MSE-415: Product Design Lecture #3. Chapter 16 Managing Projects. Lecture Objectives:. Homework #1 (Hand in blank paper with name if not done for attendance points) Group Formation Lab Notebook procedure Chapter 16 - Managing Projects Fundamental characteristics of interacting tasks - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: MSE-415: Product Design Lecture #3

1Rev: 5/05/07 MSE-415: B. Hawrylo

Chapter 16Managing Projects

MSE-415: Product DesignLecture #3

MSE-415: Product DesignLecture #3

Page 2: MSE-415: Product Design Lecture #3

2Rev: 5/05/07 MSE-415: B. Hawrylo

Lecture Objectives:

Lecture Objectives:

•Homework #1 (Hand in blank paper with name if not done for attendance points)

•Group Formation•Lab Notebook procedure•Chapter 16 - Managing Projects

Fundamental characteristics of interacting tasks

•Agree upon design project

Page 3: MSE-415: Product Design Lecture #3

3Rev: 5/05/07 MSE-415: B. Hawrylo

Chapter 16 – Managing ProjectsChapter 16 – Managing Projects

3 Types of tasks

Page 4: MSE-415: Product Design Lecture #3

4Rev: 5/05/07 MSE-415: B. Hawrylo

Chapter 16 – Managing ProjectsChapter 16 – Managing Projects

We’re going to talk about task-based…

Page 5: MSE-415: Product Design Lecture #3

5Rev: 5/05/07 MSE-415: B. Hawrylo

Chapter 16 – Managing ProjectsChapter 16 – Managing Projects

Project task

Page 6: MSE-415: Product Design Lecture #3

6Rev: 5/05/07 MSE-415: B. Hawrylo

Practice

Practice

A B C D E F G H I J

A *                  

B X *               X

C     * X   X     X  

D       *           X

E         *       X  

F   X       *     X  

G X     X     *      

H X             * X X

I X               *  

J             X X X *

• Task C requires information from what tasks?• Task D transfers information to what tasks?

Example #1 Example #2

A B C D E F G H I J

A *   X              

B   *                

C     *   X X        

D       *            

E X       * X        

F         X *        

G   X         *      

H   X           *    

I           X     *  

J X X       X       *

• Task E requires information from what tasks?• Which tasks are interdependent coupled?

Page 7: MSE-415: Product Design Lecture #3

7Rev: 5/05/07 MSE-415: B. Hawrylo

Practice

Practice

A B C D E F G H I J

A *                  

B X *               X

C     * X   X     X  

D       *           X

E         *       X  

F   X       *     X  

G X     X     *      

H X             * X X

I X               *  

J             X X X *

• Task C requires information from D, F, I• Task D transfers information to C, G

Example #1 Example #2

A B C D E F G H I J

A *   X              

B   *                

C     *   X X        

D       *            

E X       * X        

F         X *        

G   X         *      

H   X           *    

I           X     *  

J X X       X       *

• Task E requires information A, F• E, F tasks are interdependent coupled.

Page 8: MSE-415: Product Design Lecture #3

8Rev: 5/05/07 MSE-415: B. Hawrylo

Gantt BasicsGantt Basics

•Basically, a timeline with tasks that can be connected to each other

•Can be created with simple tools like Excel, but specialised tools like Microsoft Project make life easier

Page 9: MSE-415: Product Design Lecture #3

9Rev: 5/05/07 MSE-415: B. Hawrylo

Making a Gantt chartMaking a Gantt chart

•Step 1 – list the tasks in the project

Page 10: MSE-415: Product Design Lecture #3

10Rev: 5/05/07 MSE-415: B. Hawrylo

•Step 2 – add task durations

Making a Gantt chartMaking a Gantt chart

Page 11: MSE-415: Product Design Lecture #3

11Rev: 5/05/07 MSE-415: B. Hawrylo

•Step 3 – add dependencies (which tasks cannot start before another task finishes)

Making a Gantt chartMaking a Gantt chart

Page 12: MSE-415: Product Design Lecture #3

12Rev: 5/05/07 MSE-415: B. Hawrylo

•The arrows indicate dependencies.

•Task 1 is a predecessor of task 2 – i.e. task 2 cannot start before task 1 ends.

•Task 3 is dependent on task 2. Task 7 is dependent on two other tasks

•Electrics, plumbing and landscaping are concurrent tasks and can happen at the same time, so they overlap on the chart. All 3 can start after task 4 ends.

•Painting must wait for both electrics and plumbing to be finished.

•Task 9 has zero duration, and is a milestone

Making a Gantt chartMaking a Gantt chart

Page 13: MSE-415: Product Design Lecture #3

13Rev: 5/05/07 MSE-415: B. Hawrylo

•Step 4 – find the critical path

The critical path is the sequence of tasks from beginning to end that takes the longest time to complete.

It is also the shortest possible time that the project can be finished in.

Any task on the critical path is called a critical task.

No critical task can have its duration changed without affecting the end date of the project.

Making a Gantt chartMaking a Gantt chart

Page 14: MSE-415: Product Design Lecture #3

14Rev: 5/05/07 MSE-415: B. Hawrylo

• MS Project can work out the critical path for you!• The length of the critical path is the sum of the lengths

of all critical tasks (the red tasks 1,2,3,4,5,7) which is 2+3+1+1.5+2+1 = 10.5 days.

• In other words, the minimum amount of time required to get all tasks completed is 10.5 days

• The other tasks (6,8) can each run over-time before affecting the end date of the project

Page 15: MSE-415: Product Design Lecture #3

15Rev: 5/05/07 MSE-415: B. Hawrylo

• The amount of time a task can be extended before it affects other tasks is called slack (or float).

• Task 6 can take an extra day and a half before it affects the project’s end date, so each has 1.5 day’s slack.

Making a Gantt chartMaking a Gantt chart

Page 16: MSE-415: Product Design Lecture #3

16Rev: 5/05/07 MSE-415: B. Hawrylo

Critical tasks, by definition, can have NO slack.

Tip:

If ever asked Can task X’s duration be changed without affecting the end date of the project?, if it is a critical task the answer is always NO!

Making a Gantt chartMaking a Gantt chart

Page 17: MSE-415: Product Design Lecture #3

17Rev: 5/05/07 MSE-415: B. Hawrylo

This PERT chart follows the “Activity on Arrow” style.

•The tasks are shown by arrows. Task name are shown by letters, in this case.

•The circles are called nodes. The nodes indicate the start or end of tasks.

•Task durations are the shown by the numbers.

PERT ChartsPERT Charts

Page 18: MSE-415: Product Design Lecture #3

18Rev: 5/05/07 MSE-415: B. Hawrylo

The path duration is:

•A-B-C-E-I = 2+3+1+4+3=13

•A-B-D-F-I = 2+3+3+3+3=14

•A-G-H-I = 2+2+5+3 = 12

Therefore,

•Completion time = 14

•Critical path is A-B-D-F-I

•Slack time of A-B-C-E-1 = 1

•Slack time of A-G-H-1 = 2

PERT ChartsPERT Charts

Page 19: MSE-415: Product Design Lecture #3

19Rev: 5/05/07 MSE-415: B. Hawrylo

Pert Example

Pert Example

A.1

B.2

C.1

D.2

E.3

F.1

G.1

H.2

I.2

J.1

K.2

L.1

M.1

What is the duration to complete path A-D-H-J-L?What is the critical path?How does the project duration change if task E is shorten to 2? How about 1?What is the best way to shorten the total duration?

Page 20: MSE-415: Product Design Lecture #3

20Rev: 5/05/07 MSE-415: B. Hawrylo

Chapter 16 – Managing ProjectsChapter 16 – Managing Projects

Baseline Project Planning

The Contract BookProject Task ListTeam Staffing and OrganizationProject ScheduleProject BudgetProject Risk Plan

Page 21: MSE-415: Product Design Lecture #3

21Rev: 5/05/07 MSE-415: B. Hawrylo

Chapter 16 – Managing ProjectsChapter 16 – Managing Projects

The Contract Book Documents the project plan

Mission Statement, Customer needs list, competitiveanalysis, product specifications, sketches, concept report,sales forecast, economic analyses, manufacturing plan,project plan, project performance, incentives…

Page 22: MSE-415: Product Design Lecture #3

22Rev: 5/05/07 MSE-415: B. Hawrylo

Chapter 16 – Managing ProjectsChapter 16 – Managing Projects

Project Task List

List the tasks which make up the project.Estimate the amount of time required for each task

Task Estimated Person-WeeksTask 1 8Task 2 16Task 3 24

Page 23: MSE-415: Product Design Lecture #3

23Rev: 5/05/07 MSE-415: B. Hawrylo

Chapter 16 – Managing ProjectsChapter 16 – Managing Projects

Team Staffing and Organization The speed at which a team can complete a projectis based upon 7 criteria.

1. There are 10 or fewer members of the team.2. Members volunteer to serve on team.3. Members serve on the team from the time of concept

development to launch.4. Members are assigned to the team full-time.5. Members report directly to team leader.6. The key functions are on the team.7. Members are located within conversational distance to

one another.

Page 24: MSE-415: Product Design Lecture #3

24Rev: 5/05/07 MSE-415: B. Hawrylo

Chapter 16 – Managing ProjectsChapter 16 – Managing Projects

Project Schedule Merger of the project task and project timeline.

1. Use the DSM or PERT to identify dependencies.2. Position key milestones.3. Schedule tasks, considering the project staffing and

critical resources.4. Adjust the timing of the milestone to be consistent

with the time required for the tasks.

Page 25: MSE-415: Product Design Lecture #3

25Rev: 5/05/07 MSE-415: B. Hawrylo

Chapter 16 – Managing ProjectsChapter 16 – Managing Projects

Project Budget Often represented by a simple spreadsheet.

1. Staff salaries2. Materials/services3. Prototype Molds4. Outside Resources5. Travel6. Other?

Page 26: MSE-415: Product Design Lecture #3

26Rev: 5/05/07 MSE-415: B. Hawrylo

Chapter 16 – Managing ProjectsChapter 16 – Managing Projects

Project Risk PlanDealing with project variation

Teams should compile a list of what can go wrong and how to solve problems should they occur.

Risk Risk Level Actions to MinimizeA Moderate A1, A2, A3B Low B1, B2C High C1, C2, C3, C4

Page 27: MSE-415: Product Design Lecture #3

27Rev: 5/05/07 MSE-415: B. Hawrylo

Chapter 16 – Managing ProjectsChapter 16 – Managing Projects

Modifying the Baseline PlanAccelerating the Plan

1. Start the project early.2. Manage the project scope.

• Don’t allow ‘feature creep’3. Facilitate the exchange of essential information.4. Complete tasks on critical path more quickly.5. Aggregate safety times.6. Eliminate some critical paths entirely.7. Eliminate waiting days for critical path resources.8. Overlap some critical tasks.9. Pipeline large tasks10.Outsource some tasks

Page 28: MSE-415: Product Design Lecture #3

28Rev: 5/05/07 MSE-415: B. Hawrylo

Chapter 16 – Managing ProjectsChapter 16 – Managing Projects

Modifying the Baseline PlanAccelerating the Plan

11.Perform more iterations quickly.12.Decouple tasks to avoid iterations.13.Consider sets of solutions.

Page 29: MSE-415: Product Design Lecture #3

29Rev: 5/05/07 MSE-415: B. Hawrylo

Chapter 16 – Managing ProjectsChapter 16 – Managing Projects

Project ExecutionSmooth execution of a well-planned project should pay attention to 3 components:

1. What mechanisms can be used to coordinate tasks.2. How can the project status be assessed?3. How can we correct undesirable deviations?

Page 30: MSE-415: Product Design Lecture #3

30Rev: 5/05/07 MSE-415: B. Hawrylo

Chapter 16 – Managing ProjectsChapter 16 – Managing Projects

What mechanisms can be used to coordinate tasks?

1. Informal Communication2. Meetings3. Schedule Display4. Weekly Updates5. Incentives6. Process Documents

Page 31: MSE-415: Product Design Lecture #3

31Rev: 5/05/07 MSE-415: B. Hawrylo

Chapter 16 – Managing ProjectsChapter 16 – Managing Projects

Corrective Actions

1. Change the timing or frequency of meetings.2. Change the project staff.3. Locate the team together physically.4. Solicit more time and effort from the team.5. Focus more effort on critical tasks.6. Engage outside resources.7. Change the project scope/schedule

Page 32: MSE-415: Product Design Lecture #3

32Rev: 5/05/07 MSE-415: B. Hawrylo

Next WeekSeptember 19, 2007

Next WeekSeptember 19, 2007

• Homework #2 - Handout• Design and Development Project

Prepare a detailed project plan– Project timeline and major milestones– Goals, objectives and scope – Risk assessment, assumptions and critical project barriers– Milestones– Project roles and responsibilities– Estimated start and completion of each step

•Read Chapter 4 – Identifying Customer Needs Product specifications

•Prepare for a potential quiz on chapters 1,2,3,4,16, and additional readings