Minutes of the 24th Meeting of the State Level Monitoring Committee (SLMC) for PM Package held on 30.9.13 and 01/10/2013(Phase-wise) from 0930 hrs in the Banquet Hall at Itanagar

The 24th meeting of the SLMC for PM Package was held under the Chairmanship of Dr. H.K. Paliwal, Chief

Secretary on 30.9.13 and 01.10.2013(Phase-wise) at Itanagar. Shri Sonam Chombay, Secretary (Planning) welcomed all the Officers and placed the agenda before the committee. He then requested the Chairman to take up the agenda items one by one for discussion.

The list of officers who attended the meeting is attached at Annexure-A.

1. New Secretariat Building at Itanagar:

� The overall Physical progress is 79% � Blockwise physical progress :-

Block-1 _ 53% Block-2 _ 65%

Block-3 _ 90% Block-4 _ 95%

� Financial Progress is 100% of released amount (i.e 87.47 crores). � Revised Target Date for completion of Blocks 3 & 4 is 31.12.2013 and Blocks 1 & 2 is 31.7.2014.

Action Points:

o A weekly action plan must be drawn for completion of the project.[ PWD]

2. Pare Hydroelectric Project (110 MW):

� Project to be implemented in 4 packages: a) Package-I , Civil Works –75.77% b) Package-II, Hydro-Mechanical Works – Work under progress c) Package-III, Electro- Mechanical Works – Work under progress d) Package-IV, Switch Yard and transformer Works – Mobilization done and work under progress

� Financial Progress: Rs.678.82 Cr (100% of Released amount i.e Rs.678.82 Cr) � PDC –September 2014.

A. Decision taken in the meeting: � The representatives from NEEPCO shall meet Commissioner (PWD) for Hoj-Potin road on quarry

issue. [Action: NEEPCO]

3. Dibang Multipurpose Project (3000 MW): Land Acquisition:

� The follow up action is being done from NHPC and the series of meeting was held with district administrations and DCs of both the district by NHPC.

� Proposal of issue of section 4 for 1628.44 ha land at L/Dibang Valley district submitted to Secretary,LM on 27.6.2013.

� Proposal of issue of section 4 for 2202.075 ha land coming under submergence in Dibang Valley district submitted to Secretary, LM on 5.7.2013.

� Approval has been accorded by Parliamentary Sec., LM and by HCM,GoAP for above two proposals. � Proposal of issue of section 4 for 57.60 ha for approach road from Dambuk to project site has been

approved by HCM,GoAP. Director LM, Itanagar has requested for some details regarding Grid Reference from DC, Roing.

Forest Clearance:

� FAC of MoEF has turndown the proposal. Environment Clearance :

� The report on Public hearing stands submitted to MoEF,New Delhi. � Proposal for Environmental Clearance has been discussed in EAC (MoEF,New Delhi) meeting held on

23.9.13.EAC had raised some observation which shall be sorted out as soon as possible.

A. Decision taken in the meeting: � ED, NHPC must follow up LA process very vigorously. � A compliance report on all observations of Forest Advisory Committee has been made by NHPC and

submitted for approval of Forest Clearance proposal. [Action: PCCF/DC, Anini/DC, Roing, NHPC]

3

4. Itanagar Water Supply Scheme (JNNURM): The project is complete.

5. Harmuti-Naharlagun Railway Line Project (21.75 km):

A. Present Status/Action taken: � Regarding Conversion of 1 Ha of forest land in Assam, “In Principle Approval” from GoI is received.

Boundary demarcated. Further works are in progress.

B. Decision taken in the meeting: � Condition of Yupia road must be improved for mobilization of heavy concreting and earthwork

machinery. � The site for Road Bridge on river Pachin must immediately be finalized by DC Capital Complex. � Regarding shifting of Overhead High Tension Electrical Lines and Towers, DC Papumpare must settle

this issue urgently. � The Committee has urged the executing agency to complete the project by Dec. 2013, so that, it could

be inaugurated by Hon’ble Prime Minister during his visit in the State. [Action: CE(C), NF Railways /DC, Capital Complex/DC, Papumpare] (II) Projects for which Hon’ble PM made Announcements on 31st Jan 2008

6. Electrification of all Houses (2121 villages) in the State: DHPD Component: Electrification of 1325 villages

PART- A (40 nos)

� 4 incomplete projects are to be completed by December 2013.

PART-B (4 nos) � Out of 4, 2 projects are completed. � Physical progress of remaining 2 projects are-

1) Kush MHS is 65%. 2) Halaipani SHP is 75%.

� PDC for both is March, 2014.

PART-C (Ph-I-14 nos. & Ph-II-35 nos.) � Phase-I- 14 Projects are complete. � Out of 35 projects in Phase-II, 21 projects have been completed. Out of 14 incomplete projects, 12

projects are targeted to be completed by December, 2013 and remaining 2 projects namely Nuranang Ph-II MHS & Khajalong MHS is to be completed by January, 2014.

APEDA component (for electrification of 796 villages- 546 through SHLS & 250 through MHS)

Part-I Illumination of 546 Border

Villages through Solar Home Lighting Systems (S/Amount Rs.11.725 crores)

100% completed 523 villages

Part-II Electrification of 191 villages through 67 MMHPs.( from 10 kw to 200 kw) (Sanctioned Amount Rs.52.85 crores)Revised.

Out of 67 projects, 63 projects – 100% completed. 3 projects - 90% completed. 1 project - 80% completed. PDC for the above 3 incomplete projects is November 2013.

57 villages

Part-III Electrification of 57 remote villages and one hamlet through 31 on-going MHPs (Rs.2.7439 cr)

100% completed

58 Villages

C. Decision taken in the meeting: � By November 1st week, a detailed project-wise presentation to be made to the CS.

[Action: Secretary Power/CE – DHPD/Dir(APEDA)]

4

7. Construction of Greenfield Airport at Itanagar:

A. Present Status/Action taken: � Matter followed up with AAI for expediting preparation & process of DPR by incorporating various cost

components. Also, AAI has been requested to expedite Environment Clearance, Defence Clearance etc.

� However, all actions were stopped due to status quo order of Guwahati High Court on PIL filed against shifting of the site from Banderdewa to Holongi.

� On the last Hearing on 30.8.2013, Hon’ble Court has ordered the Central Govt to constitute a Committee under Chairmanship of Justice A.C Upadhyay with Director General of Civil Aviation, Joint Secretary (MHA, NE) and Joint Secretary (RD),GoI as members to visit both the sites, peruse all records and give its report in context of the allegation in the PIL. Next date of hearing is fixed on 8.10.2013. Action Points:

o Secy., CA/Dir., CA must immediately follow up the development for early solution. [Action: Secy. CA/Dir. CA]

8. Operationalization of Tezu, Pasighat, Along, Daporijo and Ziro Airports:

Sl.No

Airports Status

1 Ziro The Government has approved the rate for land compensation. DC, Ziro, must immediately expedite handing over of additional land for extension of runaway.

2 Aalo DC Aalo has taken up the matter with army authorities. Last meeting was held on 28.6.2013. Reply from army authority is awaited. Further, in case of expansion of the ALG, the existing Aalo-Yinkiong BRTF road passing all along the existing ALG will have to be re-located for which, DC Aalo will seek comments from BRO. DC Aalo has also decided to re-survey a site at Tamoba area earlier identified for construction of ALG, in view of the difficulties faced in developing the existing ALG.

3 Daporijo The First meeting of the committee was held on 05-6-2013 under the Chairmanship of Development Commissioner. A Detailed report is to be submitted by DC, Daporijo and the matter is being taken up with IAF to confirm if Daporijo Airport is a strategic requirement for defense.

4 Tezu Work is under progress. As intimated by DC, Tezu , PDC is December 2014.

5 Pasighat NOC has been issued. IAF is requesting for the balance 53 acres land status of the same not yet received from DC Pasighat. DC is exploring possibility to acquire some additional land from green belt area and taking up the matter with forest department.

9. Improvement of ALGs:

Sl. No.

Location of ALGs

Status

1 Tuting DC Yingkiong has forwarded the proposal of additional land allotment (128.75 acres) to Director (Land Management) vide letter Dtd 29.06.2012 for approval, which is still awaited.

2 Mechuka DC Aalo had intimated additional land of 11 acres available towards north-east side of ALG which is low lying area on the bank of Yargap Chu river. However, for this, existing BRTF road leading towards Yorlung outpost and one Artillary unit of Army will have to be shifted. Besides, two small scale industries will also have to be shifted subject to compensation. Matter taken up with Army, IAF & BRTF.

3 Pasighat NOC has been issued. IAF is requesting for the balance 53 acres land status which is yet received from DC Pasighat. DC is exploring possibility to acquire some additional land from green belt area and taking up the matter with forest department.

4 Aalo DC Aalo has taken up the matter with Army authorities.

5 Vijaynagar Re-surfacing work done by PWD.

6 Walong The Barracks have already been vacated. 7 Ziro The Government has approved the rate for land compensation. DC, Ziro, must

handover land at the earliest for runway extension. 8 Tawang Earlier identified site at ‘Kitpi’ has been cancelled due to reluctance shown by the

land owners. An alternate site at Thirillam village in Lumla has been jointly surveyed by representatives of Army, IAF and District Administration on 13.6.2013. Report submitted to Secretary, MoD on 19.8.2013 for further action.

5

10. Helicopter connectivity between Guwahati and Tawang: Already implemented w.e.f. 29 .6.08. 11. Release of Corpus fund to RK Mission Hospital: Already released.

12. Providing Connectivity to 513 settlements (under Bharat Nirman):

The status of connecting rural habitations in border areas as on April 2013:

Sl. No

Survey & Investigation

Schedule for

Submission of DPRs

Length (Km)

Habita-tion (No.)

Clearanceof DPRs

Award of Work

Completion Of projects

Present Status

Original Revised

1 April to June 08

July to Aug 08

93.56 26 Aug.,08 Dec.,08 Mar-11 July 11

Physical Progress -97.25% Out of 7 roads, 4 have been completed benefitting 16 habitations.

2 Sept to Nov 08

Dec 08 to Jan 09

412.73 134 Oct.,09 Jan.,10 Feb- 2012

Dec 12

Physical Progress -85.74% Out of 35 roads, 28 have been completed benefitting 92 habitations.

3 June to July 09

Dec 09 to Jan 10

622.75 123 May,10 Dec,11 to

May,12

Jan-2013

Mar 13

Physical Progress -46.46% Out of 38 roads, 24 have been completed benefitting 4 habitations.

4 March to Nov 10

Dec 10 to Jan 11

738.53 129 ---

----

--- ----

Covers 129 habitations, of which- 1st Batch- DPR for 46 habitations are cleared 2nd Batch-DPR for 50 habitations are cleared 3rd Batch – DPR for 45 habitations are pending (33 nos. being the original+12 unconnected habitations for which take off points were not available.

5 Take off point not yet connected

466.42 101 12 unconnected habitations taken up as above mentioned.

Total 2333.99 513 Physical Progress-65% Financial Progress- 49% 36 roads completed covering 112 habitations.

Action Points:

o A detailed presentation on the project (road wise) to be made before the Chief Secy. on 4.10.13 [RWD]

13. Completion of Incomplete Projects: Department wise status-

Sl. no.

Department No. of projects Financial (All figures in Rs. Lac)

Target Achievement Allocation Achievement % UC submitted %

1 PWD 1055 1055 21815 21815 100 100 2 RWD 131 130 3043 3043 100 100 3 Hydropower 40 36 16925 16925 100 100 4 Power

(T&D) 34 34 3318 3316 99.94 99.94

5 Monitoring 408 380 93.14 93.63 Total 1260 1255 45509 15479 98.62 98.62

� Originally projects under Hydropower were 42; however due to non-feasibility of the two projects (Sipit & Sidip) were dropped out. Therefore, Rs 13.18 Crore as allotted for Sipit & Sidip has been Diverted to Halaipani SHP under Part-B.

� Out of the 131 projects, 130 projects have been completed. As intimated by Secretary, RWD, the remaining 1 project (C/o Steel bridge on Bokam to Chambang road in Kurungkumey district) will be completed by December 2013.

6

Name of Work Status

Shaikangchu MHP(3x2000 kw)

95 % (Civil works)

1 DG set, turbine and generator for 3 units of 2 MW installed capacity each has been erected. Switchyard and control panel are not erected.

Mago MHS(2x50 kw)

95 % (Civil works)

At trial run.

Angong Nallah MHS(3x1500 kw)

81% (Civil works)

Machines partly delivered at project site & erection under progress.

Kachopani MHS(2x100 kw)

90% (Civil works)

Machines delivered at project site. Erection is in progress.

14. ACA for Reconstruction of Flood Damaged Infrastructure:

Name of

Department

Allocation (Rs.lac) (Including 10% loan)

Expenditure (Against 1st installment)

UC submitted

to Planning Commissio

n

Expenditure (Against 2nd installment)

UC submitted to Planning Commission

Installments Total Rs. in Lac In (%) Rs. in Lac In (%) 1st(2008-

09) 2nd(2009-

10) WRD 160.00 160.00 320.00 160.00 100.00 160.00 100 Power (T&D)

556.00 556.00 1112.00 502.61 90.40 556.00 100

Hydropower 677.00 677.00 1354.00 677.00 100.00 677.00 100 PWD -

Roads/Bridges

11472.00 11472.00 22944.00 11472.00 100.00 11472.00 100

Housing 634.00 634.00 1268.00 634.00 100.00 634.00 100 RWD-Rural

roads 5453.00 5452.66 10906.00 5453.00 100.00 5452.66 100

Water Supply & Sanitation

1008.00 1008.00 2016.00 1008.00 100.00 1008.00 100

Total 19960.00 19960.00 39920 19906.61 98.62 19960.00 100

15. Drinking Water Facilities in Remote Locations: The Department has submitted the DPR for providing potable drinking water supplying to 760 left out habitations under PM’s package at an estimated cost of Rs.377.76 Cr to the Secretary (Planning) vide letter No. PHED-IV/359/10-11 dated 01.9.2010 and the same was handed over to Planning Commission on 08.9.2010 at New Delhi. The Department must follow up with Planning Commission through State Planning Department.

16. Four-lane highway for Itanagar: Total length of this 4-lane highway in Arunachal Pradesh is 51.870 km stretch from Banderdewa to Holongi via Itanagar It consists of two stretches - Banderdewa to PHQ (31.60 km) and from PHQ to Holongi (20.40 km) under SARDP-NE.

Holongi to Itanagar (20.40km

(a) Chimpu Nallah to Holongi (20.40 Km)

� Physical progress till date is only 40.45%. � Although, the original length was 20.40 km, the designed length is 19.6 km. � Revised compensation cost approved by MoRTH on 10.9.12. � The combined application has been submitted to the State Forest Department on 24-01-2013.

(b) PHQ to Chimpu Nallah (2.75 km) � All necessary documents submitted by CE (Highway) in this regard. Wildlife Clearance proposal

submitted by forest Department to MoEF on 12.01.2012. Forest Department must follow it up with MoEF,GOI.

Itanagar to Banderdewa (31.60 km)

� DPR submitted to MoRTH on 20.9.2010, reply awaited. It must be followed up by the State PWD.

7

17. Two-Lane connectivity for District HQs: Of the 16 District HQs, 11 Districts directly fall along the alignment of Trans-Arunachal Highway (TAH). To provide improved connectivity to the remaining 5 Districts, this project involving 805.00 km of roads is being taken up. This component consists of the following 6 roads:

Sl. No

Segment

Length (km)

To be executed by

1 Koloriang - Joram 158.00 BRO (Arunank) 2 Pasighat - Mariyang - Yingkiong 140.00 APPWD 3 Anini - Meka (Roing) 228.50 BRO (Udayak) 4 Hawai - Hawa Camp 141.00 BRO (Udayak) 5 Pappu – Yupia - Hoj 32.00 APPWD 6 Bame - Likabali - Akajan 105.00 BRO (Brahmank)

Total 804.50

1. Koloriang - Joram Road (158 Km-Arunank)

Sl.

Road length Status

a

0.00 - 20.00 Km Physical Progress: 20.33% Financial Progress: 41.71% Payment was made to Forest Department, shifting of utilities and private land compensation, Out of 346 enlisted individuals, 10 individuals have not accepted the compensation amount. Re-assessment to be done on the same.PHE and Power Deptt were directed to start shifting of utilities at the earliest As the road is required to be handed over to PWD on completed of works by 31st March 2015,therefore all pending issues related to compensation and shifting of utilities needs to be resolved on high priority.

b

20.00–40.00 km

Joint Survey which was to be carried out by July 2013 has not been done. DC ,Ziro has instructed ADC, Yachuli and SP, Ziro for suitable action.

c

40.00-70.0 Km (30 km)

Road alignment plan submitted to MoRT&H on 30th August 2013.LA assessment proposal submitted to DC, Kurungkumey on 25.2.2013. Muck disposal plan is under finalization and will be submitted to Forest department shortly.

d 70.00-100 km (30 km)

Road alignment plan submitted by HQ DGBR to MoRTH on June 2013. LA Assessment proposal submitted to DC, Kurungkumey on 25.5.2013. Muck disposal plan is under finalization and will be submitted to Forest department shortly.

e 100.00-138.00 km (38 km)

Road alignment plan submitted to MoRTH on 25 July 2013. LA Assessment proposal submitted to DC, Kurungkumey on 11.7.2013. Muck disposal plan is under finalization and will be submitted to Forest department shortly.

f

138.00–158.00 km

Approval of pre-constructional activities received from MoRTH. Payment of shifting of utilities and LA is under progress. FC report submitted by DFO, Kurungkumey to CCF,Banderdewa on 13.9.2013.

� Recently, on 6.9.2013, MoRTH has proposed to execute the stretch from Km 20.00 to 158.00 by

MoRTH on EPC mode through PMU.

2. Akajan – Likabali - Bame Road [BRO (Brahmank) 105 Km]

Sl Stretch Present Status

1 0 - 12 Km Tender accepted. Work will be started in Oct. 2013. 2 12 - 33 Km DPR approved by HPC of MoRTH on 19.12.2012. EPC cum feasibility report to be

submitted by 25th Oct. 2013. Land Acquisition – Rs. 1219.12 lac stands approved which is being deposited to Revenue department. Forest Clearance – Rs. 98.78 lac approved for the stretch between km 12.00 and km 22.00. Payment to be made after finalization of court cases on LA held at Hon’ble high court Guwahati at Itanagar.

3 33–65.81 Km EPC cum feasibility report to be submitted by 25th Oct. 2013.Case for FC held with PCCF Shillong.

4 65.81 - 97 Km Realignment plan sent to Army Authority for approval. Survey under process. DPR will be submitted by Oct. 2013.

5 97 - 105 Km DPR sanctioned on 28th January 2013. Tendering action is in progress by MoRTH.

� Due to constant slippages in work done by BRO, the road section from 12 to 97 km shall be transferred to PWD.

8

The status of forest clearance of above road segment is as below: Sl No

Stretch Status

1 0-12 km FC not required. 2 12-22 km AIP issued by CCF Shillong.

3 22-40 km Proposal held up with CCF Shillong.

3 40-65 km Case with PCCF, Itanagar. 4 65-71 km Case with PCCF, Itanagar 5 71-97 km Proposal will be initiated on finalization of re-alignment. 6 97-105 km Case with PCCF, Itanagar.

3. Anini - Meka Road (BRO-Udayak) - 228.50 Km:

Name of Road

Length (in Km)

Location (in Km)

Status

From To

1

Meka –Roing- Hunli

19.80 0.00 16.00 DPR has been submitted to MoRTH on 13 Dec 2012.Pre-construction activities approved by MoRTH for Rs 10.86 lacs which is in progress.

74.00 16.00 90.00 DPR has been submitted to MoRTH on 4th Apr 2013. Case taken up for Forest/Environmental Clearance.

2

Hunli-Anini

128.50 0.00 128.50 Revised DPR has been submitted to MoRTH on 30.4.2013 after rectifying the observations. 10.00 128.50 138.50

Status of Forest Clearance:

1. Meka to Km 2.00 Roing -Hunli road: not in forest area. 2. Km 2.00 to 6.00 Roing-Hunli road: FC case pending with MoEF shillong for final approval. 3. Km 6.00 to 16.00 R-H road: Case held with PCCF Itanagar. 4. Km 16.00 R-H road to 21.550 on Hunli-Anini road : Case held with PCCF Itanagar.

A. Decisions taken in the meeting: � RO, MoRTH to co-ordinate and expedite the DPR process. � PCCF to expedite Forest Clearance at the earliest. [Action: RO, MoRTH/PCCF]

4. Digaru- Tezu-Tohangam – Hayuliang – Hawai (BRO-Udayak):

Sl. No.

Name of Road

Length (in Km)

Location (in Km) PDC Present Status From To

1 Approach Digaru bridge (both sides)

2.29 687.505 689.800 2012 Work Completed.

2 Digaru-Tezu-Tohangam

15.485 689.800 705.285 2014 Physical progress-12.20%

12.390 705.285 717.675 2014 PCCF, Itanagar has been requested for early issue of AIP by a letter on 31st Aug. 2013.

17.425 717.675 735.100 2015 Realignment proposal approved. Corrigendum issued on 27th Aug. 2013 and preparation of feasibility report in action.

3 Tohangam-Hayuliang

76.00 0.000 76.000 --- Corrigendum to Adm approval issued on 27th Aug 2013 for AE preparation of DPR. Preparation of feasibility report in action

4 Hayuliang-Changwinti-Hawai (last 15 Km with State PWD)

65.00 0.000 65.000 2016

DPR for Khupa-Hayuliang hawai (Km 65) has been submitted to MoRTH dt 18 Jun 2013. Km 45 Hayuliang-Changwinti road to Hawai Joint Inspection with locals has been completed and AE for shifting of utilities submitted other works in action.

9

5. Pasighat – Mariyang -Yingkiong Road (APPWD–140Km):

Sl. no.

Name of Road

Present Status

Physical (in %) Financial (in %)

a Pasighat - Singer River Road (20 km) Physical Progress-50.96%

60.03 %

b Singer River - Sijon Nallah (24km) This section will be awarded on EPC Model, where, LA/FC has to be completed in advance for at least 90% of the road corridor length.

c Sijon Nallah - Mariyang- Gobuk stretch (50.00 km)

Physical progress-10.59% FC not yet issued.

14.79%

d Gobuk-Yinkiong stretch (25 km) Physical progress-15.60%

16.42%

� LA has been completed except in Singer Nallah- Sijoh Nallah section for which estimate has been submitted to MoRTH for sanction.

6. Papu – Yupia - Hoj Road (APPWD–32Km):

Sl. no.

Name of Road Present Status

Physical (in %) Financial (in %)

a Papu-Yupia road (10 km) 65.57% 70.17%

b Yupia – Hoj road (22 km) 57.60% 58.30% c Hoj – Potin road 43.34% 52.47%

� LA has been completed in this road section. All stage-I conditions has been complied for Nyorch Nallah

to Kan Nallah Sector. Final Forest Clearance awaited. Wildlife Conservation Plan for Kan Nallah to 50.00 km, submitted to PCCF on 24/9/2013.

18. Sixty Km missing link (Bridges and approaches to them) between NH-37 and NH-52:

. Sl. No

Segment Length (KM) Ex. Agency

Present Status/Action taken

1

Sadiyaghat to Shantipur on NH 37

28.50 km (Dhola to Islampur)

Assam PWD

The project is under BOT mode. Foundatin of Dhola Bridge is completed. Physical progress is 42%.

10.40 km (Islampur to Shantipur)

Physical progress is 73%.

2

Shantipur- Meka (NH52)

19.50

AP PWD

Physical & Financial Progress is 100% as on 31.8.13. Forest clearance for all stage-I conditions complied by user Agency and final FC awaited.

19. Two-Lane Trans-Arunachal Highway (TAH): The project consists of the following segments:

Sl. No

Name of Segment Length (km)

Executing Agency

Mode of execution

Designated as Original TDC

1 Tawang – Nechiphu 233.00 BRO (Vartak)

GS road NH 229 Mar 2013

2 Nechiphu-Seppa-Sagalee-Hoj

311.00 APPWD Annuity (DoRTH)

NH 229 Dec 2014

3 Hoj-Potin 19.06 APPWD EPC NH 229 4 Potin-Ziro-Daporijo-Aalo-

Pangin 407.00 APPWD Annuity

(DoRTH) NH 229 Dec 2014

5 Pangin-Pasighat 71.06.00 APPWD EPC NH 229 6 Pasighat-Mahadevpur 181.07 APPWD EPC NH 52 2014-17 7 Mahadevpur-Kanubari 266.64 APPWD EPC NH 52B 8 Kanubari-NH 37 link in

Assam 86.00 To be executed by Assam PWD

Total 1574.83

10

1. Tawang–Nechipu (Vartak-233.00 km)

A. Present Status:

Bomdila By-pass – Land acquisition has been inordinately delayed due to non finalization of compensation cases under Sinchung sub-division of Bomdila Sadar and Dirang Jurisdiction. The finalization of the compensation issue has been pending for more than one year. All efforts to impress upon the Civil Administration for early finalization have not fructified. Presently, the Land acquisition process is stalled and the contractual action for construction of the bye-pass is being delayed. Dirang By-pass – Representations have been made by the locals against the compensation finalized by the earlier constituted BOO. Hence, the proposed alignment is under dispute stands cancelled. New BOO has to be constituted by the Civ Adm to finalise a fresh alignment and subsequent to the above BOO will finalize the assessment of compensation. The construction of Dirang bye-pass will commence only after the above actions are completed. Jang By-pass – The alternative 4thalignment for Jung bye-pass has already been surveyed and alignment plan forwarded to ADC Jang for verification. The same is awaited from ADC Office. B. Decisions taken in the meeting: � All the three Bye-pass issues must be resolved by 15th October 2013.

[Action: BRO, DC (Tawang/West Kameng]

2. Nechipu – Seppa – Sagalee – Hoj ( APPWD -311.00 km)

� Land Acquisition: Final Forest Clearance obtained for entire length. Project is under DBFOT Mode with MORTH. Appointed date (commencement) has been fixed by MoRTH on 18.7.13.LA completed and 91% length handed over to Concessionaire.

3. Hoj – Potin (APPWD-19.06 km)

� Physical Progress is 43.34%. � Financial Progress is 52.47%. � Forest Clearance: All Stage-I conditions complied by the User Agency.

4. Potin – Ziro – Daporijo –Aalo – Pangin (APPWD- 407.00 km)

1 Potin to Bopi / Godak Forest Clearance: Final Forest Clearance obtained on two segments Viz Potin to Bopi (157.27 Km) on 27th May 2013 and Bame Trijunction- Aalo- Gabu stream (55.31 Km) on 14th January 2013. All pending Stage-I conditions for the remaining sectors Viz Godak to Tai (141.39 Km). Tai- Bame junction (38.43 Km) compiled by both the user Agency and Forest Department. Final Clearance awaited for these three segments. Other issues related to LA: LA assessment being done by DCs.

2 Godak / Bopi to Tai

3 Tai to Bame

4 Bame to Aalo

5 Aalo to Pangin

5. Pangin-Pasighat (APPWD-76km)

Sl. no.

Sub Category Present Status

1 Package-I (0-28 km)

To be awarded on true EPC Model.

Forest Clearance Stage-I has been received for two forest proposals on this road viz Pasighat-Pangin(0.00 to 20 Km) and Pasighat-Pangin (20.00 to 56.00 Km). All stage –I conditions compiled by the user Agency for 0.00km to 20.00 km. Final Forest clearance awaited. For the entire section, Wildlife Conservation plan submitted to PCCF on 24.9.13. Land Acquisition This has been completed in package II/III/IV. LA estimate for package-I submitted to MoRTH.

2 Package-II (28-42 Km)

Physical Progress is 25.45%. Financial Progress is 48.40%.

3 Package-III (42-59 km)

To be awarded on true EPC Model.

4 Package-IV (59-76 km)

Physical Progress is 33.01%. Financial Progress is 55.97%.

11

6. Pasighat-Mahadevpur (APPWD-181.07 km)

� Forest clearance: Stage-I Clearance for both the Dibang Road & Bridge system and the Lohit Road & Bridge system has been received. Forest payments included in the LA package estimate submitted to MORTH during Sep 2012 and cleared in HPC on 13th sept 2013.

� Foundation work completed for Lohit Bridge (span 2.10 Km) and casting of 370 decking segments completed out of 643 segments. Sub-structure piling completed for 15 nos. and 2 nos. piling works in progress in Dibang Bridge (span:5.17 Km).

7. Mahadevpur-Kanubari (APPWD -334 km)

There are 7 construction packages on this road-

1 Mahadevpur to BuriDihing (33km) Directed for Re-tendering. As per new MORTH guideline all pending packages are to be tendered on new EPC Model (LA/FC has to be completed in advance for at least 90% of the road corridor length).

2 Buri Dihing bridge point to Lalpul (25km)

Sanction of DPR is awaited .Work to be awarded under new EPC Mode.

3 Lalpul-Manmao-Changlang (68.30km)

Physical progress is 16.20% Financial Progress is 24.90%.

4 Changlang to Tirap boundary (21 km)

Sanction of DPR is awaited. Work to be awarded under new EPC Mode.

5 Changlang/Tirap boundary to Khonsa(43 km)

Directed for Re-tendering.

6 Khonsa-Tissa-Longding(42.50 km) Physical progress is 25.16% Financial Progress is 30.77%.

7 Longding to Kanubari (50 km) Sanction of DPR is awaited. Work to be awarded under new EPC Mode.

� There are 7 forest diversion proposals on this road-

1 Mahadevpur to DirakNallah Forest Clearance: Stage-I/AIP has been received for all the 7(seven) Forest proposals Latest Stage-I received on 26th June. 2013 for New Jhukki to changlang Bye Pass. Forest compensation amounts yet to be received from Forest Deptt. All Stage-I conditions complied by User Agency for

a) Mahadevpur to Dirak Nallah b) Changlang Bye-pass to Laiwang(23.40 km of CK

road) c) 23.40km of CK road to Khonsa. d) Khonsa to Tissa e) Tissa to Kanubari f) Bordumsa/Dirak to New Jhukki

Stage-I Conditions for following segments being complied

a) New Jhukki to Changlang Bye-pass.

2 Bordumsa/Dirak to New Jhukki

3 New Jhukki to Changlang Bye-pass

4 Changlang Bye-pass to Laiwang (23.40 km of CK road)

5 23.40km of CK road to Khonsa

6 Khonsa to Tissa

7 Tissa to Kanubari

12

Trans-Arunachal Highway works implemented by BRO and the progress is as under:

Status of land Allotment to Arunank: DC, Capital Complex, Itanagar dated 10/4/2013 addressed to the Director of Land Management intimated to refund the money to BRO. Money has not yet been refunded by Land Management Department.

Taliha-Tato road (Brahmank-100.00Km)- Tato End

Sl. no.

Road Status given by Brahmank

1 0-15 Km Work suspended for want of approval of revised DPR .Reply to observations on revised DPR submitted to MoRTH on 27/8/2012.Inspective report of RO sent to MoRTH.

2 15-30Km Reframed DPR planned to be submitted by March 2014. 3 30-50Km DPR being prepared through consultancy. L1 based AE submitted to MoRTH.

Sl. No.

Name of Road

Length (Km)

Location (in Km) Physical Progress (%)

Financial Progress (%)

Executing Department From To

(i) Jonai-Pasighat-Ranaghat (Km 510 to km 550.150 on NH-52)

40.15 510.000 522.000 100% 98.51%

BRO (Brahmank)

522.000 536.000 23.42% 536.000 550.150 94.90%

(ii) Ranaghat-Mebo-Dambuk -Bomjir (Km 550.150 to km 613.500 on NH-52)

63.35 550.150 566.290 Physical progress is 96.84% PDC-March 2014

BRO (Brahmank)

566.290 583.450 Physical progress is 43.03%, PDC - March 2014 Case for diversion of forest land pending with MoEF,New Delhi.

583.450 595.000 DPR approved in principle by HPC of MoRTH.AA/ES awaited. Direction for diversion of forest land between Silluk and Siseri has been issued by MoEF. AIP from km 597.00 to km 605.60 is awaited. This case has been forwarded to CCF Tezu for early action. PDC - March 2015

595.000 613.500 Physical progress is 60.95%, PDC- 2014

BRO (Brahmank)

Km 594.945 (Bridge) Physical progress of 200m long Sissari bridge is 50.03%. PDC- 31st May 2014.

(iii) Bomjir-Iphipani-Meka (NH-52) Dibang Bridge

18.95 613.500 632.450 Piling of 4 bridge foundation in progress

(iv)

Meka-Roing-Koronu-Paya-Digaru (NH-52)

47.20 632.450 650.615 50.32% 71.1% BRO (Udayak) 650.615 679.650 62.12%

86.50%

(v) Digaru-Alubarighat-Chowkham (NH-52 via Alubarighat) Lohit Bridge

12.50 679.500 806.750 All the piers of the Lohit bridge have been constructed.

On BOT under MoRTH.

(vi) Chowkham-Namsai-Dirak

38.25 806.750 832.000 34% 28.8% BRO (Udayak) 832.000 845.000 100%

13

Taliha-Tato road (74 Km)- Taliha End(Arunank)

Sl.no. Road Present Status

1 0-15 Km Physical progress - 52.00% Financial progress- 85.60%

2 15-30Km Physical progress - 12.18% Financial progress- 22.02%

3 30-50Km Work not started due to non-connectivity and inaccessibility. 4 50-74 km Once connectivity established upto km 50.00, then RSTC can be carried out

and DPR will be initiated. Bile-Migging road (Brahmank-93.00 Km)

(Bile End) 0-15 Km Physical Progress is 44.51% 15-30 Km Reframed DPR under preparation and will be submitted by March 2014. 30-52 Km Departmental Survey under process for preparation of DPR.

(Migging End)

0-10 Km Work suspended for want of approval of revised DPR. Revised DPR submitted to MoRTH on 13/7/2012.

10-38 Km Physical Progress is 18.23%.

It was decided that Executive Engineers will submit weekly progress to the Chief Engineers,

who will in turn brief the Commissioner, PWD. Commissioner, PWD will submit a monthly progress report to the Chief Secretary.

It was decided that the Commissioner, PWD will review the progress of all Road projects prior

to the SLMC and brief the committee on progress, pending issues before the Committee. In the end it was decided that all concerned must strictly adhere to the timelines of the

decisions taken in the meeting and pending action points of previous meetings and also send a status note to the Secretary (Planning) on compliance of the decisions.

Sd/-

H.K Paliwal Chief Secretary

Memo No. PD/PMP/01/2008(Vol-I) Dated Itanagar, the 15th Nov’ 2013

Copy to:

1. PPS to Hon’ble Chief Minister, Arunachal Pradesh, Itanagar. 2. PS to Chief Secretary, Govt. of Arunachal Pradesh, Itanagar. 3. PCCF/Development Commissioner/Principal Secretary(PWD)/Commissioner(RWD)

Commissioner (LM)/ Commissioner (Civil Aviation)/Secretary (PHE&WS)/Secretary(Power), Govt. of Arunachal Pradesh, Itanagar for information and necessary action.

4. Chief Engineer(PWD-D&P)/(EZ)/ (WZ)/ (Highways-EZ/WZ)/ (Power-WEZ/EEZ)/ (PHE&WS)/ (RWD)/ (Hydro-Power)/ CEO(ARRDA), Govt. of Arunachal Pradesh, Itanagar for Information and necessary action.

5. General Manager, N.F Railway, Maligaon, Assam. 6. Chief Engineer (Project-Udayak)/ (Project-Vartak)/ (Project-Arunank)/ (Project-Brahmank )99 APO. 7. Executive Director, NHPC, Itanagar. 8. Head of the Pare Project, NEEPCO Doimukh. 9. Director (Civil Aviation)/ Director (LM)/ Director (APEDA), Govt. of Arunachal Pradesh, Itanagar 10. Deputy Commissioner, Tawang District / West Kameng District/ East Kameng District / Kurung kumey

District / Upper Subansiri District/ Lower Subansiri District/Papumpare District/ Upper Siang District / East Siang District / West Siang District / Lower Dibang Valley / Dibang Valley District/ Lohit District / Anjaw District / Changlang District/ Tirap District/DC Capital, Itanagar for information with a direction to hold the DLMC meetings on quarterly basis without fail and submit the report to the Planning Department.

14

ANNEXURE-‘A’

LIST OF OFFICERS PRESENT IN THE 24th

REVIEW MEETING OF STATE LEVEL MONITORING

COMMITTEE FOR PM’S PACKAGE HELD ON 30-9-2013 & 01-10-2013 AT 0930 HRS IN THE

BANQUET HALL.

Sl/No. Name of Officers Designation

01. Dr H.K Paliwal Chief Secretary

02. Shri Sonam Chombay Secretary (Planning)

03. Shri Daulat Hawaldar Secretary (Finance)

04. Shri Ganesh Koyu Comm. & Secy. (PWD)

05. Shri B Pertin IAS Comm. & Secy. (Land)

06. Shri Sanjay Kumar Saxena Secy. (Power)

07. Shri J Anaw Secy. (Civil Aviation)

08. Shri T H Tayung Secy.(RWD)

09. Shri M S Negi CF, (Con.)

10. Shri Hage Appa CE(Highways)-WZ

11. Shri Toli Basar CE(Highways)-EZ

12. Shri Yogindet Kotha CE (Civil), Itanagar.

13. Shri Yogindra Kotha CE,(NHPC)

14. Shri Pura Tape CE ,Hydro Power ,W/K

15. Shri Lipe Ete CE ,Hydro Power ,E/K

16. Shri O Moyong CE ( P) ,EZ

17. Shri Ennyo Nankar Dir(Land Management)

18. Shri A K Sharma EE /NF Railway

19. Shri Marki Loya Director APEDA

20. Shri Chandrama Prasad SO-II(Plg)-Arunank

21. Shri S.Sumnyan SE ( Highways),PWD

22. Col. Raghavendra Sharma Off. Cdr 756 BRTF- ARUNANK

23. Col. Raman Kumar S.V Cdr,23 BRTF-ARUNANK

24. Col. Devendra Singh Dir (W&B),HQ-UDAYAK

25. Col. M K Sharma Dir (W&B),HQ-BRAHMANK

26. Shri Nikesh Chandra JE,Dir(plg),HQ -VARTAK

27. Shri Moto Basar SE(Pkd)(DHPD)

28. Shri M Debnath GM, Pare Hydro

29. Shri B Taye JE/wc/NF Railway

30. Shri T Doke Asst. Director(LM)

31. Shri Tage Talio SSW (WZ)-PWD

32. Shri T Kamki SE CC(PWD)

33. Shri W M Shambharkar SE & RO,MoRTH,Ita.

34. Shri Sania Ngurang Coordinator NEEPCO

35. Shri M Dirchi DPO Roing

36. Shri Marjum Karga DPO, Yupia

37. Shri R Srivastava EO,NHPC Ltd

38. Shri S Bhatacgarjee DGM (C) Pare HEP

39. Shri Techi Hitlar LRSO

40. Shri Mokir Ori Joint Director(PPP/PMU)

41. Shri L R Roy SRA(PPP/PMU)

43. Shri Tapo Yorung RA(PPP/PMU)