MODULE “PROJECT MANAGEMENTAND CONTROL”
ORGANIZATION AND ADMINISTRATIVE CONTROL
SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS
Project BG/04/B/F/PP-166005, Programme “Leonardo da Vinci”
![Page 2: MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP-166005,](https://reader036.vdocument.in/reader036/viewer/2022082711/56649eb05503460f94bb5adf/html5/thumbnails/2.jpg)
Project BG/04/B/F/PP-166005, Programme “Leonardo da Vinci” 2
CONTENTS
1. Organization and management while preparing for decommissioning
2. Organization and management during facility transition
3. Organization and management for active phases of decommissioning
4. Organization and management in a safe enclosure phase
5. Organization and management for the post-dismantling and site remediation period
![Page 3: MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP-166005,](https://reader036.vdocument.in/reader036/viewer/2022082711/56649eb05503460f94bb5adf/html5/thumbnails/3.jpg)
Project BG/04/B/F/PP-166005, Programme “Leonardo da Vinci” 3
TRAINING OBJECTIVES
Upon completion of training trainees should be able to: Describe the purpose of the decommissioning project (for specified
nuclear facility). Explain the scope of organization and management while preparing
for decommissioning. Explain the scope of organization and management during facility
transition. Explain the scope of organization and management for active phases
of decommissioning. Explain the scope of organization and management in a safe
enclosure phase. Explain the scope of organization and management for the post-
dismantling and site remediation period.
![Page 4: MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP-166005,](https://reader036.vdocument.in/reader036/viewer/2022082711/56649eb05503460f94bb5adf/html5/thumbnails/4.jpg)
Project BG/04/B/F/PP-166005, Programme “Leonardo da Vinci” 4
DECOMMISSIONING PROJECT – MAIN AREAS
Systems and equipment; Activities related to decontamination actions, cleaning and
waste management; Documentation related to permit (license) for
decommissioning; Key elements:
• Spent fuel management;• Radioactive waste management.
![Page 5: MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP-166005,](https://reader036.vdocument.in/reader036/viewer/2022082711/56649eb05503460f94bb5adf/html5/thumbnails/5.jpg)
Project BG/04/B/F/PP-166005, Programme “Leonardo da Vinci” 5
DECOMMISSIONING PROJECT – MAIN AREAS
CEALicensee / Facilities Management and Project Management
Dismantling Cleaning Global assistance contract
Planning, BudgetPreparation of contractsData, records and reportsSpecification of work packages…
Contracts
Studies or small work packages
CEA
Fuel and specific
materials
Global Contracts
StudiesEquipment procurementImplementation of work
Support Contracts for siteWaste management – Transport – Studies for regulatory bodies – Coordination…
![Page 6: MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP-166005,](https://reader036.vdocument.in/reader036/viewer/2022082711/56649eb05503460f94bb5adf/html5/thumbnails/6.jpg)
Project BG/04/B/F/PP-166005, Programme “Leonardo da Vinci” 6
ORGANIZATION AND MANAGEMENT WHILE PREPARING FOR DECOMMISSIONIG
Team Leader
Decontamination & Dismantling
Waste Management Costing Licensing Planning Safety
![Page 7: MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP-166005,](https://reader036.vdocument.in/reader036/viewer/2022082711/56649eb05503460f94bb5adf/html5/thumbnails/7.jpg)
Project BG/04/B/F/PP-166005, Programme “Leonardo da Vinci” 7
ORGANIZATION AND MANAGEMENT DURING FACILITY TRANSITION
Decommissioning Operations
Temporary character of organizational structures supporting dismantling defined by a project
Lifetime of organizational operational structures as defined by the project
Management focused on safety assurance during decommissioning tasks implementation
Management focused on safe operations of nuclear facility
Decrease of radiation and non-radiation risks in continuously changing conditions
Considerable radiation or non-radiation risk in unchangeable and routine situation
Management in continuously changing situation Management in usual operational situation
Decreased administrative infrastructure Stable administrative infrastructure
Re-qualified staff for implementation of new activities Experienced staff periodically trained to maintain knowledge and skills
Visible final usage as per the purpose – adjusting to new working objectives
Continuous purposeful utilization, objectives focused on operations
New or restored requirements of regulatory bodies Establishment and development of operational requirements
![Page 8: MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP-166005,](https://reader036.vdocument.in/reader036/viewer/2022082711/56649eb05503460f94bb5adf/html5/thumbnails/8.jpg)
Project BG/04/B/F/PP-166005, Programme “Leonardo da Vinci” 8
ORGANIZATION AND MANAGEMENT DURING FACILITY TRANSITION
Licensee
Site Manager
Operations Manager
Project Manager
Health Physics Operations MaintenanceQA and
Technical Support
Work Area A - Engineer
Work Area B - Engineer
Etc.
Staff/ Contractors
Staff/ Contractors
![Page 9: MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP-166005,](https://reader036.vdocument.in/reader036/viewer/2022082711/56649eb05503460f94bb5adf/html5/thumbnails/9.jpg)
Project BG/04/B/F/PP-166005, Programme “Leonardo da Vinci” 9
ORGANIZATION AND MANAGEMENT FOR ACTIVE PHASES OF DECOMMISSIONING
Activities related to preparation for safe enclose or storage under surveillance
Activities related to creation of temporary jobs on site Supply and installation of process equipment needed for
decommissioning Creation of specialized job positions Activities related to operation of safe enclosure or storage under
surveillance Activities related to decommissioning process management, project
engineering support, site safety, staff training, studies and developments to support decommissioning process, work with population
![Page 10: MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP-166005,](https://reader036.vdocument.in/reader036/viewer/2022082711/56649eb05503460f94bb5adf/html5/thumbnails/10.jpg)
Project BG/04/B/F/PP-166005, Programme “Leonardo da Vinci” 10
ORGANIZATION AND MANAGEMENT FOR ACTIVE PHASES OF DECOMMISSIONING
ORGANIZATION OF THE MANAGEMENT TEAM THE DECOMMISSIONING MANAGEMENT TEAM
![Page 11: MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP-166005,](https://reader036.vdocument.in/reader036/viewer/2022082711/56649eb05503460f94bb5adf/html5/thumbnails/11.jpg)
Project BG/04/B/F/PP-166005, Programme “Leonardo da Vinci” 11
ORGANIZATION AND MANAGEMENT FOR ACTIVE PHASES OF DECOMMISSIONING
Licensee
Decontamination & Dismantling
Administration Services
Decommissioning Operations
Technical Support
Waste Management
Maintenance
Specialist Contractors
Radiation Protection
Industrial Safety
Quality Assurance
Engineering
Regulatory
Accounting & Finance
Contracts & Procurement
Information Management
Personnel & Training
Security - Safeguards
![Page 12: MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP-166005,](https://reader036.vdocument.in/reader036/viewer/2022082711/56649eb05503460f94bb5adf/html5/thumbnails/12.jpg)
Project BG/04/B/F/PP-166005, Programme “Leonardo da Vinci” 12
ORGANIZATION AND MANAGEMENT FOR ACTIVE PHASES OF DECOMMISSIONING
MANAGEMENT OF CHANGE• Technical changes • Organizational changes• Plan for social impact of decommissioning• Assessment of loss of staff influence on safety
![Page 13: MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP-166005,](https://reader036.vdocument.in/reader036/viewer/2022082711/56649eb05503460f94bb5adf/html5/thumbnails/13.jpg)
Project BG/04/B/F/PP-166005, Programme “Leonardo da Vinci” 13
ORGANIZATION AND MANAGEMENT IN A SAFE ENCLOSURE PHASE
Simplified process diagram of nuclear facility, minimal operational requirements, control and maintenance, well-defined risk and its control
Minimal need of operational staff Activities that considerably decrease the emergency
preparedness activities are performed Reduced requirements for nuclear facility physical
protection Reduced necessity of environmental monitoring
![Page 14: MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP-166005,](https://reader036.vdocument.in/reader036/viewer/2022082711/56649eb05503460f94bb5adf/html5/thumbnails/14.jpg)
Project BG/04/B/F/PP-166005, Programme “Leonardo da Vinci” 14
ORGANIZATION AND MANAGEMENT IN A SAFE ENCLOSURE PHASE
Site Manager
Health Physics
Inspection & Maintenance
Record Maintenance
![Page 15: MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP-166005,](https://reader036.vdocument.in/reader036/viewer/2022082711/56649eb05503460f94bb5adf/html5/thumbnails/15.jpg)
Project BG/04/B/F/PP-166005, Programme “Leonardo da Vinci” 15
ORGANIZATION AND MANAGEMENT IN A SAFE ENCLOSURE PHASE
![Page 16: MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP-166005,](https://reader036.vdocument.in/reader036/viewer/2022082711/56649eb05503460f94bb5adf/html5/thumbnails/16.jpg)
Project BG/04/B/F/PP-166005, Programme “Leonardo da Vinci” 16
ORGANIZATION AND MANAGEMENT FOR THE POST-DISMANTLING AND SITE REMEDIATION
PERIOD
Transition of nuclear facility from dismantling to post-dismantling phase
Full or partial release from regulatory control and site release
Development of final documentation
![Page 17: MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP-166005,](https://reader036.vdocument.in/reader036/viewer/2022082711/56649eb05503460f94bb5adf/html5/thumbnails/17.jpg)
Project BG/04/B/F/PP-166005, Programme “Leonardo da Vinci” 17
REFERENCES
Decommissioning of Nuclear Power Plants and Research Reactors, Safety Guide, SS № WS-G-2.1 (1999)
Organization and Management for the Decommissioning of Large Nuclear Facility, TRS № 399 (2000)
Planning, Organizational and Management Aspects of Decommissioning: Lessons Learned, IAEA-TECDOC-1394 (2004)
Technical project for decommissioning of Units 1, 2 of NPP “Kozloduy”