modernizzazione delle turbine a vapore allo scopo di ... · pdf filemodernizzazione delle...
TRANSCRIPT
Modernizzazione delle turbine a vapore allo
scopo di aumentare l’efficienza energetica e
la redditività degli investimenti
10 anni di modernizzazione dei turbogruppi in Italia
Alberto Torre
Steam Turbine Engineering
Verona, 7 Ottobre 2010
2
Introduction
In March 1999, a legislative decree (“Bersani Decree”) was issued for the liberalization of the Italian Energy market.
New players appeared in the Italian market installing new greenfieldpower plants based on high efficiency CCGT technology.
The owners of existing conventional plants has been forced to modernize the power plants in order to maximize their competitiveness in an open market.
The basic modernization concepts and some modernization activities on the existing Italian fleet are illustrated.
3
Power Generation market in Italy now
Renewables (hydro included) are relevant
(27%)
No nuclear energy is produced (all nuclear
power plants have been shut-down after
Chernobyl)
Most generation comes from conventional
thermal sources, production by coal is only
14%, the remaining is produced mainly by
natural gas (several installations of CCGT
plants) and oil.
Today the italian generation fleet is one of the most efficient in Europe.
Installed Capacity (2009)*
105 GW
Source: *Terna web site, **IEA analysis
Main characteristics
Average efficiency:
45%**
73%
21%
6%
Thermal plants Hydroelectric Renewables
Fuel mix
4
….and 10 years ago?
The context was quite different: like today Italy got the majority of its
electricity supply from conventional thermal sources, but the bulk was
oil-fired
14%
60%
26%
Before liberalization (2008)
Average efficiency:
<39%*
15%
37%
48%
Coal Gas Oil
Average efficiency:
45%**
Introduction of new CCGT Repowering of existing PP
Fuel mix
5
Italian Power Generation market: last 10 years
The last decade of the Italian Power Generation market has been
characterized by different factors which have modified radically the
characteristics of the turbogenerator fleet:
Liberalization
Environmental Impact
6
Liberalization
• Bersani Decree (1999) for the
restructuring and liberalization of the
Italian electricity sector
• Enel share of domestic market can not
be higher than 50% due to regulatory
constrains.
• Italian government forced Enel to sell
15,000MW of installed capacity.
• Different operators emerged as
significant players in the sector:
• installing new green field CCGT
power plants
• purchasing also the former Enel
assets
• A competitive market among players in
power generation
From monopoly…
…to a truly competitive context
1999 ...after 1999
7
Environmental impact
Climate has changed over the past century (average temperature increase)
Climate is expected to continue to change in the future
The Kyoto Protocol, adopted in 1997, contains legally binding comitments to reduce the anthropogenic GHG (GreenHouse Gas)
EU large combustion plant Directive 2001/80/CE defines specific emission limits (200/200/30 mg/Nm3) for SO2/Nox/Particulate
New investments over the next 20 years to meet the expected energy
demand and to replace the ageing infrastructure
8
Effects of the liberalisationM
AR
KE
T
Liberalization
(new operators)
Greenfield Plants
Investments in new Combined
Cycles (high overall efficiency,
>55%)
Existing old Plants
Modernisation of the old power
plants to become competitive
with the new CC
9
Green field plants
Before the liberalization process, the Italian fleet was not so advanced and
efficient as today (most of the Power Plants installed in the sixties and
seventies).
=
European energy target
New competitive scenario
+
Introduction of 400MW or 800 MW advanced gas fired CC plants
• High efficiency technology
• Reduced CO2 emissions
Greenfield Plants
10
Greenfield Plants
Greenfield Plants• High efficiency technology
• Reduced CO2 emissions
Scandale
Ferrara
Teverola
Sparanise
Rosignano
Ferrera
Leini
Ponti S.M.
Around 18,000MW(at the end of 2009)
EGL
Sorgenia
Rizziconi
Turano L.
Modugno
Aprilia
S.Severo
11
Installed capacity before liberalization
120/160 MW
240/350 MW
600/660 MW
Installed Capacity (1998)*
54 GW
25 units
60 units
17 units
Subcritical RH steam PP
Supplied by Ansaldo, F.Tosi, Rateau, BBC
Efficiency (overall) 34-36 %
Before
liberalisation
Subcritical RH steam PP
Supplied by Ansaldo, F.Tosi, Rateau
Efficiency (overall) 36-37%
Supercritical RH steam PP
Supplied by Ansaldo, F.Tosi
Efficiency (overall) 38-39%
PO
WE
R P
LA
NT
S
Source: *Terna web site
12
Aged fleet: modernisation strategy
In comparison to new greenfield power plants, the conversion/modernisation of existing power plants offers several
opportunities:
Reduction of the investment cost due to the extensive reuse of existingequipments, buildings, infrastructures, electrical substations, transmission lines
Reduction of environmental impact of the existing plant (designedaccording to old standards); this issue is often an important factor in promoting the acceptance of the project al local level
13
Aged fleet: modernisation strategy
∆ Efficiency: up to 20%
160-320 MW Multifuel
PO
WE
R P
LA
NT
S
Conversion into Combined Cycles
(Repowering) to increase the efficiency as
new CCGT plants
Conversion to USC clean coal fired cycles
to increase the mixing of energy sources,
the efficiency and reduce the air pollution
Modernization of the turbines to increase
the power and the efficiency and reduce
CO2 emission.160-660 MW Coal fired
660 MW Multifuel
∆ Efficiency: up to 2%
∆ Efficiency: up to 10%
14
Modernization of existing old units
Existing old units •Modernisation activities
BrindisiFiumesanto (SS)
Turbigo (MI)
• Around 9000MW converted to CCPP
• Around 4500MW coal fired steam
turbines modernized
• Around 5000MW of large oil fired units
will be converted to USC cycles (clean
coal technology)
Eon
15
WHY REPOWERING ?
Conversion of existing Steam Power Plants into Combined Cycles by replacing
the fired Boiler with GT and HRSG is known as Repowering.
Repowering an existing steam Power Plant realizes a gain in efficiencyup to values of 56% and over.
Steam Cycle
XCombined Cycle
Repowering is the solution that best matches the optimization
goal of reduction of operating costs in an existing Power Plant.
Repowering
From Steam Cycle to Combined Cycle
16
Repowering
From Steam Cycle to Combined Cycle
In a steam cycle unit
the overall Efficiency is about 36%
mSH=100%
mHRH=80%mLP=75%
mcond=60%
Flow diagram of a conventional RH steam power plant
17
In combined cycle, the overall Efficiency is higher than 56 %
10%
32.5%
Conversion of a conventional unit in C.C. (1+1 configuration)
2 - ST steam path could beoptimized; extraction pipes
blanked
1 - Steam Generator is replaced by
GT and HRSG, Feedwater
cycle is removed
3 - Condenser is maintained
mSH=30%
mHRH=40%
mcond=65%
Note (1): Mass flows % refer to original mass flow for each point of a subcritical 350 MW ST
Repowering
From Steam Cycle to Combined Cycle
18
20
40
60
80
100
120
HP inlet RHT inlet LP inlet LP exhaust
Ste
am
flo
w to
ST
se
ctio
ns [%
]
Original
2+1
1+1
Repowering existing Power Plants causes a substantial modification of the
steam mass flow distribution across the different sections of the Turbine:
In the Steam Cycle the steam flow is reduced from HP inletto LP exhaust due to the bleeded steam for feedwater heaters
In the Combined Cycle the steam flow increases from HP inletto LP exhaust due to the addition of multiple level flows.
Steam flow distribution
before and after repowering
( ref. 320 MW ST )
Repowering
From Steam Cycle to CC - Reasons for retrofit
A partial or complete change of the old steam path in order to match the new operating
conditions permits to improve the Combined Cycle performance to a level comparable to
that of a new turbine
19
Steam ParametersLS pressure : 141 bar
HP inlet flow : 134 kg/s
SH/RH temperature : 538 / 538 °C
Exh. Pressure : 0.054 bar
Exh. Flow : 91 kg/s
Rating : 2 x 156 MW
• OEM: Franco Tosi (Westinghouse)
• Years of first operation: 1964, 1966.
• Reaction design.
• Tandem compound arrangement with a combined HP-IP section and a
double-flow LP section with 23” LSB
ITALY (P.TO CORSINI)
Original (Steam Cycle)
20
Steam ParametersLS pressure : 107 bar
HP inlet flow : 76.5 kg/s
SH/RH temperature : 538 / 538 °C
Exh. Pressure : 0.051 bar
Exh. Flow : 97 kg/s
Rating : 2 x 124 MW
From 2001, steam cycle repowered into 2 x ( 1+1 370 MW) combined cycle
using a AE94.3A Gas Turbine.
Complete replacement of LP inner block including:
· new inner casing and blade carriers
· new monoblock rotor
· modern 3D blading on front stages
· longer LS blade (33”) with 60% larger
exhaust area
Benefits: Improvement of 5.6 MW with reference to original design
Overall – Plant efficiency from 34% to 55%
ITALY (P.TO CORSINI)
Retrofit for CC conversion
21
Steam Parameters
LS pressure : 166.6 bar
HP inlet flow : 283.9 kg/s
SH/RH temperature : 538 / 538 °C
Exh. Pressure : 0.050 bar
Rating : 1 x 320 MW
• OEM: Ansaldo
• Years of first operation: 1970
• Tandem compound arrangement with a combined
HP-IP section and a two-flows LP section with 33.5” LSB
ITALY (Vado Ligure # 1) - Original (Steam Cycle)
22
• OEM: Ansaldo (impulse technology)
• Years of first operation: 1970
• Tandem compound arrangement with a combined
HP-IP section and a two-flows LP section with 33.5” LSB
Steam Parameters
LS pressure : 128 bar
HP inlet flow : 147 kg/s
SH/RH temperature : 548 / 553 °C
Exh. Pressure : 0.057 bar
Rating : 1 x 274 MW
• 2005, Conversion in C.C. 2+1 800 MW using two Ansaldo AE94.3A Gas Turbine
• Complete replacement of HP-IP section of up-to-date reaction type and materials suitable for increased
temperature
- New HP & IP stop and control valves directly connected to the outer casing
- Full-arc admission with elimination of control stage
- New rotor with 3D reaction blading and enhanced sealings
• New LP inner block (rotor, inner casing) with 43” LSB
Benefits: Increase of 12 MW with reference to the original design
Overall – Plant efficiency from 36% to 56%
ITALY (Vado Ligure # 1) - Retrofit for CC
23
Aged fleet: modernisation strategy
∆ Efficiency: up to 20%
160-320 MW Multifuel
PO
WE
R P
LA
NT
S
Conversion into Combined Cycles
(Repowering) to increase the efficiency as
new CCGT plants
Conversion to USC clean coal fired cycles
to increase the mixing of energy sources,
the efficiency and reduce the air pollution
Modernization of the turbines to increase
the power and the efficiency and reduce
CO2 emission.160-660 MW Coal fired
660 MW Multifuel
∆ Efficiency: up to 2%
∆ Efficiency: up to 10%
24
The increasing of internal efficiency of an old steam turbine can be obtained
through the introduction of modern 3D blades and larger last stage blades.
Old design with shorter LSB’s and exhaust steam velocity over 300 [m/s]
have often high exhaust losses.
In the last decades, new materials
and new design methods
allowed the development
of large LSBs .
Efficiency increase on Coal Fired PP
A larger last stage blade will reduce
exhaust losses and convert them in
additional power output
25
Steam Parameters
LS pressure : 163 bar
HP inlet flow : 283.9 kg/s
SH/RH temperature : 540 / 540 °C
Exh. Pressure : 0.050 bar
Rating : 1 x 260 MW
• OEM: Rateau Schneider.
• Years of first operation: 1966
• Tandem compound arrangement with HP and IP separated
sections and double flow LP section with 34” LSB
ITALY (Sulcis # 2) – Original Coal Fired
Steam Cycle
26
• OEM: Rateau S. (impulse technology)
• Years of first operation: 1966
• Tandem compound arrangement with HP and IP separated
sections and double flow LP section with 33.5” LSB
• 2002, The modernisation of the Plant included:
Installation of a new CFB boiler with increased capacity
Replacement of old ST with a new Ansaldo steam turbine, reaction type, with a LP DF
(43”LSB)Benefit: - Increase of gross power output up to 345 MW
- Increase of gross efficiency up to 40%
- Significant CO2 emission reductions.
Steam Parameters
LS pressure : 165 bar
HP inlet flow : 286.1 kg/s
SH/RH temperature : 565 / 580 °C
Exh. Pressure : 0.057 bar
Rating : 1 x 345 MW
ITALY (Sulcis # 2) – Modernisation of the
Unit
27 27
Steam Parameters, STPPLS pressure: 167 bar
HP inlet flow: 293.4 kg/s
LS/RH temperature: 538/538°C
Exh. Pressure: 0.05 bar
Exh. Flow: 176.8 kg/s
Rating: 2 x 329.3 MW
Steam Turbine Retrofit
Fusina 3-4 / Italy
2006 / Replacement of LP inner block• LSB length: 43”
• Exhaust area: 9.6 m2
• Front stages: 3D optimized
• New rating: 336.8MW
BENEFITS: Power output: + 7.5 MW
Heat rate: - 42 kcal/kWh
OEM: Franco Tosi / Westinghouse
Years of first operation: 1974
28 28
Steam Turbine Retrofit
Brindisi Sud 4 x 660MW / Italy
BENEFITS: Power output: + 15.5 MW
Heat rate: - 43.4 kcal/kWh
Steam Parameters, STPPLS pressure: 242 bar
HP inlet flow: 581 kg/s
LS/RH temperature: 538/538°C
Exh. Pressure: 0.049 bar
Rating: 4 x 660 MW
Replacement of LP inner blocks• LSB length: 43”
• Exhaust area: 9.6 m2
• Front stages: 3D optimized
• New rating: 4 x 675 MW
OEM: Franco Tosi / Westinghouse
Years of first operation: 1991
29
Aged fleet: modernisation strategy
∆ Efficiency: up to 20%
160-320 MW Multifuel
PO
WE
R P
LA
NT
S
Conversion into Combined Cycles
(Repowering) to increase the efficiency as
new CCGT plants
Conversion to USC clean coal fired cycles
to increase the mixing of energy sources,
the efficiency and reduce the air pollution
Modernization of the turbines to increase
the power and the efficiency and reduce
CO2 emission.
160-660 MW Coal fired
660 MW Multifuel
∆ Efficiency: up to 2%
∆ Efficiency: up to 10%
30
[%]
Evolution of cycle parameters
and their impact on overall plant efficiency
170 / 540 / 540
240 / 540 / 565
280/640/650
280/600/620
280/580/600
SC - Supercritical USC - UltraSupercriticalSubcritical
ΔHR
HR
201020001990198019701960
In development
COST 536
consolidatedconsolidated
in
operation
current
market
Efficiency increase on
Clean Coal Fired PP- USC application
The increasing of steam cycle parameters is the most promising way to improve the
efficiency of a modern coal fired Power Plant with low emissions.
7-8 %
31
• The old plant consisted of 4 x
660MW Ansaldo units, adopting an
oil fired supercritical cycle (250bar /
540°C / 540°C)
• The new plant consists of 3 x
660MW units, supplied by MHI,
adopting a clean coal ultra-
supercritical cycle (250bar/600°C/
610°C)
First unit start-up of commercial
operation: June 2009
Benefits:
• Efficiency gain from 40% to 45% => Δ 10%
• Emission SO2 ≤ 100mg/Nm3
• Emission Nox ≤ 100mg/Nm3
These values are about half of the limits stipulated in EU large combustion plant Directive
2001/80/CE.
Clean Coal Fired USC Conversion
Torrevaldaliga Nord 3 x 660MW / Italy
32
Conclusions
In these last ten years the italian power generation scenario deeply changed
The market liberalization forced the utilities to modernize the old power plants
to be competitive with new CCPP
On the old plant three basic strategies of intervention has been introduced to
gain efficiency:
• Repowering to combined cycle
• Modernization of existing coal fired power plants
• Conversion to clean coal USC of large power plants (660MW)
Example of modernizations have been illustrated, showing how a retrofit can
be attractive inside a modernization project