neilson road bridge detailed deck condition survey ... · bridge check canada limited was retained...

132
Neilson Road Bridge Bridge No. 817 Detailed Deck Condition Survey & Evaluation Report Prepared for: City of Toronto Engineering & Construction Services October 2015 1 of 265

Upload: others

Post on 07-Jul-2020

2 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Neilson Road Bridge

Bridge No. 817

Detailed Deck Condition

Survey & Evaluation Report

Prepared for:

City of Toronto Engineering & Construction Services

October 2015

1 of 265

Page 2: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Neilson Road Bridge - Enhanced OSIM & Evaluation Report

MMM Group Limited | October 2015 | 3213038-304 i

TABLE OF CONTENTS

APPENDICES ................................................................................................. II

1.0 INTRODUCTION ................................................................................ 1

2.0 STRUCTURE ...................................................................................... 1

3.0 INSPECTION METHODOLOGY ........................................................ 2

4.0 SUMMARY OF CONDITION SURVEY .............................................. 3

4.1 Asphalt Wearing Surface ....................................................................................................... 3

4.2 Waterproofing ......................................................................................................................... 3

4.3 Concrete Deck ......................................................................................................................... 4

4.4 Deck Soffit ............................................................................................................................... 5

4.5 Approaches ............................................................................................................................. 5

4.6 Deck Drainage ......................................................................................................................... 6

4.7 Joints ....................................................................................................................................... 6

4.8 Abutments and Bearings ....................................................................................................... 6

4.9 Ballast Wall .............................................................................................................................. 6

4.10 Bearing Seats .......................................................................................................................... 7

4.11 Wingwalls ................................................................................................................................ 7

4.12 Retaining Walls ....................................................................................................................... 7

4.13 Piers and Bearings ................................................................................................................. 7

4.14 Slopes ...................................................................................................................................... 7

5.0 STRUCTURE EVALUATION ............................................................. 8

2 of 265

Page 3: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Neilson Road Bridge - Enhanced OSIM & Evaluation Report

MMM Group Limited | October 2015 | 3213038-304 ii

APPENDICES

Appendix A − Condition Survey Report

Appendix B − Structural Evaluation Report

3 of 265

Page 4: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Neilson Road Bridge - Enhanced OSIM & Evaluation Report

MMM Group Limited | October 2015 | 3213038-304 1

1.0 INTRODUCTION

MMM Group Limited has been retained by The City of Toronto to provide a detailed deck condition survey

and structural evaluation of the Neilson Road Bridge. As a part of the aforementioned work, the structure

was to be visually inspected for its current level of deterioration, forming the basis for the structural

evaluation. The detailed deck condition survey of the Neilson Road structure was completed by Bridge

Check Canada Limited as sub consultant to MMM Group Limited.

This report summarizes the key findings of the detailed condition survey and structural evaluation. A

complete deck condition survey and inspection report can be found in Appendix A. The structural evaluation

report can be found in Appendix B.

2.0 STRUCTURE

Originally constructed in 1979, the Neilson Road Bridge is a four span post-tensioned structure which

consists of two independent concrete decks. The Neilson Road Bridge has single span lengths of 14.6m,

18.9m, 18.9m and 14.6m with a total overall width of 28.4m. The structure is orientated in the east-west

direction and carries traffic in each direction over two CPR railway tracks.

The substructure consists of two sets of abutments and three sets of piers; According to the existing

structure drawings, the abutments and piers are supported on spread footings. The original construction

drawings do not indicate that the footings are supported on steel piles.

The bridge structure accommodates four lanes of traffic along Neilson Road over the CPR railway with

barriers running along the north andsouth edges of each bridge deck. Transverse expansion joints are

present at both ends of the bridge deck, directly above the abutments; the deck is continuous over its piers.

According to the available records, the structure has not undergone any rehabilitation work.

A Key Plan showing the structure location is provided in Figure 1.

4 of 265

Page 5: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Neilson Road Bridge - Enhanced OSIM & Evaluation Report

MMM Group Limited | October 2015 | 3213038-304 2

Figure 1 – Key Plan

3.0 INSPECTION METHODOLOGY

Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition

survey of the Neilson Road Bridge. The field investigation was completed over three days between June 3

and 5, 2015.

The Neilson Road Bridge condition survey involved the observation and inspection of surface defects and

delaminated concrete, a corrosion potential survey and visual observation of sawn areas on the deck, as

well as the extraction of concrete cores from various locations in the structure. All condition survey

procedures used were those defined in the MTO Structure Rehabilitation Manual.

Standard practise included the following key methodologies:

• Delaminated concrete was detected by striking all vertical and overhead concrete surfaces with a

hammer and noting the sound emitted.

Bridge Site

5 of 265

Page 6: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Neilson Road Bridge - Enhanced OSIM & Evaluation Report

MMM Group Limited | October 2015 | 3213038-304 3

• The locations of all concrete patches, spalled and or delaminated concrete, exposed reinforcement,

damp areas, scaled concrete, cracked concrete and other observed defects were recorded. A

standard 1.5m square grid was used for all deck-top and soffit observations.

• The corrosion potential survey was conducted for the asphalt covered bridge deck. All survey

procedures were performed in accordance with the requirements of STM C876 and the MTO

Structure Rehabilitation Manual.

• All sawn areas of the bridge deck were carefully examined for deterioration and were hammer

sounded. Photos of all sawn samples are on file for reference. Thirty (30) sawn samples were

taken at various locations on the bridge deck

• Thirty-seven (37) concrete cores were extracted from the bridge deck and one (1) from the east and

west approach, respectively.

4.0 SUMMARY OF CONDITION SURVEY

4.1 Asphalt Wearing Surface

The total width of the asphalt covered bridge deck between abutments is 22.56 m, with a total surveyed

area of 1,529.00 m2. The condition of the asphalt wearing surface on the bridge deck was identified through

visual field observations and review of cores and sawn asphalt samples. The asphalt wearing surface on

the concrete deck is generally in fair condition with unsealed transverse (82.0 m), longitudinal (65.0 m) and

random (584.0 m) cracking, sealed transverse (10.0 m), longitudinal (6.0 m) and random (79.0 m) cracking.

The measured asphalt thickness varied from 40 mm to 110 mm with an average thickness of 69 mm.

Three (3) samples of the asphalt wearing surface were tested for asbestos contaminations according to

EPA 600/R‐93/116 test method using Polarized Light Microscope. The results indicated 1.2‐1.3% asbestos

content in the samples.

4.2 Waterproofing

Evidence of a hot rubberized asphalt waterproofing system with protection board was detected over the

concrete deck, ranging in thickness from 7 to 9 mm with an average thickness of 8 mm. The condition of the

6 of 265

Page 7: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Neilson Road Bridge - Enhanced OSIM & Evaluation Report

MMM Group Limited | October 2015 | 3213038-304 4

waterproofing membrane encountered in the test locations was generally good. The bond of waterproofing

to the concrete was generally good.

4.3 Concrete Deck

The concrete deck consists of a four span cast‐in‐place concrete post tension thick slab, supported by piers

and abutments. The condition of the concrete deck was observed at thirty-seven (37) core locations and

thirty (30) sawn asphalt sample locations. The inside of the core holes and the exposed concrete surface at

the sawn asphalt sample locations were examined carefully for cracks and other defects. A review of the

concrete cores revealed cracking in one (1) core. Visual review of the exposed concrete surface at the

sawn asphalt samples did not reveal any defects.

The concrete cover to the upper rebar layer measured in the cores and sawn asphalt samples was found to

range from 30 to 109 mm with an average cover of 68 mm. The field cores identified 15M rebar imprint in

the deck. The reinforcement steel was found to be in good condition with no evidence of corrosion.

Corrosion potential values obtained from the half‐cell test carried out on the asphalt covered deck ranged

from –0.102 V to –0.476 V with an average value of –0.218 V. The half‐cell survey indicated that 56.0% of

the deck area likely had no corrosion activity, with corrosion potential values between 0.000 V and ‐0.199 V.

The half‐cell survey indicated uncertain low corrosion activity for 34.0% of the deck area, with values

ranging from ‐0.200 V to ‐0.349 V. Probable active corrosion was detected for 10.0% of the deck area with

corrosion potential values more negative than ‐0.350 V. Active corrosion potential was found adjacent to the

north sidewalk.

Two (2) cores were tested for compressive strength of the hardened concrete in accordance with CSA

A23.2‐09‐14C. The compressive strength of the hardened concrete for these cores ranged from 38.7 MPa

to 68.9 MPa, with an average compressive strength of 53.8 MPa. This value is significantly higher than the

34.5 MPa (5000 psi) minimum specified strength on the original GA drawing.

The chloride ion content was determined for eight (8) cores using MTO LS‐417 “Method of Test for

Determination of Total Chloride Ion in Concrete – Acid Soluble”. These core samples were located at areas

prone to salt exposure (e.g. high corrosion potential areas, along construction joints, low points of the deck,

asphalt cracks). In addition, samples from other moderately exposed areas were also taken.

7 of 265

Page 8: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Neilson Road Bridge - Enhanced OSIM & Evaluation Report

MMM Group Limited | October 2015 | 3213038-304 5

The chloride threshold value necessary to depassivate embedded steel and to allow the onset of corrosion

(in the presence of oxygen and moisture) is generally taken as 0.025% by mass of concrete. The corrected

chloride content, at the rebar level, was above the chloride threshold level of 0.025% in one (1) Core.

Overall, the results indicate that chloride contamination has extended to the upper rebar level in limited

areas of the deck. Based on the concrete removal policy outlined in the Structure Rehabilitation Manual, the

following comments can be made:

• Since 10% of the deck area is more negative than ‐0.350 V, the average chloride content at the

reinforcing level is calculated using the cores with corrosion potential values more negative than ‐

0.350 V. Therefore, the average adjusted chloride content at the reinforcing steel level is 0.011%.

• Based on the above, since the average adjusted chloride content at the top reinforcement level is

less than 0.05% by mass of concrete, concrete removal is recommended to include delaminated

areas only.

4.4 Deck Soffit

The bridge deck soffit, with a total surveyed area of 1,951.60 m2, is in fair condition with clean/stained

medium width cracking (100.0 m), delamination (75.90 m2), spalls (20.90 m

2), honeycombing (3.00 m

2), and

wet areas (47.40 m2). Deteriorations were predominantly observed within the westbound lanes and along

the centreline of the deck. Exposed corroded reinforcement was observed in the spalled areas. A concrete

cover survey was conducted on the deck soffit except for the area between Piers 1 and 2 (above the CPR

tracks). The concrete cover was found to range from 30 to 64 mm with an average cover of 44 mm.

4.5 Approaches

The asphalt wearing surface on the bridge approaches is generally in good condition with unsealed cracks.

Observation of a core hole located at the east approach confirmed the presence of a concrete approach

slab with 85 mm thickness. The measured asphalt thickness was 40 mm. Observation of a core hole

located at the west approach confirmed the presence of a concrete approach slab with 65 mm thickness.

The measured asphalt thickness was 50 mm.

8 of 265

Page 9: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Neilson Road Bridge - Enhanced OSIM & Evaluation Report

MMM Group Limited | October 2015 | 3213038-304 6

4.6 Deck Drainage

Deck drains were not observed on this structure. Catch basins were observed at northeast and northwest

quadrants and in the median outside structure limits.

4.7 Joints

The expansion joints (strip seal joints) were generally in fair to poor condition with light rusting and missing

sections of the steel armoring angles. The seals were found to be damaged and covered with debris. Gap

dimensions varied from 20 to 40 mm. Leaking of the expansion joints was noted from dampness of the

deck soffit and abutments underneath. Cracking, scaling, and spalling were noted on the concrete end

dams. The east expansion joint was noted as being uneven at the north sidewalk.

4.8 Abutments and Bearings

The exposed surfaces of the abutments were inspected and sounded to check for delamination. The total

surveyed area for the east and west abutments were 126.57 and 41.50 m2, respectively. The abutments are

in fair to good condition. The field investigation of the east abutment revealed clean/stained medium width

cracking (35.0 m), pattern cracks (0.50 m2) and delamination (1.20 m

2). The field investigation of the west

abutment revealed clean medium width cracking (6.0 m), delamination (1.90 m2), and medium scaling (0.45

m2). The east abutment elastomeric bearings are in fair to good condition with cracks and bulging. The west

abutment laminated elastomeric bearings are in fair to good condition with cracks and bulging.

4.9 Ballast Wall

The east ballast wall is in fair to good condition whereas the west ballast wall is in fair condition. The east

abutment ballast wall had a total surveyed area of 7.00 m2 with spalls (0.15 m

2). The west abutment ballast

wall had a total surveyed area of 7.00 m2 with clean medium width cracks (2.0 m), delamination (0.30 m

2),

spalls (0.30 m2), and light scaling (0.10 m

2).

9 of 265

Page 10: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Neilson Road Bridge - Enhanced OSIM & Evaluation Report

MMM Group Limited | October 2015 | 3213038-304 7

4.10 Bearing Seats

The bearing seats were generally in good condition. The east abutment bearing seat had a total surveyed

area of 16.50 m2, with no visible defects. The west abutment bearing seat had a total surveyed area of

16.50 m2 with no visible defects.

4.11 Wingwalls

The exposed areas of the wingwalls were inspected visually and hammer sounded. The wingwalls were in

good condition and had a total surveyed area of 14.64 m2, with clean/stained medium width cracks (5.0 m),

light scaling (0.15 m2), and wet areas (1.40 m

2). Wet areas were observed on the southwest wingwall.

4.12 Retaining Walls

The exposed areas of the retaining walls were inspected visually and hammer sounded. The retaining walls

were in good condition and had a total surveyed area of 55.84 m2, with clean/stained medium width cracks

(21.0 m).

4.13 Piers and Bearings

The bridge piers are in good condition with total surveyed area of 221.60 m2. Inspection of the piers

revealed clean medium width cracks (4.0 m) and medium scaling (0.60 m2). Medium scaling was found on

Pier #3. The expansion Andre Rota bearings at Piers #1 and #3 were found to be in fair to good condition

with light corrosion and rust jacking. The Fixed Andre Rota bearings at Pier #2 were in good condition.

4.14 Slopes

The east slope was found to be in fair condition with soil erosion. The west slope paving was in fair to good

condition with cracks.

10 of 265

Page 11: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Neilson Road Bridge - Enhanced OSIM & Evaluation Report

MMM Group Limited | October 2015 | 3213038-304 8

5.0 STRUCTURE EVALUATION

A structural evaluation of the bridge was performed by MMM Group Limited in accordance with the 2006

Canadian Highway Bridge Design Code (CHBDC). The evaluation was based on the original construction

drawings supplied by The City of Toronto and took into consideration the condition of the structure at the

time of the evaluation.

Based on the original structural drawings the following material properties were used in the evaluation of the

structure:

Compressive strength of concrete - Deck (f’c) = 34.5 MPa

Yield strength of reinforcing steel (fy) =345 MPa

Yield Strength of stressing strand (fpu) = 1488 Mpa

According to the original structural drawings, the structure was originally designed for HS20-44 bridge

loading. The structure was analysed on SAP2000 using 2D frame elements, the live load model used was

CL-625-ON as specified in the CHBDC.

The evaluation indicated the following capacity to demand ratios (C/D) for the existing girders at their critical

locations:

TABLE 1 – C/D Ratios and Stresses for Existing Conditions

Westbound Structure

Location ULS

(Mr/Mf)

ULS

(Vr/Vf)

Stress - Top

SLS

(MPa)

Stress – Top

Allowable

(MPa)

Stress – Bot

SLS

(MPa)

Stress – Top

Allowable

(MPa)

Span 1 1.96 3.69 5.55 20.68 -0.08 -2.35

Pier 1 1.82 2.60 -0.38 -2.35 6.02 20.68

Span 2 1.82 - 6.12 20.68 -0.66 -2.35

Pier 2 1.90 2.66 0.21 20.68 5.40 20.68

Span 3 1.82 - 6.23 20.68 -0.78 -2.35

Pier 3 1.89 2.83 -0.06 -2.35 5.69 20.68

Span 4 1.92 3.36 5.56 20.68 -0.09 -2.35

11 of 265

Page 12: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

12 of 265

Page 13: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

AP

PE

ND

IX A

– C

on

ditio

n S

urv

ey R

ep

ort

13 of 265

Page 14: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                   

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

 

DETAILED CONDITION SURVEY REPORT  Site No. 817 Neilson Road over CPR 

City of Toronto, Ontario 

 

 

Prepared For: MMM Group Limited 

 Prepared by: Bridge Check Canada Ltd.  

 

BCC Project No: BCC15006 Report Date: August 20, 2015 

 

14 of 265

Page 15: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                   

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

TABLE OF CONTENTS    

1/  Structure Identification Sheet  2/  Key Plan  3/  Summary of Significant Findings  4/  Detailed Condition Survey Summary Sheets – Asphalt Covered Deck  5/  Detailed Condition Survey Summary Sheets – Exposed Concrete Components  6/  Detailed Condition Survey Summary Sheet – Expansion Joints  7/  Detailed Condition Survey Summary Sheet ‐ Drainage  8/  Survey Equipment and Calibration Procedures  9/  Core Photographs and Sketches  10/  Core Logs  11/  Sawn Asphalt Sample Photographs  12/  Sawn Asphalt Sample Logs  13/  Site Photographs  14/  Laboratory Test Results  15/  General Arrangement Drawing  16/  Drawings:  

      No. 1 – Surface Deterioration of Asphalt on Deck       No. 2 –Asphalt Thickness of Deck        No. 3 –Corrosion Potential of Deck        No. 4 – Surface Deterioration of Soffit       No. 5 – Concrete Cover of Soffit       No. 6 – Surface Deterioration of Piers        No. 7 – Surface Deterioration of Abutments, Winging Walls and Retaining Walls   

15 of 265

Page 16: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

  

 

 

 

 

 

 

        1/   Structure Identification Sheet 

16 of 265

Page 17: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

17 of 265

Page 18: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                   

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

  

 

 

 

 

 

 

        2/   Key Plan 

18 of 265

Page 19: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                   

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

KEY PLAN

Site No. 817 Neilson Road over CPR 

City of Toronto, Ontario 

 

Site # 817

19 of 265

Page 20: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

  

 

 

 

 

 

 

        3/   Summary of Significant Findings 

20 of 265

Page 21: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                   

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

SUMMARY OF SIGNIFICANT FINDINGS Site ID # 817, Neilson Road Bridge over CPR, City of Toronto, Ontario 

 

1.0  INTRODUCTION 

Bridge  Check  Canada  Ltd. was  retained  by MMM  Group  Ltd.  to  carry  out  detailed  bridge  condition survey under City of Toronto’s Work Assignment No. ECS‐BE‐C07‐15‐001. The assignment  involved the investigation and reporting for a total of seven bridges within the City of Toronto. This report presents Bridge Check Canada’s findings, through the field investigations and laboratory testing, for Neilson Road Bridge over CPR  (Site  ID # 817).  First  time  field  investigations were  carried out on  June 3‐5, 2015. A Bridge Master was utilized to inspect and hammer sound the deck soffit and substructure components.  

Site No. 817, constructed in 1979, is a four span cast‐in‐place concrete post tension thick slab, overlain with an asphalt wearing surface and carries two lanes of traffic per direction of Neilson Road. The bridge spans over CPR tracks. The slab thickness, shown on the original GA drawing, is 660 mm.  

Total span  length of the bridge  is 67.06 m and the roadway width  in each direction of Neilson Road  is 11.28 m. The structure has an east‐west orientation. Outer limits of the structure have concrete parapet walls and concrete sidewalk. A concrete median separates southbound from northbound traffic. Photo P1 shows a view of the south elevation of Site No. 817. Photo P2 shows the north elevation.  

 

South Elevation of Site No. 817, Neilson Road Bridge over CPR 

Rehabilitation history of the bridge is not available. 

 

2.0  METHODOLOGY 

In  general,  the  procedures  followed  to  conduct  the  condition  survey  and  delamination  survey were those defined in Part 1 of the MTO Structure Rehabilitation Manual (2007). This assignment involved the observation  and  recording  of  surface  defects,  delamination  detection,  grid  layouts  (1.5 m  x  1.5 m), concrete  cores  (100 mm  diameter),  corrosion  potential  survey,  and  physical  testing  of  the  concrete 

21 of 265

Page 22: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                   

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

cores.  Inspection of  the  concrete  sidewalks, parapet walls  and median was not part of  scope of  this investigation. 

The  delaminations  in  the  concrete were  detected  by  striking  the  surface with  a  heavy  hammer  and noting the type of sound being emitted. It should be mentioned that, while this method is quite reliable, it may not detect delaminations at a depth greater than 100 mm. The hammer sounding method was used  for  all  vertical  and  overhead  surfaces  inspected.  The  areas  and  locations  of  patches,  spalls, delaminations, exposed reinforcement, honey‐combing, wet areas, scaling and other observed defects were recorded.  

A  corrosion  potential  survey  was  conducted  for  the  asphalt  covered  bridge  deck.  The  survey  was performed  in accordance with  the  requirements of ASTM C876 and  the MTO Structure Rehabilitation Manual. A positive ground connection was made directly to the reinforcing steel, at the locations shown on the accompanying drawings. 

Thirty nine (39) cores (37 cores in the asphalt covered bridge deck and two cores in the approaches) and 30 sawn asphalt samples were extracted  from this structure,  in compliance with the requirements  for selecting  cores and  sawn asphalt  samples  from deteriorated and  sound areas. The  inside of  the  core holes were examined carefully for cracks and the condition of the concrete. The exposed surface of the concrete at the sawn asphalt samples was carefully examined for evidence of deterioration. All the test holes were reinstated to their original condition using MTO‐approved products.  

Enclosed  with  this  report  are  detailed  condition  survey  summary  sheets,  survey  equipment  and calibration  procedures,  core  photos/sketches,  core  logs,  sawn  asphalt  sample  photos,  sawn  asphalt sample logs, site photos, laboratory test results, and drawings. 

 

3.0  BRIDGE STRUCTURE 

3.1  Asphalt Wearing Surface 

The total width of the asphalt covered bridge deck between abutments is 22.56 m, with a total surveyed area of 1,529.00 m2. The condition of the asphalt wearing surface on the bridge deck was identified through visual field observations and review of cores and sawn asphalt samples. Drawing 1 shows the location of cores and sawn asphalt samples. The general pavement surface condition is shown in Photos P3 to P6. The asphalt wearing surface on the concrete deck is generally in fair condition with unsealed transverse (82.0 m), longitudinal (65.0 m) and random (584.0 m) cracking, sealed transverse (10.0 m), longitudinal (6.0 m) and random (79.0 m) cracking. The total asphalt thickness, measured in the drilled holes and the cores and sawn asphalt sample locations, varied from 40 mm to 110 mm with an average thickness of 69 mm (refer to Drawing No. 2). Three samples of the asphalt wearing surface were tested for asbestos contaminations according to EPA 600/R‐93/116 test method using Polarized Light Microscope. The results indicated 1.2‐1.3% asbestos content in the samples. Refer to IATL International laboratory test results.  

 

22 of 265

Page 23: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                   

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

3.2  Waterproofing 

Evidence of a hot rubberized asphalt waterproofing system with protection board was detected over the concrete deck, ranging in thickness from 7 to 9 mm with an average thickness of 8 mm. The condition of the  waterproofing  membrane  encountered  in  the  test  locations  was  generally  good.  The  bond  of waterproofing to the concrete was generally good. 

3.3  Concrete Deck 

The concrete deck consists of a  four span cast‐in‐place concrete post tension thick slab, supported by piers and abutments. The condition of the concrete deck was observed at 37 core locations and 30 sawn asphalt  sample  locations.  The  inside of  the  coreholes  and  the exposed  concrete  surface  at  the  sawn asphalt sample locations were examined carefully for cracks and other defects. A review of the concrete cores revealed cracking in core C36. Visual review of the exposed concrete surface at the sawn asphalt samples did not reveal any defects. Refer to the core and sawn asphalt sample logs and photos. 

The concrete cover to the upper rebar layer measured in the cores and sawn asphalt samples was found to  range  from 30  to 109 mm with an average  cover of 68 mm. The  field  cores  identified 15M  rebar imprint  in  the deck. The  reinforcement  steel was  found  to be  in good  condition with no evidence of corrosion. Refer to the core logs and photos.  

Corrosion  potential  values  obtained  from  the  half‐cell  test  carried  out  on  the  asphalt  covered  deck ranged from –0.102 V to –0.476 V with an average value of –0.218 V. The half‐cell survey indicated that 56.0% of the deck area likely had no corrosion activity, with corrosion potential values between 0.000 V and ‐0.199 V. The half‐cell survey  indicated uncertain  low corrosion activity for 34.0% (25.1%+8.9%) of the deck area, with values ranging from ‐0.200 V to ‐0.349 V. Probable active corrosion was detected for 10.0%  (6.3%+3.7%)  of  the  deck  area  with  corrosion  potential  values more  negative  than  ‐0.350  V. Drawing 3  shows  the  corrosion potential  readings on  the deck. Active  corrosion potential was  found adjacent to the north sidewalk. 

 

Corrosion potential distribution in the deck 

Cores C2 and C37 were  tested  for compressive strength of  the hardened concrete  in accordance with CSA A23.2‐09‐14C. The compressive strength of the hardened concrete for these cores ranged from 38.7 

56.0%25.1%

8.9%6.3%

3.7%

0 to ‐0.199 V‐0.200 to ‐0.299 V‐0.300 to ‐0.349 V‐0.350 to ‐0.449 V< ‐0.450

23 of 265

Page 24: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                   

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

MPa to 68.9 MPa, with an average compressive strength of 53.8 MPa. This value  is significantly higher than the 34.47 MPa (5000 psi) minimum strength specified on the original GA drawing.   

The  chloride  ion  content  was  determined  for  eight  cores  using  MTO  LS‐417  “Method  of  Test  for Determination of Total Chloride  Ion  in Concrete – Acid Soluble”. These core  samples were  located at areas prone to salt exposure (e.g. high corrosion potential areas, along construction joints, low points of the deck, asphalt cracks).  In addition, samples  from other moderately exposed areas were also  taken. The chloride ion content values, at the average concrete cover or at rebar level are summarized below.  

Core No.  C3  C5  C11  C17  C28  C33  C36  C39 Corrected Chloride 

Content (%)* 0.027  0.013  0.021  0.011  0.012  0.013  0.010  0.012 

Corrosion Potential (V)  ‐0.143  ‐0.131  ‐0.307  ‐0.166  ‐0.455  ‐0.161  ‐0.354  ‐0.459 * Background chloride ion content was assumed to be 0.010% for the parent concrete  The  chloride  threshold  value  necessary  to  depassivate  embedded  steel  and  to  allow  the  onset  of corrosion  (in the presence of oxygen and moisture)  is generally taken as 0.025% by mass of concrete. The  background  chloride  content  is  the  lowest  chloride  content  value  for  all  of  the  cores  tested  for chloride content. The “background” chlorides do not contribute  to corrosion, and  thus  the results are corrected for the background chloride content. The corrected chloride content, at the rebar  level, was above  the  chloride  threshold  level  of  0.025%  in  Core  C3.  Overall,  the  results  indicate  that  chloride contamination has extended to the upper rebar level in limited areas of the deck.  

Based on the concrete removal policy outlined in the Structure Rehabilitation Manual, the following comments can be made: 

• Since more than 10% of the deck area is more negative than ‐0.350 V, the average chloride content at the reinforcing level is calculated using the cores with corrosion potential values more  negative  than  ‐0.350  V.  Therefore,  the  average  adjusted  chloride  content  at  the reinforcing steel level is 0.011%. 

• Based on the above, since the average adjusted chloride content at the top reinforcement level  is  less  than 0.05% by mass of  concrete,  concrete deck  removal  is  recommended  to include delaminated areas only. 

 

Cores  C4,  C10,  and  C22 were  tested  to  determine  the  air  void  system  of  the  hardened  concrete  in accordance with  ASTM  C457  using  the Modified  Point  Count Method.  Test  results  are  summarized below:  

 

 

 

24 of 265

Page 25: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                   

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

Core No. Air Content 

(%) Specific Surface 

(mm‐1) Spacing Factor 

(mm) C4  6.1  33.4  0.090 C10  4.8  37.4  0.117 C22  4.3  36.6  0.119 

 Concrete is normally considered to be properly air entrained if the air content exceeds 3.0%, the specific surface exceeds 24 mm‐1, and the average spacing factor is less than 0.200 mm. Therefore, the air void system for all three tested cores is considered air entrained. 

3.4  Deck Soffit  

A detailed visual  inspection of deck soffit was carried out utilizing a Bridge Master. The deteriorations are shown on Drawing 4 and in Photos P7 to P24. 

The bridge deck soffit, with a total surveyed area of 1,951.60 m2, is in fair condition with clean/stained medium width cracking (100.0 m), delaminations (75.90 m2), spalls (20.90 m2), honeycombing (3.00 m2), and wet areas (47.40 m2). Deteriorations were predominantly observed within the westbound lanes and along the centreline of the deck. Exposed corroded reinforcement was observed in the spalled areas. A concrete  cover  survey was  conducted  on  the  deck  soffit  except  for  the  area  between  Piers  1  and  2 (above the CPR tracks). The concrete cover was found to range from 30 to 64 mm with an average cover of 44 mm, as shown on Drawing 5. 

 3.5  Bridge Approaches 

The  asphalt wearing  surface  on  the  bridge  approaches  is  generally  in  good  condition with  unsealed cracks. Photos P25 and P26  show  the general pavement  condition on  the east and west approaches, respectively. Observation of corehole C12, located at the east approach, confirmed presence of concrete approach slab beneath the asphalt. Asphalt thickness measured in core C12 was 40 mm. Observation of corehole C27, located at the west approach, confirmed presence of concrete approach slab beneath the asphalt. Asphalt  thickness measured  in core C27 was 50 mm. Photo P95 shows  the  inside of corehole C12.  

3.6  Deck Drainage 

Deck  drains  were  not  observed  on  this  structure.  Catch  basins  were  observed  at  northeast  and northwest quadrants and in the median outside structure limits (Photos P27 to P30).  

3.7  Deck Joints 

The expansion  joints  (strip  seal  joints) were generally  in  fair  to poor  condition with  light  rusting and missing sections of  the steel armoring angles. The seals were  found  to be damaged and covered with debris. Gap  dimensions  varied  from  20  to  40 mm.  Leaking  of  the  expansion  joints was  noted  from dampness of the deck soffit and abutments underneath. Cracking, scaling, and spalling were noted on 

25 of 265

Page 26: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                   

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

the concrete end dams. Photos P31 and P37 show general condition of  the  joints. Unevenness of  the east expansion joint was observed in the north sidewalk (Photo P34). 

3.8  Concrete Parapet Walls 

Inspection of the concrete parapet walls was not part of scope of this investigation. Photos P38 and P39 show  typical  condition  of  the  parapet walls.  Concrete  parapet walls  have  0.25 m width  and  0.61 m height. Photo P92 shows a utility box inside south parapet wall. The ducts were PVC and not containing any asbestos contaminations. 

3.9  Concrete Sidewalks 

Inspection of  the concrete  sidewalks was not part of  scope of  this  investigation. Photos P38 and P39 show typical condition of the sidewalks. Concrete sidewalks have 1.87 m width and 0.26 m height. Photo P93 shows a utility box  inside north sidewalk. GA Drawing shows 8 PVC Bell Canada Ducts  in the north sidewalk and 6 H.PC Ducts in the south sidewalk.  

3.10  Concrete Median 

Inspection of the concrete median was not part of scope of this investigation. Concrete median has 1.13 m width and 0.25 m height. Photo P40 shows typical condition of the median. 

3.11  End Posts and Guide Rails 

The concrete end posts are generally  in  fair  to good condition with cracks and delaminations  (Photos P41  to P44). The  steel beam guiderail  system at  southwest  corner of  the bridge  is  in good  condition (Photo P45).  

 

4.0  SUBSTRUCTURE COMPONENTS 

The  abutments,  piers,  retaining  walls,  and  wingwalls  were  inspected  and  hammer  sounded,  where accessible, to check for delaminations. Field measurements are presented in the field summary sheets.  4.1  Abutments and Bearings  The exposed surfaces of  the abutments were  inspected and sounded  to check  for delaminations. The total  surveyed  area  for  the  east  and west  abutments were  126.57  and  41.50 m2,  respectively.  The deteriorations  are  shown on Drawing 7. General  views of  the  abutments  and bearings  are  shown  in Photos  P46  to  P67.  The  abutments  are  in  fair  to  good  condition.  The  field  investigation  of  the  east abutment  revealed  clean/stained  medium  width  cracking  (35.0  m),  pattern  cracks  (0.50  m2)  and delaminations  (1.20 m2).  The  field  investigation of  the west  abutment  revealed  clean medium width cracking (6.0 m), delaminations (1.90 m2), and medium scaling (0.45 m2). 

26 of 265

Page 27: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                   

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

The east abutment elastomeric bearings are  in  fair  to good condition with cracks and bulging  (Photos P49 to P56). The west abutment laminated elastomeric bearings are in fair to good condition with cracks and bulging (Photos P60 to P67).  

4.2  Ballast Walls  The east ballast wall  is  in fair to good condition whereas the west ballast wall  is  in  fair condition. The deteriorations are shown on Drawing 7. The east abutment ballast wall had a total surveyed area of 7.00 m2 with  spalls  (0.15 m2). Photos P46  to P48  show  typical  condition of  the east ballast wall. The west abutment ballast wall had a  total  surveyed area of 7.00 m2 with clean medium width cracks  (2.0 m), delaminations (0.30 m2), spalls (0.30 m2), and  light scaling  (0.10 m2). Photos P57 and P58 show typical condition of the west ballast wall. 

4.3  Bearings Seats  The bearing  seats were generally  in good condition. The deteriorations are shown on Drawing 7. The east abutment bearing  seat had a  total  surveyed area of 16.50 m2, with no visible defects. The west abutment bearing seat had a total surveyed area of 16.50 m2, with no visible defects.  

4.4  Wingwalls 

The exposed areas of the wingwalls were inspected visually and hammer sounded. The wingwalls were in good condition and had a total surveyed area of 14.64 m2, with clean/stained medium width cracks (5.0 m), light scaling (0.15 m2), and wet areas (1.40 m2). The deteriorations are shown on Drawing 7 and in Photos P68 and P69. Wet areas were only observed on the southwest wingwall. 

 

4.5  Retaining Walls 

The exposed areas of  the  retaining walls were  inspected visually and hammer sounded. The  retaining walls were  in good  condition and had a  total  surveyed area of 55.84 m2, with  clean/stained medium width cracks (21.0 m). The deteriorations are shown on Drawing 7 and in Photos P70 and P71.  

4.6  Piers and Bearings  

The bridge piers are  in good condition with  total  surveyed area of 221.60 m2.  Inspection of  the piers revealed clean medium width cracks (4.0 m) and medium scaling (0.60 m2). Deteriorations are shown on Drawing  6  and  in  Photos  P72  to  P89. Medium  scaling was  found  on  Pier  #3.  The  expansion  Andre Rotaflon bearings at Piers #1 and #3 were found to be in fair to good condition with light corrosion and rust jacking. The Fixed Andre Rota bearings at Pier #2 were in good condition.  

4.7  Slopes  

The east slope was found to be in fair condition with soil erosion (Photo P90). The west slope paving was in fair to good condition with cracks (Photo P91).  

27 of 265

Page 28: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

28 of 265

Page 29: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                   

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

  

 

 

 

 

 

 

4/   Detailed Condition Survey Summary Sheets – Asphalt Covered Deck 

29 of 265

Page 30: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No. #817

Width between E abutment curbs 22.56 m Width between W abutment curbs 22.56 mLength between abutment joints 67.06 m Area of deck riding surface 1529.00 m²

* Asphalt potholes/patches = 0.00 m²* Asphalt Alligator Cracks = 0.00 m²* Asphalt Ravelling = 0.00 m²

Transverse 82.0 10.0 mLongitudinal 65.0 6.0 mRandom 584.0 79.0 m

Min Max AvgF 40 110 69 mm

* G – Good, F – Fair, P – Poor, V - Variable Good to Poor

Min Max AvgHot rubberized

asphalt with protection board

G G 7 9 8 mm

* G – Good, F – Fair, P – Poor, V - Variable Good to Poor** Report only thickness of waterproofing membrane but note presence of protection board

RemarksDeck dimensions

were taken from the structural drawings

Remarks

Remarks

DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4ASPHALT COVERED DECK

DECK RIDING SURFACE

Orientation Unsealed Sealed

1. Dimensions and Area of Survey

Condition * Conc. Bond *

2. Asphalt Surface Cracks

Depth3. Asphalt Depth

Condition *

4. WaterproofingThickness (mm) **Type

30 of 265

Page 31: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No. #817

5. Concrete Cover – Cores and Sawn SamplesMinimum Maximum Average

30 109 68 mm

Note: Only include covers for upper layer of rebars.

6. Corrosion ActivityMinimum Maximum Average

-0.102 -0.476 -0.218 V

0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V856.2 383.8 136.1 96.3 56.6 m2

56.0 25.1 8.9 6.3 3.7 %

7. Defective Cores and Sawn Samples

No. m2 % No. m2 %0 to -0.20 35 0 0.0 0.0 0 0.0 0.0

-0.20 to -0.30 14 0 0.0 0.0 0 0.0 0.0-0.30 to -0.35 10 0 0.0 0.0 0 0.0 0.0-0.35 to -0.45 3 0 0.0 0.0 0 0.0 0.0

<-0.45 5 0 0.0 0.0 0 0.0 0.0

Remarks

Cores and Sawn Samples

Total in Each Area

DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4ASPHALT COVERED DECK

DECK RIDING SURFACE

* The percent calculation should be of the entire deck area investigated. The values obtained should be used with caution as large errors may occur when a small number of samples are used for the calculation or when the samples are not randomly distributed over the entire deck area.

Delaminated, Spalled, Severe Scaling and Disintegration * Medium Scaling *Corrosion

Activity (Volts)

Remarks

Remarks

31 of 265

Page 32: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No. #817

8. Adjusted Chloride Content Profile *Background (parent concrete) chloride content = 0.010

0 to -0.20 -0.20 to -0.35 ≤-0.350-10 mm 0.023 0.034 0.02020-30 mm 0.020 0.029 0.01540-50 mm 0.018 0.028 0.01460-70 mm 0.016 0.021 0.01180-90 mm 0.011 0.017 0.009

100-110 mm 0.017 ‐ ‐

Core No. C3 C5 C11 C17 C28 C33 C36Chloride Content* 0.027 0.013 0.021 0.011 0.012 0.013 0.010

Corrosion Potential -0.143 -0.131 -0.307 -0.166 -0.455 -0.161 -0.354

Core No. C39Chloride Content* 0.012

Corrosion Potential -0.459

Core No.Chloride Content*

* Chloride content as % chloride by weight of concrete after deducting background chlorides.

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

Table # 10 is Not Applicable.

Remarks

RemarksMeasured AC Resistance between Connection #1 and #2 Calculated AC

Resistance Connection #1Connection #2

10. AC Resistance Test Data of Epoxy Coated Rebar

* See Appendix 1E for calculating AC resistance contributed by individual rebar.

* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.

DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4ASPHALT COVERED DECK

DECK RIDING SURFACE

Corrosion Activity at Core

Chloride Content*

9. Chloride Content at Rebar Level

Corrosion Potential

32 of 265

Page 33: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No. #817

11. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

12. Concrete Air EntrainmentYes No Marginal

Concrete Air Entrained?C4 YesC10 YesC22 Yes

13. Compressive Strength

Average Compressive Strength 53.8 MPa

RemarksTable # 11 is Not

Applicable.

* Half cell reading taken on the same rebar with the ground connection.

DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4ASPHALT COVERED DECK

DECK RIDING SURFACE

IR Drop Between Connection #1 and #2 True Half Cell

Potential *Connection #1

(positive)Connection #2 (negative)

33 of 265

Page 34: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                   

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

  

 

 

 

 

 

 

5/   Detailed Condition Survey Summary Sheets – Exposed Concrete Components 

34 of 265

Page 35: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817

Component Type & Location: Soffit OSIM Identifier: Decks

1. Dimensions and AreaWidth 28.34 m Length 67.67 m Height 0.25 m x 2Diameter - Total Area Surveyed 1951.60 m²

2. Cracks (medium and wide)Transverse Longitudinal Other Total

Clean 0.0 15.0 25.0Stained 12.0 33.0 15.0Clean 0.0 0.0 0.0

Stained 0.0 0.0 0.0

3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²

Minimum Maximum Average30 64 44 mm

0.0 1424.7 m2

0.0 73.0 %521.1 5.9 m2

26.7 0.3 %over 60 mm

Type

100.0

DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component

0 – 20 mm

20 – 40 mm

mWide Width

Medium Width

RemarksDimensions were taken

from the structural drawings & site measurements

Remarks

m

40 – 60 mm

0.0

4. Concrete Cover

35 of 265

Page 36: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: Soffit OSIM Identifier: Decks

Minimum Maximum Average- - - V

0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V

- - - - - m2

- - - - - %

6. Delaminations and Spalls

Defect Type Delaminations Spalls Patches *Wet areas = 47.40 m²Area (m2) 75.90 20.90 0.00

96.80 m² 5.0 % N/A N/A

Light Medium Severe to Very Severe

0.00 0.00 0.00 m2

0.0 0.0 0.0 %

8. Honeycombing

Total Area 3.00 m²

Remarks

5. Corrosion Activity

Remarks

7. Scaling

Total Delaminations and Spalls

DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS

Total Delaminations and Spalls in Areas ≤-0.35 V

Table # 5 is Not Applicable.

Remarks

36 of 265

Page 37: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: Soffit OSIM Identifier: Decks

9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35

0-10 mm - - -

20-30 mm - - -

40-50 mm - - -

60-70 mm - - -

80-90 mm - - -

100-110 mm - - -

10. Chloride Content at Rebar LevelCore No. - - - - - -

Chloride Content* - - - - - -

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

* Chloride content as % chloride by weight of concrete after deducting background chlorides.

Measured AC Resistance between Connection #1 and #2 Calculated AC

Resistance Connection #1

Remarks

DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS

Corrosion Activity at Core Location (volts)

* See Appendix 1E for calculating AC resistance contributed by individual rebar.

Remarks

* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.

Table # 9 and 10 are Not Applicable.

11. AC Resistance Test Data of Epoxy Coated Rebar

Connection #2

Table # 11 is Not Applicable.

Chloride Content*

37 of 265

Page 38: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: Soffit OSIM Identifier: Decks

12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

13. Concrete Air Entrainment

Concrete Air Entrained: not tested

14. Compressive Strength

Average Compressive Strength: not tested

DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS

Connection #2 (negative)

* Half cell reading taken on the same rebar with the ground connection.

Connection #1 (positive)

True Half Cell

Potential *

RemarksTable # 12 is Not

Applicable.

IR Drop Between Connection #1 and #2

38 of 265

Page 39: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817

Component Type & Location: West Abutment Wall OSIM Identifier: Abutments

1. Dimensions and AreaWidth 29.23 m Length - Height Avg. 1.42 mDiameter - Total Area Surveyed 41.50 m²

2. Cracks (medium and wide)Vertical Horizontal Diagonal Total

Clean 2.0 0.0 4.0Stained 0.0 0.0 0.0Clean 0.0 0.0 0.0

Stained 0.0 0.0 0.0

3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²

Minimum Maximum Average- - - mm

- - m2

- - %- - m2

- - %

4. Concrete Cover

0 – 20 mm 40 – 60 mm

20 – 40 mm over 60 mm

RemarksTable # 4 is Not

Applicable.

DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component

Type

Medium Width 6.0 m

Wide Width 0.0 m

RemarksDimensions were taken

from the structural drawings & site measurements

39 of 265

Page 40: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: West Abutment Wall OSIM Identifier: Abutments

Minimum Maximum Average- - - V

0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V

- - - - - m2

- - - - - %

6. Delaminations and Spalls

Defect Type Delaminations Spalls Patches *Wet areas = 0.00 m²Area (m2) 1.90 0.00 0.00

1.90 m² 4.6 % N/A N/A

Light Medium Severe to Very Severe

0.00 0.45 0.00 m2

0.0 1.1 0.0 %

8. Honeycombing

Total Area 0.00 m²

RemarksTable # 5 is Not

Applicable.

Remarks

Remarks

5. Corrosion Activity

Total Delaminations and Spalls

Total Delaminations and Spalls in Areas ≤-0.35 V

7. Scaling

DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS

40 of 265

Page 41: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: West Abutment Wall OSIM Identifier: Abutments

9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35

0-10 mm - - -

20-30 mm - - -

40-50 mm - - -

60-70 mm - - -

80-90 mm - - -

100-110 mm - - -

10. Chloride Content at Rebar LevelCore No. - - - - - -

Chloride Content* - - - - - -

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

RemarksTable # 9 and 10 are

Not Applicable.

RemarksTable # 11 is Not

Applicable.

* See Appendix 1E for calculating AC resistance contributed by individual rebar.

Corrosion Activity at Core Location (volts)

Chloride Content*

* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.

* Chloride content as % chloride by weight of concrete after deducting background chlorides.

11. AC Resistance Test Data of Epoxy Coated RebarMeasured AC Resistance between Connection #1 and #2 Calculated

AC Resistance Connection #1

Connection #2

DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS

41 of 265

Page 42: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: West Abutment Wall OSIM Identifier: Abutments

12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

13. Concrete Air Entrainment

Concrete Air Entrained: not tested

14. Compressive Strength

Average Compressive Strength: not tested

* Half cell reading taken on the same rebar with the ground connection.

DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS

IR Drop Between Connection #1 and #2 True Half Cell

Potential *Connection #1

(positive)Connection #2 (negative)

Table # 12 is Not Applicable.

Remarks

42 of 265

Page 43: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817

Component Type & Location: West Ballast Wall OSIM Identifier: Abutments

1. Dimensions and AreaWidth 29.23 m Length - Height -Diameter - Total Area Surveyed 7.00 m²

2. Cracks (medium and wide)Vertical Horizontal Diagonal Total

Clean 1.0 0.0 1.0Stained 0.0 0.0 0.0Clean 0.0 0.0 0.0

Stained 0.0 0.0 0.0

3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²

Minimum Maximum Average- - - mm

- - m2

- - %- - m2

- - %

4. Concrete Cover

0 – 20 mm 40 – 60 mm

20 – 40 mm over 60 mm

RemarksTable # 4 is Not

Applicable.

DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component

Type

Medium Width 2.0 m

Wide Width 0.0 m

RemarksDimensions were taken

from the structural drawings & site measurements

43 of 265

Page 44: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: West Ballast Wall OSIM Identifier: Abutments

Minimum Maximum Average- - - V

0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V

- - - - - m2

- - - - - %

6. Delaminations and Spalls

Defect Type Delaminations Spalls Patches *Wet areas = 0.00 m²Area (m2) 0.30 0.30 0.00

0.60 m² 8.6 % N/A N/A

Light Medium Severe to Very Severe

0.10 0.00 0.00 m2

1.4 0.0 0.0 %

8. Honeycombing

Total Area 0.00 m²

RemarksTable # 5 is Not

Applicable.

Remarks

Remarks

5. Corrosion Activity

Total Delaminations and Spalls

Total Delaminations and Spalls in Areas ≤-0.35 V

7. Scaling

DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS

44 of 265

Page 45: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: West Ballast Wall OSIM Identifier: Abutments

9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35

0-10 mm - - -

20-30 mm - - -

40-50 mm - - -

60-70 mm - - -

80-90 mm - - -

100-110 mm - - -

10. Chloride Content at Rebar LevelCore No. - - - - - -

Chloride Content* - - - - - -

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

RemarksTable # 9 and 10 are

Not Applicable.

RemarksTable # 11 is Not

Applicable.

* See Appendix 1E for calculating AC resistance contributed by individual rebar.

Corrosion Activity at Core Location (volts)

Chloride Content*

* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.

* Chloride content as % chloride by weight of concrete after deducting background chlorides.

11. AC Resistance Test Data of Epoxy Coated RebarMeasured AC Resistance between Connection #1 and #2 Calculated

AC Resistance Connection #1

Connection #2

DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS

45 of 265

Page 46: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: West Ballast Wall OSIM Identifier: Abutments

12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

13. Concrete Air Entrainment

Concrete Air Entrained: not tested

14. Compressive Strength

Average Compressive Strength: not tested

* Half cell reading taken on the same rebar with the ground connection.

DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS

IR Drop Between Connection #1 and #2 True Half Cell

Potential *Connection #1

(positive)Connection #2 (negative)

Table # 12 is Not Applicable.

Remarks

46 of 265

Page 47: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817

Component Type & Location: West Abutment Bearing Seat OSIM Identifier: Abutments

1. Dimensions and AreaWidth 0.61 m Length 29.23 m Height -Diameter - Total Area Surveyed 16.50 m²

2. Cracks (medium and wide)Transverse Longitudinal Other Total

Clean 0.0 0.0 0.0Stained 0.0 0.0 0.0Clean 0.0 0.0 0.0

Stained 0.0 0.0 0.0

3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²

Minimum Maximum Average- - - mm

- - m2

- - %- - m2

- - %

RemarksTable # 4 is Not

Applicable.

Dimensions were taken from the

structural drawings & site measurements

4. Concrete Cover

0 – 20 mm 40 – 60 mm

20 – 40 mm over 60 mm

DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component

Type

Medium Width 0.0 m

Wide Width 0.0 m

Remarks

47 of 265

Page 48: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: West Abutment Bearing Seat OSIM Identifier: Abutments

Minimum Maximum Average- - - V

0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V

- - - - - m2

- - - - - %

6. Delaminations and Spalls

Defect Type Delaminations Spalls Patches *Wet areas = 0.00 m²Area (m2) 0.00 0.00 0.00

0.00 m² 0.0 % N/A N/A

Light Medium Severe to Very Severe

0.00 0.00 0.00 m2

0.0 0.0 0.0 %

8. Honeycombing

Total Area 0.00 m²

RemarksTable # 5 is Not

Applicable.

Remarks

Remarks

DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS

5. Corrosion Activity

Total Delaminations and Spalls

Total Delaminations and Spalls in Areas ≤-0.35 V

7. Scaling

48 of 265

Page 49: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: West Abutment Bearing Seat OSIM Identifier: Abutments

9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35

0-10 mm - - -

20-30 mm - - -

40-50 mm - - -

60-70 mm - - -

80-90 mm - - -

100-110 mm - - -

10. Chloride Content at Rebar LevelCore No. - - - - - -

Chloride Content* - - - - - -

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

Table # 9 and 10 are Not Applicable.

RemarksTable # 11 is Not

Applicable.

* See Appendix 1E for calculating AC resistance contributed by individual rebar.

Corrosion Activity at Core Location (volts)

Chloride Content*

* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.

* Chloride content as % chloride by weight of concrete after deducting background chlorides.

11. AC Resistance Test Data of Epoxy Coated RebarMeasured AC Resistance between Connection #1 and #2 Calculated

AC Resistance Connection #1

Connection #2

Remarks

DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS

49 of 265

Page 50: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: West Abutment Bearing Seat OSIM Identifier: Abutments

12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

13. Concrete Air Entrainment

Concrete Air Entrained: not tested

14. Compressive Strength

Average Compressive Strength: not tested

* Half cell reading taken on the same rebar with the ground connection.

DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS

IR Drop Between Connection #1 and #2 True Half Cell

Potential *Connection #1

(positive)Connection #2 (negative)

Table # 12 is Not Applicable.

Remarks

50 of 265

Page 51: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817

Component Type & Location: East Abutment Wall OSIM Identifier: Abutments

1. Dimensions and AreaWidth 29.23 m Length - Height Avg. 4.33 mDiameter - Total Area Surveyed 126.57 m²

2. Cracks (medium and wide)Vertical Horizontal Diagonal Total

Clean 13.0 0.0 18.0Stained 2.0 0.0 2.0Clean 0.0 0.0 0.0

Stained 0.0 0.0 0.0Pattern cracks= 0.5 m²

3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²

Minimum Maximum Average- - - mm

- - m2

- - %- - m2

- - %

4. Concrete Cover

0 – 20 mm 40 – 60 mm

20 – 40 mm over 60 mm

RemarksTable # 4 is Not

Applicable.

DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component

Type

Medium Width 35.0 m

Wide Width 0.0 m

RemarksDimensions were taken

from the structural drawings & site measurements

51 of 265

Page 52: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: East Abutment Wall OSIM Identifier: Abutments

Minimum Maximum Average- - - V

0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V

- - - - - m2

- - - - - %

6. Delaminations and Spalls

Defect Type Delaminations Spalls Patches *Wet areas = 0.00 m²Area (m2) 1.20 0.00 0.00

1.20 m² 0.9 % N/A N/A

Light Medium Severe to Very Severe

0.00 0.00 0.00 m2

0.0 0.0 0.0 %

8. Honeycombing

Total Area 0.00 m²

RemarksTable # 5 is Not

Applicable.

Remarks

Remarks

5. Corrosion Activity

Total Delaminations and Spalls

Total Delaminations and Spalls in Areas ≤-0.35 V

7. Scaling

DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS

52 of 265

Page 53: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: East Abutment Wall OSIM Identifier: Abutments

9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35

0-10 mm - - -

20-30 mm - - -

40-50 mm - - -

60-70 mm - - -

80-90 mm - - -

100-110 mm - - -

10. Chloride Content at Rebar LevelCore No. - - - - - -

Chloride Content* - - - - - -

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

RemarksTable # 9 and 10 are

Not Applicable.

RemarksTable # 11 is Not

Applicable.

* See Appendix 1E for calculating AC resistance contributed by individual rebar.

Corrosion Activity at Core Location (volts)

Chloride Content*

* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.

* Chloride content as % chloride by weight of concrete after deducting background chlorides.

11. AC Resistance Test Data of Epoxy Coated RebarMeasured AC Resistance between Connection #1 and #2 Calculated

AC Resistance Connection #1

Connection #2

DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS

53 of 265

Page 54: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: East Abutment Wall OSIM Identifier: Abutments

12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

13. Concrete Air Entrainment

Concrete Air Entrained: not tested

14. Compressive Strength

Average Compressive Strength: not tested

* Half cell reading taken on the same rebar with the ground connection.

DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS

IR Drop Between Connection #1 and #2 True Half Cell

Potential *Connection #1

(positive)Connection #2 (negative)

Table # 12 is Not Applicable.

Remarks

54 of 265

Page 55: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817

Component Type & Location: East Ballast Wall OSIM Identifier: Abutments

1. Dimensions and AreaWidth 29.23 m Length - Height -Diameter - Total Area Surveyed 7.00 m²

2. Cracks (medium and wide)Vertical Horizontal Diagonal Total

Clean 0.0 0.0 0.0Stained 0.0 0.0 0.0Clean 0.0 0.0 0.0

Stained 0.0 0.0 0.0

3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²

Minimum Maximum Average- - - mm

- - m2

- - %- - m2

- - %

4. Concrete Cover

0 – 20 mm 40 – 60 mm

20 – 40 mm over 60 mm

RemarksTable # 4 is Not

Applicable.

DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component

Type

Medium Width 0.0 m

Wide Width 0.0 m

RemarksDimensions were taken

from the structural drawings & site measurements

55 of 265

Page 56: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: East Ballast Wall OSIM Identifier: Abutments

Minimum Maximum Average- - - V

0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V

- - - - - m2

- - - - - %

6. Delaminations and Spalls

Defect Type Delaminations Spalls Patches *Wet areas = 0.00 m²Area (m2) 0.00 0.15 0.00

0.15 m² 2.1 % N/A N/A

Light Medium Severe to Very Severe

0.00 0.00 0.00 m2

0.0 0.0 0.0 %

8. Honeycombing

Total Area 0.00 m²

RemarksTable # 5 is Not

Applicable.

Remarks

Remarks

5. Corrosion Activity

Total Delaminations and Spalls

Total Delaminations and Spalls in Areas ≤-0.35 V

7. Scaling

DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS

56 of 265

Page 57: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: East Ballast Wall OSIM Identifier: Abutments

9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35

0-10 mm - - -

20-30 mm - - -

40-50 mm - - -

60-70 mm - - -

80-90 mm - - -

100-110 mm - - -

10. Chloride Content at Rebar LevelCore No. - - - - - -

Chloride Content* - - - - - -

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

RemarksTable # 9 and 10 are

Not Applicable.

RemarksTable # 11 is Not

Applicable.

* See Appendix 1E for calculating AC resistance contributed by individual rebar.

Corrosion Activity at Core Location (volts)

Chloride Content*

* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.

* Chloride content as % chloride by weight of concrete after deducting background chlorides.

11. AC Resistance Test Data of Epoxy Coated RebarMeasured AC Resistance between Connection #1 and #2 Calculated

AC Resistance Connection #1

Connection #2

DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS

57 of 265

Page 58: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: East Ballast Wall OSIM Identifier: Abutments

12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

13. Concrete Air Entrainment

Concrete Air Entrained: not tested

14. Compressive Strength

Average Compressive Strength: not tested

* Half cell reading taken on the same rebar with the ground connection.

DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS

IR Drop Between Connection #1 and #2 True Half Cell

Potential *Connection #1

(positive)Connection #2 (negative)

Table # 12 is Not Applicable.

Remarks

58 of 265

Page 59: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817

Component Type & Location: East Abutment Bearing Seat OSIM Identifier: Abutments

1. Dimensions and AreaWidth 0.61 m Length 29.23 m Height -Diameter - Total Area Surveyed 16.50 m²

2. Cracks (medium and wide)Transverse Longitudinal Other Total

Clean 0.0 0.0 0.0Stained 0.0 0.0 0.0Clean 0.0 0.0 0.0

Stained 0.0 0.0 0.0

3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²

Minimum Maximum Average- - - mm

- - m2

- - %- - m2

- - %

RemarksTable # 4 is Not

Applicable.

Dimensions were taken from the

structural drawings & site measurements

4. Concrete Cover

0 – 20 mm 40 – 60 mm

20 – 40 mm over 60 mm

DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component

Type

Medium Width 0.0 m

Wide Width 0.0 m

Remarks

59 of 265

Page 60: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: East Abutment Bearing Seat OSIM Identifier: Abutments

Minimum Maximum Average- - - V

0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V

- - - - - m2

- - - - - %

6. Delaminations and Spalls

Defect Type Delaminations Spalls Patches *Wet areas = 0.00 m²Area (m2) 0.00 0.00 0.00

0.00 m² 0.0 % N/A N/A

Light Medium Severe to Very Severe

0.00 0.00 0.00 m2

0.0 0.0 0.0 %

8. Honeycombing

Total Area 0.00 m²

Remarks7. Scaling

DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS

5. Corrosion Activity

Total Delaminations and Spalls

Total Delaminations and Spalls in Areas ≤-0.35 V

RemarksTable # 5 is Not

Applicable.

Remarks

60 of 265

Page 61: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: East Abutment Bearing Seat OSIM Identifier: Abutments

9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35

0-10 mm - - -

20-30 mm - - -

40-50 mm - - -

60-70 mm - - -

80-90 mm - - -

100-110 mm - - -

10. Chloride Content at Rebar LevelCore No. - - - - - -

Chloride Content* - - - - - -

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

RemarksTable # 9 and 10 are

Not Applicable.

RemarksTable # 11 is Not

Applicable.

11. AC Resistance Test Data of Epoxy Coated RebarMeasured AC Resistance between Connection #1 and #2 Calculated

AC Resistance Connection #1

Connection #2

* See Appendix 1E for calculating AC resistance contributed by individual rebar.

DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS

Corrosion Activity at Core Location (volts)

Chloride Content*

* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.

* Chloride content as % chloride by weight of concrete after deducting background chlorides.

61 of 265

Page 62: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: East Abutment Bearing Seat

12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

13. Concrete Air Entrainment

Concrete Air Entrained: not tested

14. Compressive Strength

Average Compressive Strength: not tested

Connection #1 (positive)

Connection #2 (negative)

OSIM Identifier: Abutments

Table # 12 is Not Applicable.

* Half cell reading taken on the same rebar with the ground connection.

DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS

IR Drop Between Connection #1 and #2 True Half Cell

Potential *

Remarks

62 of 265

Page 63: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817

Component Type & Location: Wingwalls OSIM Identifier: Abutments

1. Dimensions and AreaWidth - Length 3.66 m x 2 Height Avg. 2.00 mDiameter - Total Area Surveyed 14.64 m²

2. Cracks (medium and wide)Vertical Horizontal Diagonal Total

Clean 0.0 1.0 2.0Stained 0.0 2.0 0.0Clean 0.0 0.0 0.0

Stained 0.0 0.0 0.0

3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²

Minimum Maximum Average- - - mm

- - m2

- - %- - m2

- - %

RemarksDimensions were taken

from the structural drawings & site measurements

Remarks

m

Table # 4 is Not Applicable.

0.0

0 – 20 mm 40 – 60 mm

20 – 40 mm over 60 mm

Wide Width

4. Concrete Cover

DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component

Type

Medium Width m5.0

63 of 265

Page 64: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: Wingwalls OSIM Identifier: Abutments

Minimum Maximum Average- - - V

0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V

- - - - - m2

- - - - - %

6. Delaminations and Spalls

Defect Type Delaminations Spalls Patches *Wet areas = 1.40 m²Area (m2) 0.00 0.00 0.00

0.00 m² 0.0 % N/A N/A

Light Medium Severe to Very Severe

0.15 0.00 0.00 m2

1.0 0.0 0.0 %

8. Honeycombing

Total Area 0.00 m²

Remarks

RemarksTable # 5 is Not

Applicable.

Remarks

7. Scaling

DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS

5. Corrosion Activity

Total Delaminations and Spalls

Total Delaminations and Spalls in Areas ≤-0.35 V

64 of 265

Page 65: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: Wingwalls OSIM Identifier: Abutments

9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35

0-10 mm - - -

20-30 mm - - -

40-50 mm - - -

60-70 mm - - -

80-90 mm - - -

100-110 mm - - -

10. Chloride Content at Rebar LevelCore No. - - - - - -

Chloride Content* - - - - - -

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

Table # 11 is Not Applicable.

RemarksTable # 9 and 10 are

Not Applicable.

Remarks

11. AC Resistance Test Data of Epoxy Coated RebarMeasured AC Resistance between Connection #1 and #2 Calculated

AC Resistance

* Chloride content as % chloride by weight of concrete after deducting background chlorides.

DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS

Corrosion Activity at Core Location (volts)

Chloride Content*

* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.

Connection #1Connection #2

* See Appendix 1E for calculating AC resistance contributed by individual rebar.

65 of 265

Page 66: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: Wingwalls OSIM Identifier: Abutments

12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

13. Concrete Air Entrainment

Concrete Air Entrained: not tested

14. Compressive Strength

Average Compressive Strength: not tested

Remarks

DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS

* Half cell reading taken on the same rebar with the ground connection.

IR Drop Between Connection #1 and #2 True Half Cell

Potential *Connection #1

(positive)Connection #2 (negative)

Table # 12 is Not Applicable.

66 of 265

Page 67: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817

Component Type & Location: Piers OSIM Identifier: Piers

1. Dimensions and AreaWidth - Length - Height -Diameter - Total Area Surveyed 221.60 m²

2. Cracks (medium and wide)Vertical Horizontal Diagonal Total

Clean 3.0 0.0 1.0Stained 0.0 0.0 0.0Clean 0.0 0.0 0.0

Stained 0.0 0.0 0.0

3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²

Minimum Maximum Average- - - mm

- - m2

- - %- - m2

- - %

RemarksDimensions were taken

from the structural drawings & site measurements

RemarksTable # 4 is Not

Applicable.

m

4. Concrete Cover

Type

Medium Width m4.0

0 – 20 mm 40 – 60 mm

20 – 40 mm over 60 mm

Wide Width 0.0

DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component

67 of 265

Page 68: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: Piers OSIM Identifier: Piers

Minimum Maximum Average- - - V

0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V

- - - - - m2

- - - - - %

6. Delaminations and Spalls

Defect Type Delaminations Spalls Patches *Wet areas = 0.00 m²Area (m2) 0.00 0.00 0.00

0.00 m² 0.0 % N/A N/A

Light Medium Severe to Very Severe

0.00 0.60 0.00 m2

0.0 0.3 0.0 %

8. Honeycombing

Total Area 0.00 m²

Remarks

Remarks

RemarksTable # 5 is Not

Applicable.

DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS

5. Corrosion Activity

7. Scaling

Total Delaminations and Spalls

Total Delaminations and Spalls in Areas ≤-0.35 V

68 of 265

Page 69: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: Piers OSIM Identifier: Piers

9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35

0-10 mm - - -

20-30 mm - - -

40-50 mm - - -

60-70 mm - - -

80-90 mm - - -

100-110 mm - - -

10. Chloride Content at Rebar LevelCore No. - - - - - -

Chloride Content* - - - - - -

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

RemarksTable # 11 is Not

Applicable.

RemarksTable # 9 and 10 are

Not Applicable.

Chloride Content*

* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.

* See Appendix 1E for calculating AC resistance contributed by individual rebar.

11. AC Resistance Test Data of Epoxy Coated RebarMeasured AC Resistance between Connection #1 and #2

* Chloride content as % chloride by weight of concrete after deducting background chlorides.

DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS

Corrosion Activity at Core Location (volts)

Calculated AC

Resistance Connection #1Connection #2

69 of 265

Page 70: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: Piers OSIM Identifier: Piers

12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

13. Concrete Air Entrainment

Concrete Air Entrained: not tested

14. Compressive Strength

Average Compressive Strength: not tested

DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS

* Half cell reading taken on the same rebar with the ground connection.

IR Drop Between Connection #1 and #2 True Half Cell

Potential *Connection #1

(positive)Connection #2 (negative)

RemarksTable # 12 is Not

Applicable.

70 of 265

Page 71: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817

Component Type & Location: Retaining Walls OSIM Identifier: Retaining Walls

1. Dimensions and AreaWidth - Length Avg. 13.36 m x 2 Height Avg. 2.09 mDiameter - Total Area Surveyed 55.84 m²

2. Cracks (medium and wide)Vertical Horizontal Diagonal Total

Clean 0.0 0.0 7.0Stained 9.0 0.0 5.0Clean 0.0 0.0 0.0

Stained 0.0 0.0 0.0

3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²

Minimum Maximum Average- - - mm

- - m2

- - %- - m2

- - %

RemarksDimensions were taken

from the structural drawings & site measurements

RemarksTable # 4 is Not

Applicable.

m

4. Concrete Cover

Type

Medium Width m21.0

0 – 20 mm 40 – 60 mm

20 – 40 mm over 60 mm

Wide Width 0.0

DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component

71 of 265

Page 72: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: Retaining Walls OSIM Identifier: Retaining Walls

Minimum Maximum Average- - - V

0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V

- - - - - m2

- - - - - %

6. Delaminations and Spalls

Defect Type Delaminations Spalls Patches *Wet areas = 0.00 m²Area (m2) 0.00 0.00 0.00

0.00 m² 0.0 % N/A N/A

Light Medium Severe to Very Severe

0.00 0.00 0.00 m2

0.0 0.0 0.0 %

8. Honeycombing

Total Area 0.00 m²

Remarks

Remarks

RemarksTable # 5 is Not

Applicable.

DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS

5. Corrosion Activity

7. Scaling

Total Delaminations and Spalls

Total Delaminations and Spalls in Areas ≤-0.35 V

72 of 265

Page 73: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: Retaining Walls OSIM Identifier: Retaining Walls

9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35

0-10 mm - - -

20-30 mm - - -

40-50 mm - - -

60-70 mm - - -

80-90 mm - - -

100-110 mm - - -

10. Chloride Content at Rebar LevelCore No. - - - - - -

Chloride Content* - - - - - -

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

RemarksTable # 11 is Not

Applicable.

RemarksTable # 9 and 10 are

Not Applicable.

Chloride Content*

* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.

* See Appendix 1E for calculating AC resistance contributed by individual rebar.

11. AC Resistance Test Data of Epoxy Coated RebarMeasured AC Resistance between Connection #1 and #2

* Chloride content as % chloride by weight of concrete after deducting background chlorides.

DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS

Corrosion Activity at Core Location (volts)

Calculated AC

Resistance Connection #1Connection #2

73 of 265

Page 74: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Site No: #817Component Type & Location: Retaining Walls OSIM Identifier: Retaining Walls

12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar

G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -

13. Concrete Air Entrainment

Concrete Air Entrained: not tested

14. Compressive Strength

Average Compressive Strength: not tested

DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS

* Half cell reading taken on the same rebar with the ground connection.

IR Drop Between Connection #1 and #2 True Half Cell

Potential *Connection #1

(positive)Connection #2 (negative)

RemarksTable # 12 is Not

Applicable.

74 of 265

Page 75: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                   

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

  

 

 

 

 

 

 

6/   Detailed Condition Survey Summary Sheet – Expansion Joints 

75 of 265

Page 76: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

 

CONDITION SURVEY SUMMARY SHEET EXPANSION JOINTS Site No. 817 EBL

Dimension

Abutments Intermediate

Remarks

Joint 1

Joint 2

Joint 3

Joint 4

E W

a (mm) 254+1876 254+1876 - -

b (mm) 260 245 - -

b' (mm) 265 250 - -

c (mm) 11278 11278 - -

d (mm) 250 250 - -

d' (mm) 255 255 - -

e (mm) 762 762 - -

Depth of Asphalt @ Deck Side N/E S/E N/E S/W

1 (mm) 45 50 - - - -

2 (mm) 50 40 - - - -

3 (mm) 55 75 - - - -

Width: Top of Ballast Wall and End Dams

N/E

S/W

N/E S/W N/E S/W N/E S/W

1 (mm) - - - - - - - -

2 (mm) - - - - - - - -

3 (mm) - - - - - - - -

Gap Dimensions

1 (mm) 20 40 - -

2 (mm) 20 40 - - 3 (mm) 20 40 - -

Misc. Joint Details

Skew Angle 00º 00’ 00”

Exp YES YES - -

Fixed NO NO - -

Type STRIP SEAL JOINT -

Leaking YES YES - -

Angle size - - - -

Temp °C

Deck 10ºC Ambient 10ºC

N JOINT DIMENSIONSS

Typical Sections at Joints: E - W

STEEL ANGLE

EXPOSED CONCRETE

EXPOSED CONCRETE

STRIP SEAL

DECK

140mm

70mm

STEEL ANGLE85mm

220mm

STEEL ANGLE

EXPOSED CONCRETE

EXPOSED CONCRETE

STRIP SEAL

EAST APPROACH SLAB

DECK

120mm

90mm

STEEL ANGLE90mm

210mm

WEST APPROACH SLAB

76 of 265

Page 77: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

 

CONDITION SURVEY SUMMARY SHEET EXPANSION JOINTS Site No. 817WBL

Dimension

Abutments Intermediate

Remarks

Joint 1

Joint 2

Joint 3

Joint 4

E W

a (mm) 762 762 - -

b (mm) 250 245 - -

b' (mm) 255 250 - -

c (mm) 11278 11278 - -

d (mm) 250 265 - -

d' (mm) 255 270 - -

e (mm) 254+1876 254+1876 - -

Depth of Asphalt @ Deck Side N/E S/E N/E S/W

1 (mm) 75 85 - - - -

2 (mm) 40 80 - - - -

3 (mm) 75 80 - - - -

Width: Top of Ballast Wall and End Dams

N/E

S/W

N/E S/W N/E S/W N/E S/W

1 (mm) - - - - - - - -

2 (mm) - - - - - - - -

3 (mm) - - - - - - - -

Gap Dimensions

1 (mm) 20 40 - -

2 (mm) 20 40 - - 3 (mm) 20 40 - -

Misc. Joint Details

Skew Angle 00º 00’ 00”

Exp YES YES - -

Fixed NO NO - -

Type STRIP SEAL JOINT -

Leaking YES YES - -

Angle size - - - -

Temp °C

Deck 10ºC Ambient 10ºC

N JOINT DIMENSIONSS

Typical Sections at Joints: E - W

STEEL ANGLE

EXPOSED CONCRETE

EXPOSED CONCRETE

STRIP SEAL

DECK

140mm

70mm

STEEL ANGLE85mm

220mm

STEEL ANGLE

EXPOSED CONCRETE

EXPOSED CONCRETE

STRIP SEAL

EAST APPROACH SLAB

DECK

120mm

90mm

STEEL ANGLE90mm

210mm

WEST APPROACH SLAB

77 of 265

Page 78: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                   

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

  

 

 

 

 

 

 

7/   Detailed Condition Survey Summary Sheet – Drainage 

78 of 265

Page 79: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

                                                                                                                                 

DRAINAGE Site No. 817

Deck Drains

Number

Type Length Angle Depth *

- - - - -

* For asphalt covered decks, recess depth in mm between top of asphalt and top of drain.

Catch Basins

Yes N/E, N/W, S/E (median), S/W (median)

No

* Identify location of catch basins as N/E, N/W, S/E etc. using the same direction of north as shown on the drawings.

Drainage Tubes

- Void

Drains -

No No

North-East Catch Basin  

79 of 265

Page 80: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

  

 

 

 

 

 

 

8/   Survey Equipment and Calibration Procedures 

80 of 265

Page 81: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

                                                                                                                                 

SURVEY EQUIPMENT AND CALIBRATION PROCEDURES  Component Type:  Asphalt‐Covered Bridge Deck                                    Site No: 817   1.   Delaminations: 

 Weight of Chain:       2.2          Kg/m   Other Equipment:             Hammer  2. Concrete Cover: Covermeter Make & Model:               Elcometer Protovale 331 Battery Check:  Reading at Start of Test:          OK     Reading at End of Test:     OK Concrete Cover Check: Location of Check:                   SS2 Actual Depth & Rebar Dia:                    ‐ 

Reading Before Test:   64 mm    Reading Each 30 min During Test:        64 mm 

Reading End of Test:     64 mm 

3. Corrosion Activity: 

Half Cell Make & Model:                MC MILLER Electrode RE ‐ 3A (3” Dia) 

Multimeter Make & Model:          Mastercraft Digital Multimeter 3 R93 

Length and Gauge of Lead Wires:   150 m of 18 gauge 

Deck Temp:                           Start of Test:       10°C                       End of Test:     10°C 

Ambient Temp:                    Start of Test:      10°C                        End of Test:      10°C 

Battery Check:               OK                                                                                                                                            Ground Check: Method of Connection:    Self‐tapping screw                                                                                       Ground Location: C1, C13, C21, C29        Check Location: C8, C15, C26, C38 

Measured Resistance: 2.2, 2.9, 2.6, 2.3           Ω       (A)))                                                                                                           , Measured resistance is the circuit resistance of deck, including the resistance of the leads 

Lead Resistance:             1.8      Ω    (B)                               Voltage Drop (mV’s):      0.1           

Net Resistance:    0.4, 1.1, 0.8, 0.5       Ω    (C)                Resistance Reversed:    0.4, 1.1, 0.8, 0.5 Ω                                           (C = A – B) 

Grid Point Potential Readings Check – See Table Below

Location Initial Reading Check Reading ¹ Check Reading – Latex

Concrete Overlay ²

A1/I1/J1/R1 -0.318/-0.322/-0.325/-0.457 -0.317/-0.323/-0.327/-0.455 -

A2/I2/J2/R2 -0.268/-0.237/-0.282/-0.454 -0.267/-0.235/-0.284/-0.453 -

A3/I3/J3/R3 -0.264/-0.255/-0.220/-0.461 -0.265/-0.256/-0.222/-0.462 -

A4/I4/J4/R4 -0.152/-0.275/-0.245/-0.452 -0.153/-0.274/-0.244/-0.450 -

A5/I5/J5/R5 -0.134/-0.344/-0.210/-0.428 -0.135/-0.345/-0.211/-0.427 -

1 Check at least five readings at beginning of test and each change in ground 2 On decks with latex modified concrete overlay, check at least five locations by drilling holes through the latex concrete overlay into the original

concrete substrate

81 of 265

Page 82: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                   

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

  

 

 

 

 

 

 

9/   Core Photographs and Sketches 

82 of 265

Page 83: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C1

100mm

75m

mA

SPH

ALT

85m

mC

ON

CR

ETE

W/P Membrane (7 - 9mm)

Rebar imprint @ 80mm(Longitudinal)

83 of 265

Page 84: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C2

100mm

W/P Membrane (7 - 9mm)

60m

mA

SPH

ALT

160m

mC

ON

CR

ETE

84 of 265

Page 85: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C3

  

100mm

W/P Membrane (7 - 9mm)

70m

mA

SPH

ALT

170m

mC

ON

CR

ETE

85 of 265

Page 86: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C4

  

100mm

70m

mA

SPH

ALT

140m

mC

ON

CR

ETE

W/P Membrane (7 - 9mm)

86 of 265

Page 87: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C5

100mm

W/P Membrane (7 - 9mm)

70m

mA

SPH

ALT

145m

mC

ON

CR

ETE

Asphalt core damagedupon removal

87 of 265

Page 88: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C6

100mm

W/P Membrane (7 - 9mm)

80m

mA

SPH

ALT

150m

mC

ON

CR

ETE

88 of 265

Page 89: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C7

100mm

80m

mA

SPH

ALT

150m

mC

ON

CR

ETE

W/P Membrane (7 - 9mm)

89 of 265

Page 90: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C8

100mm

W/P Membrane (7 - 9mm)

45m

mA

SPH

ALT

165m

mC

ON

CR

ETE

15M-Rebar @ 70mm(Longitudinal)

90 of 265

Page 91: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C9

100mm

W/P Membrane (7 - 9mm)

65m

mA

SPH

ALT

180m

mC

ON

CR

ETE

91 of 265

Page 92: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C10

100mm

40m

mA

SPH

ALT

205m

mC

ON

CR

ETE

W/P Membrane (7 - 9mm)

92 of 265

Page 93: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C11

100mm

W/P Membrane (7 - 9mm)

55m

mA

SPH

ALT

95m

mC

ON

CR

ETE 15M-Rebar @ 60mm

(Longitudinal)

PTD imprint @ 80mm

93 of 265

Page 94: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C12

100mm

40m

mA

SPH

ALT

85m

mC

ON

CR

ETE

Rebar imprint @ 80mm(Longitudinal)

94 of 265

Page 95: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C13

100mm

50m

mA

SPH

ALT

70m

mC

ON

CR

ETE

W/P Membrane (7 - 9mm)

Rebar imprint @ 65mm(Transverse)

95 of 265

Page 96: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C14

100mm

W/P Membrane (7 - 9mm)

60m

mA

SPH

ALT

145m

mC

ON

CR

ETE

PTD imprint @ 130mm

96 of 265

Page 97: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C15

100mm

W/P Membrane (7 - 9mm)

70m

mA

SPH

ALT

140m

mC

ON

CR

ETE

15M-Rebar @ 60mm(Transverse)

97 of 265

Page 98: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C16

100mm

110m

mA

SPH

ALT

95m

mC

ON

CR

ETE

W/P Membrane (7 - 9mm)

98 of 265

Page 99: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C17

100mm

W/P Membrane (7 - 9mm)

75m

mA

SPH

ALT

115m

mC

ON

CR

ETE

99 of 265

Page 100: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C18

100mm

W/P Membrane (7 - 9mm)

55m

mA

SPH

ALT

180m

mC

ON

CR

ETE

100 of 265

Page 101: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C19

100mm

45m

mA

SPH

ALT

115m

mC

ON

CR

ETE

W/P Membrane (7 - 9mm)

PTD imprint @ 100mm

101 of 265

Page 102: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C20

100mm

W/P Membrane (7 - 9mm)

75m

mA

SPH

ALT

115m

mC

ON

CR

ETE

102 of 265

Page 103: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C21

100mm

W/P Membrane (7 - 9mm)

60m

mA

SPH

ALT

85m

mC

ON

CR

ETE

Rebar imprint @ 75mm(Transverse)

103 of 265

Page 104: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C22

100mm

55m

mA

SPH

ALT

130m

mC

ON

CR

ETE

W/P Membrane (7 - 9mm)

PTD imprint @ 120mm

104 of 265

Page 105: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C23

100mm

W/P Membrane (7 - 9mm)

50m

mA

SPH

ALT

130m

mC

ON

CR

ETE

15M-Rebar @ 50mm(Transverse)

105 of 265

Page 106: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C24

100mm

W/P Membrane (7 - 9mm)

70m

mA

SPH

ALT

155m

mC

ON

CR

ETE

15M-Rebar @ 40mm(Transverse)

106 of 265

Page 107: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C25

100mm

45m

mA

SPH

ALT

150m

mC

ON

CR

ETE

W/P Membrane (4 - 6mm)

15M-Rebar @ 70mm(Transverse)

107 of 265

Page 108: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C26

100mm

W/P Membrane (4 - 6mm)

80m

mA

SPH

ALT

145m

mC

ON

CR

ETE 15M-Rebar @ 80mm

(Longitudinal)

108 of 265

Page 109: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C27

100mm

W/P Membrane (4 - 6mm)

50m

mA

SPH

ALT

65m

mC

ON

CR

ETE

109 of 265

Page 110: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C28

100mm

85m

mA

SPH

ALT

135m

mC

ON

CR

ETE

W/P Membrane (4 - 6mm)

110 of 265

Page 111: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C29

100mm

W/P Membrane (4 - 6mm)

65m

mA

SPH

ALT

80m

mC

ON

CR

ETE

Rebar imprint @ 65mm(Transverse)

111 of 265

Page 112: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C30

100mm

W/P Membrane (4 - 6mm)

80m

mA

SPH

ALT

120m

mC

ON

CR

ETE

112 of 265

Page 113: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C31

100mm

70m

mA

SPH

ALT

80m

mC

ON

CR

ETE

W/P Membrane (4 - 6mm) 15M-Rebar @ 30mm(Longitudinal)

113 of 265

Page 114: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C32

100mm

W/P Membrane (4 - 6mm)

70m

mA

SPH

ALT

130m

mC

ON

CR

ETE

Rebar imprint @ 120mm(Transverse)

114 of 265

Page 115: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C33

100mm

W/P Membrane (4 - 6mm)

75m

mA

SPH

ALT

115m

mC

ON

CR

ETE

115 of 265

Page 116: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C34

100mm

90m

mA

SPH

ALT

125m

mC

ON

CR

ETE

W/P Membrane (4 - 6mm)

116 of 265

Page 117: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C35

100mm

W/P Membrane (4 - 6mm)

65m

mA

SPH

ALT

155m

mC

ON

CR

ETE

117 of 265

Page 118: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C36

100mm

W/P Membrane (4 - 6mm)

65m

mA

SPH

ALT

155m

mC

ON

CR

ETE

15M-Rebar @ 40mm(Transverse)

15M-Rebar @ 95mm(Longitudinal)

Vertical Crack

Core damaged upon removal

118 of 265

Page 119: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C37

100mm

W/P Membrane (4 - 6mm)

80m

mA

SPH

ALT

335m

mC

ON

CR

ETE

119 of 265

Page 120: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C38

W/P Membrane (4 - 6mm)

75m

mA

SPH

ALT

100m

mC

ON

CR

ETE

100mm

Rebar imprint @ 90mm(Transverse)

120 of 265

Page 121: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

Bridge 817 Neilson Road over CPR, Toronto, Ontario    

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection 

CORE C39

100mm

W/P Membrane (4 - 6mm)

55m

mA

SPH

ALT

95m

mC

ON

CR

ETE

 

121 of 265

Page 122: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

  

 200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8                                         Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com    [email protected]                   

BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection  

  

 

 

 

 

 

 

          10/   Core Logs 

122 of 265

Page 123: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Page 1 of 13 Site: #817

Total Corrected Total Corrected Total Corrected 0-10 mm 0.039 0.02920-30 mm 0.038 0.02840-50 mm 0.038 0.02860-70 mm 0.037 0.02780-90 mm 0.034 0.024

100-110 mm 0.027 0.017AIR VOIDS

TEST LABORATORY

Waterproofing (W/P) Type

Condition of W/P (1)

W/P Thickness, mmBond of Asphalt or W/P to Concrete

Chloride Content % Chloride by Weight of Concrete

BCCBARE

Thickness of Asphalt @ Nearest Grid Point

Defects in Concrete (2)

Thickness of Concrete, mmFull Depth (yes/no)Condition of Asphalt (1)

C1Core No.Location (between gridlines)Diameter, mmThickness of Asphalt, mm

Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm

G7 to 9 mm

G-

Condition of Rebar (3)

Corrosion PotentialCompressive Strength, MPa

Rebar imprint @ 80mm (Longitudinal).

REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects

1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas

100.070.0

G

NoF to G

-

F to GNo

GG

C3

75.075.085.0

60.060.0160.0

100.0

C2

100.0

Hot rubberized asphalt with

protection board

7 to 9 mm 7 to 9 mm

F to GNo

G--

G

CORE LOG ASPHALT COVERED BRIDGE DECKS

-

68.9

70.0

‘F’ and ‘10’‘D’ and ‘6’‘A’ and ‘1’

-0.143-0.318 -0.111

Hot rubberized asphalt with

protection board

Hot rubberized asphalt with

protection board

170.0

123 of 265

Page 124: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Page 2 of 13 Site: #817

Total Corrected Total Corrected Total Corrected 0-10 mm 0.033 0.02320-30 mm 0.026 0.01640-50 mm 0.024 0.01460-70 mm 0.023 0.01380-90 mm 0.021 0.011

AIR VOIDS 6.1

33.40.090

TEST LABORATORY BCC BCC

REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects

Asphalt core damaged upon removal.

Corrosion PotentialCompressive Strength, MPa

Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm

Chloride Content % Chloride by Weight of Concrete

-0.166-0.131-0.178

- -Condition of Rebar (3) - - -Defects in Concrete (2) -

G G

Location (between gridlines)100.0

Core No. C4

Diameter, mm‘E’ and ‘20’

F to G F to GNo No

145.0

100.070.070.0

100.080.0

C6

CORE LOG ASPHALT COVERED BRIDGE DECKS

70.0Thickness of Asphalt, mm

Hot rubberized asphalt with

protection board

Hot rubberized asphalt with

protection board

Hot rubberized asphalt with

protection board

Condition of W/P (1)

150.0

1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas

Waterproofing (W/P) Type

7 to 9 mm 7 to 9 mmBond of Asphalt or W/P to Concrete GW/P Thickness, mm 7 to 9 mm

70.0

Full Depth (yes/no) NoCondition of Asphalt (1) F to G

Thickness of Concrete, mm 140.0Thickness of Asphalt @ Nearest Grid Point

‘C’ and ‘12’ ‘A’ and ‘17’

G G

80.0

G

C5

124 of 265

Page 125: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Page 3 of 13 Site: #817

Total Corrected Total Corrected Total Corrected 0-10 mm20-30 mm40-50 mm60-70 mm80-90 mm

AIR VOIDS

TEST LABORATORY

Chloride Content % Chloride by Weight of Concrete

Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm

REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects

15M-Rebar @ 70mm (Longitudinal).

Condition of Rebar (3) - G -Corrosion PotentialCompressive Strength, MPa

-0.150

Bond of Asphalt or W/P to Concrete G G GDefects in Concrete (2) - - -

Condition of W/P (1) G G GW/P Thickness, mm 7 to 9 mm 7 to 9 mm 7 to 9 mm

Condition of Asphalt (1) F to G G G

Waterproofing (W/P) Type

Hot rubberized asphalt with

protection board

Hot rubberized asphalt with

protection board

Hot rubberized asphalt with

protection board

Thickness of Concrete, mm 155.0 165.0 180.0Full Depth (yes/no) No No No

Thickness of Asphalt, mm 80.0 45.0 65.0Thickness of Asphalt @ Nearest Grid Point 80.0 45.0 65.0

CORE LOG ASPHALT COVERED BRIDGE DECKS

1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas

Core No. C7 C8 C9Location (between gridlines)Diameter, mm 100.0 100.0 100.0

‘E’ and ‘29’ ‘B’ and ‘33’‘B’ and ‘24’

-0.134 -0.127

125 of 265

Page 126: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Page 4 of 13 Site: #817

Total Corrected Total Corrected Total Corrected 0-10 mm 0.044 0.03420-30 mm 0.039 0.02940-50 mm 0.038 0.02860-70 mm 0.031 0.02180-90 mm 0.027 0.017

AIR VOIDS 4.8

37.40.117

TEST LABORATORY

Chloride Content % Chloride by Weight of Concrete

Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm

BCC BCC

REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects

Condition of Rebar (3) - G GCorrosion PotentialCompressive Strength, MPa

Bond of Asphalt or W/P to Concrete G GDefects in Concrete (2) - - -

Condition of W/P (1) G GW/P Thickness, mm 7 to 9 mm 7 to 9 mm

Condition of Asphalt (1) F to G F to G G

Waterproofing (W/P) Type

Hot rubberized asphalt with

protection board

Hot rubberized asphalt with

protection boardN/A

Thickness of Concrete, mm 205.0 95.0 85.0Full Depth (yes/no) No No No

Thickness of Asphalt, mm 40.0 55.0 40.0Thickness of Asphalt @ Nearest Grid Point 40.0 55.0

Core No. C10 C11 C12Location (between gridlines)Diameter, mm 100.0 100.0 100.0

‘E’ and ‘41’

CORE LOG ASPHALT COVERED BRIDGE DECKS

East Approach

Rebar imprint @ 80mm (Longitudinal).

1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas

15M-Rebar @ 60mm (Longitudinal).PT cable imprint @ 80mm.

‘A’ and ‘45’

-0.148 -0.307

126 of 265

Page 127: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Page 5 of 13 Site: #817

Total Corrected Total Corrected Total Corrected 0-10 mm20-30 mm40-50 mm60-70 mm80-90 mm

AIR VOIDS

TEST LABORATORY

Chloride Content % Chloride by Weight of Concrete

Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm

-0.327 -0.163

REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects

Rebar imprint @ 65mm (Transverse).

PT cable imprint @ 130mm.

15M-Rebar @ 60mm (Transverse).

Condition of Rebar (3) G - GCorrosion PotentialCompressive Strength, MPa

Bond of Asphalt or W/P to Concrete G G GDefects in Concrete (2) - - -

Condition of W/P (1) G G GW/P Thickness, mm 7 to 9 mm 7 to 9 mm 7 to 9 mm

Condition of Asphalt (1) F to G F to G F to G

Waterproofing (W/P) Type

Hot rubberized asphalt with

protection board

Hot rubberized asphalt with

protection board

Hot rubberized asphalt with

protection board

70.0Thickness of Concrete, mm 70.0 145.0 140.0Full Depth (yes/no) No No No

60.0

100.0Thickness of Asphalt, mm 50.0 60.0 70.0

‘G’ and ‘9’‘H’ and ‘1’Core No. C13 C14 C15

CORE LOG ASPHALT COVERED BRIDGE DECKS

Location (between gridlines)Diameter, mm

1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas

Thickness of Asphalt @ Nearest Grid Point 50.0

‘G’ and ‘15’

-0.165

100.0 100.0

127 of 265

Page 128: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Page 6 of 13 Site: #817

Total Corrected Total Corrected Total Corrected 0-10 mm 0.028 0.01820-30 mm 0.027 0.01740-50 mm 0.021 0.01160-70 mm 0.021 0.01180-90 mm 0.010 0.000

AIR VOIDS

TEST LABORATORY

Chloride Content % Chloride by Weight of Concrete

Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm

BCC

REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects

Condition of Rebar (3) - - -Corrosion PotentialCompressive Strength, MPa

-0.166

Bond of Asphalt or W/P to Concrete G G GDefects in Concrete (2) - - -

Condition of W/P (1) G G GW/P Thickness, mm 7 to 9 mm 7 to 9 mm 7 to 9 mm

Condition of Asphalt (1) F to G F to G F to G

Waterproofing (W/P) Type

Hot rubberized asphalt with

protection board

Hot rubberized asphalt with

protection board

Hot rubberized asphalt with

protection board

Thickness of Concrete, mm 95.0 115.0 180.0Full Depth (yes/no) No No No

Thickness of Asphalt, mm 110.0 75.0 55.0

‘I’ and ‘23’

Thickness of Asphalt @ Nearest Grid Point 110.0 75.0 55.0

Core No. C16 C17 C18Location (between gridlines)Diameter, mm 100.0 100.0 100.0

‘F’ and ‘26’

CORE LOG ASPHALT COVERED BRIDGE DECKS

1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas

‘G’ and ‘35’

-0.135-0.233

128 of 265

Page 129: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Page 7 of 13 Site: #817

Total Corrected Total Corrected Total Corrected 0-10 mm20-30 mm40-50 mm60-70 mm80-90 mm

AIR VOIDS

TEST LABORATORY

-0.288Compressive Strength, MPa

Condition of Rebar (3)

Bond of Asphalt or W/P to Concrete

REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects

PT cable imprint @ 100mm.

Rebar imprint @ 75mm (Transverse).

--

Waterproofing (W/P) Type

G GW/P Thickness, mm

G7 to 9 mm

Condition of W/P (1)

Hot rubberized asphalt with

protection board

G

Condition of Asphalt (1) F to G F to G

Defects in Concrete (2)

Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm

Chloride Content % Chloride by Weight of Concrete

-Corrosion Potential

G-

Thickness of Concrete, mm 115.0 115.0 85.0Full Depth (yes/no) No No No

Thickness of Asphalt, mm 45.0 75.0 60.0Thickness of Asphalt @ Nearest Grid Point 45.0 75.0 60.0

Core No. C19 C20 C21Location (between gridlines)Diameter, mm 100.0 100.0 100.0

‘K’ and ‘39’

1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas

CORE LOG ASPHALT COVERED BRIDGE DECKS

-

‘J’ and ‘44’

-0.314 -0.309

F to G

G G

Hot rubberized asphalt with

protection board

Hot rubberized asphalt with

protection board

7 to 9 mm 7 to 9 mm

‘I’ and ‘44’

129 of 265

Page 130: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Page 8 of 13 Site: #817

Total Corrected Total Corrected Total Corrected 0-10 mm20-30 mm40-50 mm60-70 mm80-90 mm

AIR VOIDS 4.3

36.60.119

TEST LABORATORY

C23 C24Location (between gridlines) ‘L’ and ‘29’ ‘K’ and ‘22’ ‘J’ and ‘14’

CORE LOG ASPHALT COVERED BRIDGE DECKS

Core No. C22

Thickness of Asphalt, mm 55.0 50.0 70.0Diameter, mm 100.0 100.0 100.0

Thickness of Concrete, mm 130.0 130.0 155.0Thickness of Asphalt @ Nearest Grid Point 55.0 50.0 70.0

Condition of Asphalt (1) F to G F to G F to GFull Depth (yes/no) No No No

Condition of W/P (1) G G G

Waterproofing (W/P) Type

Hot rubberized asphalt with

protection board

Hot rubberized asphalt with

protection board

Hot rubberized asphalt with

protection board

Bond of Asphalt or W/P to Concrete G G GW/P Thickness, mm 7 to 9 mm 7 to 9 mm 7 to 9 mm

Condition of Rebar (3) - G GDefects in Concrete (2) - - -

Compressive Strength, MPaCorrosion Potential -0.184 -0.250 -0.240

REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects

PT cable imprint @ 120mm.

15M-Rebar @ 50mm (Transverse).

15M-Rebar @ 40mm (Transverse).

Chloride Content % Chloride by Weight of Concrete

Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm

BCC

1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas

130 of 265

Page 131: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Page 9 of 13 Site: #817

Total Corrected Total Corrected Total Corrected 0-10 mm20-30 mm40-50 mm60-70 mm80-90 mm

AIR VOIDS

TEST LABORATORY

Location (between gridlines) ‘L’ and ‘6’ ‘J’ and ‘1’ West Approach

CORE LOG ASPHALT COVERED BRIDGE DECKS

Core No. C25 C26 C27

Thickness of Asphalt, mm 45.0 80.0 50.0Diameter, mm 100.0 100.0 100.0

Thickness of Concrete, mm 150.0 145.0 65.0Thickness of Asphalt @ Nearest Grid Point 45.0 80.0 50.0

Condition of Asphalt (1) F F FFull Depth (yes/no) No No No

Condition of W/P (1) G G G

Waterproofing (W/P) Type

Hot rubberized asphalt with

protection board

Hot rubberized asphalt with

protection board

Hot rubberized asphalt with

protection board

Bond of Asphalt or W/P to Concrete G G GW/P Thickness, mm 4 to 6 mm 4 to 6 mm 4 to 6 mm

Condition of Rebar (3) G G -Defects in Concrete (2) - - -

Compressive Strength, MPaCorrosion Potential -0.190 -0.325

REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects

15M-Rebar @ 70mm (Transverse).

15M-Rebar @ 80mm (Longitudinal).

Chloride Content % Chloride by Weight of Concrete

Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm

1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas

131 of 265

Page 132: Neilson Road Bridge Detailed Deck Condition Survey ... · Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition survey of the Neilson

Page 10 of 13 Site: #817

Total Corrected Total Corrected Total Corrected 0-10 mm 0.030 0.02020-30 mm 0.025 0.01540-50 mm 0.023 0.01360-70 mm 0.022 0.01280-90 mm 0.020 0.010

AIR VOIDS

TEST LABORATORY

Location (between gridlines) ‘Q’ and ‘1’ ‘P’ and ‘6’ ‘R’ and ‘10’

CORE LOG ASPHALT COVERED BRIDGE DECKS

Core No. C28 C29 C30

Thickness of Asphalt, mm 85.0 65.0 80.0Diameter, mm 100.0 100.0 100.0

Thickness of Concrete, mm 135.0 80.0 120.0Thickness of Asphalt @ Nearest Grid Point 85.0 65.0 80.0

Condition of Asphalt (1) F F FFull Depth (yes/no) No No No

Condition of W/P (1) G G G

Waterproofing (W/P) Type

Hot rubberized asphalt with

protection board

Hot rubberized asphalt with

protection board

Hot rubberized asphalt with

protection board

Bond of Asphalt or W/P to Concrete G G GW/P Thickness, mm 4 to 6 mm 4 to 6 mm 4 to 6 mm

Condition of Rebar (3) - G -Defects in Concrete (2) - - -

Compressive Strength, MPaCorrosion Potential -0.455 -0.254 -0.458

REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects

Rebar imprint @ 65mm (Tranverse).

Chloride Content % Chloride by Weight of Concrete

Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm

BCC

1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas

132 of 265