miyar hydro electric power co. ltd. · 2014-12-12 · m/s miyar hydro electric power co. limited...
TRANSCRIPT
Miyar Hydro Electric Power Co. Ltd.
Miyar HEP (3 x 40 MW)
Six Monthly Progress Report
Compliance Status of Environmental Clearance
December, 2014
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
Index
S. No. Items Page No.
1. Data Sheet of regional Ministry of Environment & Forests 1-3
2. Annexure-A Salient Features of Miyar HEP 4 - 6
3. Annexure-B Salient Features of EMP 7-10
4. Annexure-C Year wise Breakup of budget allocated for EMP 11-12
5. Annexure-D Status of Conditions Stipulated by MoEF 13-19
6. Annexure-E Letter to MoEF submitting landholding of PAFs 20-39
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
1
Six Monthly Progress Report for the period ending November, 2014
1. Project Type: River Valley (run of the river) Project
2. Name of the Project: Miyar (120 MW) HEP
3. Clearance letter(s) OM No. & Dates: a) Environment clearance- F. No. J-12011/47 /2009-
IA-1, 30th
July 2012 & amendment dated 08th
October 2012.
b) Forest clearance- F.No.8-81/2011-FC, 27th
July
2012
4. Locations
a) State(s) Himachal Pradesh
b) District(s) Lahual & Spiti
c) Latitude/Longitude Diversion Site Power House Site
1 Latitude 32°46'08" N 32°43'06" N
2 Longitude 76°42'27'' E 76°40'14" E
5. Address for correspondence:
Mr. S.K. Khare
Chief Project Officer
M/s Miyar Hydro Electric Power Co. Limited
239, Okhla Industrial Estate
Phase-III, New Delhi-110020
Tel: +91-11-47624321
Email- [email protected]
6. Salient features:
a) Of the Project
b) Of the Environmental
Management Plan
a) Salient Features of the Project enclosed as
Annexure-A.
b) Enclosed as Annexure-B.
7. Break-up of the project area. (land
details)
a) Submergence area. (forest & non-
forest)
b) Others
Total- 69.9473 Ha (63.0596 Ha forest land + 6.8877
Ha Private Land)
a) 15.7285 Ha (15.6383 Ha Forest Land + 0.0902
Ha Pvt. Land) of land is under submergence.
b) 4.9063 Ha underground activities & 49.3125 Ha
for other surface activities.
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
2
8. Breakup of the project affected
population with enumeration of those
losing houses/ dwelling units only,
agricultural land only. Both dwelling
units and agricultural land and
landless labourers / artisans.
a) SC /ST /Adivasis.
b) Others
(Please indicate whether these figures
are based on any scientific and
systematic survey carried out or only
provisional figures. If a survey has
been carried out give details and year
of survey).
a) 71 Project affected families (PAFs) were
identified as part of EIA studies as per Socio-
economic survey undertaken in August 2010. The
number of PAFs increased to 108 on account of
division in their families. Project affected families
losing 6.8877 ha of agricultural land only. All
families are Scheduled Tribe. No dwelling
units/houses are affected due to the Project. No
PAF is becoming landless.
b) Nil
(The figures are based on the land records of
respective Panchayats)
9.
Financial details.
a) Project cost as originally planned
and subsequent revised estimates
and the years of price reference.
b) Allocations made for
Environmental management plans
with item wise and year wise
breakup.
c) Benefit Cost ratio/Internal Rate of
Return and the year of assessment.
d) Whether (c) includes the cost of
environmental management as
shown in b) above.
e) Actual expenditure incurred on the
project so far.
f) Actual expenditure incurred on
environmental management plan
so far.
a) Rs. 1125.16 Crores (Completed cost including
IDC) at April 2012 price level.
b) Rs. 5116.78 Lakhs. Details enclosed as
Annexure-C.
c) Benefit Cost ratio is 1.046; year of assessment is
March 2011.
d) Yes.
e) Nil. Construction of the Project yet to
start.
f) Nil. EMP implementation will be started with
commencement of construction. Status of
conditions of Environmental Clearance is
enclosed as Annexure-D.
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
3
10. Forest land requirements.
a) Status of approval for diversion of
forest land for non-forestry use.
b) The status of clear felling in the
forest land.
c) The status of compensatory
afforestation, if any.
d) Comments on the viability &
sustainability of compensatory
afforestation programme in the
light of actual field experience so
far.
a) Stage-I Approval for diversion of 63.0569 ha of
forest land granted by MoEF vide letter dated
27-07-2012 and compliance of conditions for
Final Forest Clearance is under progress.
b) Clear felling in the forest land shall be done only
after final Forest Clearance.
c) Compensatory Afforestation to be started after
Final Forest Clearance.
d) Compensatory Afforestation still to be started.
11. The status of clear felling in non-
forest area (such as submergence area
of reservoir, approach road) if any,
with quantitative information.
Clear felling to be started after completion of Land
Acquisition process of non-forest land.
12. Status of construction
a) Date of commencement
(actual and/or planned)
b) Date of completion. (actual
and/or planned)
June 2015 (planned)
August 2024 (planned)
13.
Reasons for the delay, if the project is
yet to be started.
Forest Clearance is in progress.
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
4
Annexure-A
Salient Features of (3x40 MW) Miyar HEP
PROJECT LOCATION
State Himachal Pradesh
District Lahaul & Spiti
River Miyar Nala
Vicinity Udaipur Village
Diversion Site Power House Site
Latitude 32°46'08" N 32°43'06" N
Longitude 76°42'27'' E 76°40'14" E
HYDROLOGY
Catchment area km² 901
Snow fed catchment area km² 601
Standard Project Flood (SPF) cumec 832
Probable Maximum Flood cumec 1353
Diversion flood (Monsoon/Non monsoon) cumec 401/149
PONDAGE
Full Reservoir Level m 2845
Minimum Draw Down Level m 2837.23
Live storage MCM 0.90
Submergence Area Ha 15.728
BARRAGE
Barrage height (above sill level) m 27
Total width of Barrage structure (including non-
overflow blocks)
m 91
Bridge Deck Level m 2847
Barrage Crest Level m 2820
Gate type and Number of Gates Radial, 4 Nos.
Size (WXH) m 6.0 x 4.0
RIVER DIVERSION
Diversion Tunnel Type D-shape
Length & Diameter m 232.5, 6.5
DT Gate type and Number Fixed wheel type, 2
Size (W X H) m 6.5 x 6.5
TUNNEL INTAKE
Invert sill elevation m 2826.8
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
5
Intake Gate type & Number Stop log gate &
fixed wheel type
gate
Number of Gate 1 No. each
Size (W x H) m 3.7 x 4.7
HEADRACE TUNNEL
Excavated Shape Modified Horse
Shoe
Finished Shape Circular
Length km 6.643
Finished Diameter m 4.7
Design Discharge m3/s 61.35
ADITS
Number of Adits 4
Adit-1 (4.5 m dia D-shaped) m 196
Adit-2 (4.5 m dia D-shaped) m 473
Adit-3 (4.5 m dia D-shaped) m 402
Adit-4 (5.0 m dia D-shaped) m 356
SURGE SHAFT
Type Restricted Orifice,
open to sky
Top elevation m 2895
Bottom elevation m 2780
Total Height m 115
Finished Diameter m 10
Restricted Orifice Diameter m 3.6
VALVE HOUSE
Type & Number Underground, one
Spherical valves
Number One
Diameter m 2.6
PRESSURE TUNNEL/SHAFT
Numbers One
Shape Circular, Steel
Lined
Diameter m 3.6
Length m 537
Unit Penstock (circular)
Number 3
Shape Circular
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
6
Internal Dia m 2.1
Total length of all penstocks m 77.92
POWERHOUSE
Type Surface
Size (L x W) m 85.5 x 17
Turbine type Vertical Francis
Number of units 3
Unit Capacity MW 40
Installed capacity MW 120
Rated discharge per unit Cumec 20.45
Rated head m 215.54
Speed of turbine rpm 428.6
Voltage /Frequency kV /Hz 11.0/50
Power factor cos φ 0.9
TRANSFORMER DECK
Transformer type 3 phase
Location Outdoor
Number 3
Rating 11.0/400 kV, 50
MVA
TAIL RACE CHANNEL
Number One
Size (L x W) m 133 x 15.5
Outlet sill elevation m 2608.8
Normal TWL m 2610.6
Minimum TWL m 2608.8
POWER BENEFITS
Installed Capacity MW 120
Annual Energy 90% dep. energy MU 453.73
Design Energy MU 440.48
Annual load factor % 41.9
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
7
Annexure-B
Salient Features of Environmental Management Plan (EMP) of (3 X 40 MW) Miyar HEP
EMP is focused on following components to mitigate the environmental impacts due to project
construction and operation to the extent possible.
• Biodiversity Conservation & Management Plan
• Catchment Area Treatment Plan
• Fishery Development and Management Plan
• Solid Waste Management Plan
• Public Health Delivery System
• Energy Conservation Measures
• Muck Management Plan
• Landscaping & Restoration of Quarry & Construction Areas
• Air & Water Environment Management & Hazard Mitigation Plan
• Reservoir Rim Treatment Plan
• Compensatory Afforestation Plan
• Rehabilitation & Resettlement Plan
• Environmental Monitoring Programme
• Net Present Value (NPV)
• Disaster Management Plan
An amount of `̀̀̀ 5116.78 lakhs has been allocated for the implementation of different environmental
management plan (including cost of Compensatory afforestation & Net Present Value (NPV) to be
deposited for forest land diversion) in EMP. The summary of total cost estimates for the execution of
different plans is given in Table below.
Table: 1 Cost estimates for the implementation of various measures under EMP
S. No. Management Plan Amount (Rs. in
lakhs)
Remarks
1 Biodiversity Conservation & Management
Plan
156.70
2 Catchment Area Treatment Plan 2813.00 Revised for concurred
DPR Cost
3 Fishery Development and Management Plan 153.10
4 Solid Waste Management Plan 125.60
5 Public Health Delivery System 95.00
6 Energy Conservation Measures 21.00
7 Muck Disposal Plan 266.70
8 Landscaping & Restoration of Quarry &
Construction Areas
32.00
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
8
S. No. Management Plan Amount (Rs. in
lakhs)
Remarks
9 Air & Water Environment Management &
Hazard Mitigation Plan
80.00
10 Reservoir Rim Treatment Plan 15.67
11 Rehabilitation & Resettlement Plan 225.87 Revised for 108 PAFs.
12 Environmental Monitoring Programme 112.52 Revised as per
concurred DPR Cost
13 Disaster Management Plan 37.60
14 Compensatory Afforestation 503.24 Revised by Forest
Department
15 NPV 478.78 Revised by Forest
Department
TOTAL 5116.78
Table-2: Salient Features of EMP
S. No. Management Plan Salient Features
1 Biodiversity Conservation &
Management Plan • Mitigation of Impact due to Noise.
• Habitat improvement for local species to reproduce
and survive.
• Cultivation of Medicinal Plants.
• Natural Resource Management and Awareness
Program.
• Control of grazing.
2 Catchment Area Treatment
Plan • Total catchment of 901 sq. Km has been divided into
34 sub-watersheds.
• Treatment measures shall be implemented over a
period of ten years.
• Biological Measures- raising of native medicinal
herbs & shrubs and Afforestation proposed.
• Engineering measures- check walls/crate walls
construction for treatment of avalanche prone areas &
protection from landslide in the catchment.
• Other measures includes energy saving devices, Eco-
tourism, Forest protection, Publicity & awareness,
payment for eco-services, Wildlife protection,
training of forest staff, participatory action research.
3 Fishery Development and
Management Plan • Up-gradation and augmentation of fish farm having a
flow through hatchery (seed production unit) is
proposed.
• Stocking of fingerlings to the reservoir.
• Distribution of fingerlings to the farmer.
4 Solid Waste Management • Management of waste from worker colonies having
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
9
S. No. Management Plan Salient Features
Plan peak population of 1300 workers is proposed.
• Solid waste generated shall be managed by
reuse/recycling, storage/segregation, collection,
transportation & disposal at designated sanitary land
fill.
5 Public Health Delivery
System • Ambulance : 1 no. with all the basic Medicare
facilities and small DG set, etc. to cater for villages in
the project area
• Two first aid posts including sheds, furniture and
basic equipment (dam and near power house sites)
• Budget for strengthening existing medical facilities,
Health Awareness/ Vaccination Camps, combating
communicable diseases, combating vector borne
diseases.
6 Energy Conservation
Measures • LPG and Kerosene Depot Construction
• Supply of Gas and Cylinders, Kerosene
• Distribution of Pressure Cookers and Solar Cookers
• Community Kitchen (1 Nos.) & Canteen (1 No.).
7 Muck Disposal Plan • About 4.59 Lakh m3 muck to be dumped.
• Four Muck Dumping Sites with total capacity of 4.61
Lakh m3 to be constructed.
• For stacking of dumped material two different types
of concrete reinforced retaining walls are proposed.
• In case of steep gorge, retaining wall, gabion structure
shall be constructed to retain the fill material.
• Biological measures include plantations with
Rhizobium, Azotobacter and Mycorrhiza inoculums,
Turfing with Rhizobium and Azotobacter and
Fencing, sprinkler system, bio-fertilisers, FYM, soil
testing, etc.
8 Landscaping & Restoration
of Quarry & Construction
Areas
• Engineering measures includes filling of crates,
carpeting with geo-textiles etc.
• Biological measures include plantation around
various project appurtenances.
9 Air & Water Environment
Management & Hazard
Mitigation Plan
• Air & Noise control measures proposed.
• Setting up of Wastewater Treatment, procuring and
replenishing the stock of PPEs during the
construction phase
• Training and Awareness programs for local residents,
contractors labour, drivers, cleaners, etc.
10 Reservoir Rim Treatment
Plan • Construction of Toe-wall is proposed.
• Shotcrete is also proposed.
11 Compensatory Afforestation
Plan* • Compensatory afforestation is to be carried out over
128.6267 Ha degraded forest land in lieu of 63.0596
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
10
S. No. Management Plan Salient Features
Ha forest land.
• Total 11 patches in Udaipur (Triloknath, Miyar &
Udaipur Forest Blocks) forest range is identified by
Forest Department for the same.
• Broad Leave and Conifer i.e. Willow, Popular,
Robinia, Cedrus deodara, Pinus walliachiana,
Medicinal plants and Grasses will be planted.
12 Rehabilitation &
Resettlement Plan • Total 71 Project affected families identified on
account of losing land only and no dwelling units
affected. Now 71 PAFs have increased to 108 due to
division of the families.
• All families are Scheduled Tribes.
• Provisions kept as per NRRP 2007.
13 Environmental Monitoring
Programme • Monitoring of Air quality, Water quality & Noise
proposed for construction & operation phase.
14 Disaster Management Plan • Setting up of V-SAT communication system
• Installation of alert systems,
• Notification and publication procedures
15 NPV To be paid as per guidelines of MoEF as part of forest
land diversion.
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
11
Annexure-C
Table-3: Tentative year-wise breakup of budget allocated for EMP implementation of Miyar HEP (reference table-1)
S.
No.
Management
Plan
Amount
(`̀̀̀ in
lakhs)
Year-wise budget (`̀̀̀ in lakhs)
2015 2016 2017 2018 2019 2020 2021 2022 2023 2024
1 Biodiversity
Conservation &
Management
Plan *
156.70 17.4111 17.4111 17.4111 17.4111 17.4111 17.4111 17.4111 17.4111 17.4111 0.0000
2 Catchment Area
Treatment Plan *
2813.00 312.5556 312.5556 312.5556 312.5556 312.5556 312.5556 312.5556 312.5556 312.5556 0.0000
3 Fishery
Development and
Management
Plan*
153.10 73.4556 9.9556 9.9556 9.9556 9.9556 9.9556 9.9556 9.9556 9.9556 0.0000
4 Solid Waste
Management
Plan
125.60 7.2462 14.4923 14.4923 14.4923 14.4923 14.4923 14.4923 14.4923 14.4923 2.4154
5 Public Health
Delivery System
95.00 6.3333 10.8571 10.8571 10.8571 10.8571 10.8571 10.8571 10.8571 10.8571 1.8100
6 Energy
Conservation
Measures
21.00 1.4000 2.4000 2.4000 2.4000 2.4000 2.4000 2.4000 2.4000 2.4000 0.4000
7 Muck Disposal
Plan
266.70 185.50 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 18.0444 54.1333 9.0222
8 Landscaping &
Restoration of
Quarry &
Construction
Areas
32.00 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 24.8889 7.1111
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
12
S.
No.
Management
Plan
Amount
(`̀̀̀ in
lakhs)
Year-wise budget (`̀̀̀ in lakhs)
2015 2016 2017 2018 2019 2020 2021 2022 2023 2024
9 Air & Water
Environment
Management &
Hazard Mitigation
Plan
80.00 5.3333 9.1429 9.1429 9.1429 9.1429 9.1429 9.1429 9.1429 9.1429 1.5238
10 Reservoir Rim
Treatment Plan
15.67 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 9.7938 5.8763 0.0000
11 Compensatory
Afforestation
Plan
503.24 503.24 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
12 Rehabilitation &
Resettlement
Plan*
225.87 215.87 1.2500 1.2500 1.2500 1.2500 1.2500 1.2500 1.2500 1.2500 0.0000
13 Environmental
Monitoring
Programme*
112.52 12.5019 12.5019 12.5019 12.5019 12.5019 12.5019 12.5019 12.5019 12.5019 0.0000
14 NPV* 478.78 478.78 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
15 Disaster
Management
Plan
37.60 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 31.3333 6.2667
TOTAL 5116.78 1819.6270 390.5665 390.5665 390.5665 390.5665 390.5665 390.5665 418.4047 506.7983 28.5492
Note- 1. Funds at Sl. No. 11 & 14 to be deposited to CAMPA account for diversion of forest land.
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
13
Annexure-D
Table:4 Status of Conditions Stipulated by MoEF in EC Letter
Sl. No. Conditions Status
PART A: Specific Conditions
(i) The Catchment Area Treatment Plan as
proposed in the EIA/EMP Report shall be
undertaken in consultation with the State
Forests Department and major work shall be
completed before impounding of reservoir.
CAT Plan shall be implemented by State
Forest Department (concerned DFO) with the
funds provided by MHEPCL during
construction phase. Total financial outlay
proposed for CAT Plan has been revised to
Rs. 28,13,00,000/- as per concurred DPR
cost and same has been approved by
Himachal Pradesh State Forest Department,
Government of Himachal.
(ii) All the commitments made during the public
hearings shall be fulfilled completely.
Agreed. All the commitments made during
Public hearing shall be fulfilled during
construction/operation phase of the Project
(iii)
The details of land holding of project
affected persons whose land is being
acquired shall be submitted to this Ministry.
The R&R benefits for the land losing
households will be as per the National
Rehabilitation and Resettlement Policy,
2007 (NRRP, 2007) or as per the State
Rehabilitation and Resettlement Policy,
whichever is higher. Adequate publicity of
the compensation package shall be made in
the affected villages.
R&R Plan has been formulated as per
provisions of NRRP 2007 in EMP and same
shall be implemented for 108 PAFs during
construction phase. List of PAFs along with
their individual land holding has been
submitted to MoEF vide letter dated 28-11-
2014 (Copy enclosed as Annexure-E).
Provisions of R&R Plan formulated as per
provisions of NRRP 2007 as part of EMP and
already discussed in Public Hearing of the
Project.
(iv)
A Monitoring Committee for R&R should be
constituted which must include
representatives of project affected persons
from SC/ST category and a woman
beneficiary.
R&R Committee will be constituted by
GoHP / Commissioner R&R of the State, as
per provisions of NRRP 2007 during
construction phase. The composition of R&R
Committee as per NRRP 2007 is mentioned
below-
• Administrator for R&R (DC)
• Representative of Miyar Hydroelectric
Power Company Ltd.
• Representatives of village level
Committees (VLC)
• Representatives of women of the affected
villages
• Representatives of Nationalized Bank
• Representatives of Forest Department
• Representatives of Local NGOs
• MLA/MP of the Area
• Representative of STs residing in the
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
14
Table:4 Status of Conditions Stipulated by MoEF in EC Letter
Sl. No. Conditions Status
affected area.
• Land Acquisition Officer of the project.
(v)
Muck Management Plan as given in the
EIA/EMP Report shall be strictly
implemented. Consolidation and compilation
of the muck shall be carried-out only in the
designated muck dumping sites. As per the
proposed muck disposal plan, about 4,59,254
cum of muck is expected to be generated
after deducting 25% of utilizable muck. The
muck shall be disposed of only at four
designated locations approved by State
Pollution Control Board. For Muck
Dumping Site-3, which is only about 12 m
from HFL, an RCC retaining structures upto
the requisite height shall be provided to
ensure that muck does not roll down to river.
Retaining structures shall be constructed
before dumping any muck at any site. The
sites shall be restored once the construction
is over.
Muck Disposal Plan shall be complied as per
provisions of Miyar EMP during construction
phase. Total financial outlay of Rs. 266.70
Lakh kept for the same.
(vi) There are no fish in the Miyar nalla
however, as proposed by you, Rs. 89.60
Lakh shall be budgeted for Fisheries
Development Plan for considering the
possibility of developing snow trout in the
area in future. This shall be implemented in
consultation with State Fisheries
Department.
Financial Outlay of Rs. 89.60 Lakh proposed
for implementation of Fisheries Development
Plan to be released to Fisheries Department
in phase wise manner on receipt of demand
during construction phase.
(vii) A minimum water discharge of 1.04 cumecs
i.e. 28% of the minimum discharge available
during four leanest months of the 90%
dependable year shall be released as
environmental flow for sustenance of aquatic
life and downstream
use. Regarding release of Monsoon flow the
project proponent explained that the average
spill during three monsoon months i.e. June,
July and August is more than 30% in 31
years out of 33 years for which data have
been approved by CWC.
Project Proponent shall maintain the same
average spill i.e. more than 30% of average
monsoon discharge during the three
Agreed. Same shall be complied during
operation phase of the Project.
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
15
Table:4 Status of Conditions Stipulated by MoEF in EC Letter
Sl. No. Conditions Status
monsoon months.
(viii) The environmental flow shall be through an
ungated /uncontrolled opening (without any
valve) in one of the piers. Design aspect of
the same would be discussed with CWC to
ensure that no choking takes place in this
opening.
Same shall be complied while construction
and designing of the barrage.
(ix) Continuous Monitoring system for
environmental flow measurement shall be
installed and data shall be displayed at
appropriate site for information of civil
society and stake holders. Six monthly
results shall be submitted to the concern
Regional Office of the Ministry and SPCB.
Same shall be complied during operation
phase.
(x) Real time telemetry and data acquisition
system including all weather hydro
metrological stations shall be installed for in-
flow monitoring and advance flood warning.
Advance flood warning and advance
communication systems shall be installed in
consultation with the downstream District
Authorities.
Disaster Management Plan with a total
financial outlay of Rs. 37.60 Lakh has been
proposed in EMP for setting up of V-SAT
communication system etc and same shall be
implemented during construction phase.
(xi) As proposed in the EMP, the Afforestation
Programme on about 128 ha of land shall be
undertaken immediately @ 1500 plants per
hectare. Native species should be preferred
in plantation.
Compensatory Afforestation (CA) over
double of the degraded forest land i.e.
128.6267 ha already formulated as part of
Forest proposal. The funds to the tune of Rs.
5,03,24604/- shall be deposited to CAMPA
for implementation of the same during
construction phase.
(xii) Greenbelt development along the approach
roads, residential areas, office complex,
barrage site and other working areas shall be
undertaken immediately. The allocated
budget of Rs. 20 lakhs shall not be diverted
to any other purpose.
Site wise Green belt development shall be
done with progress of construction works
including Roads, Colonies etc.
Greenbelt development is proposed as part of
“Landscaping & Restoration of Quarry &
Construction Areas” proposed in EMP.
(xiii) The Biodiversity Conservation and Wildlife
Management Plans, as proposed in the EMP
shall be taken up immediately and
implemented in consultation with the State
Forest Department without any diversion of
allocated funds. A report of implementation
shall be included in the sixth monthly
compliance report to be submitted to the
Ministry.
Same shall be complied as per provisions
mentioned in EMP in consultation with HP
Forest Department during construction phase.
Total budget proposed for the plan is Rs.
156.70 Lakh.
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
16
Table:4 Status of Conditions Stipulated by MoEF in EC Letter
Sl. No. Conditions Status
(xiv) A minimum of 1.5% of the total project cost
shall be spent for the Local Area
Development. Cost estimates for all other
aspects as provided in EIA/EMP shall-be-
adhered to,
Agreed. LADA cost will be to the tune of Rs.
1687.755 Lakhs as per concurred DPR Cost.
LADP to be implemented in consultation
with District LADC & concerned Panchayats
during construction phase.
(xv) The equipment likely to generate high noise
levels during the construction period or
otherwise shall meet the ambient noise
standards as notified under the Noise
Pollution (Regulation and Control) Rules,
2000, as amended in 2010 under the
Environment Protection Act (EPA), 1986.
The vegetative cover as proposed for Noise
mitigation measures may not be effective
therefore; other measures like construction
enclosures, use of silent generators etc.
should also be used during construction.
An amount of Rs. 25 Lakh kept in
Biodiversity Conservation Plan for noise
mitigation & same will be utilized for noise
mitigation measures during construction
phase.
(xvi) Quarry sites shall be restored once
construction is over.
“Landscaping & Restoration of Quarry &
Construction Areas” proposed in EMP with
total provision of Rs. 32 Lakh including
engineering works and same shall be
implemented on completion of construction
work.
(xvii) The project falls in seismic zone -V. The site
specific responses spectra study has been
carried out by Department of Earthquake
Engineering, I1T Roorkee. Approval from
NCSDP shall be obtained before starting
construction for the project.
National Committee on Seismic Design
Parameters (NCSDP) has approved the
revised site specific seismic study report
carried out by Department of Earthquake
Engineering, I1T Roorkee vide its letter
dated 03-09-2013.
(xviii) A provision of Rs. 10.96 Crore earmarked
towards the Local Area Development
Activities shall not be diverted for any
purpose. The activities as submitted to the
Ministry shall be taken up as soon as
possible. This will be in addition to Rs. 2.40
Crore earmarked for Corporate Social
Responsibility (CSR).
LADP to be implemented in consultation
with District LADC & concerned Panchayats
during construction phase.
CSR activities as proposed under brand name
EECHO (Education, Environment,
Community Development, Health & hygiene,
Other Activities) shall be implemented
during construction period of the Project.
(xix) Any other clearance from any other
organization/department, if required, shall be
obtained.
Agreed.
PART B: General Conditions
(i) Adequate arrangement for providing free
fuel like kerosene/ wood/ LPG shall be made
at project cost for the labour engaged in the
Energy Conservation Measures including
provisions of kerosene, LPG, Solar Cookers
etc. have been made in EMP with total
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
17
Table:4 Status of Conditions Stipulated by MoEF in EC Letter
Sl. No. Conditions Status
construction work so that indiscriminate
felling of trees is prevented.
provision of Rs. 21 Lakh and same shall be
implemented during construction phase.
(ii) Medical facilities as well as recreational
facilities shall also be provided to labourers.
Public Health Delivery System proposed in
EMP with total provision of Rs. 95 Lakh and
same shall be implemented during
construction phase. Recreation facilities may
be taken up as part of CSR.
(iii)
All the labourers to be engaged for
construction works shall be thoroughly
examined by health personnel and
adequately treated before issuing them work
permit.
Shall be complied before deploying laborers
during construction phase. Contractors may
be advised to produce health report of their
laborers.
(iv)
No fugitive dust emissions should be
observed at the construction sites. Water
sprinkling arrangements should be made to
suppress the fugitive emissions.
Air & Water Environment Management &
Hazard Mitigation Plan proposed in EMP
with total provision of Rs. 80.00 Lakh and
same shall be implemented during
construction phase.
(v)
Potable drinking water and proper sanitary
facilities shall be provided for the labour
force and the local area people.
Sanitary facilities etc. are proposed under the
Solid Waste Management Plan in EMP with
total budget of Rs. 125.60 Lakh and same
shall be implemented during construction
phase.
(vi) Restoration of construction area including
dumping site of excavated materials shall be
ensured by levelling, filling up of burrow
pits, landscaping etc. The area should be
properly treated with suitable plantation.
“Landscaping & Restoration of Quarry &
Construction Areas” proposed in EMP with
total provision of Rs. 32 Lakh including
engineering works.
(vii) Environmental parameters shall be
monitored and six monthly reports shall be
submitted to the concerned Regional Office
of the Ministry and State Pollution Control
Board for review.
Environmental Monitoring Programme
proposed in the EMP with total budget for
construction phase Rs. 52.50 Lakh & Rs. 21
Lakh for operation phase. Air, Water &
Noise monitoring to be undertaken in
consultation with HPSPCB. Six Monthly
Monitoring report for Air, Water & Noise
will be submitted along with Six Monthly
compliance report during construction.
(viii) The project proponent shall also submit six
monthly compliance reports of the stipulated
EC conditions (both hard copies as well as
by e-mail) to the respective Regional Office
of MoEF and State Pollution Control Board.
Both monitoring report and compliance
report shall be up-loaded on the web-site of
the Proponent
Same is being complied. Six Monthly
Compliance Reports are being uploaded on
the website of Miyar Hydro Electric Power
Co. Ltd. i.e.
http://www.miyarhydropower.com
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
18
Table:4 Status of Conditions Stipulated by MoEF in EC Letter
Sl. No. Conditions Status
5. The Project Proponent shall provide full
cooperation and all required documents/data
to the Officials of relevant Regional Office
of MOEF who would be monitoring the
implementation of environmental
safeguards.
Same shall be complied as and when asked
by RMoEF.
6. Besides the above stated conditions, the
Project Proponent and Government of
Himachal Pradesh shall also implement all
other environmental safeguards, as proposed
in the EIA/EMP report and other reports
from time to time.
Agreed.
7. Any change in the scope of the project shall
be intimated to the Ministry and fresh
approval, if required, shall be taken from the
Ministry.
Agreed.
8. The Ministry reserves the right to add
additional safeguard measures subsequently,
if found necessary and to take action
including revoking of the clearance under
the provisions of the Environment
(Protection) Act, 1986, to ensure effective
implementation of the suggested safeguard
measures. In a time- bound and satisfactory
manner.
Agreed.
9. This clearance letter is valid for a period of
10 years from the date of issue of this letter
for commencement of construction work.
Agreed.
10. A Multi-disciplinary Committee for
monitoring the implementation of
environmental safe guards during
construction shall be constituted by the
Proponent in consultation with the Ministry.
The Proponent shall suggest the members for
approval of the Ministry. Proponent shall
organize six monthly meetings of the
Committee and submit the monitoring report
to the Ministry.
Multi-disciplinary Committee (MDC) will be
constituted in consultation with MoEF and
same shall be implemented during
construction phase of the Project. A request
with proposed composition of the committee
including local representatives, eminent
ecologist (to be identified) etc. will be made
to MoEF. General composition of MDC is
given below-
i. Environment Expert (To be
identified)
ii. Deputy Commissioner, Lahual &
Spiti
iii. Director, MOEF-Member Secretary
iv. Representative, HP State Pollution
Control Board
Six Monthly Progress Report M/s Miyar Hydro Electric Power Co Limited
For 120 MW Miyar HEP
19
Table:4 Status of Conditions Stipulated by MoEF in EC Letter
Sl. No. Conditions Status
v. Representative of State Foresr
Department
vi. Wildlife Expert (To be identified)
vii. Local Representative of Gram
Panchayats
viii. Representative of National Level
Forest Institute (To be identified in
consultation with MOEF)
ix. Project Head, Miyar HEP-convener
11. A copy of the clearance letter shall be sent
by the Proponent to concerned Panchayat,
Zilla Parishad/ Municipal Corporation,
Urban local body and the local NGO, if any,
from whom suggestions / representations
were received while processing the proposal.
The clearance letter shall also be put on the
website of the Company by the Proponent.
Complied.
The clearance letter sent to the concerned
authorities and same is being displayed
permanently on the website of the company
i.e. http://www.miyarhydropower.com/.
12. The proponent should advertise at least in
two local newspapers widely circulated in
the region around the project, one of which
shall be in the vernacular language of the
locality concerned informing that the project
has been accorded environmental clearance
and copies of clearance letter are available
with the State Pollution Control
Board/Committee and may also be seen at
Website of the Ministry of Environment and
Forests at http://www.envfor.nic.in.
Complied.
The Public Notice as per guidelines
published in Himachal Edition of “Amar
Ujala” in Hindi & Himachal Edition of “The
Tribune” in English.
13. After 5 years of the commissioning of the
Project, a study shall be undertaken
regarding impact of the project on the
environment and downstream ecology. The
study shall be undertaken by an independent
agency, decided in consultation with the
Ministry.
Agreed.
14. The project proponent shall also submit six
monthly reports on the status of compliance
of the stipulated EC conditions including
results of monitored data (both in hard
copies as well as by e-mail) to the respective
Regional office of MoEF and Zonal Office
of CPCB and the SPCB.
Agreed.
Monitored data of air, water & noise shall be
submitted during construction phase.