nathália n. araújo, maritza r. gual & marcos c. maturana brazil on... · 2019-09-10 ·...
TRANSCRIPT
Nathália N. Araújo, Maritza R. Gual & Marcos C. Maturana
Brazil
Technical Meeting on the Phenomenology, Simulation and Modelling of Accidents in Spent Fuel Pools
2-5 September 2019, Vienna, Austria
Summary
• PROBABILISTIC SAFETY ASSESSMENT (PSA)
• DESCRIPTION OF THE SFP COOLING SYSTEMS
(SFPCS)
• EVENT SEQUENCES
• SPF MODELING WITH MELCOR
• RESULTS OF THE SIMULATIONS
• CONCLUSIONS AND FUTURE WORK
Probabilistic Safety Assessment (PSA)
• Selection of the most frequent accident sequences
through PSA level 1
• Preparation of an SFP model in MELCOR
• Support the calculation of frequency and release of
radioactive material – PSA level 2 – with the
accident simulation results
PSA LevelsAt each level the risk associated
with the indicated event
is analyzed.
SFP COOLING SYSTEMS (SFPCS)
FUEL BUILDING (FB)
CONTROL ROOM (CR)
Compartment
FSP-I
Compartment
FSP-II
Compartment
FSP-III
B1 B2
B3 B4
T2
T3
P1
P2
S1
FE
Cleaning and
Purification
System (CPS)
T1
FE
Safety Water
Cooling System
(SWCS)
Drainage
System (DS)S3
V34
Tra
nsf
er
Ch
ann
el(T
C)
V47
V36
V62
V65
V72
V22
V23
V27
V25
V35
V28V31
V57
V71
V70
V52
V56
V4
V5
V7
V9
V11
V64V10V14
V17
V63
V44
V38
V76
V45 V75
V40
V73
V46
V74
V53
Sampling
System (SS)
V51
V37
S2
SFPCS OPERATIONAL MODES
Operational
Mode
Cooled
CompartmentsDescription
B
FSP-II
Normal operation. Circulation by pump B3.
Cooling by the heat exchanger T2.
B.1Degraded operation. Circulation by pump B3.
Cooling by the heat exchanger T3.
B.2Degraded operation. Circulation by pump B4.
Cooling by the heat exchanger T2.
B.3Degraded operation. Circulation by pump B4.
Cooling by the heat exchanger T3.
EVENT SEQUENCES TO BE
CONSIDERED IN PSA LEVEL 2
• PSA Level 1 results:
– Failure to open valves for
redundant circuit: first three
cases;
– CCF of B3 and B4 to start:
fourth case (3.43E-6 / yr);
– One pump unavailable due
to testing and maintenance
and standby pump failure to
start: fifth and sixth cases
(5.00E-7 and 4.70E-7 / yr);
• The set of abnormal conditions
identified in the PSA Level 1 will
be considered for the spent fuel
pool accidents in PSA Level 2.
SHUTDOWN PSA LEVEL 1 TOP 3 SFP FUEL DAMAGE FREQUENCY CUTSETS
Cutset
NumberEvent Description
Event
Probability
Frequency
(yr)
1
Plant is shutdown based on
annual availability8.22E-2
8.56E-6
Shutdown Phase II, III, IV
duration7.33E-1
Loss of SFPCS 1.00
Flag: Spent fuel elements in
FSP-II.1.00
Manual Valve _036_ Failure to
Open1.42E-4
2
Plant is shutdown based on
annual availability8.22E-2
8.56E-6
Shutdown Phase II, III, IV
duration7.33E-1
Loss of SFPCS 1.00
Flag: Spent fuel elements in
FSP-II.1.00
Manual Valve _034_ Failure to
Open1.42E-4
3
Plant is shutdown based on
annual availability8.22E-2
3.66E-6
Shutdown Phase II, III, IV
duration7.33E-1
Loss of SFPCS 1.00
Flag: Spent fuel elements in
FSP-II.1.00
Check Valve _032_ Failure to
Open6.07E-5
MELCOR SFP MODELING
• MELCOR 2.2.9541
– SFP – PWR
– 3 rings × 12 axial levels (6 for active fuel)
– 21 fuel assemblies with UO2 ~5% fuel rods
– 48 MW (NPP) ~ time decay heat of 5 days
MELCOR SFP MODELING
MELCOR RESULTS
MELCOR RESULTS
MELCOR RESULTS
CONCLUSIONS & FUTURE WORK
• The Shutdown PSA Level 1 of a reference NPPwas analysed and a set of accident sequenceswas selected;
• A MELCOR model for SFP was obtained;
• A better understand of the LOFA physicalphenomena was reached;
• The SFP accidents evaluation will be based on theresults of these simulations;
• Improvement of MELCOR model of the SFP;
• The resulting MELCOR model will be useful for thecalculation Large Early Release Frequency (LERF)of the reference NPP.
Thank You!