremendous contributions to the relative peace and stability as well as
the economic development in the country. However, there still remain critical challenges in
certain key areas. Thus policies, programmes and projects implemented in 2016, to deepen
and sustain democratic governance focused on the following areas as outlined in the Ghana
Shared Growth and Development Agenda (GSGDA), 2014 – 2017.
The Assembly organised a capacity building programme for staff of the registry in records
keeping and management.
The Assembly also organised a similar programme for senior and junior members of staff on
Local Government Service Protocols where 78 members of staff comprising of seventy (70)
males and seventeen (17) females.
Another training was held for the sub-structures in the District. This was held at Donkorkrom
with twenty two (22) participants comprising of one (1) female and twenty one (21) males
and eighteen (18) participants at Nton-aboma comprising of three (3) females and fifteen (15)
males. The training was focused on financial management and auditing.
A similar training was held for the revenue collectors, with twelve (12) participants
consisting of eleven (11) males and one (1) female.
The District Fire Service in collaboration with Forestry Commission embarked on the Safety
campaign and fire education programme in eight communities in the District. This covered
churches, schools and the communities. A total of over four hundred (400) participants, from
eight communities participated with 340 males and sixty females. The communities spanned
from Bruben, Agortime, Kayera, Asikasu, Bethel, Donkorkrom township,Adukrom and
Sawua.
18
Fire education at Kayera Safety education at Adukrom
Status of some selected indicators for 2016
From the chart above it is evident that out seven (7) indicators assessed in this area, three (3)
of their targets were exceeded while two (2) targets were achieved and the same number were
not achieved.
2.6 Update on Critical Development and Poverty Issues
2.6.1 Water and Sanitation
Good Sanitation practice among households in the District is still a major problem to be
addressed. The District has eight communal storage depots, 203 authorised refuse dumps, 131
unauthorised refuse dumps and 2 refuse trucks to convey waste to dumping sites. Many
households do not have access to refuse containers. Refuse disposal is mostly done
indiscriminately. The effect of these could be the rising trend in typhoid as it was detected
after the medical screening of food vendors in the year under review.
There are inadequate refuse containers in the District while the sanitary tools and equipment
for labourers are inadequate. The condition of the slaughter house at Donkorkrom is poor.
The provision of disposal facilities and the system of conveyance /transportation and final
disposal site for liquid waste remains a big challenge in the district. The promotion of
construction of house latrines by collaborative agencies such as NGO’S is being embraced by
some communities in the district.
0
0.5
1
1.5
2
2.5
3
3.5
TARGET EXCEEDED TARGET NOT
ACHIEVED
TARGET ACHIEVED
INDICATORS
19
The Assembly must purchase cesspool emptier to ensure that people stop manual dislodging
which pollutes the Environment. The Assembly must also purchase sanitary tools of all kinds
for labourers to work effectively. Ten (10) new refuse containers from Zoomlion would be a
welcome addition to the existing ones.
The District does not have enough drainage system therefore the incidence of malaria is at the
increase. During heavy down pours, residents along the streets dump refuse indiscriminately
into the drains. The residents have been advised to desist from that practice because it will
negatively impact on the community. District assembly should provide proper drains in the
communities for easy flow of runoff water.
Access to portable water is still a challenge since more than 60% of the population do not
have portable water. However, efforts are being made by the Assembly to provide boreholes
and other improved water systems to the people.
2.6.2 Teenage Pregnancy
Teenage pregnancy in the District has assumed an increasing trend for the past five years.
The phenomenon is largely attributed to the lack of proper supervision by parents and
institutions on the lifestyle of teenage girls. The long term effect of this is the high rate of
unskilled labour force, School dropout and difficulty in bridging the gender gap in education.
To avoid these phenomenon from becoming a canker, a number of sensitisation programmes
has been organised to educate parents and teenagers both in Schools and Communities on the
need to practice safe sex. The Assembly is collaborating with the Civil Society Organisations,
NGOs and appropriate Government institutions to take up the challenge and adopt measures
to curb the problem.
2.6.3 Maternal Mortality
There is a worrying trend in maternal mortality in the District. The current ratio of 995
maternal deaths per 100,000 live births is very high. According to the health Directorate,
almost 95% of pregnant women attend antenatal services. However, less than 30% of these
women access supervised delivery. This is attributed to poor transportation systems
especially in the rural communities, inadequate midwives and inadequate delivery systems.
The District recorded two maternal deaths for the year 2016. This was an improvement on the
five (5) recorded in the year 2015.
2.6.4 Livelihood Empowerment against Poverty
The Livelihood Empowerment Against Poverty (LEAP) serves as compliment to the existing
social protection measures. The policy had been initiated by the government to provide
20
conditional cash transfers to support the extremely poor, vulnerable and the excluded in
society. The total number of extremely poor households benefiting from the LEAP
programme had remain the same from the year 2016. The year recorded a total of Two
Thousand Nine hundred and eight (2,908) beneficiaries were paid a total amount of Two
Hundred and Forty Thousand Four Hundred and Six Ghana Cedis (GHS 240,406) from thirty
four (34) communities benefiting from the programme.
2.6.5 Child Rights, Promotion and Protection
The Assembly has the responsibility of protecting the welfare of children and also provide a
safer environment where children can explore and develop. A number of strategies have been
activated to ensure that Children are adequately safe in the district. Day Care Centres and the
only orphanage in the district were adequately monitored to ensure they meet standards for
Child promotion and development in the district. Heads and Proprietors were met to discuss
findings of the monitoring.
Casework with families were also carried out by the Department of Social Development.
Areas handled were the welfare, child custody, maintenance, Paternity and other child related
abuses. In all, an amount of Three Thousand Eight Hundred and Fifty (GH¢ 3, 850.00) were
collected as maintenance allowance to clients. The Juvenile Court was also constituted in the
year under review.
2.6.6 Sponsorship to Brilliant but Needy Students
The Assembly continues to provide support for a student who finds it difficult to provide
their educational needs. The support was mainly for providing funds for those who could not
pay their School fees. During the year under review, seven (7) sponsored with financial
support. Four (4) of them are at the Community Development Institute while three (3) others
are with Donkorkrom Agricultural Senior High School (DASHS).
2.6.7 Persons Living with Disabilities
The Disability Fund Management Committee disbursed funds allocated to Persons Living
with Disabilities.They were categorised in Educational, Health, Business and Organisational
development. The table below shows the disbursement of funds to the Persons with
Disabilities.
TYPE OF DISABILITY EDUCATION
HEALTH BUSINESS ORGANISAT
IONAL
DEV’T
No. AMOUNT
GH₵
No. AMOUNT
GH₵ No. AMOUNT
GH₵
AMOUNT
GH₵
PHYSICALLY
CHALLENGED
MALE 1 500.00 20 11,000.00 5,750.00
FEMALE 1 1,118.00 1 500.00 8 3,800.00
21
BLIND MALE 2 1,855.00
FEMALE
DEAF/DUMB MALE 1 500.00 4
FEMALE 1 600.00 1 500.00 6
MENTALLY
CHALLENGED
MALE 2 1,000.00
FEMALE
OTHERS MALE
FEMALE 1 500.00
Total 5 4,073.00 6 3,000.00 38 19,700.00 5,750.00
GRAND TOTAL 32,523.00
Source: Department of Social Development, 2016
2.6.9 School Feeding Programme
The number of Schools benefiting from the programme was 11 in 2016. The current
enrolment in these Schools stood at 1,842 pupils representing approximately 44% female
pupil as compared to 56% male pupils. The number of pupils has increased under the scheme
from 1,804 pupils to 1,842 pupils. Some farmers have expressed their excitement about the
programme in the District for providing ready market for their produce.
Though there have been some achievements under the scheme, there have been delays in the
release of funds for the programme. The payment is currently made through mobile money
service which makes it difficult to acquire data. It is expected that the programme will extend
to other schools in the District in the coming years.
2.7 Key Development Issues
2.71 BUSH BURNING
Bush burning is a major problem in the District that requires urgent intervention from all
stakeholders despite the periodic bush burning campaigns and other interventions that have
been carried out. It tends to affect communities especially those outskirts of the capital
Donkorkrom causing the loss of properties, decrease in food production in the long run and
increase the negative impact of climate change in the District.
This usually occurs in the dry season when fodder for cattle is scarce therefore herdsmen tend
to burn the bush in order to hasten the growth of fresh grass to enable them feed their cattle.
Also, people tend to burn the bush to enable them to hunt for game which tends to escalate
into wild fires.
22
Sadly, the most fire prone areas are without communication networks therefore making it
impossible to call on the Fire Service in the District in times of need and despite the training
of fire volunteers in such areas, it still poses a challenge to quench fires.
It is imminent that all stakeholders in the District aid in finding solutions to this problem as it
deprives the District further. Also, more fire volunteer squads should be trained to help
combat this problem.
A PROPERTY AFFECTED BY BUSH BURNING
State of mango plant before fire outbreak Aftermath of fire outbreak
2.8 Update on Physical Projects
The Assembly executed twenty three (23) Physical projects within the year 2016. From the
total, five (5) projects were awarded in the year 2016 whilst ten (10) were rolled over projects
from the previous years. As at the end of the year under review, four (4) projects were
completed whilst the remaining twenty one (21) were at various stages of completion. The
projects covered various sectors of the local economy including; Economic, Education,
Health and Agriculture subsector. Detailed projects description can be found in appendix
below.
23
CHAPTER THREE:
CONCLUSION AND RECOMMENDATIONS
3.1 Summary and Conclusion
The Overall assessment of this Report on the Programme and Projects implementation for
the period year under review has made some positive developmental changes which have
enhanced the socio economic wellbeing of the people particularly in the area of
24
telecommunication accessibility and water supply system which has improved the wellbeing
of the people in the district.
Some of the Government interventions in poverty reduction strategy is the introduction of the
Health Insurance Scheme, and the School Feeding Programme, this laudable policy have
impacted positively on the people in the district. Also, Ghana Social Opportunities Project
had a positive impact on the well- being of beneficiary communities.
3.2 Recommendation
It is recommended that both GoG and Donor funds for Programme and Project should be
released timely to enable the implementation agencies carry out implementation of all
proposed action plans on schedule, since delay in releasing of fund affects the smooth
implementation of Programme and Projects.
Find ways to further improve upon revenue collection, to generate enough revenue for the
development of the Assembly.
Solicit support for training, capacity building and technical assistance towards strengthening
the DPCU, Stakeholders, communities etc.
Continue the construction and monitoring of ongoing development projects of the District
which were not completed during the previous year.
25
APPENDICES
Appendix 1: Update of indicators
Indicators Indicator Level
Remarks 2013
Baseline
2016 2014 2015 2016 2017
Target Achievement
ENHANCE THE COMPETITIVENESS OF GHAN’S PRIVATE SECTOR
Objective 1: To increase access to credit facilities and other support services to groups and small scale enterprise by December 2017.
% of Co-operative Societies fully functional 45% 15% n.a 20% n.a. n.a. Lack of data
Number of youth organized and empowered
with employable skills
250 100 n.a 365 58 58 Target not achieved
No. of petty traders provided with micro
credit facilities.
-
50 n.a. 80 n.a. - Lack of data
No. of communities provided with
equipments.
6 25 n.a. 5 n.a. - Lack of data
Objective 2: Intensify the promotion of domestic tourism by December 2017
No. of Tourist attraction centres developed - 1 - - - 0 Not implemented
ACCELERATED AGRICULTURAL MODERNISATION AND NATURAL RESOURCE MANAGEMENT
Objective 1: Increase access to extension services and re-orientation of agriculture education
No. of farmers trained in modern
agricultural technologies
4 1,000 n.a. 1,091 1263 1263 Target exceeded
No. of women sensitised on the importance
of good health and nutrition.
150 50 n.a. - 41 41 Target not achieved
Organize educational campaign on animal
heath extension
25 6 n.a. - 7 7 Target exceeded
No. of farmers Trained in aquaculture
technology
20 15 n.a. - 12 12 Target not achieved
No. of AEAs trained on post-harvest
technologies.
- 500 n.a. 20 583 583 Target exceeded
Productivity Rate for Livestock Sub-sector 5% - n.a. n.a Lack of data
26
% increase in yield of selected crops
- Maize
- Rice
- Cassava
- Yam
15
10
20
10
4
2
2
5
-
1.5
1.2
1.6
3.2
1.5
1.2
1.6
3.2
Target not achieved
Objective 2: To enhance capacity to mitigate and reduce the impact of natural disasters, risks and vulnerability
% reduction in Disaster victims 8 2% - - - - Lack of data
Objective 3: To enhance natural resources management through community participation
No. of re-afforestation exercises organized - 2 n.a. 1 1 Target not achieved
Hectares of degraded forest recovered - 25 n.a n.a Lack of data
Area under wood logs cultivation (hectares) - - n.a n.a Lack of data
No. of charcoal producers educated on the
need to cultivate wood logs.
50 50 n.a. n.a. Lack of data
Objective 4: To enhance capacity to adapt to climate change impacts
No. of Educational campaign on floods,
Epidemics, Rain and windstorm and
domestic and bushfires organized
8 2 n.a. n.a. n.a - Lack of data
INFRASTRUCTURE AND HUMAN SETTLEMENT DEVELOPMENT
Objective 1: To ensure safe and affordable mode of transport by December 2017
Length of choked gutters desilted 15km 5km 20km 3km 3km Target not achieved
Length of roads Constructed - 5km - - - Not implemented
Objective 2: To rehabilitate road networks in the District by December 2017
Length of roads Rehabilitated 15km 5km 20.8km 16km 6km Target exceeded
No. of culverts Constructed 24 5 - 1 1 Target not achieved
Length of road with speed ramps
constructed
- 3km - - - Not implemented
Objective 3: To increase potable water coverage from 48% to 65% by December 2017
No. of boreholes drilled / mechanized 55 15 n.a 16 2 2 Target not achieved
Change in access to safe water 17% 10% n.a 11% n.a - Lack of data
27
No. of household refuse containers acquired - 50 n.a 200 400 400 Target exceeded
No. of public latrines constructed 14 2 n.a 1 1 Target not achieved
No. of Hygiene education organized 4 2 n.a n.a 1 1 Target not achieved
No. of CLTS Education conducted in
Communities
20 15 n.a 20 5 5 Target not achieved
Objective 4: To strengthen the operation and maintenance of water systems in all beneficiary communities by December 2017
No of small town water systems constructed 4 2 4 - Not implemented
No. of monitoring activities on water
systems organised
12 3 8 4 Target exceeded
% of water facilities Rehabilitated - 5% n.a n.a. - Not implemented
Objective 5: To promote Information and Communication Technology in the District by December 2017
No. of computers and accessories procured
for schools
- 2 n.a n.a n.a Not Implemented
Objective 7: To increase the energy supply from 23% to 45% by December 2017
Length of road with street lights functional 5km 10km n.a 15km 3km 3km Target not achieved
No. Communities connected to the National
Electricity Grid.
17 5 n.a. - 10 10 Target exceeded
HUMAN DEVELOPMENT, PRODUCTIVITY, EMPLOYMENT
Objective 1: To increase access to and participation in education and training at all levels by December 2017
No. of Classroom Blocks constructed 74 3 n.a 2 2 2 Target not achieved
No of Teachers quarters / bungalows
constructed
- 3 n.a - 0 - Not implemented
No. of institutional latrines for schools
constructed
14 5 n.a 21 n.a - Not implemented
No. of dual desks furniture provided for
schools
- 100 n.a n.a - Not implemented
No. of Community Libraries constructed - 1 n.a 1 0 - Not Implemented
28
Teacher – Pupil Ratio
-KG
-Primary
-JHS
1:34
1:32
1:15
1:60
1:56
1:46
1:14
1:64
1:42
1:16
-
Target achieved
Proportion of Girls Completing Secondary
education
90% 99% n.a. - Lack of data
Transition rate from Primary to Secondary
Education
- 95% 63% n.a. - Lack of data
Pupil- Classroom ratio
-KG
-Primary
-JHS
- 1:65
n.a
n.a
n.a
1:105
1: 39
1: 17
1:143
1: 41
1: 30
1:143
1: 41
1: 30
Target achieved
Enrolment rate (Gross Enrolment)
- KG - Primary
- JHS
123%
107.3%
82.0%
123%
107.3%
82.0%
n.a.
n.a.
n.a
112.2%
105.6%
38.6%
82.7%
66.0%
28.6%
82.7%
66.0%
28.6%
Target not achieved
Gender Parity Index
-KG
-Primary
-JHS
1.01
0.99
0.95
1.01
0.99
0.95
n.a.
n.a
n.a
0.92
1.04
0.92
0.92
0.91
0.80
0.92
0.91
0.80
Target not achieved
Completion rate
- At Primary 6
- JHS
-
n.a
n.a
0.92
1.04
51.5%
25.6%
51.5%
25.6%
Repetition rate 1.6 1.4 n.a 1.6% 1.4% 1.4 Target achieved
Text Book to Pupil ratio
-KG
-Primary
-JHS
1:0.2
1:2.8
1:2.8
1:0.4
1:0.2
1:2.0
n.a
1:0.4
1:0.2
1:2.0
1:0.2
1:0.5
1:07
1:0.2
1:0.5
1:0.7
Target not Achieved
Pass rate n.a 68.9%
58.5% 58.5% Target achieved
29
Gender parity Index
- KG
- Primary
- JHS
- SHS
1.00
1.00
1.00
1.00
n.a.
n.a.
n.a
0.92
1.04
0.92
0.92
0.91
0.80
0.92
0.91
0.80
Target not achieved
% of Schools with drinking water
- KG
- Primary
- JHS
50%
50%
50%
29%
29%
29%
31%
31%
31%
31%
31%
31%
Target not achieved
% of Schools with toilet facilities
- KG
- Primary
- JHS
65%
65%
70%
48%
48%
48%
56%
56%
56%
56%
56%
56%
Target not achieved
% of schools monitored annually
- KG
- Primary
- JHS
65%
65%
65%
100%
100%
100%
100%
100%
100%
100%
100%
100%
Target exceeded
% of Pupils/students having access to
seating places
-KG
-Primary
-JHS
50%
70%
80%
62%
72%
85%
57%
83%
100%
57%
83%
100%
Target exceeded
% of students having access to writing
places
-KG
- Primary
- JHS
50%
70%
80%
50%
50%
50%
59%
69%
95%
55%
81%
100%
55%
81%
100%
Target exceeded
30
Objective 3: To improve the quality and efficiency in education delivery through institutional strengthening by December 2017
No. of capacity building programmes
organized
- 2 4 1 1 Target not achieved
Objective 4: To increase geographical access to basic health services in deprived areas through the provision of additional CHPS centres
by December 2017.
% increase in access to health services 10% 30% n.a n.a n.a Lack of data
Objective 5: Improve access to financial and health care by extending the District Mutual Health Insurance Scheme by December 2017.
% of population registered with NHIS 15% n.a n.a. n.a Lack of data
Objective 6: Improve efficiency in service delivery in the health sector through institutional strengthening by December 2017.
No. of residential facilities provided for
GHS Staff
1 n.a n.a n.a Not implemented
Doctor-Patient ratio - n.a n.a n.a n.a Lack of data
Objective 7: To reduce the incidence of HIV/AIDS and other STDS among the high risk groups in the District (youth, female sex workers,
miners, long distance drivers) by 50% by December 2017.
HIV/AIDS prevalence rate 0.96 0.85 0.96 0.96 0.96 0.96 Target not achieved
Change in Maternal Deaths - 15% n.a n.a -60% -60% Target exceeded
% reduction in TB cases 100% 25.4% 29.2% 22.6% 22.6% Target exceeded
% change in prevalence of communicable
diseases
100% 100% 200% 200% 0% 0% Lack of data
Penta three coverage 95% 95% 65.4% 85.4% 99.6% 99.6% Target achieved
Morbidity rate n.a n.a n.a n.a n.a Lack of data
Infant mortality rate n.a n.a n.a n.a n.a Lack of data
Crude birth rate n.a n.a n.a n.a n.a Lack of data
Fertility rate n.a n.a n.a n.a n.a Lack of data
Objective 7: To create job avenues for the youth through skills and entrepreneurial training and investment support for self employment
by December 2017.
No. of youth with employable skills 50 10 n.a n.a 14 14 Target exceeded
Objective 8: To improve the wellbeing of vulnerable groups in the District (physically challenged, women and children) by December
2017
Proportion of population benefiting from
LEAP (%)
2.5% n.a 2.58% 2.58% Target exceeded
31
No of needy but brilliant students offered
financial support.
15 10 n.a 7 7 Target not achieved
No. of vulnerable identified and trained in
employable skills
200 60 n.a. n.a Lack of data
Number of abuse cases reported 30 55 n.a. n.a Lack of data
TRANSPARENT AND ACCOUNTABLE GOVERNANCE
Objective 1: To strengthen service delivery capacity of the Assembly by December 2017
No. of M&E Training workshops organised
for DPCU Members
3 1 1 1 1 Target achieved
Objective 2: To promote community participation in planning and implementation of development activities through reactivation of
urban/Town/Area councils by December 2017
No. of community mobilization exercise
organized
4 5 n.a 5 5 5 Target achieved
No. of Sub Districts meetings organized 12 9 n.a 0 3 3 Target not achieved
No. Training held for Sub District members
and Assembly members.
- 1 n.a 1 1 1 Target achieved
Objective 3: Improve the efficiency in the revenue collection machinery of the Assembly by December 2017
No. of Training programmes organised for
Revenue Collectors.
8 10 n.a. n.a 1 1 Target not achieved
Proportion of Assembly Staff trained - 10% 85% Target exceeded
% increase in revenue collection - 10% n.a -22.58% 22.09 % 22.09 % Target exceeded
32
Appendix 2: STATUS OF IMPLEMENTATION OF PROGRAMMES
INFRASTRUCTURE AND HUMAN SETTLEMENTS DEVELOPMENT;
OBJECTIVE ACTIVITY/STRA
TEGY
ACHIEVEMENTS REASONS FOR NOT
ACHIEVING TARGET
Promote a sustainable,
spatially integrated and
orderly development of
human settlements for
socio-economic
development
Undertake street
naming and
numbering of
houses
Exercise required a base map which has been
generated manually and approved by the
Assembly
Lack of funds to support the staff
in map maker training to generate
a Geo-referenced map for that
purpose
Delineate and map
out open spaces of
the district
Exercise achieved in 3 Sector Areas namely:
Adofo 1,2 & 3 and Donkorkrom
Monitor planning
activities
concerning physical
development
The Department regularly monitored physical
activities being undertaken at the environs of
Donkorkrom, Asikasu, Atakora and Adofo
Organize monthly
statutory planning
committee
meetings to
approve
applications
Three (3) quarterly Statutory Planning
committee meetings and Three (3) quarterly
TSC meetings were organised
Minimize the impact of Selection and pre- Not implemented Lack of funds
33
and develop adequate
response strategies to
disaster
information to 10
communities to
start drawing on
communities
preparedness plan
Formation and
training of disaster
volunteer
groups(DVGs)
Not implemented Lack of funds
Ensure sustainable
development in the
transport sector
Continue the
Construction of the
lorry park.
The project was 55% completed Inadequate funds released by the
Central Government
Promote a sustainable,
spatially integrated
and orderly
development of human
settlements for socio-
economic development
Reshaping, Spot
improvement and
Routine
maintenance of
30km of feeder
roads
Work was done on 50km of feeder road
ranging from Donkorkrom to Memchmfre,
Agordeke to Amankwa, Atakora to Kwae kese,
Abotanso to Donkorkrom, Presby Hospital to
Adeemra and Adeemra to Apeabra
Earth removing machine
developed fault
Construction of 4
no. Drainage
Not implemented Funds were not released
34
culvert
Complete the
rehabilitation of
Kamalo-Anidzi
feeder road (5.0km)
The project was 92% covered. Work was on-
going
Issues with labour
Complete the
rehabilitation of
Mem Chemfre –
Caterpillar tornu
feeder road(3.8km)
The project was Completed
Rehabilitate
Agordeke –
Wodidiada feeder
road (2km)
The project is on-going at 15% completion Not awarded on time or scheduled
Establish and
construct satellite
markets
Not implemented Not awarded because funds were
not released
Increase equitable
access to and
participation in
education at all levels
Construction of 5
No.3KG class room
block with ancillary
Not implemented Not awarded because funds were
not released
Completion of 3
unit primary class
room block with
The project was at Fasso Battor was 90%
completed
Funds not released
35
ancillary
Construction of
2No. 3 unit class
room blocks with
ancillary
Two 3- unit class room blocks were ongoing at
Fasso Bottor and Sihu Norfegali
Funds not released
Minimize the impact of
and develop adequate
response strategies to
disasters
Rehabilitate /
redevelop affected
water facilities
Not Implemented Funds not available
Extend pipe lines to
newly developed
communities
Not implemented Inadequate community
commitment
Provision of 2No.
boreholes
2 boreholes were drilled at Salepe and
Meyikpor
Provide adequate and
reliable power to meet
the needs of Ghanaians
and export
Extend electricity
to selected
communities
The project has been 50% completed Approval from the energy
commission delayed
Extension of
electricity to newly
develop areas
The extension project has been 50% completed Approval from the energy
commission delayed
Minimize the impact of
and develop adequate
response strategies to
Rehabilitation of
30 hectare degraded
land in three
100% completed. Mangoes were planted at
Memchemfre, Amankwa and Ntonaboma
36
disasters Communities
(Cashew/mango
plantation)
Construct
1No.footbridge
Not implemented Funds not released
Provide adequate and
reliable power to meet
the needs of Ghanaians
and export
Extend electricity
to selected
communities
Not implemented Funds not released
HUMAN DEVELOPMENT, PRODUCTIVITY AND EMPLOYMENT
OBJECTIVE ACTIVITY/STRATEGY ACHIEVEMENTS REASONS FOR NOT
ACHIEVING TARGET
Improve quality of
teaching and
learning
Organise workshop on the
preparation of ADEOP.
(15Personnel)
Not implemented No funds
Organise mgt. Training for
C/S to strengthen school
supervisors.
Two (2) new Circuit supervisors were
trained on management skills to improve the
supervision of the schools
37
Train KG teachers on
effective use of TLMS/
NALAP methodology in
teaching.
The department organised training for KG
teachers on the effective use of
TLMS/NALAP methodology in teaching at
Donkorkrom. In total, 120 teachers
participated, with fifty (50) males and
seventy (70) females.
Organise ICT training for
teachers annually.
Not implemented No funds
Bridge gender gap
in access to
education
Improve
management of
education service
delivery
Organise community
sensitisation on inclusive
in 84 school communities.
Not implemented No funds
Conduct IEC programmes
to stress awareness of the
importance of girls
education in 40 school
communities
Five (5) communities were visited. They
were Abotanso, Mem-chemfre, Bridge Ano,
Nton- Aboma and Mafe-Abiwu kope
Develop and promote
Girls’ week activities to
advocate on behalf of girls
Not implemented No funds
Develop
comprehensive
sports policy
Provide Gender friendly
sanitary facilities in basic
schools
366 girls on GPASS programme received
sanitary pads
Formation of Gender
clubs& provide use of
Thirteen (13) girl clubs were active in the
District
38
Role Models in schools
and communities
Organize District
Education Sector
Performance review
Not implemented No funds
Facilitate the organisation
of annual inter- schools,
inter district sporting
competition
Not implemented The activity has scheduled to
February, 2017
Provide sports equipment
to 12 basic schools
Thirty two (32) basic schools and three (3)
Second cycle institutions were presented
with footballs and some jerseys during the
6th March celebration
Improve
governance and
strengthen
efficiency and
effectiveness in
health service
delivery
Capacity building for
senior staff in
management and
governance
Not implemented Inadequate funds
Renovate 3 CHPS centres Not implemented Inadequate funds
Construction of 4 CHPS
Compounds
The CHPS compounds under construction
were located at Supom, Fasso Bator, Anidzi
and Abotanso
Organise family planning
campaign
Not implemented Funds not released
39
Construction of Health
Centre
Not implemented Lack of funds
Prevent and
control the spread
of communicable
and non-
communicable
diseases and
promote healthy
lifestyles
Conduct Food
Demonstration
Not implemented Inadequate funds
Capacity building of
Health promotion
Assistants
Not implemented Inadequate funds
Accelerate the
provision and
improve
environmental
sanitation
Procure sanitary tools and
chemicals
Not implemented Inadequate funds
Organize quarterly
hygienic and sanitation
education in the District
Not implemented Lack of funds
Conduct yearly hygiene
education for butchers,
meat sellers , chop bars,
restaurant and vendors
Not implemented Lack of funds
Organize public education
and create awareness on
annual sanitation week
A public education was held on stray
animals and malaria prevention in Six (6)
communities namely Agortime, Abotanso 1,
40
celebration 2, 3 Sawua, Boanya, Vegbe. Four Hundred
people participated 310 males and 90
females
Organize monthly
supervision, monitoring
and reporting of waste
management
Monthly supervision was carried out in four
Area Councils
Organize medical
screening exercise for
food vendors
1,004 vendors were screened in the District.
85% being women and 15% being men.
Typhoid was detected among
Acquire liquid waste
disposal site
A land fill site at Apeabra is being
constructed by Zoomlion.
Expand
opportunities for job
creation
Organise training in
employable skills for 100
disadvantage, vulnerable
and excluded
Not available Lack of data
Facilitate and Coordinate
programs on Juveniles
The family tribunal handled ten (5)cases on
Juveniles
Enforcement of child
labour laws
Not implemented Lack of funds
Provide support for
affected children and
families
Not implemented No funds allocated
41
Facilitate and Coordinate
program for the
aged/Elderly
The Elderly and Aged registered on
National Health Insurance Scheme
Provide assistance to
OVCs and PLWHA
Not Implemented Inadequate funds
ENHANCED COMPETITIVENESS OF GHANA’S PRIVATE SECTOR
OBJECTIVE ACTIVITY/STRATEGY ACHIEVEMENTS REASONS FOR NOT
ACHIEVING TARGET
Ensure efficient
internal
revenue
generation and
transparency in
local resource
management
Revaluation of properties and
strengthening of tax
collection system
Not implemented The Assembly did not revalue
properties due to the high cost
involved but measures were
adopted to mobilise funds in the
District
Update of revenue register The revenue register was updated monthly
Provide logistics to Revenue
Collectors
Revenue collectors were provided with
kits such boots to enhance their work
Institute incentive schemes
and reward systems for
revenue collectors
Not implemented No funds
Improve
efficiency and
Training of twenty-five (25)
women in soap and powder
Not implemented Implemented in the previous
year
42
competitiveness
of MSMEs
making
Training ten (10) young men
and women in welding and
metal fabrication
Fourteen (14) apprentices were trained
and presented with start-up kits in the last
quarter
TRANSPARENT AND ACCOUNTABLE GOVERNANCE
OBJECTIVE ACTIVITY/STRATEGY ACHIEVEMENTS REASONS FOR NOT ACHIEVING
TARGET
Strengthen functional
relationship between
Assembly Members and
Citizens
Facilitate community / unit
committee/ area council
interactive meetings
The Donkorkrom Area Council held three (3)
meetings in 2016 with minutes recorded and
submitted.
Organize community
durbars to educate the
public on government and
assembly policies and
programmes
The Assembly held durbars at Donkorkrom
and Fasso Battor in last quarter where the
citizens were educated on peace building and
development as well as projects and
programmes of the District. A total of 170
people were present with 60% being women
and 40% being men
43
Organize annual training
for staff and members of
the district sub-structures
This was held at Donkorkrom with twenty two
(22) participants comprising of one (1) female
and twenty one (21) males and eighteen (18)
participants at Nton-aboma comprising of
three (3) females and fifteen (15) males. The
training was focused on financial management
and auditing. /
Provide logistics and office
equipment for Area
Council and Unit
Committees
Not implemented Inadequate funds
Provide support to
Community Self Help
Projects
Not implemented Inadequate funds
Integrate and
institutionalize district
level planning and
budgeting through
participatory process at
all levels
Organise community level
public hearings on
planning, budgeting and
M&E to disseminate
information
The information regarding fee fixing was
disseminated at Donkorkrom
Organise quarterly DPCU
meetings and disseminate
progress reports
Four quarterly meetings were organised with
minutes recorded
Organize quarterly Four quarterly sub-committee meetings were
44
meetings for sub-
committees of the
Assembly
held and decisions made were submitted at
the Executive Committee
Procure 4NO. desktop
Computers and accessories
Not implemented Inadequate funds
Rehabilitation of 5NO.
Staff Bungalow
Not implemented Inadequate funds
Upgrade the capacity of
the public and civil
service for transparent,
accountable, efficient,
timely, effective
performance and service
delivery
Organize planned training
workshop for Heads of
Department and core
management staff.
The Assembly organised a training for staff on
appraisal and Local Government Service
Protocols. 78 staff were present with 60 being
males and 17 being females on appraisal and
Local Government Service Protocols
Prepare departmental
annual budgets for collation
into composite budget
Departmental budgets were prepared and
collated into the composite budget for the
ensuing year
Review existing Medium –
Term Development plan,
M&E plans, Annual Action
plans.
The Action plan for the year was reviewed by
District Planning Coordinating unit (DPCU)
45
Accelerated Agricultural Modernisation and Sustainable Natural Resource Management
OBJECTIVE ACTIVITY/STRATEGY ACHIEVEMENTS REASONS FOR NOT
ACHIEVING TARGET
Improve
agricultural
productivity
Agric Extension Agent
farm and Home visits
A total of 1,479 farm and home visit were made by 7
Agric Extension Agents in 82 communities’ district
wide. 60% of the households were females.
Establish and monitor 10
crop demonstration plots
Six field demonstrations were conducted at
Memchemfre, New Kyease, Donkorkrom, Adiemmra,
Apeabra and Amankwatornu. The crops were cowpea,
Maize, Yam, Cassava, Ground nuts and pepper
production respectively. 324 farmers were involved.
198 were males and 126 were females The
demonstration was successful. The crops were
harvested in December.
Organize farmer’s day
celebration.
The 38th National farmer’s day was successfully held
at Kayera. 15 farmers were awarded including 6
females. The overall best farmer from Alavanyo in the
person of Fredrick Kwasi Torble, 35 years of age.
Promote livestock
and poultry
development for
food security and
Conduct animal health
extension and livestock
disease surveillance.
Drugs were supplied for the treatment of general
ailments in both small and large ruminants
46
income
Promote fisheries
development for
food security and
income
Organize training on fish
farming for 100 farmers
Not implemented Lack of funds
Reduce
production and
distribution
risks/bottlenecks
in agriculture and
industry
Train extension staff and
500 farmers on post –
harvest loss activities
Seven (7) Agric Extension Agents (males), 4 Agric.
Development Officers were trained in post-harvest
managements of cereals, roots and tubers.
Due to inadequate funds,
community sensitization was
organized for 300 farmers
comprising of 179 males and
121 females
Educate farmers on the use
of agro-chemicals.
1,253 farmers were educated on the use of
agrochemicals in 79 communities by 7 agric.
extension agents. 795 males and 458 females
Ensuring the
restoration of
degraded natural
resources
Educate 500 people in 6
Communities on
environmental
conservation practices
Six (6) communities were educated on wildfires and
it’ s effect on the environment in collaboration with
Fire Service
Facilitate the planting of
3000 trees in five (5)
Communities
Not implemented
There were no seedlings for
the planting exercise
Reverse forest and
land degradation
Celebration of annual
world tree planting day
This was organised at the national level from 21st-27th
may 2016 where representatives the District were
invited to take part
47
Appendix 2: Status of Physical Projects
S/N
Project
Name
Sector Loc. Contractor Award
Date
Contract
Sum GHS
Amount
Paid
Start
Date
End.
Date
Source of
Funding
Status
%
Remarks
1. Const. of 6-unit
Classroom block
Education Kedekope
(Dwarf Island)
NakwabTrad.
Co.Ltd
May,
2006
143,198.38 115,183.50 May,
2006
Nov.20
06
DACF 100 Complete
2. Const. of Lorry
Park and
Passengers Lodge
Economic D’krom Amalug Const.
Complex Ltd
Oct.
2012
465,426.65
365,418.22
Oct 2012
Jan
2013
DDF
55
On-going
3. Const. of Area
Council Office
Governanc
e
Memchemfre MessrsRehimado
Enterprise
Septemb
er,2015
256,369.00 219,220.65 Jan,2016 June,
2016
DDF 80 On-going
4. Const. of
community centre
complex
Economic D’krom A.K. Dankwa Co.
Ltd
May
2006
647,311.59
539,213.68
MAY
2006
Nov.
2006
DDF 100 Complete
5. Construction of
3.8km feeder road
Economic Mem-Chemfre
–
Caterpilatonu
G&S Const.Ltd Aug.
2015
212,467.53
80,203.68
Aug.
2015
Feb.
2016
GSOP 100 Complete
6. Construction of
5km feeder road
Economic Anidzi -
Kamalo
AREC Const. Ltd Aug.
2015
306,084.35
133,000.00
Aug,
2015
Feb,
2016
GSOP 95 Ongoing
7. Construction of
2.2km feeder road
Eonomic Wodidiada-
Agordeke
G&S Const.Ltd Oct
2016
108,626.86 Nil Oct
2016
June
2017
GSOP 15 Ongoing
8. Construction of
3unit Classroom
block with
ancillary.
Education Sihu Norfegali Sermax Gee
Enterprise
Dec.
2015
246,368.10 83,878.96 Dec. 2015 June,
2016
DACF 75 Ongoing
9. Construction of
CHPS Centre
Health Kokrobuta Rehimado
enterprise
Dec.
2015
256,369.69 83,778.63 Dec. 2015 June
2016
DACF 60 Ongoing
10. Construction of
CHPS centre
Health Abotanso Messrs Imnah
Ghana Limited
June
2016
240,000.00 - Aug 2016 Oct
2016
GOG 80 Ongoing
11. Construction of
CHPS centre
Health Supom Messrs Imnah
Ghana Limited
June
2016
240,000.00 - Aug 2016 Oct
2016
GOG 80 Ongoing
12. Construction of
CHPS centre
Health Fasso Battor Messrs Imnah
Ghana Limited
June
2016
240,000.00 - Aug 2016 Oct
2016
GOG 80 Ongoing
13. Const. of 3 unit
Classroom block
with ancillary
Education FassoBattor MessrsKobigrand
Ltd
Dec.
2015
268,749.89 114,503.42 Sept 2015 March,
2016
DACF 90 Ongoing
48
14. Construction of
2No. markets in
2communities
Economic
Supom
Bruben
Messrs Rehimado
Ent.
85,000.00 District
Assembly
20 Ongoing
15. Rehabilitation of
District Assembly
Guest House
Economic
Donkorkrom Praman Trading &
Construction
Works
DEC
2015
153,790.00 143,523.50 JUNE
2016
DACF 100 Complete
16. Construction of
1unit 16 seater
W/C Toilet
Facility
Health Donkorkrom-
Zongo
Messrs Abera
Const. Ltd
January
2016
208,975.25 71,000.00 February
2016
June
2016
DACF 45 Ongoing
17. Rehabilitation of
10hectare
degraded land
(mango
plantation)
Agriculture Amankwakro
m
District Assembly April
2016
July
2017
GSOP 100 Ongoing
18. Rehabilitation of
10hectare
degraded land
(mango
plantation)
Agriculture Ntonaboma District Assembly April
2016
July
2017
GSOP 100 Ongoing
19. Rehabilitation of
10hectare
degraded land
(mango plantation
Agriculture Mem-chemfre District Assembly April
2016
July
2017
GSOP 100 Ongoing
20. Construction of
Science
Laboratory Agric.
SHS
Education Donkorkrom Septemb
er 2011
Februa
ry
2013
GETFUND On-going
21. Construction of
1no. 4 unit Semi-
detached staff
bungalow at
Donkorkrom
Education Donkorkrom GETFUND On-going
22. Construction of
1no.4 unit
Education Adeemra Feb
2016
GETFUND On-going
49
workshop block at
St. Mary’s Vocational
Institute
23. Construction of
Agricultural
Mechanisation
workshop at
Amankwah krom
Fisheries and
Agricultural
Technical Institute
Education Amankwah GETFUND Ongoing
24. Construction of
1No. Boys
Dormitory at
Amankwah krom
Fisheries and
Agricultural
Technical Institute
Education Amankwah GETFUND Ongoing
25. Construction of
1No. Girls
Dormitory at
Amankwah krom
Fisheries and
Agricultural
Technical Institute
Education Amankwah
GETFUND Ongoing
26. Construction of
Dining Hall and
Kitchen at
Amankwah krom
Fisheries and
Agricultural
Technical Institute
Education Amankwah GETFUND Ongoing