Live Webinar on Getting MNRE Exemptions
for Rooftop Solar Plants
Your Host
HOST
Puneet Singh Jaggi
Director, ezysolare
+91 9998025820
Questions
You can type in the Questions and we will take them at
the end of the Webinar
Key MNRE Notifications
http://www.mnre.gov.in/solar-mission/jnnsm/introduction-2/
Notification for Rooftop Projects
Although, the wordings mention that the policy is applicable only to the plants
not connected to the grid but grid connected solar plants are also accepted.
Notification for Rooftop Projects
Minimum Capacity of 100 KW (individual or bundled)
Only Excise Exemption; Not Customs Exemption, but….
Notification for Rooftop Projects
Civil work, Earthing material, Lighting material , Lightning Arrestors, Security,
CCTV, Fencing, Gates & misc items are excluded
Process for Claiming Exemptions
3 STEP PROCESS
1. Online Registration (7 days)
2. State Nodal Agency Approval (3 - 10 days)
3. MNRE Approval & Exemption Certificates (7 - 30 days)
Online Registration
Make an account on MNRE Portal:
http://164.100.194.45/ccm
Online Registration
The following details are to be filled while making the account:
• Name of Solar Project CEO: [Please nominate the person who shall be readily
available for signing the material dispatch documents as this activity generally
trickles to last minutes and is a recurring activity]
• Developer Name: [Full Name of the firm]
• Address: [Exact address of the location where solar plant is to be installed]
• Mobile No.: [of the CEO of the Solar project nominated above]
• Email ID: [of the CEO of the Solar project nominated above]
CEO should be of the project owning company and not of the EPC Contractor
Online Registration
Fill in online
Total Bill of Materials by
giving Block
and giving Equipment Name,
Quantity, Unit and Specs.
Online Registration
Submit the Total Bill of Materials when finalised and wait
for online MNRE Approval
Online Registration
Snapshot of Bill of Material approved by MNRE
Online Registration
Snapshot of Bill of Material approved by MNRE
3 - 7
Days
State Nodal Agency Approval
3 files need to be prepared with the following documents:
• Bill of Materials (once it is approved by MNRE) after signing by the CEO and certified by
Chartered Engineer
• Cover Letter
• Proof of Possession of Roof/Building for Solar Project
• MoA/AoA of the Project Owner Company
• Self Certified Affidavit confirming that the certificates would be used only for the project for
which they are being taken
• CA Certificate for Project Cost
• Power Evacuation Permission / Chief Electrical Inspector Approval (if applicable)
• Single Line Diagram of the Plant
• Layout of the Plant
• Detailed Project Report (DPR)
State Nodal Agency Approval
These 3 files are then submitted to the Renewable Energy State Nodal Agency
After Approval:
Nodal Agency keeps 1 file for itself
1 file is given back to the owner
1 file is submitted to MNRE with Cover Letter
State Nodal Agency Approval
These 3 files are then submitted to the Renewable Energy State Nodal Agency
After Approval:
Nodal Agency keeps 1 file for itself
1 file is given back to the owner
1 file is submitted to MNRE with Cover Letter
3 - 10
Days
MNRE Approval & Exemption Certificates
PART 1: MNRE APPROVAL
On submitting these file to MNRE, MNRE checks and approves the documents.
MNRE may ask for technical clarifications, particularly for cable and structure quantities.
Once approved, you can print the Exemption Certificates
PART 2: EXEMPTION CERTIFICATES
For each of the Exemption Certificate, you need to specify:
Excise Range Division
Commissionerate Excise No.
MNRE Approval & Exemption Certificates
MNRE Approval & Exemption Certificates
2 copies of the Exemption Certificate and the relevant Purchase Orders are
signed by the Project CEO and certified by Chartered Engineer after which they
are again submitted to MNRE.
Lastly, the certificates are signed and stamped by Director at MNRE.
1 certificate is handed over to the Owner while the other certificate is signed by
the Owner and given back to MNRE as a proof of receiving.
MNRE Approval & Exemption Certificates
2 copies of the Exemption Certificate and the relevant Purchase Orders are
signed by the Project CEO and certified by Chartered Engineer after which they
are again submitted to MNRE.
Lastly, the certificates are signed and stamped by Director at MNRE.
1 certificate is handed over to the Owner while the other certificate is signed by
the Owner and given back to MNRE as a proof of receiving.
7 - 30
Days
Advantage EZYSOLARE!
Ezysolare.com provides
FREE EXCISE EXEMPTION GUIDANCE FOR
EQUIPMENT PURCHASED THROUGH SOLARKART.
So call us to book your orders for anything solar - modules, inverters, cables,
structures, earthing and more at negotiated prices delivered at your doorstep.