mtest pixel telescope – status update david christian september 11, 2007
TRANSCRIPT
MTest Pixel Telescope – Status Update
David Christian
September 11, 2007
MTest Telescope
• Constructed using “BTeV pixels”
• Pixel size = 50 x 400 (600)
• Oriented to provide “precision-x” or “precision-y” measurements.
Layout
• Aperture ~ 3.5cm x 3.5cm• 4 – 6 stations
Beam
x
y
x
y
Nomenclature
• Station = 2 planes & an SLINK
• Plane = 3 modules mounted on a TPG heat spreader
• Module = hybrid pixel detector glued & wire-bonded to a High Density Interconnect (Kapton flex circuit)
• Hybrid = pixel sensor bump bonded to 4 FPIX2.1 ASICs
DAQ Overview
SLINK ROUTERTwin-ax(sATA)
PCI Interface
Fiber
Trigger/timing signals
Trigger/timing signalsLINUX pc
Removable disk
DAQ
• SLINK communicates with 2x3x4=24 FPIX2.1 chips & with ROUTER.– Relays commands & responses– Collects data
• Deserialize (digital phase follower)• Time order & construct data blocks w/extended
time stamp & chip ID headers• Hierarchy of 2-way data merges
DAQ - continued
• ROUTER communicates with PCI interface & SLINKs and (optionally) DUTs– 12 sATA ports, 4 RJ45 ports– Relays commands & responses– Collects data
• Hierarchy of 2-way data merges (same logic as SLINK)
• PCI Interface communicates with ROUTER & pc– Relays commands & responses– Uses 3 CSRs & 3 ring buffers in the pc main memory
(64 MB)
Detector Status/Plan
• Hybrid development complete– 11 good hybrids in hand– Balance waiting for LANL PO to VTT
• Delivery Jan – May (schedule risk)
• Module development– 4x HDI layout ~85% complete (FNAL)– Prototype by end of October, production Nov-
Dec (on the optimistic critical path)
Detector Status/Plan continued
• Plane/Station development:– TPG in hand, reinforcing about to start (FNAL)– Mechanical design underway (FNAL)– SLINK pcb layout & final design is waiting for
completion of 4x HDI (Nevis)
• Box/Area:– Cleanup has started– Mechanical design underway (FNAL)
DAQ Status/Plan
• DAQ Hardware/Firmware (Nevis)– PCI interface ~90% complete (trigger/timing hooks
not written)– Router ~70% complete (trigger/timing, implementation
of merges, integration of DUT?) – SLINK
• Prototype tested at ~90% level; linked to 2 modules• Design/layout waiting for 4x HDI• On the optimistic critical path
Software Status/Plan
• Online software (FNAL, Syracuse?, UNM?)– Core low level routines exist & have been tested.– Need to specify online, including online/offline
boundary, write & test code.• On the optimistic critical path
• Offline software (Syracuse, FNAL?, UNM?)– Data unpacking– Alignment– Tracking, integration of DUT
• On the optimistic critical path
• Strategic decisions to be made in the next 4-6 weeks
Schedule
• Focus on full telescope in ~Feb
• If bump bonding is delayed (past ~Jan)…– Install 1st station + fragments as available
(~Jan?)