Module 2 Session 2.2 Visual 1
Module 2
Structuring the Project Organization
Session 2.1 Alternative Organizational Structures
Lecture 2.2.1 The Project Charter
Module 2 Session 2.2 Visual 2
Instructional Objectives
Given a Project Analysis Report (PAR) and other information, learners will be able to:
1. Describe the characteristics of the project charter
2. Distinguish between weak and strong project charters
3. Given a PAR or vignette characterize the organizational structure and project management role stated or implied in the document
4. Prepare a project charter that describes the project’s organizational structure and the roles and responsibilities of the project manager, project management core team, and functional departments (in a matrix environment)
Module 2 Session 2.2 Visual 3
A project charter is a document that
formally defines the authority and
responsibility relationships on a project.
Module 2 Session 2.2 Visual 4
Typical Elements in a Project Charter
Authority:The project manager has the delegated authority from top management to direct all project activities.
Responsibility:The project manager’s responsibilities are to the chief executive for overall project direction according to established business objectives and contractual requirements regarding technical specifications, schedules, and budgets.
More Specifically, the Project Manager Is Responsible for:
I) Establishing the project organization
II) Establishing and maintaining the project plan
III)Managing and controlling the project, and
IV) Communicating the project status
V) Escalating decisions or unresolved problems in a timely manner
Module 2 Session 2.2 Visual 5
The Project Charter Should AddressI) Establishing the project organization
1. The project manager's position directing all project activities
2. The need for a defined authority-responsibility relationship among
The project manager,
Functional managers,
Task managers, and
Top management
3. The need for influence to cut across functional and organizational lines
4. Collaborating (with the personnel office and the functional supervisors) in staffing the project
5. Establishing a project organization (a matrix organization) for the duration of the project
6. Having a voice in maintaining the integrity of the project team during the complete life of the project
7. Participation in the merit evaluation of key project personnel assigned to the project
8. The need to state clearly who the project sponsor is and what access the project manager has to him/her/them
Module 2 Session 2.2 Visual 6
The Project Charter Should Address (continued)
II) Establishing and maintaining the project plan
9. Establishing project plans through the coordinated efforts of the organizations involved in the project
10. Providing leadership in the preparation of operational requirements, specifications, and bid packages and change control
11. Active participation in major management and technical decisions
12. Allocating and controlling the use of funds on the project
Module 2 Session 2.2 Visual 7
III) Managing and controlling the project
13. Control over the allocation and expenditure of funds, and active participation in major budgeting and scheduling deliberations
14. Selection of subcontractors to support the project and the negotiation of contracts
15. Rights in resolving conflicts that jeopardize the project goals
16 Promoting technological and managerial improvements throughout the life of the project
17. Managing the cost, schedule, and technical performance parameters of the project
IV) Communicating project status
18. Providing an information system for the project with sufficient data for the control of the project within allowable cost, schedule and technical parameters
19. Maintaining prime customer liaison and contact on project matters
20. Reporting on project progress
V) Escalating decisions or unresolved problems in a timely manner
The Project Charter Should Address
Module 2 Session 2.2 Visual 8
The Project Manager’s Charter
“ Unless the project manager’s charter is delineated very
clearly, not only to him but to others in the organization, he
is neither fish nor fowl. He is not master of his destiny. The
charter is the environment that is created for the project
manager. It is 50% of the battle of whether he is successful
or not. It says, does he have management’s support to run
his project as he sees fit, or does someone else.”
David WilemonSyracuse University
Module 2 Session 2.2 Visual 9
Evaluating Your Charter
Are Your Authority and Responsibility Commensurate?
Do You Control the Budget?
Do You Have Enough Control Over Resources to Get the Job Done?
Will You Be Able to Make Things Happen?
Will Your Influence Be Able to Make up for Your Lack of Authority (Power)?
Do you have the authority (ability) to escalate pending decisions or unresolved problems to the organizational level needed to keep the project on schedule?
Module 2 Session 2.2 Visual 10
Selling Management on the Need for a Stronger Charter
Define the Problem (Lack of Authority)
Define Exactly What You Want
Think Through What Problems Those Changes Might
Cause Management With the Functional Departments
Analyze the Pros and Cons From Management’s
Viewpoint
Present a Strong Proposal
Module 2 Session 2.2 Visual 11
Project Manager
Organizational Design
Planning and Reporting System
Three Parameters
Module 2 Session 2.2 Visual 12
Key Variables Existing organizational structure Formal integration procedures
Internal External
Management systems Personnel available for roles Degree of predetermined structure inherent in
the project Pattern of demand on staff time Geography Management style
Module 2 Session 2.2 Visual 13
Organization
Organization chart Reporting relationships Project Sponsor Position descriptions Charter Project team Functional departments
Module 2 Session 2.2 Visual 14
Project Manager
Organizational Design
Planning and Reporting System
Three Parameters