minutes of - wrpc.nic.in

41

Upload: others

Post on 27-Feb-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Minutes of2nd REIF (Renewable Energy Integration Forum)

Meeting in Western Region at WRPC on 21.08.2017.

A meeting of 2nd REIF of Western Region was held on 21.08.2017 at WRPC

Mumbai. List of participants is attached herewith.

Member Secretary, WRPC welcomed all the participants of 2nd REIF meeting in

Western Region. He stated that with increasing RE penetration, the issues

related to system operation as well as RE generation needs to be discussed and

resolved addressing the issues for maximum utilization of RE generation &

optimum utilization of conventional generations. He stated that following points

are to be covered during the meeting:

I. Effect of variability of RE generation.

II. Transmission & distribution constraints in integration of RES

III. Telemetry/Communication

IV. Compliance of CEA/CERC Regulation on LVRT

V. Voltage regulation by RES

VI. ForecastingVII. Any other issues if any.

He requested all concerns for active participation to amicable resolution of

issues. Thereafter he requested Executive Engineer (Opn) to take up the

agenda items.

Executive Engineer (Opn), WRPC welcomed all the participants once again. He

stated that agenda items are in following three folds:

1. System Operation’s concerns.

2. RE generators concerns.

3. Regulatory compliances.

Item no.1 Effect of variability of solar & wind generation

1. Effect of variability of RES generation, assessment of loss of generation &revenue, because of backing down of cheaper source of conventionalgeneration.

2. Proposed utilization of State’s own balancing plants.3. Losses in DSM purely on account of variability of renewable generation.4. Any measure taken by WRLDC/SLDC for economical green energy

absorption in the grid or any proposed plan.

Discussions:

Chief Engineer, SLDC Maharashtra stated that variability of RES

penetration has huge impact on backing down of cheaper source of

conventional generation, balancing from state resources and finally on DSM,

which leads to huge commercial impact on state system. Due to lack of

telemetry of RES, it is difficult for system operators to take decision. He told

that blind operation of several RE sources may be one of the challenges for

the system operators. MP & Gujarat endorsed the same.

Chief Engineer, SLDC Gujarat suggested that better telemetry & forecasting

may help in system operation & finally reduce the commercial impact.

Member Secretary, advised RE generators to furnish the FTP data as well as

real time data. He further requested SLDC’s for better forecasting of RE

generation.

The participants noted as above.

Item no. 2 Transmission & distribution constraints in integration of RES

Any Transmission & distribution constraints faced by STU/Discom inintegration of RES generation, if so necessary augmentation of T & Dinfrastructure which needs to be undertaken- scope & financial estimates forthe same shall also be discussed.

Discussions:

Executive Engineer (Opn), WRPC requested WRLDC for making a presentation

on RE scenario in WR. CM, WRLDC made presentation on the same (copy

enclosed).

During the presentation, WRLDC stated that the maximum generation from

Wind RES in Western Region was 7885 MW at 1100 hrs on 04.07.2017 which

was around 21 % of the instantaneous demand met in the region. At the State

level the maximum generation from Wind RES in Gujarat was 3763 MW on

05.07.2017 (35.1% of demand met); in Maharashtra was 3002 MW on

24.07.2017 (18.1 % of demand met); in Madhya Pradesh was 1779 MW on

25.07.2017 (34.7 % of demand met). Conventional generation was backed

down and few of the thermal units were taken under reserve shutdown and the

entire generation from RES was absorbed.

It was stated by WRLDC that no transmission constraints were experienced for

evacuation of RES in Western Region in this season even when the penetration

of RES in MW terms as well as MWh terms was significantly high.

Representative from States endorsed the same.

CE, SLDC Maharashtra stated that transmission planning for evacuation of RE

generation is under STU. They planned after detailed study & then only allow

any connectivity. Other SLDC’s representative endorsed the same.

Member Secretary, WRPC suggested that it is essential to monitor all the green

corridor project & requested all RE developers to adhere with timelines of the

ongoing green corridor transmission projects.

The participants noted as the same.

Item no.3 Telemetry/Communication

With increase in high penetration of wind into the grid it is very much requiredthe visibility of Renewable generation at Control Centers SLDCs and RLDC .The system operator is almost blind folded in real time with non -availability ofreal time data about huge quantum of wind generation and solar generation .As per IEGC clause 5.2(u) Special requirements for Solar/ wind generators

Quote:“System operator (SLDC/ RLDC) shall make all efforts to evacuate theavailable solar and wind power and treat as a must-run station.However, System operator may instruct the solar /wind generator to backdown generation on consideration of grid security or safety of any equipment orpersonnel is endangered and Solar/ wind generator shall comply with thesame. For this, Data Acquisition System facility shall be provided fortransfer of information to concerned SLDC and RLDC.(i)SLDC/RLDC may direct a wind farm to curtail its VAr drawl/injection in casethe security of grid or safety of any equipment or personnel is endangered.(ii) During the wind generator start-up, the wind generator shall ensure thatthe reactive power drawl (inrush currents in case of induction generators) shallnot affect the grid performance. "

Unquote:

IEGC Clause 6.2Quote“This code also provides the methodology for re-scheduling of wind and solarenergy generators which are regional entities, on one and half hourly basis andthe methodology of handling deviations of such wind and solar energygenerators. Appropriate meters shall be provided for accounting of charges fordeviation under DSM Regulations. Telemetry/communication system &Data Acquisition System shall also be provided for transfer of informationto the concerned SLDC and RLDC.”Unquote

The first meeting of Renewable Integration Forum was held at WRPCSecretariat on 21.04.2017 with wind developers of Maharashtra, SLDCMaharashtra , WRLDC and WRPC. The outcome of the First meeting wasextremely successful and within 15 days the visibility of Maharashtra wind atWRLDC has gone to 1660 MW (M/s Suzlon) out of the total Installed capacityof wind of 4662 MW in Maharashtra. Subsequently Panama wind generator of74 MW capacity and Re-Gen of 45 MW started data transfer in 10 minutesinterval through ftp to WRLDC. But no other generators are transferring thewind generation data to WRLDC. As already wind season is peaking up andgeneration is more than 5000 MW everyday , it is necessary to have telemetryat WRLDC.

In last REIF meeting it has been decided that all wind generators ofMaharashtra would furnish the average MW generation in 10 minutes ofintervals to SLDC, Maharashtra. The data shall contain Date, Time, plant,average MW etc. To begin with, this data shall be sent by email to SLDC andSLDC would integrate the data in SCADA and also configure on ICCP forWRLDC. Further this is an interim measure to enhance the visibility of REGenerator in Maharashtra and facilitate the load dispatchers in the immediatewind peak season. For Medium term measures it is to integrate the poolingstation wise real time data to SLDC and as a long term arrangement, STU shallplan to integrate the RE data from pooling station to SLDC.SLDC shall soon develop a web portal to facilitate the data entrydirectly/uploading of file in the next step.

The status of RES telemetry in Maharashtra and WRLDC in the month ofAug’17 is given below. The observability of RES telemetry in Maharashtra is55%.

Following Wind developers in Maharashtra are sending pooling data to WLRDCvia FTP

S.No Wind developer Installed capacity of Wind whosedata is being pooled through FTP(As informed by Wind Developer)

1 Suzlon 1663 MW

2 Regen 507 MW

3 Continum 80 MW

4 Gamesha 247 MW

5 Panama 72 MW

6 Reliance Global 45 MW

Total 2614 MW

Following Wind developer’s data are in pipeline for pooling data to WLRDCvia FTP

1. Senvion/Kenersys2. Maruti Wind3. Windword/Enercon4. TS Wind5. Inox Wind6. Vestas Wind

The present status of Telemetred RES at WRLDC is as followsState/Regio

nRES

InstalledCapacity

(Wind+Solar)in MW

Telemetered RESCapacity at

WRLDC(Wind+Solar) in

MW

% of RESVisibility/Observabilit

y at SLDC/WRLDC

Gujarat 6578(5348+1230)

6566 (5339+1227) 99.8

Maharashtra 5145(4769+376)

2844 (2614+230) 55.3

MadhyaPradesh

3263(2428+835)

3213 (2378+835) 98.5

Chhattisgarh 76 (0+76) 66 (0+66) 86.8Diu 10 (0+10) 0 0Daman 4.1 (0+4.1) 0 0WR 15076

(12545+2531)

12689(10331+2538)

84.2

Discussions:

a) WRLDC

WRLDC stated that telemetry of RES is mandated by IEGC regulation 5.2 (u)

and 6.2 and it is essential for real-time supervision of the grid and

facilitating must run despatch of the RES. A comparison of the RES

telemetry and the post despatch RES generation data submitted by SLDCs

was shown in presentation. It was noted that the figures were matching for

Gujarat and Madhya Pradesh but there was a huge difference between

telemetry and actual injection of RES in Maharashtra.

It was explained that during the 1stREIF meeting it was decided that the

RES whose real-time telemetry is not available in SLDC shall provide the

RES injection to SLDC and WRLDC at every 10 minute interval through file

transfer protocol (FTP) as an interim measure. Subsequently the real-time

telemetry from RES shall be provided to SLDC and WRLDC on IEC 104

protocol.

WRLDC shared that only 58.86 % of installed RES capacity in Maharashtra

was observable via ftp / SCADA whereas in Gujarat and Madhya Pradesh

the observability of RES is 99.83 % and 97.94 % of the installed RES

capacity respectively.

WRLDC informed that the data from Senvion/Kenersys, Maruti Wind,

Windword/Enercon, TS Wind and Vestas Wind through ftp was still

pending.

WRLDC representative stated that to avail the must run status, visibility in

real time at control center is mandated as per IEGC.

b) SLDC, Maharashtra

CE SLDC, Kalwa stated that cyclic data through ftp was not made available

from several RES in Maharashtra even after four months of the 1st REIF

meeting and notice for disconnection from grid had been issued to them by

MSEDCL in line with their PPA. SLDC Kalwa explained that the format for

sending the cyclic data (through ftp) was available on their website at the

following URL http://mahasldc.in/re-data/.

He further stated that a separate project for establishing communication

link from the STU pooling points to SLDC-Kalwa and for commissioning

RTUs at STU substations had been envisaged in Maharashtra. MSETCL was

requested to expedite execution of the project and it was decided that

Concerned representative from MSETCL may be invited in the next meeting

to apprise about the progress of the above project.

SLDC, Kalwa informed that they are receiving real time data of wind RES

from some of the pooling stations. WRLDC requested SLDC, Kalwa to

provide the same to RLDC on ICCP.

c) RE Developers

M/s Suzlon informed that they will be providing real time data of their wind

farms at SLDC, Kalwa in 4 to 6 weeks.

The RES developers committed to provide the cyclic data through ftp within

15-days and requested MSEDCL to allow them to reconnect to the grid so as

to avoid the generation loss in the high wind season. MSEDCL stated that

the concern of the RES shall be conveyed to their management for decision.

Member Secretary requested all RE generators to transfer the data toSLDC/RLDC in static/real time.

The group noted as above.

Item no. 4 Compliance of CEA/CERC Regulation on LVRT

LVRT/FRT is a capability of an electrical device to operate through periods of

low grid voltage. LVRT provision in a device viz. Wind/Solar Generator boosts

the terminal voltage at the grid interconnection point following voltage dip

caused by a transient fault, thereby providing transient stability support

Regulation Part II (B2) (3) and Part II (B3) of the CEA (Technical Standards for

Connectivity to the Grid) Amendment Regulations, 2013 notified on 15th

October 2013 mandates as under:

“B2. For generating station getting connected on or after completion of 6months from date of publication of these Regulations in the OfficialGazette.

(3) Wind generating stations connected at voltage level of 66 kV and above shall

remain connected to the grid when the voltage at the interconnection point on

any or all phases dips upto the levels depicted by the thick lines in the

following curve:

Provided that during the voltage dip, the individual wind generating units in

the generating station shall generate active power in proportion to the retained

voltage;

Provided further that during voltage dip, the generating station shall maximize

supply of reactive current till the time voltage starts recovering or for 300 ms,

whichever time is lower.”

“B3. For generating units which are connected before and upto 6 months after

the date of publication of these Regulations in the Official Gazette

The generating company and the licensee of the electricity system to which the

generating station is connected shall mutually discuss and agree on the

measures which can be taken to meet the standards specified in (B1) and (B2)

subject to technical feasibility.”

With regards to LVRT compliance by wind generators commissioned before

15.04.2014, Hon’ble Central Electricity Regulatory Commission vide its order

dated 05.01.16 in Petition No.420/MP/2014 mandated that

“………We are of the view that LVRT should be implemented for all windturbines commissioned before 15.4.2014 and connected to voltage levelof 66 kV and above except for Stall Type WTGs, which are not

technically feasible to be retrofitted with LVRT. However, keeping in viewthe suggestions of IWTMA, we are of the view that presently LVRT shouldbe implemented for all wind turbines (except Stall Types) commissionedbefore 15.04.2014 having installed capacity equal to or more than 500KW.”

Vide the same order CERC advised monitoring of installation and performance

of LVRT on existing LVRTs. Relevant extracts are quoted below:

“…….With regard to monitoring of the installation and performance ofLVRT installed on existing WTGs, we direct SLDCs to prepare quarterlyreports and submit it to RPCs. RPCs are directed to validate the reportssubmitted by SLDCs in consultation with RLDCs and report anydeficiency and non-compliance to the Commission in accordance withlaw.

In view of the above, grid connected Wind Generators shall be LVRTcompliant.

Discussions:

WRLDC stated that as per the CEA Technical Standards, the LVRT /FRT

facility is mandated for all Wind RES connected at 66 kV level so that they

remain connected to the grid even if the voltage dips to 0.15 pu for 300 msec at

the interconnection point and the subsequent voltage recovery is better than

the given curve. It was explained that the loss of wind generation during a

voltage dip caused by fault could lead to major disturbance in the grid.

WRLDC shared that the CERC order dated 05.01.2016 mandated that all Wind

RES commissioned after 15.04.2014 shall ensure LVRT/FRT facility while

those commissioned before 15.04.2014 may go for retrofitting.

Further vide order dated 05.01.16, CERC mandated that presently LVRT

should be implemented for all wind turbines ( except stall type) commissioned

before 15.04.14 having installed capacity equal to or more than 500 kW.

WRLDC shared that the information from RES in Maharashtra was still

pending and Gujarat and Maharashtra have submitted partial details of LVRT.

SLDC, Maharashtra was requested to submit the LVRT details and RES

developers from Gujarat and Madhya Pradesh were requested to furnish the

missing details in the data submitted by them. The capacity which are

exempted from LVRT compliance (stall type turbines and turbines with up to

500 KW capacity) shall also be informed explicitly.

Member Secretary requested all states to indicate the presentmethodology of checking LVRT compliance in vogue for giving clearancefor integration and update the status of LVRT compliance.

The group noted the same.

Item no.5 Voltage regulation by RES

As per section 16.4 of the CEA's Manual on transmission planning criteria,

"The wind and solar farms shall maintain a power factor of 0.98 (absorbing) at

their grid interconnection point for all dispatch scenarios by providing

adequate reactive compensation".

In addition to the above, the manual on transmission planning criteria states

that there shall be no reactive power flow UP through 400/220 kV, 400/132

kV, 220/132 kV, 220/66 kV whenever voltage on HV side of such ICT is more

than 1.025 per unit.

Severe high voltage is observed at various locations in WR grid particularly

when the injection from RES is high.

At the interstate level there is a mechanism for voltage dependent reactive

energy settlement. Reactive charges are payable for MVAR injection at voltage >

103% of nominal. Similarly Reactive charges are payable for MVAR drawal at

voltage < 97% of nominal at the interface point.

SLDC Maharashtra, Madhya Pradesh and Gujarat may apprise OCCregarding the following

Tariff structure for Reactive Energy exchange by RES in their States

Constraints if any for utilizing the available capability of RES for

voltage regulation.

Discussions:

During the presentation, WRLDC showed the voltage profile of 400/220 kV

Karad (Maharashtra) substation vis-à-vis RES generation in Maharashtra. It

was explained that with high injection from RES the net load in the Karad and

Kolhapur area reduces significantly and cause flow of Active and Reactive

power from LV side to HV side of the ICTs. This was causing further increase in

the voltage at the EHV level. WRLDC said that above scenario was contrary to

the provision of the CEA manual on transmission planning criteria states that

“the wind and solar farms shall maintain a power factor of 0.98 (absorbing) at

their grid interconnection point for all dispatch scenarios by providing

adequate reactive compensation and there shall be no reactive power flow up

through 400/220 kV, 400/132 kV, 220/132 kV, 220/66 kV whenever voltage

on HV side of such ICT is more than 1.025 per unit. RES developers were

requested to explain whether the Wind turbines could absorb reactive power

from the grid and support in controlling the high voltage.

Representative from Suzlon explained that the DFIG(doubly-fed induction

generator) wind turbines are capable of absorbing reactive power from the grid

and can support in controlling the high voltage but as per the prevailing tariff

the RES were liable to pay charges to the discoms for reactive energy drawal at

the interconnection point. He shared the applicable rate for reactive charges as

under:

Maharashtra: @10 paise per kVArh upto 10% of net active energy

exported and @ 25paise per kVArh above 10% of net active energy

exported.

Gujarat: @10 paise / kVArhupto 10% of net active energy exported and @

50 paise / kVArh above 10% of net active energy exported

Madhya Pradesh: @27 paise / kVArh

Rajasthan: @5.75 paise /kVArh w.e.f. 01.04.2009 escalated @ 0.25 paise

per year

Andhra Pradesh: @25paise/kVArh up to 10% and 50 paise/ kVArh above

10% of net active energy exported.

Karnataka: @40 paise / kVArh

Tamil Nadu: @25 Ps./kVArh up to 10% and 50 ps/ kVArh above 10% of

net active energy exported.

The matter was deliberated and it was opined that it might be better if the

reactive charges are made voltage dependent in line with the ISTS reactive

energy settlement instead linking it to power factor. This would be helpful in

reducing the expenditure on reactive shunt compensation at the LT as well as

EHV level.

It was decided that the above suggestion could be forwarded to SERCs, CEA

and CERC.

The group noted the same.

Item no.6 Forecasting

Though Renewable Energy Sources are variable in nature, it could be forecastedwith fair accuracy as it is being done in many renewable rich countries. Forsystem operator , the error shall be as minimum as possible. High qualityforecasting and confidence in the forecast are necessary to aid management ofbalancing energy from conventional plants. Considering high penetrations ofWind generation is gradually increased energy in May to September forecasting ofRE generation is utmost important for smooth and reliable system operations.

As per IEGC 5.3(g)

“The SLDC shall take into account the Wind Energy forecasting to meet theactive and reactive power requirement.”

And IEGC 6.5.23(ii)

Quote

“(ii) Forecasting shall be done by wind and solar generators which are regionalentities as well as the concerned RLDC. The concerned RLDC may engageforecasting agency(ies) and prepare a schedule for such generating stations.The forecast by the concerned RLDC shall be with the objective of ensuringsecure grid operation. The forecast by the wind and solar generator shall begenerator centric. The wind and solar generators which are regional entitieswill have the option of accepting the concerned RLDC’s forecast for preparingits schedule or provide the concerned RLDC with a schedule based on its ownforecast. Any commercial impact on account of deviation from schedule basedon the forecast chosen by the wind and solar generator shall be borne by it.”Unquote

Wind and Solar Generation forecasting & its real time monitoring are importanttools to address variability & uncertainty aspect of its grid integration. State-of-the-art forecasting helps grid operator to manage power system balance foreconomic, reliable & secured operation of the grid even in high RE penetrationregime.

In 1st meeting of REIF, the importance of forecasting were discussed and agreedby one and all. WRLDC agreed to take up a Pilot Project for this wind peakseason to forecast Maharashtra state by using the pooling station level databased on the longitude, latitude, blade dimension and other turbine

parameters. WRLDC have provided the data format and it was agreed thatrequired data will be furnished by wind developers in the prescribed format .

Status of Wind forecast for Maharashtra

WRLDC has entered into an MoU with Manikaran Analytics Ltd. (Forecast

Service Provider) for executing a pilot project to forecast RES generation located

in Maharashtra for six-months. During the last meeting of REIF it was agreed

that turbine level static data and real-time data required for forecasting shall

be made available by the RES developers.

The WTG details has been provided by Suzlon, ReNew, Panama and Orange.

The WTG level real-time parameters for Wind forecast has been provided for

few of the sites at Vaspet4, Jath, Mirkala, Palsi, Valsang and Welturi. Thus the

aggregate Wind forecast is now available at WRLDC for 274 WTGs amounting

to 452 MW capacity in Maharashtra.

Suzlon may expedite resolution of the discrepancies in the WTG details and

also provide real-time data so that the forecast of Suzlon turbines could also be

aggregated in the State level forecast. Other Wind developers also to expedite

sharing of WTG details and provide the real-time data. Once the model is

complete the aggregate State level forecast of Wind RE shall be shared with all

stakeholders.

Summary

Type ofAsset Location

Capacityavailable

(MW)ClientName Static detail SCADA

availability

Wind

Welturi 73.5 RenewPower Received Yes

Jath 84.6 RenewPower Received Yes

Valsang

94.5 RenewPower Received Yes

45 ReliancePower Received No

Vaspet 4 49.5 RenewPower Received Yes

Palsi 70.4 Panama Received Yes

Mirkala 80 Panama Received No

Agaswadi Tata Not Received Yes

Khanpur Orange Not Received Yes

Suzlon32 sites 2100 Suzlon Received No

Status of Solar forecast for Maharashtra

For Solar generation forecast a six-month pilot project has been taken up by

WRLDC with Manikaran Analytics for Sakri project of Mahagenco. The

modeling is complete. Forecast as well as real-time Sakri data is available at

WRLDC.

Type ofAsset Location

Capacityavailable

(MW)

ClientName

Staticdetail

SCADAavailability

Solar Sakri 125MAHAGENCO

Received

Yes

Other Solar developers also may share the details and real-time data for having

an aggregate forecast at the State level.

Gujarat and Madhya Pradesh are requested to intimate the forum regarding

the forecast of wind and solar generation for their state.

Issues being faced by RE generators. All Renewable generators solar and

Wind are requested to discuss in details all the issues being faced by them on

Telemetry ,Forecasting or any other issues .

Discussions:CE SLDC, Gujarat informed that RE forecast in Gujarat is being done by RE

Connect Energy Solutions Pvt. Ltd. and is fairly good. For high wind scenario,

the accuracy level achieved is 70-80% and for low wind scenario, the accuracy

achieved is approximately 50%.

WRLDC stated that the RES forecast was being received from SLDC Gujarat in

day-ahead as well as in intra-day while the forecast for RES in Madhya

Pradesh was received only in day-ahead.

WRLDC shared that a MoU with Manikaran Analytics Ltd. had been signed for

a pilot project on forecast of RES in Maharashtra for six months. It was

mentioned that as on date only 50 % of the RES capacity could be covered

under the pilot project as the static data and dynamic data was still awaited

from a large number of RES in Maharashtra. The issues regarding actual

injection data through FTP was also highlighted. The status was appraised as

under:

SrNo.

RES TotalInstalledCapacity(MW)

TotalForecastedCapacity(MW)

Remarks

WRLDC informed that the data provided over FTP by developers is received

with a time delay in range of 10-15 minutes and is intermittent in nature. The

accuracy of the forecasting highly depends on availability of real time data and

continuity of data. RLDC requested SLDC, Maharashtra and all wind

developers to take necessary action to provide real time data for realistic

forecasting.

The group noted the same.

ITEM NO 7. AGENDA FROM GUJARAT

Chief Engineer, SLDC Gujarat vide mail dated 21.05.2017 requested for

discussion of following points:

Declaration and scheduling of all RE generators All the renewable generators should have to comply with CEA (Technical

standard for connectivity to the grid) regulation 2007 and its

amendment.

SN RE InstalledCapacity

(MW)

Covered byFTP

(MW)

Remark

1 Wind 4769 2470 Real Time Data: At Present, delayed active power data of2806 MW is available over FTP. Real time data of all sitesrequired for accurate forecasting. Real time data of Vestas,Windworld. Kenersys, Sri Maruti not available

Static Data: Static data of Vestas, Windworld. Kenersys, SriMarutiyet to be furnished by the developers

2 Solar 376 125 Real time active power is available for 230 MW. Real time dataof remaining capacity of 146 MW is to be provided by SLDC.

Real Time weather parameters is to be provided for all solarparks.

Sharing of static and real time generation and weather data for better

forecast

Chief Engineer, SLDC Gujarat requested to RE developers to comply the above

points.

The group noted the same.

ITEM NO 8. ANY OTHER ITEMS

Addl Item No 1: INTRODUCTION OF WIND/SOLAR GENERATORS

The domain of renewable energy operates with multiple agencies viz. REdevelopers, RE generation owners, STU, SLDCs, RLDC and Regional PowerCommittee (RPC). The integration of RE in the grids thus demands a platformwhere exchange of information and ideas can take place with determinedobjectivity of fully utilizing the installed RE capacity with security of the grid.

Solar and Wind generators are new members of National Grid and they are tobe very familiar with all other entities. In this context all solar and windgenerators are requested to give a small presentation with details of theirgenerating plants in the States of Western Region. The information of REshall also to be submitted as per format attached at Annexure –1.

All RE Developers are requested to submitted introductory information ofindividual developers in format attached at Annexure –1

The group noted the same.

Addl Item no. A-2 : Integration of new RES connected to ISTS:

Status of RES for connectivity to ISTS: The following ISTS connecting RESare to be commissioned in near future. The members please update the statusof commissioning of the wind/solar parks.

Sl.No.

Organization Name GeneratingStationLocation

Capacity

Seekingconnectivity(MW)

Date fromconnectivity reqd

Grantedconnectivityfor

TentativeCommissioningdate

1 WIND WORLD (INDIA)LTD MUMBAI

Bhuj 500 500 31-Mar-17 500

2 INOX WINDINFRASTRUCTURESERVICES LIMITED

KACHCHH

500 500 30-Jul-17 500

3 Kachchh 500 500 01-Jul-17 500

4 GAMESA RENEWABLEPVT LTD

Bhuj 100 100 31-Mar-17 100

5 DHAR 218 218 31-Mar-17 Accepted andunder process

6 KP ENERGY LIMITED Kutch 400 400 25-May-17 Accepted andunder process

7 Kutch 400 400 25-May-17 Accepted andunder process

8 Kutch 400 400 25-May-17 Awaiting forAcceptance

9 Kutch 400 400 25-May-17 Awaiting forAcceptance

10 GUJARAT POWERCORPORATION LIMITED

BANASKANTHA

700 700 31-Dec-17 700

11 RENEW POWERVENTURES PRIVATELIMITED

Kutch 400 400 15-Dec-17 400

12 REWA ULTRA MEGASOLAR LIMITED

Rewa 500 750 31-Mar-17 750

13 KADAPA WIND FARMSPRIVATE LIMITED

BHUJ 100 100 31-Mar-17 Accepted andunder process

14 SRI MARUTI WINDPARK (MENDIGIRI)PRIVATE LIMITED

KucthDistrict

400 400 20-Jun-17 Awaiting forAcceptance

WRLDC shared that several pooling stations and transmission schemes were

under implementation under the Green Energy Corridor and requested the

developers to share the progress of the RES projects so that the development of

transmission projects could be matched with the RES projects. The developers

were also advised to refer the CERC regulations for connectivity and first time

charging for smooth integration of upcoming RES at ISTS level.

WRLDC informed that Hon’ble CERC hadapproved the “ Procedure for

Implementation of Framework on Forecasting, Scheduling and imbalance

Handling for Renewable Energy Generating Stations including Power Parks

based on Wind and Solar at Inter State Level andthe same was available on

CERC website at http://www.cercind.gov.in/2017/regulation/pro.pdf

It was also informed that all new RES intending to get connected at ISTS shallsubmit data in prescribed formats to WRLDC for First Time Charging (FTC), asapproved by CERC in above procedure.

It is requested to all RE developers shall submit the requisite documentsin advance as per approved procedure for connectivity to ISTS.

ITEM NO 9 DATE & VENUE OF NEXT MEETING

****************************

Annexure-I

Format for Wind Generators

State- Maharashtra/Gujarat/Madhya Pradesh

Sr. Particulars Applicant's Details

No.

1 Name of theGenerating Company

2 Address of theGenerating Company

Name :

Designation :

Address :

3Nodal Officer's Name & contact Contact Details :

Details Office No :

Fax No. :

Mobile No :

Email ID :

Location of the Generating Station

5 Total Installed Capacity

6 Connectivity /Voltage Level

7 Turbine Type & Specification

8 Optimal/Rated Wind Speedfor Turbine

9 Maximum/Minimum WindSpeed of Turbine

10 Maximum Power that canbe Generated by WindTurbine

18 Any other information useful for assisting efficient Grid Operation

Signature of the Authorized

Officer

Note- Please submit the details state-wise. A Generating station having location say both inMaharashtra & Gujarat to submit two separate forms.

Format for Solar Generators

State- Maharashtra/Gujarat/Madhya Pradesh

Sr.

Particulars Applicant's DetailsNo.

1 Name of theGenerating Company

2 Address of theGenerating Company

Name :

Designation :

Address :

3Nodal Officer's Name & contact Contact Details :

Details Office No :

Fax No. :

Mobile No :

Email ID :

4 Location of theGenerating Station

5 Total Installed Capacity

6 Connectivity /Voltage Level

7 Module type (Thinfilm/ polycrystalline)

8 Longitude

9 Latitude

10 Any other information useful forassisting efficient Grid Operation

Signature of the Authorized

Officer

Note- Please submit the details state-wise. A Generating station having location say both inMaharashtra & Gujarat to submit two separate forms.

01/09/2017

1

Welcome to participants in2nd Meeting of

Renewable Energy IntegrationForum(REIF) of Western Region

Outline of the Presentation:1. General Overview of Renewable Energy Sources in Western Region.2. Telemetry Requirements/issues.3. Low Voltage Ride Through (LVRT) requirement and issues.4. Forecasting of Wind RES in Western Region.5. Voltage Regulation by RES6. Integration of new ISTS connected RES

Type Wise Capacity

Total InstalledCapacity – 330 GW Renewable:

58 GWPeak Demand met:

160 GW

Indian Power Scenario

Coal, 194433, 59%

Gas, 25185, 8%

Diesel, 838, 0%Nuclear, 6780, 2%

Hydro, 44614, 14%

Wind, 32508, 10%

Solar, 13114, 4%

Bio power, 8296, 2%

Small Hydro, 4385, 1%

RES, 58303, [PERCENTAGE]

Fuel wise Installed capacity (as on 31.07.2017)

Coal Gas Diesel Nuclear Hydro

Wind Solar Bio power Small Hydro

Type Wise Capacity

Total InstalledCapacity – 109 GW

Wind-RE12602 MW

Peak Demand met:51 GW

Western Region Power Scenario

Peak Energy Met1180 MUs

Max Wind Gen.7885 MW

Max Gen – 58786 MW

Max Wind EnergyGen: 169 MUs

Solar-RE2697 MW

Max Solar Gen.1818 MW

Max Solar EnergyGen: 18 MUs

Max RE (Wind+Solar)Gen. 9031 MW

Coal, 70164, 64%

Gas, 11059, 10%

Diesel, 0, 0%

Nuclear, 1840, 2%

Hydro, 7448, 7%

Wind, 12545, 12%

Solar, 2531, 2%

Hydro/Bio, 3336, 3%Other, 18412, 17%

Western Region Fuel wise Installed capacity (as on 31.07.2017)

Coal Gas Diesel NuclearHydro Wind Solar Hydro/Bio

01/09/2017

2

Wind Power Capacity in WR (in MW)

ConstituentsAs on 31.07.2017

(A)Target by Year 2022

(B)Balance (C=B-A)

Gujarat 5405 8800 3395

Maharashtra 4769 7600 2831

Madhya Pradesh 2428 6200 3772

Total 12602 22600 9998

Wind Generation Targets by 2022 in Western Region:

Average WRWind Gen inJuly’17 - 114

Mus

Highest Wind generationState Gen (in MW) Date Time Demand (in MW) on

Max Wind Gen day Penetration (%)

Gujarat 3763 05.07.2017 18:00 10720 35.1

MP 1779 25.07.2017 16:00 5124 34.7

Maharashtra 3002 24.07.2017 12:00 16607 18.1

WR 7885 04.07.2017 11:00 37722 20.9

Full day total WRWind > 6000 MW

Growth in MaxWind Generation(MW) : 22.5%

Max Wind Gen- 169 Mus on25.07.17

Guj- 67 MusMah- 63 MusMP- 39 Mus

Growth in Max WindGeneration (MUs) : 20.7%

01/09/2017

3

WR Wind Generation Jan’17-June’17

Days

June’17

HoursJan’17

Installed Capacity-12545 MWHighest Ever Generation - 7885 MW on 4th July’17CUF -63%

Jul

RES GRID INTEGRATION Requirements for SECURE GridIntegration of RES :

1.Availability of Telemetry: Data visibility of RES atSLDC/WRLDC

2.Low Voltage Ride Through (LVRT)3.Forecasting and Scheduling4.Voltage Regulation by RES

01/09/2017

4

Telemetry Issues IEGC Clauses for Telemetryfor RES

Special requirements for Solar/ wind generators

IEGC Regulation 5.2 (u)• System operator (SLDC/ RLDC) shall make all efforts to evacuate the

available solar and wind power and treat as a must-run station.However, System operator may instruct the solar /wind generator toback down generation on consideration of grid security or safety ofany equipment or personnel is endangered and Solar/ wind generatorshall comply with the same. For this, Data Acquisition System facilityshall be provided for transfer of information to concerned SLDC andRLDC.

• (i) SLDC/RLDC may direct a wind farm to curtail its VAr drawl/injection in casethe security of grid or safety of any equipment or personnel is endangered.

• (ii) During the wind generator start-up, the wind generator shall ensure thatthe reactive power drawl (inrush currents in case of induction generators)shall not affect the grid performance. "

IEGC Regulation 6.2

• This code also provides the methodology for re-scheduling of windand solar energy generators which are regional entities, on one andhalf hourly basis and the methodology of handling deviations of suchwind and solar energy generators. Appropriate meters shall beprovided for accounting of charges for deviation under DSMRegulations. Telemetry/communication system & Data AcquisitionSystem shall also be provided for transfer of information to theconcerned SLDC and RLDC.”

01/09/2017

5

Telemetry of Wind RES in WR• WR Wind RES Installed

Capacity• Wind: 15545 MW

• Visibility/Observability ofWind RES at WRLDC:83.88%

• Maharashtra Wind RESvisibility at WRLDC:58.86%(over FTP)

• Real time visibility ofMasharashtra RES onreliable communicationto be expedited.

State/Region InstalledCapacity Telemetered

% ofVisibility/Obser

vability atSLDC/WRLDC

Gujarat 5348 5339 99.83

Maharashtra 4769 2806 58.86

Madhya Pradesh 2428 2378 97.94

Chhattisgarh 0 0 -

Daman & Diu 0 0 -

DNH 0 0 -

WR 12545 10523 83.88

MAH FTP

MAH FTP

01/09/2017

6

Telemetry of Solar RES in WR• WR Solar RES Installed

Capacity• Wind: 2531 MW

• Visibility/Observability ofSolar RES at WRLDC:93.16%

• Maharashtra Solar RESvisibility at WRLDC:61.17%.

State/Region InstalledCapacity

TelemeteredCapacity

% ofVisibility/Obser

vability atSLDC/WRLDC

Gujarat 1230 1227 99.75

Maharashtra 376 230 61.17

Madhya Pradesh 835 835 100

Chhattisgarh 76 66 86.84

Daman & Diu 10 0 0

DNH 4.1 0 0

WR 2531.1 2358 93.16

Maharashtra Wind RES Telemetry Status

Following developer/IPPS have provided FTP data to RLDC/SLDC.

• Suzlon: 1663 MW• Panama: 72 MW• Regen: 507 MW• Gamesa: 247 MW• Reliance Global: 45 MW• Continuum: 80 MW• Inox Wind: 192 MWTotal 2806 MW

Maharashtra Wind RES Telemetry Status

No FTP data has been received from the following wind developers.• Senvion/Kenersys• Maruti Wind• Windword/Enercon• TS Wind• Vestas Wind

• Total visibility of Maharastra wind RES over ftp at WRLDC is 58.83%.

COMPLIANCE OF CEA STANDARDSW.R.T TO LOW VOLTAGE RIDETHROUGH CAPABILITY (LVRT)

01/09/2017

7

Regulation Part II (B2) (3) of the CEA (TechnicalStandards for Connectivity to the Grid)

• Notified on 15th October 2013 mandates asunder:

• “B2. For generating station getting connected on orafter completion of 6 months from date ofpublication of these Regulations in the OfficialGazette.….

• (3) Wind generating stations connected at voltagelevel of 66 kV and above shall remain connected tothe grid when the voltage at the interconnectionpoint on any or all phases dips upto the levelsdepicted by the thick lines in the curve

CERC Order on LVRT

• Hon’ble Central Electricity Regulatory Commission vide its orderdated 05.01.16 in Petition No.420/MP/2014 mandated that

• “………We are of the view that LVRT should be implemented for allwind turbines commissioned before 15.4.2014 and connected tovoltage level of 66 kV and above except for Stall Type WTGs, whichare not technically feasible to be retrofitted with LVRT. However,keeping in view the suggestions of IWTMA, we are of the view thatpresently LVRT should be implemented for all wind turbines (exceptStall Types) commissioned before 15.04.2014 having installedcapacity equal to or more than 500 KW.”

LVRT Status Western Region:Constituent Total

Installed WindPowerCapacity (MW)

ExemptedCapacity (MW)

Informationreceived for(MW)

LVRT Complied capacityout of informationreceived (MW)

Gujarat

5348

NotAvailable

2617 471

Madhyapradesh2428

NotAvailable

1205 1205

Maharashtra

4769

NotAvailable

Nil Nil

Location Developer PoolingStation

Turbinemake

Turbinetype

TurbineCapacity

If turbinecommissioned before15.04.2014, Expecteddate of completion ofretrofitting

If turbinecommissionedafter 15.04.2014whethercompliant to LVRT(Yes/No)

… … … … … … … …… … … … … … … …

Format for Information of Wind Turbines andLVRT compliance

01/09/2017

8

FORECASTING OFRENEWABLE ENERGY

INWESTERN REGION

IEGC Clauses for Forecasting of RES

• As per IEGC 5.3(g)“The SLDC shall take into account the Wind Energy forecasting to meet the active and reactivepower requirement.”

And as per IEGC 6.5.23(ii)Forecasting shall be done by wind and solar generators which are regional entities as well as the

concerned RLDC. The concerned RLDC may engage forecasting agency(ies) and prepare a schedulefor such generating stations. The forecast by the concerned RLDC shall be with the objective ofensuring secure grid operation. The forecast by the wind and solar generator shall be generatorcentric. The wind and solar generators which are regional entities will have the option of acceptingthe concerned RLDC’s forecast for preparing its schedule or provide the concerned RLDC with aschedule based on its own forecast. Any commercial impact on account of deviation from schedulebased on the forecast chosen by the wind and solar generator shall be borne by it.”

VARIABILITY OF RES GENERATION:

• Over Drawl of MP of~900 MW

• Frequency: ~49.7 Hz• Forecasting is required :

• To schedule RES as perforecasting

• To fine tune schedules asper real time forecasting

• Prevent systemcontingencies due tosudden withdrawal ofwind

• Plan power generation tomeet the demand

VARIABILITY OF WIND GENERATION:• For real time Grid Operation it is

must to have• Real-time telemetry from RES in

the State• Forecast of RES and demand by the

SLDCs

Reduction of WR Wind from 6000 MW to 3000 MW

01/09/2017

9

Status of Forecasting of RES in Western Region:

State/Region Status of ForecastingGujarat Wind Forecasting is done and shared with WRLDC

Maharashtra Not DoneMadhya Pradesh Not Done

Chhattisgarh Not DoneDaman & Diu Not Done

DNH Not Done

WRLDCPilot Project for forecasting of Maharashtra RESundertaken and is being done for around 50% ofinstalled capacity based on data received over FTP.

Status of Availability of data for MaharashraRES Forecasting Pilot Project

Sr No. RES TotalInstalledCapacity(MW)

TotalForecastedCapacity (MW)

Remarks

1 Wind 4769 2470 Real Time Data: At Present, delayed active powerdata of 2806 MW is available over FTP. Real timedata of all sites required for accurate forecasting.Real time data of Vestas, Windworld. Kenersys,Sri Maruti not provided.Static Data: Static data of Vestas, Windworld.Kenersys, Sri Maruti not provided.

2 Solar 376 125 Real time active power is available for 230 MW.Real time data of remaining capacity of 146 MWis to be provided by SLDC.Real Time weather parameters is to be providedfor all solar parks.

Voltage Regulation by RES:

• Most of the wind RES are connected on lower voltage level the grid. Duringthe high wind season, the demand at lower voltage level is being met bywind RES resulting high voltages on many nodes of south Maharashtra andMadhyapradesh.

• The capability of reactive power drawl/injection by wind RES can beharnessed to support the grid for Voltage Management.

390

395

400

405

410

415

420

425

430

435

0

200

400

600

800

1000

1200

1400

1600

1800

11.0

8.17

11.0

8.17

11.0

8.17

11.0

8.17

11.0

8.17

12.0

8.17

12.0

8.17

12.0

8.17

12.0

8.17

12.0

8.17

13.0

8.17

13.0

8.17

13.0

8.17

13.0

8.17

13.0

8.17

14.0

8.17

14.0

8.17

14.0

8.17

14.0

8.17

14.0

8.17

15.0

8.17

15.0

8.17

15.0

8.17

15.0

8.17

16.0

8.17

16.0

8.17

16.0

8.17

16.0

8.17

16.0

8.17

17.0

8.17

17.0

8.17

17.0

8.17

17.0

8.17

17.0

8.17

Volta

ge a

t Kar

ad 4

00 k

V Bu

s

Win

d Ge

nera

tion

MW

Date

Karad Substation Voltage Variation Vs Wind Generation

Wind Generation (MW) Voltage

High Voltage Scenerio isobserved atsub-station situated inareas with high density ofwind farms .Voltage remained above420 KV for 60-70% of thetime at Karad and Dhulesub-station.As the wind generationpicks up during high windseason, overvoltagescenario observed in thesub-stations.Reactive powerinjection/drawl capabilityof wind turbines can beused for voltagemanagement in suchscenarios.

01/09/2017

10

INTEGRATION OF NEW ISTSCONNECTED RENEWABLE

ENERGY SOURCES

NEW RES YET TO BE CONNECTED TO ISTSSl.No. Organization Name Generating

Station Location Capacity in MW Date from connectivityreqd Granted connectivity for

1 WIND WORLD (INDIA) LTD MUMBAI Bhuj 500 31-Mar-17 500

2 INOX WIND INFRASTRUCTURE SERVICESLIMITED

KACHCHH 500 30-Jul-17 500

3 Kachchh 500 01-Jul-17 5004

GAMESA RENEWABLE PVT LTDBhuj 100 31-Mar-17 100

5 DHAR 218 31-Mar-17 Accepted and under process6

KP ENERGY LIMITED

Kutch 400 25-May-17 Accepted and under process7 Kutch 400 25-May-17 Accepted and under process

8 Kutch 400 25-May-17 Awaiting for Acceptance

9 Kutch 400 25-May-17 Awaiting for Acceptance

10 GUJARAT POWER CORPORATION LIMITED BANASKANTHA 700 31-Dec-17 700

11 RENEW POWER VENTURES PRIVATELIMITED Kutch 400 15-Dec-17 400

12 REWA ULTRA MEGA SOLAR LIMITED Rewa 500 31-Mar-17 750

13 KADAPA WIND FARMS PRIVATE LIMITED BHUJ 100 31-Mar-17 Accepted and under process

14 SRI MARUTI WIND PARK (MENDIGIRI)PRIVATE LIMITED Kucth District 400 20-Jun-17 Awaiting for Acceptance

Total Capacity to be connected byDec.’17 5518

Procedure for Connectivity:

• Hon’ble CERC have issued “ Procedure for Implementation ofFramework on Forecasting, Scheduling and imbalance Handling forRenewable Energy Generating Stations including Power Parks basedon Wind and Solar at Inter State Level.”

• The same is available on CERC website athttp://www.cercind.gov.in/2017/regulation/pro.pdf

• All new ISTS connecting RES shall submit data in prescribed formatsto WRLDC for First Time Charging (FTC), as approved by CERC inabove procedure.

Data requisite for Grid Connectivity:

• For First Time Charging (FTC), following data shall be submitted to WRLDC for ISTSconnecting RES.

For Wind RES:1. Static data of the wind turbines and wind parks as mentioned in framework ( covers 70

points including details of turbine, blade, generator, transformer, performanceparameters etc.)

2. First Time Charging Formats A to C ( includes details of T/L, transformer, bays, SLD,communication conformity, energy meter conformity etc.)

3. Undertaking by RE/Lead/Principal regarding discharging all operational andcommercial responsibilities on behalf of generating stations as per the prevalent CERCRegulations.

4. Copy of application for connectivity which was submitted to CTU.5. Undertaking to indemnify, defend and save the SLDCs/RLDCs harmless from any and

all damages, losses including commercial losses.

01/09/2017

11

Data requisite for Grid Connectivity:

For Solar RES:1. Static data of the solar PV modules and Solar Parks as mentioned in framework

( covers 16 points including details of PV modules, Geographical information,inverter, transformer specifications etc.)

2. First Time Charging Formats A to C ( includes details of T/L, transformer, bays,SLD, communication conformity, energy meter conformity etc.)

3. Undertaking by RE/Lead/Principal regarding discharging all operational andcommercial responsibilities on behalf of generating stations as per theprevalent CERC Regulations.

4. Copy of application for connectivity which was submitted to CTU.5. Undertaking to indemnify, defend and save the SLDCs/RLDCs harmless from

any and all damages, losses including commercial losses.