neilson road bridge detailed deck condition survey ... · bridge check canada limited was retained...
TRANSCRIPT
Neilson Road Bridge
Bridge No. 817
Detailed Deck Condition
Survey & Evaluation Report
Prepared for:
City of Toronto Engineering & Construction Services
October 2015
1 of 265
Neilson Road Bridge - Enhanced OSIM & Evaluation Report
MMM Group Limited | October 2015 | 3213038-304 i
TABLE OF CONTENTS
APPENDICES ................................................................................................. II
1.0 INTRODUCTION ................................................................................ 1
2.0 STRUCTURE ...................................................................................... 1
3.0 INSPECTION METHODOLOGY ........................................................ 2
4.0 SUMMARY OF CONDITION SURVEY .............................................. 3
4.1 Asphalt Wearing Surface ....................................................................................................... 3
4.2 Waterproofing ......................................................................................................................... 3
4.3 Concrete Deck ......................................................................................................................... 4
4.4 Deck Soffit ............................................................................................................................... 5
4.5 Approaches ............................................................................................................................. 5
4.6 Deck Drainage ......................................................................................................................... 6
4.7 Joints ....................................................................................................................................... 6
4.8 Abutments and Bearings ....................................................................................................... 6
4.9 Ballast Wall .............................................................................................................................. 6
4.10 Bearing Seats .......................................................................................................................... 7
4.11 Wingwalls ................................................................................................................................ 7
4.12 Retaining Walls ....................................................................................................................... 7
4.13 Piers and Bearings ................................................................................................................. 7
4.14 Slopes ...................................................................................................................................... 7
5.0 STRUCTURE EVALUATION ............................................................. 8
2 of 265
Neilson Road Bridge - Enhanced OSIM & Evaluation Report
MMM Group Limited | October 2015 | 3213038-304 ii
APPENDICES
Appendix A − Condition Survey Report
Appendix B − Structural Evaluation Report
3 of 265
Neilson Road Bridge - Enhanced OSIM & Evaluation Report
MMM Group Limited | October 2015 | 3213038-304 1
1.0 INTRODUCTION
MMM Group Limited has been retained by The City of Toronto to provide a detailed deck condition survey
and structural evaluation of the Neilson Road Bridge. As a part of the aforementioned work, the structure
was to be visually inspected for its current level of deterioration, forming the basis for the structural
evaluation. The detailed deck condition survey of the Neilson Road structure was completed by Bridge
Check Canada Limited as sub consultant to MMM Group Limited.
This report summarizes the key findings of the detailed condition survey and structural evaluation. A
complete deck condition survey and inspection report can be found in Appendix A. The structural evaluation
report can be found in Appendix B.
2.0 STRUCTURE
Originally constructed in 1979, the Neilson Road Bridge is a four span post-tensioned structure which
consists of two independent concrete decks. The Neilson Road Bridge has single span lengths of 14.6m,
18.9m, 18.9m and 14.6m with a total overall width of 28.4m. The structure is orientated in the east-west
direction and carries traffic in each direction over two CPR railway tracks.
The substructure consists of two sets of abutments and three sets of piers; According to the existing
structure drawings, the abutments and piers are supported on spread footings. The original construction
drawings do not indicate that the footings are supported on steel piles.
The bridge structure accommodates four lanes of traffic along Neilson Road over the CPR railway with
barriers running along the north andsouth edges of each bridge deck. Transverse expansion joints are
present at both ends of the bridge deck, directly above the abutments; the deck is continuous over its piers.
According to the available records, the structure has not undergone any rehabilitation work.
A Key Plan showing the structure location is provided in Figure 1.
4 of 265
Neilson Road Bridge - Enhanced OSIM & Evaluation Report
MMM Group Limited | October 2015 | 3213038-304 2
Figure 1 – Key Plan
3.0 INSPECTION METHODOLOGY
Bridge Check Canada Limited was retained by MMM Group Limited to carry out a detailed bridge condition
survey of the Neilson Road Bridge. The field investigation was completed over three days between June 3
and 5, 2015.
The Neilson Road Bridge condition survey involved the observation and inspection of surface defects and
delaminated concrete, a corrosion potential survey and visual observation of sawn areas on the deck, as
well as the extraction of concrete cores from various locations in the structure. All condition survey
procedures used were those defined in the MTO Structure Rehabilitation Manual.
Standard practise included the following key methodologies:
• Delaminated concrete was detected by striking all vertical and overhead concrete surfaces with a
hammer and noting the sound emitted.
Bridge Site
5 of 265
Neilson Road Bridge - Enhanced OSIM & Evaluation Report
MMM Group Limited | October 2015 | 3213038-304 3
• The locations of all concrete patches, spalled and or delaminated concrete, exposed reinforcement,
damp areas, scaled concrete, cracked concrete and other observed defects were recorded. A
standard 1.5m square grid was used for all deck-top and soffit observations.
• The corrosion potential survey was conducted for the asphalt covered bridge deck. All survey
procedures were performed in accordance with the requirements of STM C876 and the MTO
Structure Rehabilitation Manual.
• All sawn areas of the bridge deck were carefully examined for deterioration and were hammer
sounded. Photos of all sawn samples are on file for reference. Thirty (30) sawn samples were
taken at various locations on the bridge deck
• Thirty-seven (37) concrete cores were extracted from the bridge deck and one (1) from the east and
west approach, respectively.
4.0 SUMMARY OF CONDITION SURVEY
4.1 Asphalt Wearing Surface
The total width of the asphalt covered bridge deck between abutments is 22.56 m, with a total surveyed
area of 1,529.00 m2. The condition of the asphalt wearing surface on the bridge deck was identified through
visual field observations and review of cores and sawn asphalt samples. The asphalt wearing surface on
the concrete deck is generally in fair condition with unsealed transverse (82.0 m), longitudinal (65.0 m) and
random (584.0 m) cracking, sealed transverse (10.0 m), longitudinal (6.0 m) and random (79.0 m) cracking.
The measured asphalt thickness varied from 40 mm to 110 mm with an average thickness of 69 mm.
Three (3) samples of the asphalt wearing surface were tested for asbestos contaminations according to
EPA 600/R‐93/116 test method using Polarized Light Microscope. The results indicated 1.2‐1.3% asbestos
content in the samples.
4.2 Waterproofing
Evidence of a hot rubberized asphalt waterproofing system with protection board was detected over the
concrete deck, ranging in thickness from 7 to 9 mm with an average thickness of 8 mm. The condition of the
6 of 265
Neilson Road Bridge - Enhanced OSIM & Evaluation Report
MMM Group Limited | October 2015 | 3213038-304 4
waterproofing membrane encountered in the test locations was generally good. The bond of waterproofing
to the concrete was generally good.
4.3 Concrete Deck
The concrete deck consists of a four span cast‐in‐place concrete post tension thick slab, supported by piers
and abutments. The condition of the concrete deck was observed at thirty-seven (37) core locations and
thirty (30) sawn asphalt sample locations. The inside of the core holes and the exposed concrete surface at
the sawn asphalt sample locations were examined carefully for cracks and other defects. A review of the
concrete cores revealed cracking in one (1) core. Visual review of the exposed concrete surface at the
sawn asphalt samples did not reveal any defects.
The concrete cover to the upper rebar layer measured in the cores and sawn asphalt samples was found to
range from 30 to 109 mm with an average cover of 68 mm. The field cores identified 15M rebar imprint in
the deck. The reinforcement steel was found to be in good condition with no evidence of corrosion.
Corrosion potential values obtained from the half‐cell test carried out on the asphalt covered deck ranged
from –0.102 V to –0.476 V with an average value of –0.218 V. The half‐cell survey indicated that 56.0% of
the deck area likely had no corrosion activity, with corrosion potential values between 0.000 V and ‐0.199 V.
The half‐cell survey indicated uncertain low corrosion activity for 34.0% of the deck area, with values
ranging from ‐0.200 V to ‐0.349 V. Probable active corrosion was detected for 10.0% of the deck area with
corrosion potential values more negative than ‐0.350 V. Active corrosion potential was found adjacent to the
north sidewalk.
Two (2) cores were tested for compressive strength of the hardened concrete in accordance with CSA
A23.2‐09‐14C. The compressive strength of the hardened concrete for these cores ranged from 38.7 MPa
to 68.9 MPa, with an average compressive strength of 53.8 MPa. This value is significantly higher than the
34.5 MPa (5000 psi) minimum specified strength on the original GA drawing.
The chloride ion content was determined for eight (8) cores using MTO LS‐417 “Method of Test for
Determination of Total Chloride Ion in Concrete – Acid Soluble”. These core samples were located at areas
prone to salt exposure (e.g. high corrosion potential areas, along construction joints, low points of the deck,
asphalt cracks). In addition, samples from other moderately exposed areas were also taken.
7 of 265
Neilson Road Bridge - Enhanced OSIM & Evaluation Report
MMM Group Limited | October 2015 | 3213038-304 5
The chloride threshold value necessary to depassivate embedded steel and to allow the onset of corrosion
(in the presence of oxygen and moisture) is generally taken as 0.025% by mass of concrete. The corrected
chloride content, at the rebar level, was above the chloride threshold level of 0.025% in one (1) Core.
Overall, the results indicate that chloride contamination has extended to the upper rebar level in limited
areas of the deck. Based on the concrete removal policy outlined in the Structure Rehabilitation Manual, the
following comments can be made:
• Since 10% of the deck area is more negative than ‐0.350 V, the average chloride content at the
reinforcing level is calculated using the cores with corrosion potential values more negative than ‐
0.350 V. Therefore, the average adjusted chloride content at the reinforcing steel level is 0.011%.
• Based on the above, since the average adjusted chloride content at the top reinforcement level is
less than 0.05% by mass of concrete, concrete removal is recommended to include delaminated
areas only.
4.4 Deck Soffit
The bridge deck soffit, with a total surveyed area of 1,951.60 m2, is in fair condition with clean/stained
medium width cracking (100.0 m), delamination (75.90 m2), spalls (20.90 m
2), honeycombing (3.00 m
2), and
wet areas (47.40 m2). Deteriorations were predominantly observed within the westbound lanes and along
the centreline of the deck. Exposed corroded reinforcement was observed in the spalled areas. A concrete
cover survey was conducted on the deck soffit except for the area between Piers 1 and 2 (above the CPR
tracks). The concrete cover was found to range from 30 to 64 mm with an average cover of 44 mm.
4.5 Approaches
The asphalt wearing surface on the bridge approaches is generally in good condition with unsealed cracks.
Observation of a core hole located at the east approach confirmed the presence of a concrete approach
slab with 85 mm thickness. The measured asphalt thickness was 40 mm. Observation of a core hole
located at the west approach confirmed the presence of a concrete approach slab with 65 mm thickness.
The measured asphalt thickness was 50 mm.
8 of 265
Neilson Road Bridge - Enhanced OSIM & Evaluation Report
MMM Group Limited | October 2015 | 3213038-304 6
4.6 Deck Drainage
Deck drains were not observed on this structure. Catch basins were observed at northeast and northwest
quadrants and in the median outside structure limits.
4.7 Joints
The expansion joints (strip seal joints) were generally in fair to poor condition with light rusting and missing
sections of the steel armoring angles. The seals were found to be damaged and covered with debris. Gap
dimensions varied from 20 to 40 mm. Leaking of the expansion joints was noted from dampness of the
deck soffit and abutments underneath. Cracking, scaling, and spalling were noted on the concrete end
dams. The east expansion joint was noted as being uneven at the north sidewalk.
4.8 Abutments and Bearings
The exposed surfaces of the abutments were inspected and sounded to check for delamination. The total
surveyed area for the east and west abutments were 126.57 and 41.50 m2, respectively. The abutments are
in fair to good condition. The field investigation of the east abutment revealed clean/stained medium width
cracking (35.0 m), pattern cracks (0.50 m2) and delamination (1.20 m
2). The field investigation of the west
abutment revealed clean medium width cracking (6.0 m), delamination (1.90 m2), and medium scaling (0.45
m2). The east abutment elastomeric bearings are in fair to good condition with cracks and bulging. The west
abutment laminated elastomeric bearings are in fair to good condition with cracks and bulging.
4.9 Ballast Wall
The east ballast wall is in fair to good condition whereas the west ballast wall is in fair condition. The east
abutment ballast wall had a total surveyed area of 7.00 m2 with spalls (0.15 m
2). The west abutment ballast
wall had a total surveyed area of 7.00 m2 with clean medium width cracks (2.0 m), delamination (0.30 m
2),
spalls (0.30 m2), and light scaling (0.10 m
2).
9 of 265
Neilson Road Bridge - Enhanced OSIM & Evaluation Report
MMM Group Limited | October 2015 | 3213038-304 7
4.10 Bearing Seats
The bearing seats were generally in good condition. The east abutment bearing seat had a total surveyed
area of 16.50 m2, with no visible defects. The west abutment bearing seat had a total surveyed area of
16.50 m2 with no visible defects.
4.11 Wingwalls
The exposed areas of the wingwalls were inspected visually and hammer sounded. The wingwalls were in
good condition and had a total surveyed area of 14.64 m2, with clean/stained medium width cracks (5.0 m),
light scaling (0.15 m2), and wet areas (1.40 m
2). Wet areas were observed on the southwest wingwall.
4.12 Retaining Walls
The exposed areas of the retaining walls were inspected visually and hammer sounded. The retaining walls
were in good condition and had a total surveyed area of 55.84 m2, with clean/stained medium width cracks
(21.0 m).
4.13 Piers and Bearings
The bridge piers are in good condition with total surveyed area of 221.60 m2. Inspection of the piers
revealed clean medium width cracks (4.0 m) and medium scaling (0.60 m2). Medium scaling was found on
Pier #3. The expansion Andre Rota bearings at Piers #1 and #3 were found to be in fair to good condition
with light corrosion and rust jacking. The Fixed Andre Rota bearings at Pier #2 were in good condition.
4.14 Slopes
The east slope was found to be in fair condition with soil erosion. The west slope paving was in fair to good
condition with cracks.
10 of 265
Neilson Road Bridge - Enhanced OSIM & Evaluation Report
MMM Group Limited | October 2015 | 3213038-304 8
5.0 STRUCTURE EVALUATION
A structural evaluation of the bridge was performed by MMM Group Limited in accordance with the 2006
Canadian Highway Bridge Design Code (CHBDC). The evaluation was based on the original construction
drawings supplied by The City of Toronto and took into consideration the condition of the structure at the
time of the evaluation.
Based on the original structural drawings the following material properties were used in the evaluation of the
structure:
Compressive strength of concrete - Deck (f’c) = 34.5 MPa
Yield strength of reinforcing steel (fy) =345 MPa
Yield Strength of stressing strand (fpu) = 1488 Mpa
According to the original structural drawings, the structure was originally designed for HS20-44 bridge
loading. The structure was analysed on SAP2000 using 2D frame elements, the live load model used was
CL-625-ON as specified in the CHBDC.
The evaluation indicated the following capacity to demand ratios (C/D) for the existing girders at their critical
locations:
TABLE 1 – C/D Ratios and Stresses for Existing Conditions
Westbound Structure
Location ULS
(Mr/Mf)
ULS
(Vr/Vf)
Stress - Top
SLS
(MPa)
Stress – Top
Allowable
(MPa)
Stress – Bot
SLS
(MPa)
Stress – Top
Allowable
(MPa)
Span 1 1.96 3.69 5.55 20.68 -0.08 -2.35
Pier 1 1.82 2.60 -0.38 -2.35 6.02 20.68
Span 2 1.82 - 6.12 20.68 -0.66 -2.35
Pier 2 1.90 2.66 0.21 20.68 5.40 20.68
Span 3 1.82 - 6.23 20.68 -0.78 -2.35
Pier 3 1.89 2.83 -0.06 -2.35 5.69 20.68
Span 4 1.92 3.36 5.56 20.68 -0.09 -2.35
11 of 265
12 of 265
AP
PE
ND
IX A
– C
on
ditio
n S
urv
ey R
ep
ort
13 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
DETAILED CONDITION SURVEY REPORT Site No. 817 Neilson Road over CPR
City of Toronto, Ontario
Prepared For: MMM Group Limited
Prepared by: Bridge Check Canada Ltd.
BCC Project No: BCC15006 Report Date: August 20, 2015
14 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
TABLE OF CONTENTS
1/ Structure Identification Sheet 2/ Key Plan 3/ Summary of Significant Findings 4/ Detailed Condition Survey Summary Sheets – Asphalt Covered Deck 5/ Detailed Condition Survey Summary Sheets – Exposed Concrete Components 6/ Detailed Condition Survey Summary Sheet – Expansion Joints 7/ Detailed Condition Survey Summary Sheet ‐ Drainage 8/ Survey Equipment and Calibration Procedures 9/ Core Photographs and Sketches 10/ Core Logs 11/ Sawn Asphalt Sample Photographs 12/ Sawn Asphalt Sample Logs 13/ Site Photographs 14/ Laboratory Test Results 15/ General Arrangement Drawing 16/ Drawings:
No. 1 – Surface Deterioration of Asphalt on Deck No. 2 –Asphalt Thickness of Deck No. 3 –Corrosion Potential of Deck No. 4 – Surface Deterioration of Soffit No. 5 – Concrete Cover of Soffit No. 6 – Surface Deterioration of Piers No. 7 – Surface Deterioration of Abutments, Winging Walls and Retaining Walls
15 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
1/ Structure Identification Sheet
16 of 265
17 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
2/ Key Plan
18 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
KEY PLAN
Site No. 817 Neilson Road over CPR
City of Toronto, Ontario
Site # 817
19 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
3/ Summary of Significant Findings
20 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
SUMMARY OF SIGNIFICANT FINDINGS Site ID # 817, Neilson Road Bridge over CPR, City of Toronto, Ontario
1.0 INTRODUCTION
Bridge Check Canada Ltd. was retained by MMM Group Ltd. to carry out detailed bridge condition survey under City of Toronto’s Work Assignment No. ECS‐BE‐C07‐15‐001. The assignment involved the investigation and reporting for a total of seven bridges within the City of Toronto. This report presents Bridge Check Canada’s findings, through the field investigations and laboratory testing, for Neilson Road Bridge over CPR (Site ID # 817). First time field investigations were carried out on June 3‐5, 2015. A Bridge Master was utilized to inspect and hammer sound the deck soffit and substructure components.
Site No. 817, constructed in 1979, is a four span cast‐in‐place concrete post tension thick slab, overlain with an asphalt wearing surface and carries two lanes of traffic per direction of Neilson Road. The bridge spans over CPR tracks. The slab thickness, shown on the original GA drawing, is 660 mm.
Total span length of the bridge is 67.06 m and the roadway width in each direction of Neilson Road is 11.28 m. The structure has an east‐west orientation. Outer limits of the structure have concrete parapet walls and concrete sidewalk. A concrete median separates southbound from northbound traffic. Photo P1 shows a view of the south elevation of Site No. 817. Photo P2 shows the north elevation.
South Elevation of Site No. 817, Neilson Road Bridge over CPR
Rehabilitation history of the bridge is not available.
2.0 METHODOLOGY
In general, the procedures followed to conduct the condition survey and delamination survey were those defined in Part 1 of the MTO Structure Rehabilitation Manual (2007). This assignment involved the observation and recording of surface defects, delamination detection, grid layouts (1.5 m x 1.5 m), concrete cores (100 mm diameter), corrosion potential survey, and physical testing of the concrete
21 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
cores. Inspection of the concrete sidewalks, parapet walls and median was not part of scope of this investigation.
The delaminations in the concrete were detected by striking the surface with a heavy hammer and noting the type of sound being emitted. It should be mentioned that, while this method is quite reliable, it may not detect delaminations at a depth greater than 100 mm. The hammer sounding method was used for all vertical and overhead surfaces inspected. The areas and locations of patches, spalls, delaminations, exposed reinforcement, honey‐combing, wet areas, scaling and other observed defects were recorded.
A corrosion potential survey was conducted for the asphalt covered bridge deck. The survey was performed in accordance with the requirements of ASTM C876 and the MTO Structure Rehabilitation Manual. A positive ground connection was made directly to the reinforcing steel, at the locations shown on the accompanying drawings.
Thirty nine (39) cores (37 cores in the asphalt covered bridge deck and two cores in the approaches) and 30 sawn asphalt samples were extracted from this structure, in compliance with the requirements for selecting cores and sawn asphalt samples from deteriorated and sound areas. The inside of the core holes were examined carefully for cracks and the condition of the concrete. The exposed surface of the concrete at the sawn asphalt samples was carefully examined for evidence of deterioration. All the test holes were reinstated to their original condition using MTO‐approved products.
Enclosed with this report are detailed condition survey summary sheets, survey equipment and calibration procedures, core photos/sketches, core logs, sawn asphalt sample photos, sawn asphalt sample logs, site photos, laboratory test results, and drawings.
3.0 BRIDGE STRUCTURE
3.1 Asphalt Wearing Surface
The total width of the asphalt covered bridge deck between abutments is 22.56 m, with a total surveyed area of 1,529.00 m2. The condition of the asphalt wearing surface on the bridge deck was identified through visual field observations and review of cores and sawn asphalt samples. Drawing 1 shows the location of cores and sawn asphalt samples. The general pavement surface condition is shown in Photos P3 to P6. The asphalt wearing surface on the concrete deck is generally in fair condition with unsealed transverse (82.0 m), longitudinal (65.0 m) and random (584.0 m) cracking, sealed transverse (10.0 m), longitudinal (6.0 m) and random (79.0 m) cracking. The total asphalt thickness, measured in the drilled holes and the cores and sawn asphalt sample locations, varied from 40 mm to 110 mm with an average thickness of 69 mm (refer to Drawing No. 2). Three samples of the asphalt wearing surface were tested for asbestos contaminations according to EPA 600/R‐93/116 test method using Polarized Light Microscope. The results indicated 1.2‐1.3% asbestos content in the samples. Refer to IATL International laboratory test results.
22 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
3.2 Waterproofing
Evidence of a hot rubberized asphalt waterproofing system with protection board was detected over the concrete deck, ranging in thickness from 7 to 9 mm with an average thickness of 8 mm. The condition of the waterproofing membrane encountered in the test locations was generally good. The bond of waterproofing to the concrete was generally good.
3.3 Concrete Deck
The concrete deck consists of a four span cast‐in‐place concrete post tension thick slab, supported by piers and abutments. The condition of the concrete deck was observed at 37 core locations and 30 sawn asphalt sample locations. The inside of the coreholes and the exposed concrete surface at the sawn asphalt sample locations were examined carefully for cracks and other defects. A review of the concrete cores revealed cracking in core C36. Visual review of the exposed concrete surface at the sawn asphalt samples did not reveal any defects. Refer to the core and sawn asphalt sample logs and photos.
The concrete cover to the upper rebar layer measured in the cores and sawn asphalt samples was found to range from 30 to 109 mm with an average cover of 68 mm. The field cores identified 15M rebar imprint in the deck. The reinforcement steel was found to be in good condition with no evidence of corrosion. Refer to the core logs and photos.
Corrosion potential values obtained from the half‐cell test carried out on the asphalt covered deck ranged from –0.102 V to –0.476 V with an average value of –0.218 V. The half‐cell survey indicated that 56.0% of the deck area likely had no corrosion activity, with corrosion potential values between 0.000 V and ‐0.199 V. The half‐cell survey indicated uncertain low corrosion activity for 34.0% (25.1%+8.9%) of the deck area, with values ranging from ‐0.200 V to ‐0.349 V. Probable active corrosion was detected for 10.0% (6.3%+3.7%) of the deck area with corrosion potential values more negative than ‐0.350 V. Drawing 3 shows the corrosion potential readings on the deck. Active corrosion potential was found adjacent to the north sidewalk.
Corrosion potential distribution in the deck
Cores C2 and C37 were tested for compressive strength of the hardened concrete in accordance with CSA A23.2‐09‐14C. The compressive strength of the hardened concrete for these cores ranged from 38.7
56.0%25.1%
8.9%6.3%
3.7%
0 to ‐0.199 V‐0.200 to ‐0.299 V‐0.300 to ‐0.349 V‐0.350 to ‐0.449 V< ‐0.450
23 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
MPa to 68.9 MPa, with an average compressive strength of 53.8 MPa. This value is significantly higher than the 34.47 MPa (5000 psi) minimum strength specified on the original GA drawing.
The chloride ion content was determined for eight cores using MTO LS‐417 “Method of Test for Determination of Total Chloride Ion in Concrete – Acid Soluble”. These core samples were located at areas prone to salt exposure (e.g. high corrosion potential areas, along construction joints, low points of the deck, asphalt cracks). In addition, samples from other moderately exposed areas were also taken. The chloride ion content values, at the average concrete cover or at rebar level are summarized below.
Core No. C3 C5 C11 C17 C28 C33 C36 C39 Corrected Chloride
Content (%)* 0.027 0.013 0.021 0.011 0.012 0.013 0.010 0.012
Corrosion Potential (V) ‐0.143 ‐0.131 ‐0.307 ‐0.166 ‐0.455 ‐0.161 ‐0.354 ‐0.459 * Background chloride ion content was assumed to be 0.010% for the parent concrete The chloride threshold value necessary to depassivate embedded steel and to allow the onset of corrosion (in the presence of oxygen and moisture) is generally taken as 0.025% by mass of concrete. The background chloride content is the lowest chloride content value for all of the cores tested for chloride content. The “background” chlorides do not contribute to corrosion, and thus the results are corrected for the background chloride content. The corrected chloride content, at the rebar level, was above the chloride threshold level of 0.025% in Core C3. Overall, the results indicate that chloride contamination has extended to the upper rebar level in limited areas of the deck.
Based on the concrete removal policy outlined in the Structure Rehabilitation Manual, the following comments can be made:
• Since more than 10% of the deck area is more negative than ‐0.350 V, the average chloride content at the reinforcing level is calculated using the cores with corrosion potential values more negative than ‐0.350 V. Therefore, the average adjusted chloride content at the reinforcing steel level is 0.011%.
• Based on the above, since the average adjusted chloride content at the top reinforcement level is less than 0.05% by mass of concrete, concrete deck removal is recommended to include delaminated areas only.
Cores C4, C10, and C22 were tested to determine the air void system of the hardened concrete in accordance with ASTM C457 using the Modified Point Count Method. Test results are summarized below:
24 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
Core No. Air Content
(%) Specific Surface
(mm‐1) Spacing Factor
(mm) C4 6.1 33.4 0.090 C10 4.8 37.4 0.117 C22 4.3 36.6 0.119
Concrete is normally considered to be properly air entrained if the air content exceeds 3.0%, the specific surface exceeds 24 mm‐1, and the average spacing factor is less than 0.200 mm. Therefore, the air void system for all three tested cores is considered air entrained.
3.4 Deck Soffit
A detailed visual inspection of deck soffit was carried out utilizing a Bridge Master. The deteriorations are shown on Drawing 4 and in Photos P7 to P24.
The bridge deck soffit, with a total surveyed area of 1,951.60 m2, is in fair condition with clean/stained medium width cracking (100.0 m), delaminations (75.90 m2), spalls (20.90 m2), honeycombing (3.00 m2), and wet areas (47.40 m2). Deteriorations were predominantly observed within the westbound lanes and along the centreline of the deck. Exposed corroded reinforcement was observed in the spalled areas. A concrete cover survey was conducted on the deck soffit except for the area between Piers 1 and 2 (above the CPR tracks). The concrete cover was found to range from 30 to 64 mm with an average cover of 44 mm, as shown on Drawing 5.
3.5 Bridge Approaches
The asphalt wearing surface on the bridge approaches is generally in good condition with unsealed cracks. Photos P25 and P26 show the general pavement condition on the east and west approaches, respectively. Observation of corehole C12, located at the east approach, confirmed presence of concrete approach slab beneath the asphalt. Asphalt thickness measured in core C12 was 40 mm. Observation of corehole C27, located at the west approach, confirmed presence of concrete approach slab beneath the asphalt. Asphalt thickness measured in core C27 was 50 mm. Photo P95 shows the inside of corehole C12.
3.6 Deck Drainage
Deck drains were not observed on this structure. Catch basins were observed at northeast and northwest quadrants and in the median outside structure limits (Photos P27 to P30).
3.7 Deck Joints
The expansion joints (strip seal joints) were generally in fair to poor condition with light rusting and missing sections of the steel armoring angles. The seals were found to be damaged and covered with debris. Gap dimensions varied from 20 to 40 mm. Leaking of the expansion joints was noted from dampness of the deck soffit and abutments underneath. Cracking, scaling, and spalling were noted on
25 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
the concrete end dams. Photos P31 and P37 show general condition of the joints. Unevenness of the east expansion joint was observed in the north sidewalk (Photo P34).
3.8 Concrete Parapet Walls
Inspection of the concrete parapet walls was not part of scope of this investigation. Photos P38 and P39 show typical condition of the parapet walls. Concrete parapet walls have 0.25 m width and 0.61 m height. Photo P92 shows a utility box inside south parapet wall. The ducts were PVC and not containing any asbestos contaminations.
3.9 Concrete Sidewalks
Inspection of the concrete sidewalks was not part of scope of this investigation. Photos P38 and P39 show typical condition of the sidewalks. Concrete sidewalks have 1.87 m width and 0.26 m height. Photo P93 shows a utility box inside north sidewalk. GA Drawing shows 8 PVC Bell Canada Ducts in the north sidewalk and 6 H.PC Ducts in the south sidewalk.
3.10 Concrete Median
Inspection of the concrete median was not part of scope of this investigation. Concrete median has 1.13 m width and 0.25 m height. Photo P40 shows typical condition of the median.
3.11 End Posts and Guide Rails
The concrete end posts are generally in fair to good condition with cracks and delaminations (Photos P41 to P44). The steel beam guiderail system at southwest corner of the bridge is in good condition (Photo P45).
4.0 SUBSTRUCTURE COMPONENTS
The abutments, piers, retaining walls, and wingwalls were inspected and hammer sounded, where accessible, to check for delaminations. Field measurements are presented in the field summary sheets. 4.1 Abutments and Bearings The exposed surfaces of the abutments were inspected and sounded to check for delaminations. The total surveyed area for the east and west abutments were 126.57 and 41.50 m2, respectively. The deteriorations are shown on Drawing 7. General views of the abutments and bearings are shown in Photos P46 to P67. The abutments are in fair to good condition. The field investigation of the east abutment revealed clean/stained medium width cracking (35.0 m), pattern cracks (0.50 m2) and delaminations (1.20 m2). The field investigation of the west abutment revealed clean medium width cracking (6.0 m), delaminations (1.90 m2), and medium scaling (0.45 m2).
26 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
The east abutment elastomeric bearings are in fair to good condition with cracks and bulging (Photos P49 to P56). The west abutment laminated elastomeric bearings are in fair to good condition with cracks and bulging (Photos P60 to P67).
4.2 Ballast Walls The east ballast wall is in fair to good condition whereas the west ballast wall is in fair condition. The deteriorations are shown on Drawing 7. The east abutment ballast wall had a total surveyed area of 7.00 m2 with spalls (0.15 m2). Photos P46 to P48 show typical condition of the east ballast wall. The west abutment ballast wall had a total surveyed area of 7.00 m2 with clean medium width cracks (2.0 m), delaminations (0.30 m2), spalls (0.30 m2), and light scaling (0.10 m2). Photos P57 and P58 show typical condition of the west ballast wall.
4.3 Bearings Seats The bearing seats were generally in good condition. The deteriorations are shown on Drawing 7. The east abutment bearing seat had a total surveyed area of 16.50 m2, with no visible defects. The west abutment bearing seat had a total surveyed area of 16.50 m2, with no visible defects.
4.4 Wingwalls
The exposed areas of the wingwalls were inspected visually and hammer sounded. The wingwalls were in good condition and had a total surveyed area of 14.64 m2, with clean/stained medium width cracks (5.0 m), light scaling (0.15 m2), and wet areas (1.40 m2). The deteriorations are shown on Drawing 7 and in Photos P68 and P69. Wet areas were only observed on the southwest wingwall.
4.5 Retaining Walls
The exposed areas of the retaining walls were inspected visually and hammer sounded. The retaining walls were in good condition and had a total surveyed area of 55.84 m2, with clean/stained medium width cracks (21.0 m). The deteriorations are shown on Drawing 7 and in Photos P70 and P71.
4.6 Piers and Bearings
The bridge piers are in good condition with total surveyed area of 221.60 m2. Inspection of the piers revealed clean medium width cracks (4.0 m) and medium scaling (0.60 m2). Deteriorations are shown on Drawing 6 and in Photos P72 to P89. Medium scaling was found on Pier #3. The expansion Andre Rotaflon bearings at Piers #1 and #3 were found to be in fair to good condition with light corrosion and rust jacking. The Fixed Andre Rota bearings at Pier #2 were in good condition.
4.7 Slopes
The east slope was found to be in fair condition with soil erosion (Photo P90). The west slope paving was in fair to good condition with cracks (Photo P91).
27 of 265
28 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
4/ Detailed Condition Survey Summary Sheets – Asphalt Covered Deck
29 of 265
Site No. #817
Width between E abutment curbs 22.56 m Width between W abutment curbs 22.56 mLength between abutment joints 67.06 m Area of deck riding surface 1529.00 m²
* Asphalt potholes/patches = 0.00 m²* Asphalt Alligator Cracks = 0.00 m²* Asphalt Ravelling = 0.00 m²
Transverse 82.0 10.0 mLongitudinal 65.0 6.0 mRandom 584.0 79.0 m
Min Max AvgF 40 110 69 mm
* G – Good, F – Fair, P – Poor, V - Variable Good to Poor
Min Max AvgHot rubberized
asphalt with protection board
G G 7 9 8 mm
* G – Good, F – Fair, P – Poor, V - Variable Good to Poor** Report only thickness of waterproofing membrane but note presence of protection board
RemarksDeck dimensions
were taken from the structural drawings
Remarks
Remarks
DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4ASPHALT COVERED DECK
DECK RIDING SURFACE
Orientation Unsealed Sealed
1. Dimensions and Area of Survey
Condition * Conc. Bond *
2. Asphalt Surface Cracks
Depth3. Asphalt Depth
Condition *
4. WaterproofingThickness (mm) **Type
30 of 265
Site No. #817
5. Concrete Cover – Cores and Sawn SamplesMinimum Maximum Average
30 109 68 mm
Note: Only include covers for upper layer of rebars.
6. Corrosion ActivityMinimum Maximum Average
-0.102 -0.476 -0.218 V
0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V856.2 383.8 136.1 96.3 56.6 m2
56.0 25.1 8.9 6.3 3.7 %
7. Defective Cores and Sawn Samples
No. m2 % No. m2 %0 to -0.20 35 0 0.0 0.0 0 0.0 0.0
-0.20 to -0.30 14 0 0.0 0.0 0 0.0 0.0-0.30 to -0.35 10 0 0.0 0.0 0 0.0 0.0-0.35 to -0.45 3 0 0.0 0.0 0 0.0 0.0
<-0.45 5 0 0.0 0.0 0 0.0 0.0
Remarks
Cores and Sawn Samples
Total in Each Area
DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4ASPHALT COVERED DECK
DECK RIDING SURFACE
* The percent calculation should be of the entire deck area investigated. The values obtained should be used with caution as large errors may occur when a small number of samples are used for the calculation or when the samples are not randomly distributed over the entire deck area.
Delaminated, Spalled, Severe Scaling and Disintegration * Medium Scaling *Corrosion
Activity (Volts)
Remarks
Remarks
31 of 265
Site No. #817
8. Adjusted Chloride Content Profile *Background (parent concrete) chloride content = 0.010
0 to -0.20 -0.20 to -0.35 ≤-0.350-10 mm 0.023 0.034 0.02020-30 mm 0.020 0.029 0.01540-50 mm 0.018 0.028 0.01460-70 mm 0.016 0.021 0.01180-90 mm 0.011 0.017 0.009
100-110 mm 0.017 ‐ ‐
Core No. C3 C5 C11 C17 C28 C33 C36Chloride Content* 0.027 0.013 0.021 0.011 0.012 0.013 0.010
Corrosion Potential -0.143 -0.131 -0.307 -0.166 -0.455 -0.161 -0.354
Core No. C39Chloride Content* 0.012
Corrosion Potential -0.459
Core No.Chloride Content*
* Chloride content as % chloride by weight of concrete after deducting background chlorides.
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
Table # 10 is Not Applicable.
Remarks
RemarksMeasured AC Resistance between Connection #1 and #2 Calculated AC
Resistance Connection #1Connection #2
10. AC Resistance Test Data of Epoxy Coated Rebar
* See Appendix 1E for calculating AC resistance contributed by individual rebar.
* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.
DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4ASPHALT COVERED DECK
DECK RIDING SURFACE
Corrosion Activity at Core
Chloride Content*
9. Chloride Content at Rebar Level
Corrosion Potential
32 of 265
Site No. #817
11. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
12. Concrete Air EntrainmentYes No Marginal
Concrete Air Entrained?C4 YesC10 YesC22 Yes
13. Compressive Strength
Average Compressive Strength 53.8 MPa
RemarksTable # 11 is Not
Applicable.
* Half cell reading taken on the same rebar with the ground connection.
DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4ASPHALT COVERED DECK
DECK RIDING SURFACE
IR Drop Between Connection #1 and #2 True Half Cell
Potential *Connection #1
(positive)Connection #2 (negative)
33 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
5/ Detailed Condition Survey Summary Sheets – Exposed Concrete Components
34 of 265
Site No: #817
Component Type & Location: Soffit OSIM Identifier: Decks
1. Dimensions and AreaWidth 28.34 m Length 67.67 m Height 0.25 m x 2Diameter - Total Area Surveyed 1951.60 m²
2. Cracks (medium and wide)Transverse Longitudinal Other Total
Clean 0.0 15.0 25.0Stained 12.0 33.0 15.0Clean 0.0 0.0 0.0
Stained 0.0 0.0 0.0
3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²
Minimum Maximum Average30 64 44 mm
0.0 1424.7 m2
0.0 73.0 %521.1 5.9 m2
26.7 0.3 %over 60 mm
Type
100.0
DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component
0 – 20 mm
20 – 40 mm
mWide Width
Medium Width
RemarksDimensions were taken
from the structural drawings & site measurements
Remarks
m
40 – 60 mm
0.0
4. Concrete Cover
35 of 265
Site No: #817Component Type & Location: Soffit OSIM Identifier: Decks
Minimum Maximum Average- - - V
0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V
- - - - - m2
- - - - - %
6. Delaminations and Spalls
Defect Type Delaminations Spalls Patches *Wet areas = 47.40 m²Area (m2) 75.90 20.90 0.00
96.80 m² 5.0 % N/A N/A
Light Medium Severe to Very Severe
0.00 0.00 0.00 m2
0.0 0.0 0.0 %
8. Honeycombing
Total Area 3.00 m²
Remarks
5. Corrosion Activity
Remarks
7. Scaling
Total Delaminations and Spalls
DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS
Total Delaminations and Spalls in Areas ≤-0.35 V
Table # 5 is Not Applicable.
Remarks
36 of 265
Site No: #817Component Type & Location: Soffit OSIM Identifier: Decks
9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35
0-10 mm - - -
20-30 mm - - -
40-50 mm - - -
60-70 mm - - -
80-90 mm - - -
100-110 mm - - -
10. Chloride Content at Rebar LevelCore No. - - - - - -
Chloride Content* - - - - - -
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
* Chloride content as % chloride by weight of concrete after deducting background chlorides.
Measured AC Resistance between Connection #1 and #2 Calculated AC
Resistance Connection #1
Remarks
DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS
Corrosion Activity at Core Location (volts)
* See Appendix 1E for calculating AC resistance contributed by individual rebar.
Remarks
* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.
Table # 9 and 10 are Not Applicable.
11. AC Resistance Test Data of Epoxy Coated Rebar
Connection #2
Table # 11 is Not Applicable.
Chloride Content*
37 of 265
Site No: #817Component Type & Location: Soffit OSIM Identifier: Decks
12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
13. Concrete Air Entrainment
Concrete Air Entrained: not tested
14. Compressive Strength
Average Compressive Strength: not tested
DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS
Connection #2 (negative)
* Half cell reading taken on the same rebar with the ground connection.
Connection #1 (positive)
True Half Cell
Potential *
RemarksTable # 12 is Not
Applicable.
IR Drop Between Connection #1 and #2
38 of 265
Site No: #817
Component Type & Location: West Abutment Wall OSIM Identifier: Abutments
1. Dimensions and AreaWidth 29.23 m Length - Height Avg. 1.42 mDiameter - Total Area Surveyed 41.50 m²
2. Cracks (medium and wide)Vertical Horizontal Diagonal Total
Clean 2.0 0.0 4.0Stained 0.0 0.0 0.0Clean 0.0 0.0 0.0
Stained 0.0 0.0 0.0
3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²
Minimum Maximum Average- - - mm
- - m2
- - %- - m2
- - %
4. Concrete Cover
0 – 20 mm 40 – 60 mm
20 – 40 mm over 60 mm
RemarksTable # 4 is Not
Applicable.
DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component
Type
Medium Width 6.0 m
Wide Width 0.0 m
RemarksDimensions were taken
from the structural drawings & site measurements
39 of 265
Site No: #817Component Type & Location: West Abutment Wall OSIM Identifier: Abutments
Minimum Maximum Average- - - V
0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V
- - - - - m2
- - - - - %
6. Delaminations and Spalls
Defect Type Delaminations Spalls Patches *Wet areas = 0.00 m²Area (m2) 1.90 0.00 0.00
1.90 m² 4.6 % N/A N/A
Light Medium Severe to Very Severe
0.00 0.45 0.00 m2
0.0 1.1 0.0 %
8. Honeycombing
Total Area 0.00 m²
RemarksTable # 5 is Not
Applicable.
Remarks
Remarks
5. Corrosion Activity
Total Delaminations and Spalls
Total Delaminations and Spalls in Areas ≤-0.35 V
7. Scaling
DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS
40 of 265
Site No: #817Component Type & Location: West Abutment Wall OSIM Identifier: Abutments
9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35
0-10 mm - - -
20-30 mm - - -
40-50 mm - - -
60-70 mm - - -
80-90 mm - - -
100-110 mm - - -
10. Chloride Content at Rebar LevelCore No. - - - - - -
Chloride Content* - - - - - -
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
RemarksTable # 9 and 10 are
Not Applicable.
RemarksTable # 11 is Not
Applicable.
* See Appendix 1E for calculating AC resistance contributed by individual rebar.
Corrosion Activity at Core Location (volts)
Chloride Content*
* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.
* Chloride content as % chloride by weight of concrete after deducting background chlorides.
11. AC Resistance Test Data of Epoxy Coated RebarMeasured AC Resistance between Connection #1 and #2 Calculated
AC Resistance Connection #1
Connection #2
DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS
41 of 265
Site No: #817Component Type & Location: West Abutment Wall OSIM Identifier: Abutments
12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
13. Concrete Air Entrainment
Concrete Air Entrained: not tested
14. Compressive Strength
Average Compressive Strength: not tested
* Half cell reading taken on the same rebar with the ground connection.
DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS
IR Drop Between Connection #1 and #2 True Half Cell
Potential *Connection #1
(positive)Connection #2 (negative)
Table # 12 is Not Applicable.
Remarks
42 of 265
Site No: #817
Component Type & Location: West Ballast Wall OSIM Identifier: Abutments
1. Dimensions and AreaWidth 29.23 m Length - Height -Diameter - Total Area Surveyed 7.00 m²
2. Cracks (medium and wide)Vertical Horizontal Diagonal Total
Clean 1.0 0.0 1.0Stained 0.0 0.0 0.0Clean 0.0 0.0 0.0
Stained 0.0 0.0 0.0
3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²
Minimum Maximum Average- - - mm
- - m2
- - %- - m2
- - %
4. Concrete Cover
0 – 20 mm 40 – 60 mm
20 – 40 mm over 60 mm
RemarksTable # 4 is Not
Applicable.
DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component
Type
Medium Width 2.0 m
Wide Width 0.0 m
RemarksDimensions were taken
from the structural drawings & site measurements
43 of 265
Site No: #817Component Type & Location: West Ballast Wall OSIM Identifier: Abutments
Minimum Maximum Average- - - V
0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V
- - - - - m2
- - - - - %
6. Delaminations and Spalls
Defect Type Delaminations Spalls Patches *Wet areas = 0.00 m²Area (m2) 0.30 0.30 0.00
0.60 m² 8.6 % N/A N/A
Light Medium Severe to Very Severe
0.10 0.00 0.00 m2
1.4 0.0 0.0 %
8. Honeycombing
Total Area 0.00 m²
RemarksTable # 5 is Not
Applicable.
Remarks
Remarks
5. Corrosion Activity
Total Delaminations and Spalls
Total Delaminations and Spalls in Areas ≤-0.35 V
7. Scaling
DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS
44 of 265
Site No: #817Component Type & Location: West Ballast Wall OSIM Identifier: Abutments
9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35
0-10 mm - - -
20-30 mm - - -
40-50 mm - - -
60-70 mm - - -
80-90 mm - - -
100-110 mm - - -
10. Chloride Content at Rebar LevelCore No. - - - - - -
Chloride Content* - - - - - -
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
RemarksTable # 9 and 10 are
Not Applicable.
RemarksTable # 11 is Not
Applicable.
* See Appendix 1E for calculating AC resistance contributed by individual rebar.
Corrosion Activity at Core Location (volts)
Chloride Content*
* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.
* Chloride content as % chloride by weight of concrete after deducting background chlorides.
11. AC Resistance Test Data of Epoxy Coated RebarMeasured AC Resistance between Connection #1 and #2 Calculated
AC Resistance Connection #1
Connection #2
DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS
45 of 265
Site No: #817Component Type & Location: West Ballast Wall OSIM Identifier: Abutments
12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
13. Concrete Air Entrainment
Concrete Air Entrained: not tested
14. Compressive Strength
Average Compressive Strength: not tested
* Half cell reading taken on the same rebar with the ground connection.
DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS
IR Drop Between Connection #1 and #2 True Half Cell
Potential *Connection #1
(positive)Connection #2 (negative)
Table # 12 is Not Applicable.
Remarks
46 of 265
Site No: #817
Component Type & Location: West Abutment Bearing Seat OSIM Identifier: Abutments
1. Dimensions and AreaWidth 0.61 m Length 29.23 m Height -Diameter - Total Area Surveyed 16.50 m²
2. Cracks (medium and wide)Transverse Longitudinal Other Total
Clean 0.0 0.0 0.0Stained 0.0 0.0 0.0Clean 0.0 0.0 0.0
Stained 0.0 0.0 0.0
3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²
Minimum Maximum Average- - - mm
- - m2
- - %- - m2
- - %
RemarksTable # 4 is Not
Applicable.
Dimensions were taken from the
structural drawings & site measurements
4. Concrete Cover
0 – 20 mm 40 – 60 mm
20 – 40 mm over 60 mm
DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component
Type
Medium Width 0.0 m
Wide Width 0.0 m
Remarks
47 of 265
Site No: #817Component Type & Location: West Abutment Bearing Seat OSIM Identifier: Abutments
Minimum Maximum Average- - - V
0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V
- - - - - m2
- - - - - %
6. Delaminations and Spalls
Defect Type Delaminations Spalls Patches *Wet areas = 0.00 m²Area (m2) 0.00 0.00 0.00
0.00 m² 0.0 % N/A N/A
Light Medium Severe to Very Severe
0.00 0.00 0.00 m2
0.0 0.0 0.0 %
8. Honeycombing
Total Area 0.00 m²
RemarksTable # 5 is Not
Applicable.
Remarks
Remarks
DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS
5. Corrosion Activity
Total Delaminations and Spalls
Total Delaminations and Spalls in Areas ≤-0.35 V
7. Scaling
48 of 265
Site No: #817Component Type & Location: West Abutment Bearing Seat OSIM Identifier: Abutments
9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35
0-10 mm - - -
20-30 mm - - -
40-50 mm - - -
60-70 mm - - -
80-90 mm - - -
100-110 mm - - -
10. Chloride Content at Rebar LevelCore No. - - - - - -
Chloride Content* - - - - - -
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
Table # 9 and 10 are Not Applicable.
RemarksTable # 11 is Not
Applicable.
* See Appendix 1E for calculating AC resistance contributed by individual rebar.
Corrosion Activity at Core Location (volts)
Chloride Content*
* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.
* Chloride content as % chloride by weight of concrete after deducting background chlorides.
11. AC Resistance Test Data of Epoxy Coated RebarMeasured AC Resistance between Connection #1 and #2 Calculated
AC Resistance Connection #1
Connection #2
Remarks
DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS
49 of 265
Site No: #817Component Type & Location: West Abutment Bearing Seat OSIM Identifier: Abutments
12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
13. Concrete Air Entrainment
Concrete Air Entrained: not tested
14. Compressive Strength
Average Compressive Strength: not tested
* Half cell reading taken on the same rebar with the ground connection.
DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS
IR Drop Between Connection #1 and #2 True Half Cell
Potential *Connection #1
(positive)Connection #2 (negative)
Table # 12 is Not Applicable.
Remarks
50 of 265
Site No: #817
Component Type & Location: East Abutment Wall OSIM Identifier: Abutments
1. Dimensions and AreaWidth 29.23 m Length - Height Avg. 4.33 mDiameter - Total Area Surveyed 126.57 m²
2. Cracks (medium and wide)Vertical Horizontal Diagonal Total
Clean 13.0 0.0 18.0Stained 2.0 0.0 2.0Clean 0.0 0.0 0.0
Stained 0.0 0.0 0.0Pattern cracks= 0.5 m²
3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²
Minimum Maximum Average- - - mm
- - m2
- - %- - m2
- - %
4. Concrete Cover
0 – 20 mm 40 – 60 mm
20 – 40 mm over 60 mm
RemarksTable # 4 is Not
Applicable.
DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component
Type
Medium Width 35.0 m
Wide Width 0.0 m
RemarksDimensions were taken
from the structural drawings & site measurements
51 of 265
Site No: #817Component Type & Location: East Abutment Wall OSIM Identifier: Abutments
Minimum Maximum Average- - - V
0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V
- - - - - m2
- - - - - %
6. Delaminations and Spalls
Defect Type Delaminations Spalls Patches *Wet areas = 0.00 m²Area (m2) 1.20 0.00 0.00
1.20 m² 0.9 % N/A N/A
Light Medium Severe to Very Severe
0.00 0.00 0.00 m2
0.0 0.0 0.0 %
8. Honeycombing
Total Area 0.00 m²
RemarksTable # 5 is Not
Applicable.
Remarks
Remarks
5. Corrosion Activity
Total Delaminations and Spalls
Total Delaminations and Spalls in Areas ≤-0.35 V
7. Scaling
DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS
52 of 265
Site No: #817Component Type & Location: East Abutment Wall OSIM Identifier: Abutments
9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35
0-10 mm - - -
20-30 mm - - -
40-50 mm - - -
60-70 mm - - -
80-90 mm - - -
100-110 mm - - -
10. Chloride Content at Rebar LevelCore No. - - - - - -
Chloride Content* - - - - - -
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
RemarksTable # 9 and 10 are
Not Applicable.
RemarksTable # 11 is Not
Applicable.
* See Appendix 1E for calculating AC resistance contributed by individual rebar.
Corrosion Activity at Core Location (volts)
Chloride Content*
* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.
* Chloride content as % chloride by weight of concrete after deducting background chlorides.
11. AC Resistance Test Data of Epoxy Coated RebarMeasured AC Resistance between Connection #1 and #2 Calculated
AC Resistance Connection #1
Connection #2
DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS
53 of 265
Site No: #817Component Type & Location: East Abutment Wall OSIM Identifier: Abutments
12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
13. Concrete Air Entrainment
Concrete Air Entrained: not tested
14. Compressive Strength
Average Compressive Strength: not tested
* Half cell reading taken on the same rebar with the ground connection.
DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS
IR Drop Between Connection #1 and #2 True Half Cell
Potential *Connection #1
(positive)Connection #2 (negative)
Table # 12 is Not Applicable.
Remarks
54 of 265
Site No: #817
Component Type & Location: East Ballast Wall OSIM Identifier: Abutments
1. Dimensions and AreaWidth 29.23 m Length - Height -Diameter - Total Area Surveyed 7.00 m²
2. Cracks (medium and wide)Vertical Horizontal Diagonal Total
Clean 0.0 0.0 0.0Stained 0.0 0.0 0.0Clean 0.0 0.0 0.0
Stained 0.0 0.0 0.0
3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²
Minimum Maximum Average- - - mm
- - m2
- - %- - m2
- - %
4. Concrete Cover
0 – 20 mm 40 – 60 mm
20 – 40 mm over 60 mm
RemarksTable # 4 is Not
Applicable.
DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component
Type
Medium Width 0.0 m
Wide Width 0.0 m
RemarksDimensions were taken
from the structural drawings & site measurements
55 of 265
Site No: #817Component Type & Location: East Ballast Wall OSIM Identifier: Abutments
Minimum Maximum Average- - - V
0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V
- - - - - m2
- - - - - %
6. Delaminations and Spalls
Defect Type Delaminations Spalls Patches *Wet areas = 0.00 m²Area (m2) 0.00 0.15 0.00
0.15 m² 2.1 % N/A N/A
Light Medium Severe to Very Severe
0.00 0.00 0.00 m2
0.0 0.0 0.0 %
8. Honeycombing
Total Area 0.00 m²
RemarksTable # 5 is Not
Applicable.
Remarks
Remarks
5. Corrosion Activity
Total Delaminations and Spalls
Total Delaminations and Spalls in Areas ≤-0.35 V
7. Scaling
DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS
56 of 265
Site No: #817Component Type & Location: East Ballast Wall OSIM Identifier: Abutments
9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35
0-10 mm - - -
20-30 mm - - -
40-50 mm - - -
60-70 mm - - -
80-90 mm - - -
100-110 mm - - -
10. Chloride Content at Rebar LevelCore No. - - - - - -
Chloride Content* - - - - - -
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
RemarksTable # 9 and 10 are
Not Applicable.
RemarksTable # 11 is Not
Applicable.
* See Appendix 1E for calculating AC resistance contributed by individual rebar.
Corrosion Activity at Core Location (volts)
Chloride Content*
* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.
* Chloride content as % chloride by weight of concrete after deducting background chlorides.
11. AC Resistance Test Data of Epoxy Coated RebarMeasured AC Resistance between Connection #1 and #2 Calculated
AC Resistance Connection #1
Connection #2
DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS
57 of 265
Site No: #817Component Type & Location: East Ballast Wall OSIM Identifier: Abutments
12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
13. Concrete Air Entrainment
Concrete Air Entrained: not tested
14. Compressive Strength
Average Compressive Strength: not tested
* Half cell reading taken on the same rebar with the ground connection.
DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS
IR Drop Between Connection #1 and #2 True Half Cell
Potential *Connection #1
(positive)Connection #2 (negative)
Table # 12 is Not Applicable.
Remarks
58 of 265
Site No: #817
Component Type & Location: East Abutment Bearing Seat OSIM Identifier: Abutments
1. Dimensions and AreaWidth 0.61 m Length 29.23 m Height -Diameter - Total Area Surveyed 16.50 m²
2. Cracks (medium and wide)Transverse Longitudinal Other Total
Clean 0.0 0.0 0.0Stained 0.0 0.0 0.0Clean 0.0 0.0 0.0
Stained 0.0 0.0 0.0
3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²
Minimum Maximum Average- - - mm
- - m2
- - %- - m2
- - %
RemarksTable # 4 is Not
Applicable.
Dimensions were taken from the
structural drawings & site measurements
4. Concrete Cover
0 – 20 mm 40 – 60 mm
20 – 40 mm over 60 mm
DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component
Type
Medium Width 0.0 m
Wide Width 0.0 m
Remarks
59 of 265
Site No: #817Component Type & Location: East Abutment Bearing Seat OSIM Identifier: Abutments
Minimum Maximum Average- - - V
0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V
- - - - - m2
- - - - - %
6. Delaminations and Spalls
Defect Type Delaminations Spalls Patches *Wet areas = 0.00 m²Area (m2) 0.00 0.00 0.00
0.00 m² 0.0 % N/A N/A
Light Medium Severe to Very Severe
0.00 0.00 0.00 m2
0.0 0.0 0.0 %
8. Honeycombing
Total Area 0.00 m²
Remarks7. Scaling
DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS
5. Corrosion Activity
Total Delaminations and Spalls
Total Delaminations and Spalls in Areas ≤-0.35 V
RemarksTable # 5 is Not
Applicable.
Remarks
60 of 265
Site No: #817Component Type & Location: East Abutment Bearing Seat OSIM Identifier: Abutments
9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35
0-10 mm - - -
20-30 mm - - -
40-50 mm - - -
60-70 mm - - -
80-90 mm - - -
100-110 mm - - -
10. Chloride Content at Rebar LevelCore No. - - - - - -
Chloride Content* - - - - - -
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
RemarksTable # 9 and 10 are
Not Applicable.
RemarksTable # 11 is Not
Applicable.
11. AC Resistance Test Data of Epoxy Coated RebarMeasured AC Resistance between Connection #1 and #2 Calculated
AC Resistance Connection #1
Connection #2
* See Appendix 1E for calculating AC resistance contributed by individual rebar.
DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS
Corrosion Activity at Core Location (volts)
Chloride Content*
* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.
* Chloride content as % chloride by weight of concrete after deducting background chlorides.
61 of 265
Site No: #817Component Type & Location: East Abutment Bearing Seat
12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
13. Concrete Air Entrainment
Concrete Air Entrained: not tested
14. Compressive Strength
Average Compressive Strength: not tested
Connection #1 (positive)
Connection #2 (negative)
OSIM Identifier: Abutments
Table # 12 is Not Applicable.
* Half cell reading taken on the same rebar with the ground connection.
DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS
IR Drop Between Connection #1 and #2 True Half Cell
Potential *
Remarks
62 of 265
Site No: #817
Component Type & Location: Wingwalls OSIM Identifier: Abutments
1. Dimensions and AreaWidth - Length 3.66 m x 2 Height Avg. 2.00 mDiameter - Total Area Surveyed 14.64 m²
2. Cracks (medium and wide)Vertical Horizontal Diagonal Total
Clean 0.0 1.0 2.0Stained 0.0 2.0 0.0Clean 0.0 0.0 0.0
Stained 0.0 0.0 0.0
3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²
Minimum Maximum Average- - - mm
- - m2
- - %- - m2
- - %
RemarksDimensions were taken
from the structural drawings & site measurements
Remarks
m
Table # 4 is Not Applicable.
0.0
0 – 20 mm 40 – 60 mm
20 – 40 mm over 60 mm
Wide Width
4. Concrete Cover
DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component
Type
Medium Width m5.0
63 of 265
Site No: #817Component Type & Location: Wingwalls OSIM Identifier: Abutments
Minimum Maximum Average- - - V
0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V
- - - - - m2
- - - - - %
6. Delaminations and Spalls
Defect Type Delaminations Spalls Patches *Wet areas = 1.40 m²Area (m2) 0.00 0.00 0.00
0.00 m² 0.0 % N/A N/A
Light Medium Severe to Very Severe
0.15 0.00 0.00 m2
1.0 0.0 0.0 %
8. Honeycombing
Total Area 0.00 m²
Remarks
RemarksTable # 5 is Not
Applicable.
Remarks
7. Scaling
DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS
5. Corrosion Activity
Total Delaminations and Spalls
Total Delaminations and Spalls in Areas ≤-0.35 V
64 of 265
Site No: #817Component Type & Location: Wingwalls OSIM Identifier: Abutments
9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35
0-10 mm - - -
20-30 mm - - -
40-50 mm - - -
60-70 mm - - -
80-90 mm - - -
100-110 mm - - -
10. Chloride Content at Rebar LevelCore No. - - - - - -
Chloride Content* - - - - - -
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
Table # 11 is Not Applicable.
RemarksTable # 9 and 10 are
Not Applicable.
Remarks
11. AC Resistance Test Data of Epoxy Coated RebarMeasured AC Resistance between Connection #1 and #2 Calculated
AC Resistance
* Chloride content as % chloride by weight of concrete after deducting background chlorides.
DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS
Corrosion Activity at Core Location (volts)
Chloride Content*
* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.
Connection #1Connection #2
* See Appendix 1E for calculating AC resistance contributed by individual rebar.
65 of 265
Site No: #817Component Type & Location: Wingwalls OSIM Identifier: Abutments
12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
13. Concrete Air Entrainment
Concrete Air Entrained: not tested
14. Compressive Strength
Average Compressive Strength: not tested
Remarks
DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS
* Half cell reading taken on the same rebar with the ground connection.
IR Drop Between Connection #1 and #2 True Half Cell
Potential *Connection #1
(positive)Connection #2 (negative)
Table # 12 is Not Applicable.
66 of 265
Site No: #817
Component Type & Location: Piers OSIM Identifier: Piers
1. Dimensions and AreaWidth - Length - Height -Diameter - Total Area Surveyed 221.60 m²
2. Cracks (medium and wide)Vertical Horizontal Diagonal Total
Clean 3.0 0.0 1.0Stained 0.0 0.0 0.0Clean 0.0 0.0 0.0
Stained 0.0 0.0 0.0
3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²
Minimum Maximum Average- - - mm
- - m2
- - %- - m2
- - %
RemarksDimensions were taken
from the structural drawings & site measurements
RemarksTable # 4 is Not
Applicable.
m
4. Concrete Cover
Type
Medium Width m4.0
0 – 20 mm 40 – 60 mm
20 – 40 mm over 60 mm
Wide Width 0.0
DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component
67 of 265
Site No: #817Component Type & Location: Piers OSIM Identifier: Piers
Minimum Maximum Average- - - V
0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V
- - - - - m2
- - - - - %
6. Delaminations and Spalls
Defect Type Delaminations Spalls Patches *Wet areas = 0.00 m²Area (m2) 0.00 0.00 0.00
0.00 m² 0.0 % N/A N/A
Light Medium Severe to Very Severe
0.00 0.60 0.00 m2
0.0 0.3 0.0 %
8. Honeycombing
Total Area 0.00 m²
Remarks
Remarks
RemarksTable # 5 is Not
Applicable.
DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS
5. Corrosion Activity
7. Scaling
Total Delaminations and Spalls
Total Delaminations and Spalls in Areas ≤-0.35 V
68 of 265
Site No: #817Component Type & Location: Piers OSIM Identifier: Piers
9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35
0-10 mm - - -
20-30 mm - - -
40-50 mm - - -
60-70 mm - - -
80-90 mm - - -
100-110 mm - - -
10. Chloride Content at Rebar LevelCore No. - - - - - -
Chloride Content* - - - - - -
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
RemarksTable # 11 is Not
Applicable.
RemarksTable # 9 and 10 are
Not Applicable.
Chloride Content*
* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.
* See Appendix 1E for calculating AC resistance contributed by individual rebar.
11. AC Resistance Test Data of Epoxy Coated RebarMeasured AC Resistance between Connection #1 and #2
* Chloride content as % chloride by weight of concrete after deducting background chlorides.
DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS
Corrosion Activity at Core Location (volts)
Calculated AC
Resistance Connection #1Connection #2
69 of 265
Site No: #817Component Type & Location: Piers OSIM Identifier: Piers
12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
13. Concrete Air Entrainment
Concrete Air Entrained: not tested
14. Compressive Strength
Average Compressive Strength: not tested
DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS
* Half cell reading taken on the same rebar with the ground connection.
IR Drop Between Connection #1 and #2 True Half Cell
Potential *Connection #1
(positive)Connection #2 (negative)
RemarksTable # 12 is Not
Applicable.
70 of 265
Site No: #817
Component Type & Location: Retaining Walls OSIM Identifier: Retaining Walls
1. Dimensions and AreaWidth - Length Avg. 13.36 m x 2 Height Avg. 2.09 mDiameter - Total Area Surveyed 55.84 m²
2. Cracks (medium and wide)Vertical Horizontal Diagonal Total
Clean 0.0 0.0 7.0Stained 9.0 0.0 5.0Clean 0.0 0.0 0.0
Stained 0.0 0.0 0.0
3. Alkali Aggregate ReactionArea of component with severe to very severe aggregate reaction 0.0 m²
Minimum Maximum Average- - - mm
- - m2
- - %- - m2
- - %
RemarksDimensions were taken
from the structural drawings & site measurements
RemarksTable # 4 is Not
Applicable.
m
4. Concrete Cover
Type
Medium Width m21.0
0 – 20 mm 40 – 60 mm
20 – 40 mm over 60 mm
Wide Width 0.0
DETAILED CONDITION SURVEY SUMMARY SHEET Page 1 of 4EXPOSED CONCRETE COMPONENTS (Exposed Deck, Deck Soffit, Curbs, Medians, Sidewalks, Barrier/Parapet Walls, etc.): Use separate form for each component
71 of 265
Site No: #817Component Type & Location: Retaining Walls OSIM Identifier: Retaining Walls
Minimum Maximum Average- - - V
0 to -0.20 -0.20 to -0.30 -0.30 to -0.35 -0.35 to -0.45 < -0.45 V
- - - - - m2
- - - - - %
6. Delaminations and Spalls
Defect Type Delaminations Spalls Patches *Wet areas = 0.00 m²Area (m2) 0.00 0.00 0.00
0.00 m² 0.0 % N/A N/A
Light Medium Severe to Very Severe
0.00 0.00 0.00 m2
0.0 0.0 0.0 %
8. Honeycombing
Total Area 0.00 m²
Remarks
Remarks
RemarksTable # 5 is Not
Applicable.
DETAILED CONDITION SURVEY SUMMARY SHEET Page 2 of 4 EXPOSED CONCRETE COMPONENTS
5. Corrosion Activity
7. Scaling
Total Delaminations and Spalls
Total Delaminations and Spalls in Areas ≤-0.35 V
72 of 265
Site No: #817Component Type & Location: Retaining Walls OSIM Identifier: Retaining Walls
9. Adjusted Chloride Content Profile0 to -0.20 -0.20 to -0.35 ≤ -0.35
0-10 mm - - -
20-30 mm - - -
40-50 mm - - -
60-70 mm - - -
80-90 mm - - -
100-110 mm - - -
10. Chloride Content at Rebar LevelCore No. - - - - - -
Chloride Content* - - - - - -
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
RemarksTable # 11 is Not
Applicable.
RemarksTable # 9 and 10 are
Not Applicable.
Chloride Content*
* Average chloride content as % chloride by weight of concrete after deducting background chlorides for all cores taken in each range of corrosion potential.
* See Appendix 1E for calculating AC resistance contributed by individual rebar.
11. AC Resistance Test Data of Epoxy Coated RebarMeasured AC Resistance between Connection #1 and #2
* Chloride content as % chloride by weight of concrete after deducting background chlorides.
DETAILED CONDITION SURVEY SUMMARY SHEET Page 3 of 4 EXPOSED CONCRETE COMPONENTS
Corrosion Activity at Core Location (volts)
Calculated AC
Resistance Connection #1Connection #2
73 of 265
Site No: #817Component Type & Location: Retaining Walls OSIM Identifier: Retaining Walls
12. IR Drop and Truce Half Cell Potential Measurements of Epoxy Coated Rebar
G1 G2 G3 G4 G5G1 N/A - - - - -G2 - N/A - - - -G3 - - N/A - - -G4 - - - N/A - -G5 - - - - N/A -
13. Concrete Air Entrainment
Concrete Air Entrained: not tested
14. Compressive Strength
Average Compressive Strength: not tested
DETAILED CONDITION SURVEY SUMMARY SHEET Page 4 of 4 EXPOSED CONCRETE COMPONENTS
* Half cell reading taken on the same rebar with the ground connection.
IR Drop Between Connection #1 and #2 True Half Cell
Potential *Connection #1
(positive)Connection #2 (negative)
RemarksTable # 12 is Not
Applicable.
74 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
6/ Detailed Condition Survey Summary Sheet – Expansion Joints
75 of 265
CONDITION SURVEY SUMMARY SHEET EXPANSION JOINTS Site No. 817 EBL
Dimension
Abutments Intermediate
Remarks
Joint 1
Joint 2
Joint 3
Joint 4
E W
a (mm) 254+1876 254+1876 - -
b (mm) 260 245 - -
b' (mm) 265 250 - -
c (mm) 11278 11278 - -
d (mm) 250 250 - -
d' (mm) 255 255 - -
e (mm) 762 762 - -
Depth of Asphalt @ Deck Side N/E S/E N/E S/W
1 (mm) 45 50 - - - -
2 (mm) 50 40 - - - -
3 (mm) 55 75 - - - -
Width: Top of Ballast Wall and End Dams
N/E
S/W
N/E S/W N/E S/W N/E S/W
1 (mm) - - - - - - - -
2 (mm) - - - - - - - -
3 (mm) - - - - - - - -
Gap Dimensions
1 (mm) 20 40 - -
2 (mm) 20 40 - - 3 (mm) 20 40 - -
Misc. Joint Details
Skew Angle 00º 00’ 00”
Exp YES YES - -
Fixed NO NO - -
Type STRIP SEAL JOINT -
Leaking YES YES - -
Angle size - - - -
Temp °C
Deck 10ºC Ambient 10ºC
N JOINT DIMENSIONSS
Typical Sections at Joints: E - W
STEEL ANGLE
EXPOSED CONCRETE
EXPOSED CONCRETE
STRIP SEAL
DECK
140mm
70mm
STEEL ANGLE85mm
220mm
STEEL ANGLE
EXPOSED CONCRETE
EXPOSED CONCRETE
STRIP SEAL
EAST APPROACH SLAB
DECK
120mm
90mm
STEEL ANGLE90mm
210mm
WEST APPROACH SLAB
76 of 265
CONDITION SURVEY SUMMARY SHEET EXPANSION JOINTS Site No. 817WBL
Dimension
Abutments Intermediate
Remarks
Joint 1
Joint 2
Joint 3
Joint 4
E W
a (mm) 762 762 - -
b (mm) 250 245 - -
b' (mm) 255 250 - -
c (mm) 11278 11278 - -
d (mm) 250 265 - -
d' (mm) 255 270 - -
e (mm) 254+1876 254+1876 - -
Depth of Asphalt @ Deck Side N/E S/E N/E S/W
1 (mm) 75 85 - - - -
2 (mm) 40 80 - - - -
3 (mm) 75 80 - - - -
Width: Top of Ballast Wall and End Dams
N/E
S/W
N/E S/W N/E S/W N/E S/W
1 (mm) - - - - - - - -
2 (mm) - - - - - - - -
3 (mm) - - - - - - - -
Gap Dimensions
1 (mm) 20 40 - -
2 (mm) 20 40 - - 3 (mm) 20 40 - -
Misc. Joint Details
Skew Angle 00º 00’ 00”
Exp YES YES - -
Fixed NO NO - -
Type STRIP SEAL JOINT -
Leaking YES YES - -
Angle size - - - -
Temp °C
Deck 10ºC Ambient 10ºC
N JOINT DIMENSIONSS
Typical Sections at Joints: E - W
STEEL ANGLE
EXPOSED CONCRETE
EXPOSED CONCRETE
STRIP SEAL
DECK
140mm
70mm
STEEL ANGLE85mm
220mm
STEEL ANGLE
EXPOSED CONCRETE
EXPOSED CONCRETE
STRIP SEAL
EAST APPROACH SLAB
DECK
120mm
90mm
STEEL ANGLE90mm
210mm
WEST APPROACH SLAB
77 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
7/ Detailed Condition Survey Summary Sheet – Drainage
78 of 265
DRAINAGE Site No. 817
Deck Drains
Number
Type Length Angle Depth *
- - - - -
* For asphalt covered decks, recess depth in mm between top of asphalt and top of drain.
Catch Basins
Yes N/E, N/W, S/E (median), S/W (median)
No
* Identify location of catch basins as N/E, N/W, S/E etc. using the same direction of north as shown on the drawings.
Drainage Tubes
- Void
Drains -
No No
North-East Catch Basin
79 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
8/ Survey Equipment and Calibration Procedures
80 of 265
SURVEY EQUIPMENT AND CALIBRATION PROCEDURES Component Type: Asphalt‐Covered Bridge Deck Site No: 817 1. Delaminations:
Weight of Chain: 2.2 Kg/m Other Equipment: Hammer 2. Concrete Cover: Covermeter Make & Model: Elcometer Protovale 331 Battery Check: Reading at Start of Test: OK Reading at End of Test: OK Concrete Cover Check: Location of Check: SS2 Actual Depth & Rebar Dia: ‐
Reading Before Test: 64 mm Reading Each 30 min During Test: 64 mm
Reading End of Test: 64 mm
3. Corrosion Activity:
Half Cell Make & Model: MC MILLER Electrode RE ‐ 3A (3” Dia)
Multimeter Make & Model: Mastercraft Digital Multimeter 3 R93
Length and Gauge of Lead Wires: 150 m of 18 gauge
Deck Temp: Start of Test: 10°C End of Test: 10°C
Ambient Temp: Start of Test: 10°C End of Test: 10°C
Battery Check: OK Ground Check: Method of Connection: Self‐tapping screw Ground Location: C1, C13, C21, C29 Check Location: C8, C15, C26, C38
Measured Resistance: 2.2, 2.9, 2.6, 2.3 Ω (A))) , Measured resistance is the circuit resistance of deck, including the resistance of the leads
Lead Resistance: 1.8 Ω (B) Voltage Drop (mV’s): 0.1
Net Resistance: 0.4, 1.1, 0.8, 0.5 Ω (C) Resistance Reversed: 0.4, 1.1, 0.8, 0.5 Ω (C = A – B)
Grid Point Potential Readings Check – See Table Below
Location Initial Reading Check Reading ¹ Check Reading – Latex
Concrete Overlay ²
A1/I1/J1/R1 -0.318/-0.322/-0.325/-0.457 -0.317/-0.323/-0.327/-0.455 -
A2/I2/J2/R2 -0.268/-0.237/-0.282/-0.454 -0.267/-0.235/-0.284/-0.453 -
A3/I3/J3/R3 -0.264/-0.255/-0.220/-0.461 -0.265/-0.256/-0.222/-0.462 -
A4/I4/J4/R4 -0.152/-0.275/-0.245/-0.452 -0.153/-0.274/-0.244/-0.450 -
A5/I5/J5/R5 -0.134/-0.344/-0.210/-0.428 -0.135/-0.345/-0.211/-0.427 -
1 Check at least five readings at beginning of test and each change in ground 2 On decks with latex modified concrete overlay, check at least five locations by drilling holes through the latex concrete overlay into the original
concrete substrate
81 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
9/ Core Photographs and Sketches
82 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C1
100mm
75m
mA
SPH
ALT
85m
mC
ON
CR
ETE
W/P Membrane (7 - 9mm)
Rebar imprint @ 80mm(Longitudinal)
83 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C2
100mm
W/P Membrane (7 - 9mm)
60m
mA
SPH
ALT
160m
mC
ON
CR
ETE
84 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C3
100mm
W/P Membrane (7 - 9mm)
70m
mA
SPH
ALT
170m
mC
ON
CR
ETE
85 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C4
100mm
70m
mA
SPH
ALT
140m
mC
ON
CR
ETE
W/P Membrane (7 - 9mm)
86 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C5
100mm
W/P Membrane (7 - 9mm)
70m
mA
SPH
ALT
145m
mC
ON
CR
ETE
Asphalt core damagedupon removal
87 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C6
100mm
W/P Membrane (7 - 9mm)
80m
mA
SPH
ALT
150m
mC
ON
CR
ETE
88 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C7
100mm
80m
mA
SPH
ALT
150m
mC
ON
CR
ETE
W/P Membrane (7 - 9mm)
89 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C8
100mm
W/P Membrane (7 - 9mm)
45m
mA
SPH
ALT
165m
mC
ON
CR
ETE
15M-Rebar @ 70mm(Longitudinal)
90 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C9
100mm
W/P Membrane (7 - 9mm)
65m
mA
SPH
ALT
180m
mC
ON
CR
ETE
91 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C10
100mm
40m
mA
SPH
ALT
205m
mC
ON
CR
ETE
W/P Membrane (7 - 9mm)
92 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C11
100mm
W/P Membrane (7 - 9mm)
55m
mA
SPH
ALT
95m
mC
ON
CR
ETE 15M-Rebar @ 60mm
(Longitudinal)
PTD imprint @ 80mm
93 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C12
100mm
40m
mA
SPH
ALT
85m
mC
ON
CR
ETE
Rebar imprint @ 80mm(Longitudinal)
94 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C13
100mm
50m
mA
SPH
ALT
70m
mC
ON
CR
ETE
W/P Membrane (7 - 9mm)
Rebar imprint @ 65mm(Transverse)
95 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C14
100mm
W/P Membrane (7 - 9mm)
60m
mA
SPH
ALT
145m
mC
ON
CR
ETE
PTD imprint @ 130mm
96 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C15
100mm
W/P Membrane (7 - 9mm)
70m
mA
SPH
ALT
140m
mC
ON
CR
ETE
15M-Rebar @ 60mm(Transverse)
97 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C16
100mm
110m
mA
SPH
ALT
95m
mC
ON
CR
ETE
W/P Membrane (7 - 9mm)
98 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C17
100mm
W/P Membrane (7 - 9mm)
75m
mA
SPH
ALT
115m
mC
ON
CR
ETE
99 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C18
100mm
W/P Membrane (7 - 9mm)
55m
mA
SPH
ALT
180m
mC
ON
CR
ETE
100 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C19
100mm
45m
mA
SPH
ALT
115m
mC
ON
CR
ETE
W/P Membrane (7 - 9mm)
PTD imprint @ 100mm
101 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C20
100mm
W/P Membrane (7 - 9mm)
75m
mA
SPH
ALT
115m
mC
ON
CR
ETE
102 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C21
100mm
W/P Membrane (7 - 9mm)
60m
mA
SPH
ALT
85m
mC
ON
CR
ETE
Rebar imprint @ 75mm(Transverse)
103 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C22
100mm
55m
mA
SPH
ALT
130m
mC
ON
CR
ETE
W/P Membrane (7 - 9mm)
PTD imprint @ 120mm
104 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C23
100mm
W/P Membrane (7 - 9mm)
50m
mA
SPH
ALT
130m
mC
ON
CR
ETE
15M-Rebar @ 50mm(Transverse)
105 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C24
100mm
W/P Membrane (7 - 9mm)
70m
mA
SPH
ALT
155m
mC
ON
CR
ETE
15M-Rebar @ 40mm(Transverse)
106 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C25
100mm
45m
mA
SPH
ALT
150m
mC
ON
CR
ETE
W/P Membrane (4 - 6mm)
15M-Rebar @ 70mm(Transverse)
107 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C26
100mm
W/P Membrane (4 - 6mm)
80m
mA
SPH
ALT
145m
mC
ON
CR
ETE 15M-Rebar @ 80mm
(Longitudinal)
108 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C27
100mm
W/P Membrane (4 - 6mm)
50m
mA
SPH
ALT
65m
mC
ON
CR
ETE
109 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C28
100mm
85m
mA
SPH
ALT
135m
mC
ON
CR
ETE
W/P Membrane (4 - 6mm)
110 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C29
100mm
W/P Membrane (4 - 6mm)
65m
mA
SPH
ALT
80m
mC
ON
CR
ETE
Rebar imprint @ 65mm(Transverse)
111 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C30
100mm
W/P Membrane (4 - 6mm)
80m
mA
SPH
ALT
120m
mC
ON
CR
ETE
112 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C31
100mm
70m
mA
SPH
ALT
80m
mC
ON
CR
ETE
W/P Membrane (4 - 6mm) 15M-Rebar @ 30mm(Longitudinal)
113 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C32
100mm
W/P Membrane (4 - 6mm)
70m
mA
SPH
ALT
130m
mC
ON
CR
ETE
Rebar imprint @ 120mm(Transverse)
114 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C33
100mm
W/P Membrane (4 - 6mm)
75m
mA
SPH
ALT
115m
mC
ON
CR
ETE
115 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C34
100mm
90m
mA
SPH
ALT
125m
mC
ON
CR
ETE
W/P Membrane (4 - 6mm)
116 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C35
100mm
W/P Membrane (4 - 6mm)
65m
mA
SPH
ALT
155m
mC
ON
CR
ETE
117 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C36
100mm
W/P Membrane (4 - 6mm)
65m
mA
SPH
ALT
155m
mC
ON
CR
ETE
15M-Rebar @ 40mm(Transverse)
15M-Rebar @ 95mm(Longitudinal)
Vertical Crack
Core damaged upon removal
118 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C37
100mm
W/P Membrane (4 - 6mm)
80m
mA
SPH
ALT
335m
mC
ON
CR
ETE
119 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C38
W/P Membrane (4 - 6mm)
75m
mA
SPH
ALT
100m
mC
ON
CR
ETE
100mm
Rebar imprint @ 90mm(Transverse)
120 of 265
Bridge 817 Neilson Road over CPR, Toronto, Ontario
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
CORE C39
100mm
W/P Membrane (4 - 6mm)
55m
mA
SPH
ALT
95m
mC
ON
CR
ETE
121 of 265
200 Viceroy Road, Unit 4, Vaughan, ON L4K 3N8 Tel: 905‐660‐6608 Fax: 905‐660‐6609 www.Bridgecheckcanada.com [email protected]
BRIDGE CHECK CANADA Ltd.Pioneer in bridge inspection
10/ Core Logs
122 of 265
Page 1 of 13 Site: #817
Total Corrected Total Corrected Total Corrected 0-10 mm 0.039 0.02920-30 mm 0.038 0.02840-50 mm 0.038 0.02860-70 mm 0.037 0.02780-90 mm 0.034 0.024
100-110 mm 0.027 0.017AIR VOIDS
TEST LABORATORY
Waterproofing (W/P) Type
Condition of W/P (1)
W/P Thickness, mmBond of Asphalt or W/P to Concrete
Chloride Content % Chloride by Weight of Concrete
BCCBARE
Thickness of Asphalt @ Nearest Grid Point
Defects in Concrete (2)
Thickness of Concrete, mmFull Depth (yes/no)Condition of Asphalt (1)
C1Core No.Location (between gridlines)Diameter, mmThickness of Asphalt, mm
Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm
G7 to 9 mm
G-
Condition of Rebar (3)
Corrosion PotentialCompressive Strength, MPa
Rebar imprint @ 80mm (Longitudinal).
REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects
1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas
100.070.0
G
NoF to G
-
F to GNo
GG
C3
75.075.085.0
60.060.0160.0
100.0
C2
100.0
Hot rubberized asphalt with
protection board
7 to 9 mm 7 to 9 mm
F to GNo
G--
G
CORE LOG ASPHALT COVERED BRIDGE DECKS
-
68.9
70.0
‘F’ and ‘10’‘D’ and ‘6’‘A’ and ‘1’
-0.143-0.318 -0.111
Hot rubberized asphalt with
protection board
Hot rubberized asphalt with
protection board
170.0
123 of 265
Page 2 of 13 Site: #817
Total Corrected Total Corrected Total Corrected 0-10 mm 0.033 0.02320-30 mm 0.026 0.01640-50 mm 0.024 0.01460-70 mm 0.023 0.01380-90 mm 0.021 0.011
AIR VOIDS 6.1
33.40.090
TEST LABORATORY BCC BCC
REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects
Asphalt core damaged upon removal.
Corrosion PotentialCompressive Strength, MPa
Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm
Chloride Content % Chloride by Weight of Concrete
-0.166-0.131-0.178
- -Condition of Rebar (3) - - -Defects in Concrete (2) -
G G
Location (between gridlines)100.0
Core No. C4
Diameter, mm‘E’ and ‘20’
F to G F to GNo No
145.0
100.070.070.0
100.080.0
C6
CORE LOG ASPHALT COVERED BRIDGE DECKS
70.0Thickness of Asphalt, mm
Hot rubberized asphalt with
protection board
Hot rubberized asphalt with
protection board
Hot rubberized asphalt with
protection board
Condition of W/P (1)
150.0
1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas
Waterproofing (W/P) Type
7 to 9 mm 7 to 9 mmBond of Asphalt or W/P to Concrete GW/P Thickness, mm 7 to 9 mm
70.0
Full Depth (yes/no) NoCondition of Asphalt (1) F to G
Thickness of Concrete, mm 140.0Thickness of Asphalt @ Nearest Grid Point
‘C’ and ‘12’ ‘A’ and ‘17’
G G
80.0
G
C5
124 of 265
Page 3 of 13 Site: #817
Total Corrected Total Corrected Total Corrected 0-10 mm20-30 mm40-50 mm60-70 mm80-90 mm
AIR VOIDS
TEST LABORATORY
Chloride Content % Chloride by Weight of Concrete
Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm
REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects
15M-Rebar @ 70mm (Longitudinal).
Condition of Rebar (3) - G -Corrosion PotentialCompressive Strength, MPa
-0.150
Bond of Asphalt or W/P to Concrete G G GDefects in Concrete (2) - - -
Condition of W/P (1) G G GW/P Thickness, mm 7 to 9 mm 7 to 9 mm 7 to 9 mm
Condition of Asphalt (1) F to G G G
Waterproofing (W/P) Type
Hot rubberized asphalt with
protection board
Hot rubberized asphalt with
protection board
Hot rubberized asphalt with
protection board
Thickness of Concrete, mm 155.0 165.0 180.0Full Depth (yes/no) No No No
Thickness of Asphalt, mm 80.0 45.0 65.0Thickness of Asphalt @ Nearest Grid Point 80.0 45.0 65.0
CORE LOG ASPHALT COVERED BRIDGE DECKS
1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas
Core No. C7 C8 C9Location (between gridlines)Diameter, mm 100.0 100.0 100.0
‘E’ and ‘29’ ‘B’ and ‘33’‘B’ and ‘24’
-0.134 -0.127
125 of 265
Page 4 of 13 Site: #817
Total Corrected Total Corrected Total Corrected 0-10 mm 0.044 0.03420-30 mm 0.039 0.02940-50 mm 0.038 0.02860-70 mm 0.031 0.02180-90 mm 0.027 0.017
AIR VOIDS 4.8
37.40.117
TEST LABORATORY
Chloride Content % Chloride by Weight of Concrete
Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm
BCC BCC
REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects
Condition of Rebar (3) - G GCorrosion PotentialCompressive Strength, MPa
Bond of Asphalt or W/P to Concrete G GDefects in Concrete (2) - - -
Condition of W/P (1) G GW/P Thickness, mm 7 to 9 mm 7 to 9 mm
Condition of Asphalt (1) F to G F to G G
Waterproofing (W/P) Type
Hot rubberized asphalt with
protection board
Hot rubberized asphalt with
protection boardN/A
Thickness of Concrete, mm 205.0 95.0 85.0Full Depth (yes/no) No No No
Thickness of Asphalt, mm 40.0 55.0 40.0Thickness of Asphalt @ Nearest Grid Point 40.0 55.0
Core No. C10 C11 C12Location (between gridlines)Diameter, mm 100.0 100.0 100.0
‘E’ and ‘41’
CORE LOG ASPHALT COVERED BRIDGE DECKS
East Approach
Rebar imprint @ 80mm (Longitudinal).
1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas
15M-Rebar @ 60mm (Longitudinal).PT cable imprint @ 80mm.
‘A’ and ‘45’
-0.148 -0.307
126 of 265
Page 5 of 13 Site: #817
Total Corrected Total Corrected Total Corrected 0-10 mm20-30 mm40-50 mm60-70 mm80-90 mm
AIR VOIDS
TEST LABORATORY
Chloride Content % Chloride by Weight of Concrete
Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm
-0.327 -0.163
REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects
Rebar imprint @ 65mm (Transverse).
PT cable imprint @ 130mm.
15M-Rebar @ 60mm (Transverse).
Condition of Rebar (3) G - GCorrosion PotentialCompressive Strength, MPa
Bond of Asphalt or W/P to Concrete G G GDefects in Concrete (2) - - -
Condition of W/P (1) G G GW/P Thickness, mm 7 to 9 mm 7 to 9 mm 7 to 9 mm
Condition of Asphalt (1) F to G F to G F to G
Waterproofing (W/P) Type
Hot rubberized asphalt with
protection board
Hot rubberized asphalt with
protection board
Hot rubberized asphalt with
protection board
70.0Thickness of Concrete, mm 70.0 145.0 140.0Full Depth (yes/no) No No No
60.0
100.0Thickness of Asphalt, mm 50.0 60.0 70.0
‘G’ and ‘9’‘H’ and ‘1’Core No. C13 C14 C15
CORE LOG ASPHALT COVERED BRIDGE DECKS
Location (between gridlines)Diameter, mm
1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas
Thickness of Asphalt @ Nearest Grid Point 50.0
‘G’ and ‘15’
-0.165
100.0 100.0
127 of 265
Page 6 of 13 Site: #817
Total Corrected Total Corrected Total Corrected 0-10 mm 0.028 0.01820-30 mm 0.027 0.01740-50 mm 0.021 0.01160-70 mm 0.021 0.01180-90 mm 0.010 0.000
AIR VOIDS
TEST LABORATORY
Chloride Content % Chloride by Weight of Concrete
Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm
BCC
REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects
Condition of Rebar (3) - - -Corrosion PotentialCompressive Strength, MPa
-0.166
Bond of Asphalt or W/P to Concrete G G GDefects in Concrete (2) - - -
Condition of W/P (1) G G GW/P Thickness, mm 7 to 9 mm 7 to 9 mm 7 to 9 mm
Condition of Asphalt (1) F to G F to G F to G
Waterproofing (W/P) Type
Hot rubberized asphalt with
protection board
Hot rubberized asphalt with
protection board
Hot rubberized asphalt with
protection board
Thickness of Concrete, mm 95.0 115.0 180.0Full Depth (yes/no) No No No
Thickness of Asphalt, mm 110.0 75.0 55.0
‘I’ and ‘23’
Thickness of Asphalt @ Nearest Grid Point 110.0 75.0 55.0
Core No. C16 C17 C18Location (between gridlines)Diameter, mm 100.0 100.0 100.0
‘F’ and ‘26’
CORE LOG ASPHALT COVERED BRIDGE DECKS
1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas
‘G’ and ‘35’
-0.135-0.233
128 of 265
Page 7 of 13 Site: #817
Total Corrected Total Corrected Total Corrected 0-10 mm20-30 mm40-50 mm60-70 mm80-90 mm
AIR VOIDS
TEST LABORATORY
-0.288Compressive Strength, MPa
Condition of Rebar (3)
Bond of Asphalt or W/P to Concrete
REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects
PT cable imprint @ 100mm.
Rebar imprint @ 75mm (Transverse).
--
Waterproofing (W/P) Type
G GW/P Thickness, mm
G7 to 9 mm
Condition of W/P (1)
Hot rubberized asphalt with
protection board
G
Condition of Asphalt (1) F to G F to G
Defects in Concrete (2)
Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm
Chloride Content % Chloride by Weight of Concrete
-Corrosion Potential
G-
Thickness of Concrete, mm 115.0 115.0 85.0Full Depth (yes/no) No No No
Thickness of Asphalt, mm 45.0 75.0 60.0Thickness of Asphalt @ Nearest Grid Point 45.0 75.0 60.0
Core No. C19 C20 C21Location (between gridlines)Diameter, mm 100.0 100.0 100.0
‘K’ and ‘39’
1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas
CORE LOG ASPHALT COVERED BRIDGE DECKS
-
‘J’ and ‘44’
-0.314 -0.309
F to G
G G
Hot rubberized asphalt with
protection board
Hot rubberized asphalt with
protection board
7 to 9 mm 7 to 9 mm
‘I’ and ‘44’
129 of 265
Page 8 of 13 Site: #817
Total Corrected Total Corrected Total Corrected 0-10 mm20-30 mm40-50 mm60-70 mm80-90 mm
AIR VOIDS 4.3
36.60.119
TEST LABORATORY
C23 C24Location (between gridlines) ‘L’ and ‘29’ ‘K’ and ‘22’ ‘J’ and ‘14’
CORE LOG ASPHALT COVERED BRIDGE DECKS
Core No. C22
Thickness of Asphalt, mm 55.0 50.0 70.0Diameter, mm 100.0 100.0 100.0
Thickness of Concrete, mm 130.0 130.0 155.0Thickness of Asphalt @ Nearest Grid Point 55.0 50.0 70.0
Condition of Asphalt (1) F to G F to G F to GFull Depth (yes/no) No No No
Condition of W/P (1) G G G
Waterproofing (W/P) Type
Hot rubberized asphalt with
protection board
Hot rubberized asphalt with
protection board
Hot rubberized asphalt with
protection board
Bond of Asphalt or W/P to Concrete G G GW/P Thickness, mm 7 to 9 mm 7 to 9 mm 7 to 9 mm
Condition of Rebar (3) - G GDefects in Concrete (2) - - -
Compressive Strength, MPaCorrosion Potential -0.184 -0.250 -0.240
REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects
PT cable imprint @ 120mm.
15M-Rebar @ 50mm (Transverse).
15M-Rebar @ 40mm (Transverse).
Chloride Content % Chloride by Weight of Concrete
Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm
BCC
1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas
130 of 265
Page 9 of 13 Site: #817
Total Corrected Total Corrected Total Corrected 0-10 mm20-30 mm40-50 mm60-70 mm80-90 mm
AIR VOIDS
TEST LABORATORY
Location (between gridlines) ‘L’ and ‘6’ ‘J’ and ‘1’ West Approach
CORE LOG ASPHALT COVERED BRIDGE DECKS
Core No. C25 C26 C27
Thickness of Asphalt, mm 45.0 80.0 50.0Diameter, mm 100.0 100.0 100.0
Thickness of Concrete, mm 150.0 145.0 65.0Thickness of Asphalt @ Nearest Grid Point 45.0 80.0 50.0
Condition of Asphalt (1) F F FFull Depth (yes/no) No No No
Condition of W/P (1) G G G
Waterproofing (W/P) Type
Hot rubberized asphalt with
protection board
Hot rubberized asphalt with
protection board
Hot rubberized asphalt with
protection board
Bond of Asphalt or W/P to Concrete G G GW/P Thickness, mm 4 to 6 mm 4 to 6 mm 4 to 6 mm
Condition of Rebar (3) G G -Defects in Concrete (2) - - -
Compressive Strength, MPaCorrosion Potential -0.190 -0.325
REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects
15M-Rebar @ 70mm (Transverse).
15M-Rebar @ 80mm (Longitudinal).
Chloride Content % Chloride by Weight of Concrete
Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm
1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas
131 of 265
Page 10 of 13 Site: #817
Total Corrected Total Corrected Total Corrected 0-10 mm 0.030 0.02020-30 mm 0.025 0.01540-50 mm 0.023 0.01360-70 mm 0.022 0.01280-90 mm 0.020 0.010
AIR VOIDS
TEST LABORATORY
Location (between gridlines) ‘Q’ and ‘1’ ‘P’ and ‘6’ ‘R’ and ‘10’
CORE LOG ASPHALT COVERED BRIDGE DECKS
Core No. C28 C29 C30
Thickness of Asphalt, mm 85.0 65.0 80.0Diameter, mm 100.0 100.0 100.0
Thickness of Concrete, mm 135.0 80.0 120.0Thickness of Asphalt @ Nearest Grid Point 85.0 65.0 80.0
Condition of Asphalt (1) F F FFull Depth (yes/no) No No No
Condition of W/P (1) G G G
Waterproofing (W/P) Type
Hot rubberized asphalt with
protection board
Hot rubberized asphalt with
protection board
Hot rubberized asphalt with
protection board
Bond of Asphalt or W/P to Concrete G G GW/P Thickness, mm 4 to 6 mm 4 to 6 mm 4 to 6 mm
Condition of Rebar (3) - G -Defects in Concrete (2) - - -
Compressive Strength, MPaCorrosion Potential -0.455 -0.254 -0.458
REMARKS- orientation of rebars and cover- presence of overlay, patch and thickness- other observed defects
Rebar imprint @ 65mm (Tranverse).
Chloride Content % Chloride by Weight of Concrete
Air Content,%Spec. Surf.,mm2/mm3Spacing Factor, mm
BCC
1. Condition-G=Good, F=Fair, P=Poor.2. Defects-C= Cracked, D= Delamination, R= Rough, Sc= Scaling, S= Spalling3. Condition Rebar-LR= Light Rust, SR= Severe Rust, N/A= No rebar exposedCondition of Epoxy Coating – ECG=Good, ECF=Fair, ECP=Poor-rusted & debonded areas
132 of 265