  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    1/21

     

    P u b l i c W o r k s A u t h o r i t y

    DRAINAGE AFFAIRS  

    DOHA WEST SEWAGE TREATMENT WORKS

    EXTENSION 05

    CONSULTANT

    egis

    CONTRACTOR

    Suez Environment- Marubeni JV

    SUB CONTRACTOR

    Gulf East Engineering, Contg. & Trading Co.

    Method S ta tement fo r the Ins ta l la t ion & T ie - In o f UG-GRP

    Pipe- 533__ESA103_  

    00 15-03-2016 21 AJIT CHACKO ANISH DEV SHASHI PILLAI

    REV. DATE PAGES PREPARED CHECKED REVIEWD APPROVED CLIENT APPRD

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    2/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 2 / 21  Date: 15/03/2016 

    TABLE OF CONTENTS

    1.  PURPOSE

    2.  SCOPE

    3.  APPLICABLE CODES, STANDARDS AND REFERENCES

    4.  DEFINITIONS AND ABBREVIATIONS

    5.  RESPONSIBILITY

    6.  TRAINING

    7.  MATERIALS HANDLING AND STORAGE

    8.  MANPOWER, TOOLS AND EQUIPMENT

    9.  PROCEDURE

    10.  SEQUENCE OF INSTALLATION

    11.  SAFETY PRECAUTIONS

    12.  LIFTING PLAN

    13.  ATTACHMENTS

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    3/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 3 / 21  Date: 15/03/2016 

    1.  PURPOSE 

    This Method Statement is prepared to define the procedures that Gulf East Engineering will implement in

    process of Tie-in Connection (Tie-in No.38 & 39) for line no. 533__ESA103_. These Tie-In’s are done to

    avoid clash with the pipes 539__EFI018_ & 589B_ETT001_, which shall be laid in future.

    Where and when required, all the revisions, modifications and additions to this Method statement shall be

    submitted to the consultant for information and/or approval.

     Area highlighted yellow in Fig 1. below shows the area of work.

    Fig 1.

    2.  SCOPE 

    The scope of this method statement covers the minimum requirements, Procedures and Standards that

    must be adhered to while installing the UG Pipelines. The activities include material reception from Stores,

    Loading, Shifting the material to area of work, Unloading and Installation.

    The Scope is limited to the following category of pipelines identified as listed hereunder.

    a) 533__ESA103_ - Dirty Water from Existing UF to inlet works.

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    4/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 4 / 21  Date: 15/03/2016 

    3.  APPLICABLE CODES, STANDARDS AND REFERENCES

    3.1. DOCUMENTATION1. QCS 2010

    2. PROJECT HSE PLAN

    3. PROJECT QUALITY PLAN

    3.2. INTERCONNECTING PIPE DRAWINGS1. DGT-M-DR-000-801-C 

    2. DGT-M-DR-000-805-C

    3. DGT-M-DR-000-821-C

    4. DGT-M-DR-000-827-A

    3.3. ISOMETRIC DRAWINGS1. 533__ESA103_ Rev 2

    3.4. FLOWTITE Installation guide for buried pipes  –AWWA.3.5. Pipe List DGT-X-LT-000-801

    4.  DEFINITIONS AND ABBREVIATIONS 

    4.1. Definition

    Pipes : Circular tubes through which fluid can flow

    Installation : Material transport and handling, pipe laying including the complete operationof laying, jointing and testing pipes in trenches.

    Pipeline : long, continuous line of pipes and fittings including valves and ancillary structures

    Plant : Doha West STP

    Client : Suez Environment Marubeni JV

    Consultant : Egis.

    Contractor : Gulf East Engineering, Contracting & Trading

    4.2. Abbreviation

    SUEZ : Suez Environment

    GE : Gulf East Engineering, Contracting & Trading

    HSE : Health, Safety & Environment

    BLDG. : Building

    GRP : Glass Reinforced Plastic

    UG : Under Ground

    PTW : Permit To work

    QA/QC : Quality Assurance / Quality Control

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    5/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 5 / 21  Date: 15/03/2016 

    5.  RESPONSIBILITY

    GUILHEM JOLY

    HSE MANAGER

    MATTHEIU PILLOT

    CONSTRUCTION

    MANAGER

    AHMED SHAWKY SITE

    ENGINEER UNDERGROUND

    NETWORK

    KHALED YOUSSEF

    GRP ERECTION PIPING

    SUPERVISOR

    MANDAL JAGESHWARQC INSPECTOR

    SUEZ

    SAISH K PILLAI

    PROJECT MANAGER

    SHASHI KUMAR PILLAI

    CONSTRUCTION

    MANAGER

    PLANNINGENGINEER

    AJIT CHACKODOC.

    CONTROLLER

    ANISH DEV.SPROJECT ENGINEER

    QA/QCSITE SUPERVISORS

    WORKERS

    VISHNU K.VHSE OFFICER

    GULF EAST

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    6/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 6 / 21  Date: 15/03/2016 

    The Project Manager- GULFEAST 

    a) Supervise and coordinate between the project teams.

    b) Attend site meetings on regular basis.c) To ensure the effective implementation for the Quality management system

    d) Coordination and comply with project work program.

    e) To ensure the overall progress of project to the agreed program.

    f) To ensure availability of the required resources on time.

    g) To supervise the Project engineers.

    The Construction Manager- GULFEAST 

    a) Manage and oversee the day to day construction management of the Project.

    b) Plan, Develop and Organise the construction effort to formulate the most effective plan for the

    timely completion of each activity and in effect the Project.

    c) Responsible for implementation of scope of work  –  fabrication, erection, testing, hook-up in

    conformance with the project requirements.

    d) Monitor and report to PM the project details including progress, risks, Pull backs and Open

    opportunities.

    e) Investigate reasons for unsatisfactory performance and provide recommendation and institute

    measures for improvement.

    The Project Engineer- GULFEAST 

    a) Act as the main contact for the Construction Manager

    b) Ensure the progress of Project to agreed Program

    c) To coordinate with the design team dedicated to the Project

    d) To check all technical details in liaise with the QA QC.

    e) To Supervise the Site in all.

    QA/QC Engineer/Inspector- GULFEAST 

    a) Ensure work has been done as per the specification and drawings, inspections are done as per

    Quality Control Procedure and the Inspection and Test plan are up to date.

    b) Prepare all quality documents and procedures as required.

    c) Perform random site inspections on regular basis.

    d) Raise RFI’s through Site Query (SQ) systems. 

    e) To raise non- Conformances for any deviations in the materials, installation procedures,

    workmanship.

    f) To follow up all non-conformance notices till the closure and maintain logs of all these items.

    g) Ensure that the latest approved drawings are being used by the site personnel.

    HSE Officer- GULFEAST 

    a) Confirm that all people working at site are safety inducted.

    b) To make sure that all personnel’s are wearing the proper required PPE’s 

    c) Identify the hazards involved in each work activity and advice the workforce the correct safety

    measures to be followed.

    d) Perform routine checks for validation of Certificates of trained Manpower and machines utilized

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    7/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 7 / 21  Date: 15/03/2016 

    e) Attend weekly meeting with the Client HSE Manager.

    f) Observe that the working hours are strictly followed during Summer.

    Construction Manager –

     SUEZWill be in charge to ensure that the works are done in accordance with the project

    requirements. He will also make sure about proper between site engineer carrying out simultaneous

    activities such as Piping , Equipment etc.. He will be attending the construction meeting with the client

    representative and will report to his team the client expectation.

    Site Engineer  –SUEZ

    Shall be responsible of the coordination of the works. He will be the one making sure proper

    interfaces with civil work partner as well as with the client representative. He will also check and solve the

    technical concerns.

    Site Supervisor -SUEZ

    Is responsible to follow the work at site and to make sure that works happen

    according to method statement and project requirements. The site Supervisor will attend to all site

    inspection.

    QC Inspector -SUEZ

    Is responsible to organize and attend site inspection in accordance with the project

    specification, QCS and ITP. He will be responsible to follow the inspection up the issuance of the

    inspection report dully signed.

    HSE Manager -SUEZ

    Will make sure that safety requirement as HSE project plan and procedure are fulfilled.

    6.  TRAINING

    6.1. Safety Induction shall be provided to any employee/ Visitor entering the site. 6.2. Before start of any work, VIGIMINUTE to be performed by all work Crew members on a daily basis.6.3. Only trained and certified personnel’s shall be engaged in activities demonstrating high risk rate or in

    situations where the presence of a trained personnel is mandatory.

    7.  MATERIALS HANDLING AND STORAGE 

    7.1. All materials shall be inspected for any fabrication defects, In-transit defects such as deep scratches,cracks etc.. prior to reception of materials from Stores. Further the person in charge for accepting thematerials should assure that the permanent identification tags denoting the nominal diameter, name ofmanufacturer, Spool number etc. are present on each material received.

    7.2. Any Visible defects beyond the agreed tolerances shall not be accepted and the anomaly shall beimmediately reported to the concerned Engineer.

    7.3. Coordination with the installation team and logistics should go hand in hand to avoid trouble handlingand reduce unnecessary material transfer and time wastage.

    7.4. Transportation, Handling and Storage shall be strictly in accordance with the manufacturer’srecommendation.

    7.5. During Transporta) Pipes and fittings shall be well secured and adequately supported along their length.

    b) Nesting of pipes may be permitted.

    c) No pipe shall overhang the end of a vehicle.

    7.6. Handling shall be carried out as follows:a) Pipes should be lifted singly and not handled as bunches

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    8/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 8 / 21  Date: 15/03/2016 

    b) Pipes shall be handled only by means of approved hooks or fabric slings

    c) Use of wire ropes, chains will not be permitted.

    d) Pipes and fittings of diameter smaller than 300mm may be handled manually.e) Pipes and fittings shall not be dropped or bumped.

    f) Pipes shall not be dragged over the ground.

    6. Storage of jointing material shall be as follows: 

    a) Under cover

    b) Rubber ring gaskets shall be stored in their original packing and not be exposed to sunlight.

    c) Rubber ring gaskets must be protected from exposure to grease and oils.

    d) Gasket lubricant shall be stored in shade and in the original container.

    8.  MANPOWER, TOOLS AND EQUIPMENT

    8.1. Direct Manpower

    - Supervisor - 01

    - Safety Officer - 01

    - QA/QC Inspector - 01

    - Surveyor - 01

    - Fitter - 04

    - Helper - 04

    - Rigger - 01

    8.2. Tools & Equipment

    - Trailer / Truck - 01

    - Crane 25T - 01

    - Total Station - 01

    - Hand Tools - Lot

    - Chain puller - As per requirement

    - Webbing slings - As per requirement

    -

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    9/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 9 / 21  Date: 15/03/2016 

    9. PROCEDURE

    9.1.1. Preparation for work

    - Obtain PTW prior to start of any work.

    - Barricade the area to avoid unauthorized/unwanted entry and encroachment.

    - Conduct topographic survey of existing pipelines and mark the area for tie-in 38 & 39 asshown in Fig2.

    - As-Built drawings shall be prepared based on this survey. Variations if any with theisometric drawings shall be noted down and the drawings revised accordingly. The newdrawing shall be submitted to the consultant for approval.

    - Check the bottom level and width of trench and make sure it meets the requirements.

    - List out the required tools and tackles to carry out the shutdown activity and accumulatethose items in the reserved tool box.

    - When all the above requirements are met shift all pipes of portion A to A as shown in Fig3.

    - The pipes and fittings shall be transported by using trailer/ Truck and will be offloaded tothe trench using crane in a safe and proper way.

    Fig 2.

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    10/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 10 / 21  Date: 15/03/2016 

    Fig 3.

    9.1.2. Joining of GRP pipes:

    Joining of pipes shall be made as per the procedure and directions of pipe supplier. Thefollowing steps to be followed during installation of GRP pipes. There are different types methodof joining and the following joining method and procedure shall be applied;

     All the pipes as per the required length shall be joined with coupling, which is called as double

    bell coupling joint. The following steps shall be followed;

    - Foundation & Bedding: The bed must be over excavated at each joint location to ensure

    that the pipe will have continuous support and does not rest on the coupling. The

    coupling area must be properly bedded and backfilled after the joint assembly completed.

    - Cleaning of Coupling:  All the coupling grooves and other parts shall be thoroughly

    cleaned to ensure no dirt, presence of oil and any other unwanted particles inside the

    coupling and its groove. (see below cleaning method)

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    11/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 11 / 21  Date: 15/03/2016 

    - Install Gaskets:  Insert the rubber gasket in to the coupling groove leaping loops (typically

    two to four) of rubber extending out of the groove. And it is restricted to apply any kind of

    lubricants in the groove or on the gasket at this stage of assembly. Water may be used to

    moisten the gasket and groove to ease positioning and insertion of the gasket. (See below

    picture). Apply uniform pressure and push each loop of the rubber gasket in to the gasket

    groove. After insertion pull carefully in the radial direction around the circumference to

    distribute compression of the gasket.

    - Lubricate Gaskets: Apply a thin layer of lubricant to the rubber gaskets (see below picture)

    in order to get flexibility and easiness to insert the pipe.

    - Clean and Lubricate Spigots: Clean thoroughly the pipe spigots to remove any dirt, grit,

    grease and other unwanted/foreign materials (see below picture). Inspect the spigot sealing

    surface for possible damage and apply a thin layer of lubricant to the spigots from the end to

    the black alignment stripe. Keep clean both the coupling and spigot until completion of

    insertion.

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    12/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 12 / 21  Date: 15/03/2016 

    - Coupling shall be mounted on one pipe, prior join two pipes together, by using clamp or

    sling around the pipe at a distance of 1 to 2 meter from the spigot on to which the

    coupling will be mounted.

    - Make sure that the coupling as well as the pipe should have enough gaps from the

    ground or at least 100 mm above the ground level to keep away from dirt. Other

    techniques may also be used to joining the coupling/pipes.

    - Fixing of Clamps: Clamp/slings shall be fixed on the first pipe or left in the position from

    the previous joint. (See below pictures). Clamp contact with the pipe shall be padded or

    otherwise protected to prevent damage to the pipe surface.

    - Join Coupling: Come alone jacks or any other alternative mechanism placed on the pipe

    and connected to the clamps. Pipe shall be pulled into position in to the coupling until it

    reaches the home line or touches the centre register. Then it shall be moved on to the

    next pipe to be joined.

    Home line = (Width of coupling- Gap between adjacent pipes)/2.

    Normally the pipes we are using at site have either single spigot (SP) or double

    spigot (DSP). Refer the Table 1 below for spigot dimensions

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    13/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 13 / 21  Date: 15/03/2016 

    Table 1

    The final spool or the closure spool to be installed will be DSP spools, in some cases it will be

    the rocker pipes with DSP.

    Select two couplings to be installed and place one coupling square onto the end of closure

    pipe (with DSP) so that the gasket is in contract around its entire circumference. Push or pull

    the coupling uniformly onto closure pipe until the entire coupling is resting on the spigot end. It

    may be necessary to gently help the second ring over the chamfered end of the pipes. Repeat

    with the second coupling on the other end.

    Set the closure pipe (with DSP) in the trench aligned with the adjacent pipes and with equal

    clearance on either side.

    Keep the closure pipe centred and minimize pipe end contact. Pull the coupling till it touches

    the home line of adjacent pipe.

     All this have been shown in the drawing below.

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    14/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 14 / 21  Date: 15/03/2016 

    - Flanged Joints: GRP flanges shall be joined according to the following procedure;

    1. Clean the flange face thoroughly and the O-ring groove as well

    2. Ensure the sealing gasket / O-ring is clean and undamaged.

    3. Position the sealing gasket/ O-ring in the cleaned groove and be secured with small

    strips of tape or adhesive.

    4. Align flanges to be joined and tightened with required bolts, nuts and washers.

    5. Tighten all the bolts by using proper spanners/torque wrench and check the torque

    value with Manufacturer.

    6. Check all the bolts once again after one hour to ensure the bolts are properly tightened

    or to adjust to get the required torque value if necessary.

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    15/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 15 / 21  Date: 15/03/2016 

    - Other Joining Methods: Mainly there are two kinds of other methods are there to join

    two pipes or to join 2 different kind of materials. In this case we have to follow the below

    mentioned procedure/steps.

    Flexible steel Coupling method (See below picture): When a GRP pipe connecting to

    other pipe materials with different outside diameter, the flexible steel coupling joining

    method shall be applicable. These couplings consist of a steel mantle with an interior

    rubber sealing sleeve.

    It is important that to control the bolting torque of the flexible steel coupling. Do not over

    tight/torque these coupling bolts and follow only manufactures recommended assembly

    instructions, but with the pipe supplier’s recommended bolt torque limits. 

    Mechanical Steel Couplings: Mechanical couplings have been successfully to join pipes

    of different materials and diameters, and to adapt to flange outlets. If a mechanical

    coupling is used to join GRP to another pipe material then only mechanical coupling with

    dual independent bolting system shall be used (see below picture). This allows for the

    independent tightening of the GRP pipe side, which typically requires less torque than

    recommended by the coupling supplier.

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    16/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 16 / 21  Date: 15/03/2016 

    - Joints shall be capable of withstanding the various tests specified for the appropriate class

    of pipe. Joints shall withstand, while maintain the specified test pressure ,a deflection of

    not less than 1.5% in any direction.

    - After completing the pipeline installation the entire system shall be tested according to the

    procedure submitted separately as well as pipe list DGT-X-LT-000-801 B.

    - Clear the area and do the house keeping properly prior to handover to civil for backfilling.

    - A joint inspection shall be made along with the consultant and main contractor Engineer

    as per ITP/RFI for final approval and hand over to civil contractor.

    10. SEQUENCE OF INSTALLATION

    a) Pipe installation shall commence in portion A-B (Ref Fig 4) .Pipes shall be laid in

    sequence as shown in fig 4. This installation shall be done without disturbing the

    existing lines nearby. 

    b) Pre-assemble the spool from B to C and A to D (Ref Fig 4) . This is done to save time

    during the actual installation process during tie-in. 

    Fig 4

    c) Partial backfilling of portion A to B shall be done by the civil contractor. The joints shall

    be exposed for detection of any leaks during operation.

    d) Existing pipe shall be emptied of fluid and valves to be isolated shall be locked out.

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    17/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 17 / 21  Date: 15/03/2016 

    This shall be done in coordination with O&M.

    e) Obtain PTW and LOTO before commencing any cutting or modification works on the

    existing pipe. The Supervisor should confirm that the correct valves have been shut as

    mentioned in the LOTO sheet.

    f) Upon reception of the PTW, Cut out the existing pipe from the previously marked area

    to a length favorable for the installation of new pipe. Two teams shall work

    simultaneously for this activity. 

    g) Pre-assembled spools shall now be placed inside the trench. The connection at point

     A & B shall be made via GRP Bell coupling and at point C&D where the connection to

    existing pipe occurs, shall be done through Steel Coupling. The data sheet for steel

    coupling is attached here with this MOS. 

    11. SAFETY PRECAUTIONS

    a) Isolate the area with proper barrier and warning tape in order to control unauthorized entry to

    the working area.

    b) Provide common safety equipment at site (fire extinguisher, bucket with sand, fire watch etc.)

    in accordance with fire and safety regulations.

    c) Prior to start the activity; ensure that all work permit have been obtained from concerned

    authorities as per the general site requirements.

    d) Ensure that all lifting equipment shall be certified and the lift/drop zone shall be barricaded

    with warning tape and sign boards.

    e) Daily tool box talk shall be conducted by the supervisor prior to commencement of each day

    activity.

    f) Make sure that there shall be adequate air circulation or proper ventilation for the working

    area.

    g)  A dedicated safety officer and supervisor shall be responsible to ensure all safety precautions

    and requirements.

    h) Ensure proper PPEs for all working groups at all time.

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    18/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 18 / 21  Date: 15/03/2016 

    12. LIFTING PLAN

      The Lifting Plan describes the List of Equipments and Safety measures deployed for theinstallation of GRP underground Pipe identified as 533__ESA103_

      As outlined in this method statement, any activity shall commence only after the receptionof a valid work permit.

      The concerned Work Supervisor shall coordinate with the Lifting team in arranging allrequired tools and tackles for the work. He must ensure that the Crane Operator, Riggerand Banks man are competent and are holding a valid training certificate.   It shall beconfirmed in advance that the crane and all associated vehicles have safe and unimpededaccess and egress to and from site.

      Communication between the crane operator and Lifting crew shall be via hand signals.

      The following Equipments are purposed for the activity

    o  Crane - 50 T Capacity, Model No. NK 500 E-V, Manufacturer - KATOo  Trailer/ Truck

    Once the approval for work is validated, Crane shall be positioned to Stages as shown inFig 5.

    Fig 5.

    The area shall be cordoned off with barrication tape and Proper Cautionary Signage. Thisstep shall be followed for positioning cranes in different stages based on the installationProgress.

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    19/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 19 / 21  Date: 15/03/2016 

    Loading Chart

     

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    20/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 20 / 21  Date: 15/03/2016 

  • 8/19/2019 MS for Installation of GRP UG Piping for 533_ESA103

    21/21

     

    DOHA WEST SEWAGE TREATMENT WORKS EXT#5

    METHOD STATEMENT FOR THE INSTALLATION &TIE-IN OF UG-GRP PIPELINE  – 533__ESA103_

    Doc No: GE-SUEZ-MS-002

    Rev. 0 

    Page 21 / 21  Date: 15/03/2016 

    13. ATTACHMENTS 

      Isometric Drawings

      ITP

      Risk Assessment

      Particular Technical Specification for Couplings

      Crane Catalogue – KATO NK-500 EV