nerc, npcc & new england compliance
DESCRIPTION
NERC, NPCC & New England Compliance. Kathleen Goodman Operations Compliance Coordinator January 19, 2005 RC Meeting. Compliance General Information. Reporting Structure. 2005 ISO-NE Compliance Responsibilities Matrix Organization Layout. Compliance Survey Timelines. - PowerPoint PPT PresentationTRANSCRIPT
NERC, NPCC & New England
Compliance
Kathleen Goodman
Operations Compliance Coordinator
January 19, 2005 RC Meeting
ComplianceGeneral Information
3
Reporting Structure
T ra n sm iss ionC o m pa n ies
G e ne ra tionC o m pa n ies
A re as(N e w E ng la n d , N e w Y ork , e tc .)
R e g io ns(N P C C )
N E R C
4
2005 ISO-NE Compliance Responsibilities
Matrix Organization Layout
Jo h n N ord enC o n su lta n t
O p e ra tio n s A d m in is tra tive = N o rd e n (G o o dm a n)O p e ra tio ns T ech n ica l = G o od m an
P la n n in g A d m in is tra tive = B u rkeP la n n in g Te ch n ica l = H e n de rson
IT D ep a rtm e ntT B D
O ve ra ll C o m p lia n ce Re sp o ns ib ilit iesS te ve R ou rke
5
Compliance Survey Timelines
Send out data request to appropriate Participants (i.e. generation, transmission) at least 2 months before due to NPCC
Give Participants at least 45 days to respond to ISO-NE
ISO-NE requires a minimum of 15 days to assimilate data for reporting Area Compliance to NPCC
NPCC reports Regional Compliance, based on Area submittals to NERC, if a NERC measure
6
2005 Program Schedule
Will be published as soon as we have it NPCC dependent on NERC to set their
schedule ISO-NE dependent on NPCC to set schedule
based on NERC requirements, as well as NPCC requirements Once NPCC sets schedule, ISO-NE modifies to
include Participant-reporting requirement deadline to ISO-NE
7
Participant Reporting Structure
Compliance Contacts Maintained Transmission Generation (by Lead Participant)
These are the Individuals who are held responsible for providing the data May request data from another individual
(i.e. station operator, protection engineer), but you are still accountable
8
Compliance Contacts Maintained
One per Company - ONLY Will CC another individual, if requested
Will not maintain multiple contacts at same company
Need to have one person to call and notify of lateness
Very burdensome due to lack of administrative staffing levels Investigating the use of CAMS
Participants are responsible for notifying us of changes
NERC Version 0 Update
10
“Plan for Accelerating the Adoption of NERC Reliability Standards” – June 15, 2004
Translation from existing requirements Existing Planning Standards, including post-
blackout Compliance Template revisions Existing Operating Policies, including post-
blackout Policy 5, 6 & 9 revisions This Committee was updated by John Norden at
their August 31st meeting
“Version 0” NERC Standards
11
“Version 0” First Ballot Initial ballot conducted from December 3 through
December 13, 2004 87.4% of the ballot pool voted, achieving a quorum a weighted average of 94.4% affirmative vote by the
ballot pool indicating approval
Several negative votes with comments were cast, requiring a recirculation ballot in accordance with NERC's ANSI-accredited standards process. The recirculation ballot provides an opportunity for the
ballot pool to view the dissenting comments and reconsider their votes
12
“Version 0” Final Ballot Results The recirculation ballot was held from December 20,
2004 through January 7, 2005 The Version 0 Reliability Standards Drafting Team
reviewed comments submitted with the ballots and prepared their consideration of the comments
Stakeholders voted to approve the Version 0 Reliability Standards by a 95.5% weighted average
The standards will now be forwarded to the NERC Board of Trustees for adoption on February 8, 2005. If adopted by the Board, the standards will become
effective on April 1, 2005
13
“Version 0” Implementation If adopted by the Board, the standards will become
effective on April 1, 2005 Because Version 0 is based on existing Policy, NERC
expects industry to be fully compliant on April 1st
The first compliance reporting period will be April 1st through June 30th
Compliance based on Registered Entities (i.e. the Functional Model) and existing Compliance Templates – if their was existing compliance measures, if not, there are no measures
14
“Version 0” ISO-NE Next Steps Project is aimed at preparing the ISO for the
conversion to Version 0 of the NERC Standards Perform Gap Analysis for the NERC Version 0
Templates with existing ISO-NE documentation Based upon the Gap Analysis finding, re-write and or
develop new Operating Procedures, M/L Procedures, SOPs, Planning Procedures etc. to fill gaps identified
Revise Compliance Procedure to ensure compliance and reporting responsibilities under Version 0, the NPCC RCEP, NRAP and ISO New England Standards
Re-write the Compliance SOP to include all compliance activities with “detailed” instructions
NERC Version 1 Update
16
Standards Authorization Requests (SARs) – Proposition that a Standard be written for a specific Reliability need Industry determines whether or not it is
needed, based on vote
Six were posted for comment until January 7th
“Related” to Blackout Recommendations, requested to be expedited
“Version 1” NERC SARs
17
Phase III/IV planning standards not included in Version 0; grouped into 4 SARs Blackstart Capability Disturbance Monitoring and Reporting Modeling Protection and Control
System Personnel Training Nuclear Offsite Supply Reliability
Posted “Version 1” NERC SARs
18
Phase III/IV Planning Standards
“Certain planning standards that were part of the Phase III and IV NERC compliance program were not included in the Version 0 reliability standards. The Version 0 drafting team, supported by industry comments, realized it could not achieve industry consensus on these specific standards in the timeframe or within the scope of the Version 0 standards project. These standards are important, nonetheless, as they contain critical reliability requirements in support of recommendations from the NERC and U.S./Canada Power System Outage Task Force reports on the August 14, 2003 blackout. Recognizing the importance of these standards, the NERC board resolved on October 15, 2004, that: "A satisfactory resolution of the issues regarding Phases III and IV of the planning standards would be to: (1) develop reliability standards covering the Phase III and Phase IV issues separate from the Version 0 effort, using the NERC standards development process; (2) have the Planning Committee expeditiously complete the drafting of the proposed standards needed to address the Phase III and Phase IV issues, and move those standards through the NERC standards development process as promptly as possible, but not later than the May 2005 board meeting." This SAR proposes the development of reliability standards that address the disturbance monitoring and reporting requirements of those Phase III and IV planning standards.”
19
Phase III/IV planning standards II.B Standards - System Modeling Data
Requirements – Generation Equipment
Field Verification• Verification of gross and net reactive power capability of
generators
• Test results of generator voltage regulator controls and limit functions
• Test results of speed/load governor controls
• Verification of excitation system dynamic modeling data
Contentious “Version 1” NERC SARs
20
III.C Standards – Generation Control and Protection Prime mover control (governors) shall operate with
appropriate speed/load characteristics to regulate frequency…
Generator owners/operators shall analyze protection system operations…
Generator owners/operators shall have a generator protection system maintenance and testing program in place…
Generation representatives should be providing input!
More Generations “Version 1”NERC SARs
21
“Version 1” NERC Standards
22
“Version 1” Implementations?
Implementing some of these requirements could cost you money!
How will these costs be recovered? Are all these requirements necessary for BES
Reliability? Are the necessary requirements included in what will
ultimately come to pass? New England will have to be compliant with the NERC
requirements – if you have not been involved, you will be held to Standards that other people have drafted
NERC StandardsRecommendations
24
Provide comments Process is designed to build greater stakeholder
participation and consensus as proposed standards proceed from the initial proposal to the final ballot
The NPCC builds consensus comments, for Member consideration; but we all provide individual company comments as well
The more “similar” comments are received the louder the voice becomes and the more influence it has
Shaping the Standards
25
We comment directly to NERC, through the Registered Ballot Body mechanism
We actively participate in the NPCC group which has been charged with tracking, commenting, recommending voting, etc. during the NERC Standards development initiative
We actively participate in the ISO/RTO/Council SRC, a review group of ISO’s and RTO’s across the country designed to participate in NERC Standards development
How is ISO-NE Involved
26
GET INVOLVED – these will impact you directly NPCC Group (CP-9) charged with reviewing and
providing consensus comments to SARs, Standards, and – additionally – recommending a vote to NPCC Membership
The Registered Ballot Body (RBB) comprises all entities that qualify and register for one of the nine industry segments as defined in the Reliability Standards Process Manual. Members of the RBB are eligible to vote on proposed reliability standards• You can participate individually!
Recommendations
27
Segment 1 – Transmission Owners Segment 2 – RTOs, ISOs, RRCs Segment 3 – Load Serving Entities (LSEs) Segment 4 – Transmission Dependent Utilities Segment 5 – Electric Generators Segment 6 – Electricity Brokers, Aggregators, and
Marketers Segment 7 – Large Electricity End Users Segment 8 – Small Electricity Users Segment 9 – Federal, State, and Provincial Regulatory
or Other Government Entities
RBB Industry Segments
2005 Compliance Proposal
29
It is certainly time to keep a close watch on compliance requirements, therefore, ISO-NE proposes: Retirement of the NEPOOL Compliance
Working Group (NCWG) with thanks for their hard work and dedication
Hold quarterly update meetings with the RC, similar to today’s and
Have annual Workshops in the Spring
2005 Compliance Proposal
30
Quarterly meetings with the RC Same format as today Piggyback on existing meetings; no
additional meetings February, May, August & October timeframes
Workshop on annual compliance requirements in the Spring of each year RC members and Compliance Contacts
invited to attend – central location
2005 Compliance Proposal Schedule
Questions?