ned status report arnaud devred cea/dsm/dapnia/sacm & cern/at/mas collège de france, paris 23...

40
NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Post on 19-Dec-2015

217 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

NED Status Report

Arnaud DevredCEA/DSM/DAPNIA/SACM & CERN/AT/MAS

Collège de France, Paris23 February 2004

We now have a logo!

Page 2: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Contents

• Introduction

• TSQP Work Package

• CD Work Package

• IDI Work Package

• Preparing for Phase II

Page 3: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Contents

• Introduction

• TSQP Work Package

• CD Work Package

• IDI Work Package

• Preparing Phase II

Page 4: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Current Status

• Following EU recommendations, the NED program has been

divided into two phases– Phase I groups together all the tasks related to

conductor development and includes some limited

studies on conductor insulation,– Phase II groups together all the tasks related to the

detailed design, manufacturing and test of a large-

aperture (up to 88 mm), high-field (up to 15 T)

dipole magnet model.• Phase I has been approved as part of the CARE project

(~13 staff.year over 3 years; total cost: ~2 M€; requested

EU funding: 979 k€).• A strategy is being devised among NED collaborators to find

the funding necessary to carry out Phase II

(~22 staff.year, material costs: ~1.2 M€).

Page 5: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

NED Phase I

• The Phase I of the NED Program is articulated around four

Work Packages

1 Management & Communication (M&C),

2 Thermal Studies and Quench Protection (TSQP),

3 Conductor Development (CD),

4 Insulation Development and Implementation (IDI).

• The Activity is coordinated by A. Devred (CEA & CERN),

helped by A. den Ouden (Twente University).

Page 6: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Cost and Manpower Distributions Among NED WP

M&CTSQPCDIDI

Total Expected Costs(2,093 k€)

Total Manpower(152 staff.month)

Page 7: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

NED Collaborators

• Six institutes have agreed to collaborate to NED

— CCLRC/RAL (UK),

— CEA/DSM/DAPNIA (France),

— CERN/AT (International),

— INFN/Milano-LASA & INFN/Genova (Italy),

— Twente University (the Netherlands),

— Wroclaw University (Poland).

• A seventh institute (CIEMAT, Spain) has expressed interest in

joining the collaboration and is ready to commit 1.5 staff.year of

manpower to Phase I and to contribute significantly to Phase II.

Page 8: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Cost and EU Funding Sharing Among NED Collaborators

0

100

200

300

400

500

600

700

800

CCLRC CEA CERN INFN TEU WUT

kilo E

uro

s

Page 9: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Steering Committee

• The oversight of NED is ensured by a Steering Committee (SC) made up of

– E. Baynham (RAL)– A. Devred, Chairman (CEA & CERN)– D. Leroy (CERN)– A. den Ouden, Secretary (TEU)– J.M. Rifflet (CEA)– G. Volpini (INFN)

• The first meeting took place on January 8, 2004.• The next meeting is scheduled on March 25, 2004.

Page 10: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

External Scientific Advisory Committee

• The JRA Coordinator is helped by an External Scientific Advisory Committee (ESAC) made up of

– J.L. Duchateau (CEA)– H.H.J. ten Kate (CERN & TEU)– P. Lebrun (CERN)– L. Rossi (CERN)– R.M. Scanlan (retired from LBNL)– J.B. Strait, Chairman (FNAL)

• The first meeting is scheduled on March 24, 2004.• A document defining the charges of the committee is

being circulated among its members.

Page 11: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Logistics & General Organization

• A. den Ouden is setting up a web page

www.tn.utwente.nl/lt/project.php?projectid=9• A. Devred is investigating the possibility of using the

CERN, web-based Engineering Data Management Service (EDMS) to circulate and store documents.

• Following the January Steering Committee, A. Devred has embarked on a tour of NED collaborators

– 13 January 2004: INFN/Genova– 16 January 2003: CIEMAT– 27 January: Twente University– 13 February 2004: INFN/Milano-LASA– 19 March 2003: RAL– End of March, beginning of April: Wroclaw

University

Page 12: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Contents

• Introduction

• TSQP Work Package

• CD Work Package

• IDI Work Package

• Preparing Phase II

Page 13: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Initial Proposal for TSQP WP

• In the initial proposal, the TSQP Work Package was supposed to address four main issues

1. What will be the level of power deposition from beam losses on NED coils?

beam loss computations (INFN/Milano-LASA; cut in final proposal)

2. How does Nb3Sn conductor insulation behave in He

environment and how much heat can be transferred through it?

heat-transfer measurements (CEA & WUT; approved in final proposal)

3. What is the optimum magnet cooling scheme? numerical model (WUT; cut in final proposal)4. What the optimum quench protection scheme? quench computations (INFN/Milano-LASA; approved in

final proposal)

Page 14: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Present TSQP Work Package

• The present TSQP Work Package is divided up into three

Tasks

2.1 Work Package coordination

2.2 heat-transfer measurements through N3Sn

conductor insulation (CEA/DSM/DAPNIA & Wroclaw

University of Technology, under CEA/DSM/DAPNIA

supervision)

2.3 quench protection computations (INFN/Milano-

LASA)

• It is coordinated by G. Volpini (INFN/Milano-LASA)

Page 15: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Task 2.2: Heat Transfer Measurements (1/2)

• The January SC meeting has defined the parameter space

and has established a “wish list” for the heat transfer

measurements.

• The wish list includes

– to perform fundamental R&D on “innovative”

insulation to study its alleged porosity to helium I and

II,

– to characterize thermal performances in helium I and

II of samples representative of insulated conductors in

magnet coils subjected to static heat deposition (in the

50-to-80 mW/cm3 range).

• The wish list has has been communicated on 21 January

2004 to the relevant persons at CEA/DSM/DAPNIA with the

charge of defining a Program fitting within the allocated

resources.

Page 16: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Task 2.2: Heat Transfer Measurements (2/2)

• 27 February 2004: Program proposal (CEA/DSM/DAPNIA)

• 12 March 2004: Informal review by P. Lebrun (ESAC

member)

• 25 March 2004: Formal approval by NED Steering

Committee

• 31 March 2004: cryostat and cryogenic modules

specifications (CEA/DSM/DAPNIA)

• 31 December 2004: cryostat and cryogenic module

fabrication

(WUT & CEA/DSM/DAPNIA)

• 1 April 2005: Facility commissioning at CEA/Saclay

(WUT & CEA/DSM/DAPNIA; EU Deliverable)

• 30 December 2005: Interim report on measurements

(CEA/DSM/DAPNIA; EU Milestone)

• 29 December 2006: Final report on measurements

(CEA/DSM/DAPNIA; EU Deliverable)

Page 17: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Task 2.3: Quench Computations (1/2) • Similarly to what has been done for Task 2.2, the January SC

meeting has defined the parameter space and has established

a “wish list” for the quench computations.

• The wish list includes

– to establish a comparison of existing quench codes in

Europe,

– to establish a European database on thermal material

properties,

– to study the influence of Cu-to-non-Cu ratio, Cu RRR,

magnet length, quench heater design and location, and

quench back on NED baseline design.

• The wish list has has been communicated on 13 February

2004 to M. Sorbi, who will be responsible to carry out this

Task at INFN/Milano-LASA, with the charge of defining a

Program.

Page 18: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Task 2.3: Quench Computations (2/2)

• 27 February 2004: Program proposal (INFN/Milano-LASA)

• 12 March 2004: Informal review by L. Rossi and H.H. ten

Kate (ESAC members)

• 25 March 2004: Formal approval by NED Steering

Committee

• 31 December 2004: Interim report on quench computations

(INFN/Milano-LASA; EU Milestone)

• 30 June 2005: Final report on quench computations

(INFN/Milano-LASA; EU Deliverable)

Page 19: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Missing Tasks of TSQP Work Package

• Two important tasks have been deleted from the initial

proposal

– beam loss computations,

– coil cooling optimization.

• We are looking into building upon INFN/Milano-LASA experience to run

limited beam loss computations for one conservative

scenario of LHC IR upgrade, building upon existing CERN/WUT collaboration to

adapt an existing numerical model to NED baseline

design.

Page 20: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Contents

• Introduction

• TSQP Work Package

• CD Work Package

• IDI Work Package

• Preparing Phase II

Page 21: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

CD Work Package

• The CD Work Package is divided up into seven Tasks

3.1 Work Package coordination

3.2 Preliminary magnet design aimed at deriving

meaningful specifications (CERN/AT)

3.3 Conductor specifications (CERN/AT)

3.4 Wire development (two industrial sub-contracts

under CERN/AT supervision)

3.5 Wire characterization (CEA/DSM/DAPNIA,

INFN/Milano-LASA and /Genova, Twente

University)

3.6 Cable development (under CERN/AT supervision)

3.7 Cable Characterization (Twente University)

• It is coordinated by D. Leroy (CERN/AT).

Page 22: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Task 3.2: Preliminary Magnet Design (1/2)

• Olivier Vincent-Viry (CERN/AT) has studied several

magnetic designs to achieve ~15 T in a 88-mm aperture

Conventional

cosdesign

Motor-type block

design

Page 23: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Task 3.2: Preliminary Magnet Design (2/2)

• Results were presented at the January SC meeting and will

be published in a report due in March 2004.

• They converge towards the following pre-specifications

– same cable for all conductor blocks, one strand type

– strand diameter: 1.25 mm,

– Cu-to-non-Cu ratio: 1.25,

– JC-non-Cu: 1500 A/mm2 at 4.2 K and 15 T,

– effective filament diameter < 50 m (no flux jump),

– Cu RRR > 70,

– cable interstrand resistance: TBD,

– quantity: 500 m of cable, corresponding to ~10 km of

wires.

Page 24: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Tasks 3.3, 3.4 & 3.6: Conductor Development (1/4)

• A market survey had been carried out by D. Leroy in early

2003 to which three manufacturers had answered positively

– Alstom/MSA (France),

– European Advanced Superconductors (formerly

Vacuumschmelze, Germany)

– ShapeMetal Innovation (the Netherlands)

• The manufacturers had agreed to contribute financially to

the Program by at least matching the EU funding.

• EAS and SMI had declared they would study the possibility of

forming a joint venture.

Page 25: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Tasks 3.3, 3.4 & 3.6: Conductor Development (2/4)

• A. Devred and D. Leroy have made three preparatory visits to

the manufacturers having answered positively to the market

survey

– 12 December 2003: Alstom/MSA

(with T. Boutboul and L. Oberli, CERN/AT),

– 15 December 2003: EAS

(with L. Oberli, CERN/AT, and a SMI representative),

– 27 January 2004: SMI

(with T. Boutboul and L. Oberli, CERN/AT, A. Unerwik,

CERN/FI, A. den Oudent, TEU and two EAS

representatives).

Page 26: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Tasks 3.3, 3.4 & 3.6: Conductor Development (3/4)

• The manufacturers confirmed that our goals were ambitious

but feasible.

• Alstom/MSA, on one side, and EAS/SMI, on the other side,

are developing a strategy to achieve our goals with a

methodology scalable to industrial production.

• EAS and SMI are talking to each other and we have

reasonable hope that they will respond to our call for tender

as a consortium.

Page 27: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Tasks 3.3, 3.4 & 3.6: Conductor Development (4/4)

• The next milestones of the Conductor Development Tasks

are

– ongoing: preparation of conductor specifications,

– mid-may 2004: call for tender (extended to all EU

manufacturers),

– June 30, 2004: contracts’ handout.

• CERN/AT has identified T. Boutboul as the main person

responsible for the follow-up of the industrial contracts.

Page 28: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Task 3.5: Wire Characterization (1/3)

• The January SC has decided the creation of a Working Group

on Wire Characterization, that will be chaired by A. den Ouden

(TEU).

• The Working Group will include

– one representative from each laboratory involved in

the measurements (CEA/DSM/DAPNIA, INFN/Milano

and /Genova, TEU)

– the CERN person responsible for industrial contract

follow-up,

– one representative from each industrial sub-

contractor.

Page 29: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Task 3.5: Wire Characterization (2/3)

• The charges of the Working Group are

– to establish an inventory of existing facilities among

NED collaborators,

– to define standardized procedures to characterize the

transport-current and magnetization properties of

virgin, deformed and extracted wires, – to develop and carry out a program of cross-

calibration of the various facilities for critical current

measurements,

– to certifying the measured data throughout the

execution of Task 3.5.

Page 30: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Task 3.5: Wire Characterization (3/3)

• The main milestones and expected deliverables of the

Working Group are

– 25 March 2004: Working Group installation,

– 30 June 2004: procedures (to be included in

industrial sub-contracts) and cross-calibration

program,

– 31 December 2004: report on cross-calibration

program,

– 30 June 2005: first characterization results,

– 30 December 2005: interim report on wire

characterization

(EU Milestone),

– 30 June 2006: final report on wire characterization

(EU Deliverable).

Page 31: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Missing Tasks of CD Work Package

• INFN/Genova has agreed

to develop FE models of

wires to compute the

stress/strain distributions

upon transverse loading

and simulate the effects of

cabling.

• Two important Tasks have been deleted from the initial

proposal

– pre-reaction studies,

– mechanical studies.

Numerical model of internal tin wire

(Courtesy S. Farinon)

Page 32: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Contents

• Introduction

• TSQP Work Package

• CD Work Package

• IDI Work Package

• Preparing Phase II

Page 33: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

IDI Work Package

• The IDI Work Package is divided up into four Tasks

4.1 Work Package coordination

4.2 Insulation specifications (CCLRC/RAL)

4.3 R&D on conventional insulation (CCLRC/RAL)

4.4 R&D on innovative insulation (CEA/DAPNIA/SAC)

• It is coordinated by E. Baynham (CCLRC/RAL)

Page 34: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Task 4.2: Insulation Specifications

• The January SC meeting has decided the creation of a Working Group on insulation , that will be chaired by E. Baynham (CCLRC/RAL).

• The membership and charges of the Working Group have yet to be defined.

• The Group will be responsible for establishing an engineering specification and a set of standard tests applicable to both insulation types.

Page 35: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Task 4.3 & 4.4: Insulation Development

• J. Greenhalgh will coordinate the work on conventional insulation at CCLRC/RAL (Task 4.3),

• while F. Rondeaux will coordinate the work on innovative insulation at CEA/DSM/DAPNIA (Task 4.4).

• Details of the R&D Program will be discussed during A. Devred visit to RAL (with F. Rondeaux and P. Védrine) on 19 March 2004.

Page 36: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Proposed Timetable for IDI WP

• 19 March 2004: membership and charges of Working Group,

• 25 March 2004: Steering Committee wish list,

• 1st April 2004: Working Group installation,

• 15 June 2004: Program proposals for both insulation types

• 30 June 2004: Report on insulation specifications

(EU milestone)

• 1st July 2004: Informal review of program proposals by L.

Rossi and H.H.J. ten Kate (ESAC members)

• July 2004: Formal approval by NED Steering Committee

• 30 July 2004: Report on insulation R&D Programs

(EU milestone)

Page 37: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Contents

• Introduction

• TSQP Work Package

• CD Work Package

• IDI Work Package

• Preparing Phase II

Page 38: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Re-enacting MDO Work Package (1/2)

• Some manpower is now available for magnet design and

optimization

– 9 staff.month from CCLRC/RAL (included in NED Phase I

contract),

– 18 staff.month from CIEMAT,

• plus

– a graduate student who started a 3-year contract at

CEA/DSM/DAPNIA in November 2003 on a topic closely

related to NED (under the supervision of Pierre Védrine),

– CERN/AT is looking for a technical student at Torino

University, who would be invited to Geneva for two years

and who could work at least for one year on NED (under

the supervision of Paolo Fessia).

Page 39: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Re-enacting MDO Work Package (2/2)

• The available manpower (with profiles not needed elsewhere in

the Program) enables us to re-enact the Magnet Design and

Optimization (MDO) Work Package, that was included in the

original proposal, but was finally deleted.

• The January SC meeting decided to create an MDO Working

Group, that will be chaired by Pierre Védrine (CEA/DSM/DAPNIA).

• The membership and charge of the Working Group have yet to

be defined.

• Once formed, the Working Group will brainstorm to propose a

Program, that will be reviewed by relevant ESAC members and

approved by the Steering Committee.

Page 40: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS Collège de France, Paris 23 February 2004 We now have a logo!

Towards Model Magnet Manufacturing

• Preliminary discussions with CIEMAT have shown that they

were also interested in participating to NED Phase II (detailed

design and manufacturing of model magnet).

• For instance, they would be ready to ask a grant from the

Spanish government to cover the material costs needed to

manufacture NED coils (~250 k€) and CIEMAT would contribute

the manpower to do the job.

• As CIEMAT has little experience with Nb3Sn technology, they

need some training, which could be done by associating them

to ongoing programs at CEA/DSM/DAPNIA and TEU.

• Once the coils are manufactured, it should be easier to

convince one of the big laboratories to complete model magnet

assembly.