nerctranslate this page actions dl/finalfiled...%pdf-1.6 %âãÏÓ 1230 0 obj >stream hÞdÍÁ...

40
116-390 Village Blvd. Princeton, NJ 08540 609.452.8060 | www.nerc.com March 30, 2011 Ms. Kimberly Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Re: NERC Abbreviated Notice of Penalty regarding Dynegy Arlington Valley, LLC, FERC Docket No. NP11-__-000 Dear Ms. Bose: The North American Electric Reliability Corporation (NERC) hereby provides this Abbreviated Notice of Penalty (NOP) regarding Dynegy Arlington Valley, LLC (DEAA), 1 with information and details regarding the nature and resolution of the violations 2 discussed in detail in the Disposition Documents attached hereto (Attachment a), in accordance with the Federal Energy Regulatory Commission’s (Commission or FERC) rules, regulations and orders, as well as NERC Rules of Procedure including Appendix 4C (NERC Compliance Monitoring and Enforcement Program (CMEP)). 3 This NOP is being filed with the Commission because DEAA does not dispute the violation of PER-002-0 Requirement (R) 3.1 and the assessed zero dollar ($0) penalty. Accordingly, the violation identified as NERC Violation Tracking Identification Numbers WECC200700439 is a Confirmed Violation, as that term is defined in the NERC Rules of Procedure and the CMEP. Statement of Findings Underlying the Violation This NOP incorporates the findings and justifications set forth in the Notice of Confirmed Violation and Proposed Penalty or Sanction (NOCV) issued on September 2, 2010, by Western Electricity Coordinating Council (WECC). The details of the findings and the basis for the 1 Arlington Valley, LLC (AVBA) is the successor in interest to Dynegy Arlington Valley, LLC (DEAA). Since this Violation was originally attributed to DEAA, for purposes of this document and attachments hereto, the Registered Entity will be referred to as DEAA. 2 For purposes of this document, each violation at issue is described as a “violation,” regardless of its procedural posture and whether it was a possible, alleged or confirmed violation. 3 Rules Concerning Certification of the Electric Reliability Organization; and Procedures for the Establishment, Approval, and Enforcement of Electric Reliability Standards (Order No. 672), III FERC Stats. & Regs. ¶ 31,204 (2006); Notice of New Docket Prefix “NP” for Notices of Penalty Filed by the North American Electric Reliability Corporation, Docket No. RM05-30-000 (February 7, 2008). See also 18 C.F.R. Part 39 (2010). Mandatory Reliability Standards for the Bulk-Power System, FERC Stats. & Regs. ¶ 31,242 (2007) (Order No. 693), reh’g denied, 120 FERC ¶ 61,053 (2007) (Order No. 693-A). See 18 C.F.R § 39.7(c)(2).

Upload: phungnga

Post on 14-Mar-2018

221 views

Category:

Documents


4 download

TRANSCRIPT

116-390 Village Blvd. Princeton, NJ 08540 609.452.8060 | www.nerc.com

March 30, 2011 Ms. Kimberly Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Re: NERC Abbreviated Notice of Penalty regarding Dynegy Arlington Valley, LLC,

FERC Docket No. NP11-__-000 Dear Ms. Bose: The North American Electric Reliability Corporation (NERC) hereby provides this Abbreviated Notice of Penalty (NOP) regarding Dynegy Arlington Valley, LLC (DEAA),1 with information and details regarding the nature and resolution of the violations2 discussed in detail in the Disposition Documents attached hereto (Attachment a), in accordance with the Federal Energy Regulatory Commission’s (Commission or FERC) rules, regulations and orders, as well as NERC Rules of Procedure including Appendix 4C (NERC Compliance Monitoring and Enforcement Program (CMEP)).3

This NOP is being filed with the Commission because DEAA does not dispute the violation of PER-002-0 Requirement (R) 3.1 and the assessed zero dollar ($0) penalty. Accordingly, the violation identified as NERC Violation Tracking Identification Numbers WECC200700439 is a Confirmed Violation, as that term is defined in the NERC Rules of Procedure and the CMEP. Statement of Findings Underlying the Violation This NOP incorporates the findings and justifications set forth in the Notice of Confirmed Violation and Proposed Penalty or Sanction (NOCV) issued on September 2, 2010, by Western Electricity Coordinating Council (WECC). The details of the findings and the basis for the

1 Arlington Valley, LLC (AVBA) is the successor in interest to Dynegy Arlington Valley, LLC (DEAA). Since this Violation was originally attributed to DEAA, for purposes of this document and attachments hereto, the Registered Entity will be referred to as DEAA. 2 For purposes of this document, each violation at issue is described as a “violation,” regardless of its procedural posture and whether it was a possible, alleged or confirmed violation. 3 Rules Concerning Certification of the Electric Reliability Organization; and Procedures for the Establishment, Approval, and Enforcement of Electric Reliability Standards (Order No. 672), III FERC Stats. & Regs. ¶ 31,204 (2006); Notice of New Docket Prefix “NP” for Notices of Penalty Filed by the North American Electric Reliability Corporation, Docket No. RM05-30-000 (February 7, 2008). See also 18 C.F.R. Part 39 (2010). Mandatory Reliability Standards for the Bulk-Power System, FERC Stats. & Regs. ¶ 31,242 (2007) (Order No. 693), reh’g denied, 120 FERC ¶ 61,053 (2007) (Order No. 693-A). See 18 C.F.R § 39.7(c)(2).

NERC Abbreviated Notice of Penalty Dynegy Arlington Valley, LLC March 30, 2011 Page 2

penalty are set forth in the Disposition Document. This NOP filing contains the basis for approval of this NOP by the NERC Board of Trustees Compliance Committee (BOTCC). In accordance with Section 39.7 of the Commission’s Regulations, 18 C.F.R. § 39.7, NERC provides the following summary table identifying each violation of a Reliability Standard at issue in this NOP.

NOC ID NERC Violation ID

Reliability Std.

Req. (R) VRF Duration

Total Penalty

($)

NOC-675 WECC200700439 PER-002-0 3.1 Medium4 6/18/07 5

0 - 4/28/08

The text of the Reliability Standard at issue and further information on the subject violations are set forth in the Disposition Document. PER-002-0 R3 - OVERVIEW WECC determined that DEAA, as a Balancing Authority, could not produce a list of training program objectives for its operators during a Compliance Audit conducted between October 23, 2007 and October 25, 2007. Statement Describing the Assessed Penalty, Sanction or Enforcement Action Imposed6

Basis for Determination Taking into consideration the Commission’s direction in Order No. 693, the NERC Sanction Guidelines and the Commission’s July 3, 2008, October 26, 2009 and August 27, 2010 Guidance Orders,7

the NERC BOTCC reviewed the NOCV and supporting documentation on February 15, 2011. The NERC BOTCC approved the NOCV and the assessment of a $0 dollar ($0) financial penalty against DEAA based upon WECC’s findings and determinations, the NERC BOTCC’s review of the applicable requirements of the Commission-approved Reliability Standards and the underlying facts and circumstances of the violation at issue.

In reaching this determination, the NERC BOTCC considered the following factors:8

1. the violation constituted DEAA’s first occurrence of violations of the subject NERC Reliability Standards;

9

4 The Regional Determination Summary document incorrectly states that the Violation Risk Factor (VRF) for the PER-002-0 R3.1 is a “High” VRF. PER-002-0 R3 has a “High” VRF, R3.1 and R3.2 each have a “Medium” VRF and R3.3 and R3.4 each have a “Lower” VRF.

5 The Regional Determination Summary document incorrectly states that the violation began on October 24, 2007. 6 See 18 C.F.R § 39.7(d)(4). 7 North American Electric Reliability Corporation, “Guidance Order on Reliability Notices of Penalty,” 124 FERC ¶ 61,015 (2008); North American Electric Reliability Corporation, “Further Guidance Order on Reliability Notices of Penalty,” 129 FERC ¶ 61,069 (2009); North American Electric Reliability Corporation, “Notice of No Further Review and Guidance Order,” 132 FERC ¶ 61,182 (2010). 8 WECC reviewed DEAA’s compliance program at the Audit but did not consider it a factor in the penalty determination. 9 As discussed in the Disposition Document, other registered entities for which Constellation Energy Control and Dispatch, LLC performs the Balancing Authority requirements have violations of PER-002-0 R3.1, which WECC

NERC Abbreviated Notice of Penalty Dynegy Arlington Valley, LLC March 30, 2011 Page 3

2. WECC reported that DEAA was cooperative throughout the compliance enforcement process;

3. there was no evidence of any attempt to conceal a violation nor evidence of intent to do so;

4. WECC considered, as a mitigating factor, that the instant violation is an older violation that was identified and fixed during the first year of mandatory standards;

5. WECC determined that the violation posed a minimal risk and did not pose a serious or substantial risk to the reliability of the bulk power system (BPS), as discussed in the Disposition Document; and

6. WECC reported that there were no other mitigating or aggravating factors or extenuating circumstances that would affect the assessed penalty.

For the foregoing reasons, the NERC BOTCC believes that the assessed penalty of zero dollars ($0) is appropriate for the violation and circumstances at issue, and is consistent with NERC’s goal to promote and ensure reliability of the bulk power system. Pursuant to 18 C.F.R. § 39.7(e), the penalty will be effective upon expiration of the 30 day period following the filing of this NOP with the Commission, or, if the Commission decides to review the penalty, upon final determination by the Commission. Attachments to be included as Part of this Notice of Penalty The attachments to be included as part of this NOP are the following documents:

a) Disposition of Violation, included as Attachment a;

b) DEAA’s Responses to the Notice of Alleged Violation and Proposed Penalty or Sanction dated February 27, 2009 and April 6, 2009, included as Attachment b;

c) WECC’s Regional Determination of Alleged Violation Summary for PER-002-0 R3 with discovery date October 24, 2007, included as Attachment c;10

d) DEAA’s Mitigation Plan and Certification of Mitigation Plan Completion therein submitted February 27, 2009, included as Attachment d; and

e) WECC’s Verification of Mitigation Plan Completion dated April 8, 2009, included as Attachment e.

A Form of Notice Suitable for Publication11

A copy of a notice suitable for publication is included in Attachment f.

did not consider an aggravating factor in determining the instant penalty. Violations for Dynegy, Inc., which owned the Arlington Valley facility for the duration of the violation, were not viewed as the same or similar to the instant violation, are discussed in the Disposition Document. 10 The Regional Determination Summary document incorrectly states that the VRF for the PER-002-0 R3.1 is a High VRF, that the violation began on October 24, 2007 and that the Notice of Alleged Violation and Proposed Penalty or Sanction was issued on January 30, 2009. 11 See 18 C.F.R. § 39.7(d)(6).

NERC Abbreviated Notice of Penalty Dynegy Arlington Valley, LLC March 30, 2011 Page 4

Notices and Communications Notices and communications with respect to this filing may be addressed to the following:

Gerald W. Cauley President and Chief Executive Officer David N. Cook* Sr. Vice President and General Counsel North American Electric Reliability Corporation 116-390 Village Boulevard Princeton, NJ 08540-5721 (609) 452-8060 (609) 452-9550 – facsimile [email protected] Mark Maher* Chief Executive Officer Western Electricity Coordinating Council 155 North 400 West, Suite 200 Salt Lake City, UT 84103 (360) 713-9598 (801) 582-3918 – facsimile [email protected] Constance White* Vice President of Compliance Western Electricity Coordinating Council 155 North 400 West, Suite 200 Salt Lake City, UT 84103 (801) 883-6885 (801) 883-6894 – facsimile [email protected] Sandy Mooy* Senior Legal Counsel Western Electricity Coordinating Council 155 North 400 West, Suite 200 Salt Lake City, UT 84103 (801) 819-7658 (801) 883-6894 – facsimile [email protected]

Rebecca J. Michael* Associate General Counsel for Corporate and Regulatory Matters North American Electric Reliability Corporation 1120 G Street, N.W. Suite 990 Washington, DC 20005-3801 (202) 393-3998 (202) 393-3955 – facsimile [email protected] Christopher Luras* Manager of Compliance Enforcement Western Electricity Coordinating Council 155 North 400 West, Suite 200 Salt Lake City, UT 84103 (801) 883-6887 (801) 883-6894 – facsimile [email protected] Woody Saylor* Asset Manager Arlington Valley, LLC 10423 Greenwillow Houston, TX 77035 (713) 447-6916 [email protected] *Persons to be included on the Commission’s service list are indicated with an asterisk. NERC requests waiver of the Commission’s rules and regulations to permit the inclusion of more than two people on the service list.

NERC Abbreviated Notice of Penalty Dynegy Arlington Valley, LLC March 30, 2011 Page 5

Conclusion Accordingly, NERC respectfully requests that the Commission accept this NOP as compliant with its rules, regulations and orders.

Respectfully submitted, /s/ Rebecca J. Michael Gerald W. Cauley President and Chief Executive Officer David N. Cook Sr. Vice President and General Counsel North American Electric Reliability Corporation 116-390 Village Boulevard Princeton, NJ 08540-5721 (609) 452-8060 (609) 452-9550 – facsimile [email protected]

Rebecca J. Michael Associate General Counsel for Corporate and Regulatory Matters North American Electric Reliability

Corporation 1120 G Street, N.W. Suite 990 Washington, DC 20005-3801 (202) 393-3998 (202) 393-3955 – facsimile [email protected]

cc: Dynegy Arlington Valley, LLC Western Electricity Coordinating Council Attachments

Attachment a

Disposition of Violation

Attachment a

Dynegy Arlington Valley, LLC Page 1 of 10

DISPOSITION OF VIOLATION1

Dated February 15, 2011

NERC TRACKING NO.

REGIONAL ENTITY TRACKING NO.

NOC#

WECC200700439 DEAA_WECC2007447 NOC-675

REGISTERED ENTITY NERC REGISTRY ID Dynegy Arlington Valley, LLC (DEAA) 2 NCR05135 REGIONAL ENTITY Western Electricity Coordinating Council (WECC)

I. REGISTRATION INFORMATION

ENTITY IS REGISTERED FOR THE FOLLOWING FUNCTIONS (BOTTOM ROW

INDICATES REGISTRATION DATE): BA DP GO GOP IA LSE PA PSE RC RP RSG TO TOP TP TSP X X X

6/17

/07

– 11

/30/

09

11/5

/07

– 11

/30/

09

11/5

/07

– 11

/30/

09

* VIOLATION APPLIES TO SHADED FUNCTIONS DESCRIPTION OF THE REGISTERED ENTITY DEAA consisted of three natural gas generators located in Maricopa, Arizona which were commissioned in June 2002. DEAA entered into a Balancing Authority Services Agreement with Constellation Energy Control & Dispatch Group, LLC (CECD). As a result of the Balancing Authority Services Agreement, CECD performs the Balancing Authority requirements applicable to DEAA as DEAA’s agent.

II. VIOLATION INFORMATION

RELIABILITY STANDARD

REQUIREMENT(S) SUB-REQUIREMENT(S)

VRF(S) VSL(S)

PER-002-0 R3 3.1 Medium3 Lower 4

1 For purposes of this document and attachments hereto, each violation at issue is described as a “violation,” regardless of its procedural posture and whether it was a possible, alleged or confirmed violation.

2 Arlington Valley, LLC (AVBA) is the successor in interest to Dynegy Arlington Valley, LLC (DEAA). Since this Violation was originally attributed to DEAA, for purposes of this document and attachments hereto, the Registered Entity will be referred to as DEAA.

Attachment a

Dynegy Arlington Valley, LLC Page 2 of 10

PURPOSE OF THE RELIABILITY STANDARD AND TEXT OF RELIABILITY STANDARD AND REQUIREMENT(S)/SUB-REQUIREMENT(S) The purpose statement of PER-002-0 provides: “Each Transmission Operator and Balancing Authority must provide their personnel with a coordinated training program that will ensure reliable system operation.” PER-002-0 R3 provides:

For personnel identified in Requirement R2, the Transmission Operator and Balancing Authority shall provide a training program meeting the following criteria:

R3.1 A set of training program objectives must be defined, based on NERC and Regional Reliability Organization[5

] standards, entity operating procedures, and applicable regulatory requirements. These objectives shall reference the knowledge and competencies needed to apply those standards, procedures, and requirements to normal, emergency, and restoration conditions for the Transmission Operator and Balancing Authority operating positions.

R3.2 The training program must include a plan for the initial and continuing training of Transmission Operator and Balancing Authority operating personnel. That plan shall address knowledge and competencies required for reliable system operations.

R3.3 The training program must include training time for all Transmission Operator and Balancing Authority operating personnel to ensure their operating proficiency.

R3.4 Training staff must be identified, and the staff must be competent in both knowledge of system operations and instructional capabilities.

VIOLATION DESCRIPTION On October 23, 2007 through October 25, 2007, WECC conducted a Compliance Audit of CECD for the Balancing Authority functions of entities that had entered into a Balancing Authority Agreement with CECD. CECD is the Balancing 3 The Regional Determination Summary document incorrectly states that the Violation Risk Factor (VRF) for the PER-002-0 R3.1 is a “High” VRF. PER-002-0 R3 has a “High” VRF, R3.1 and R3.2 each have a “Medium” VRF and R3.3 and R3.4 each have a “Lower” VRF. 4 WECC determined that this violation had a Lower Violation Severity Level (VSL) based on the VSLs assigned in the VSL Matrix to a violation of R3. If the VSL were determined based on the VSLs for a violation of R3.1, the VSL would be Severe. 5 Consistent with applicable FERC precedent, the term ‘Regional Reliability Organization’ in this context refers to WECC.

Attachment a

Dynegy Arlington Valley, LLC Page 3 of 10

Authority Services Provider for multiple Balancing Authorities located in both WECC and SERC Reliability Corporation (SERC) Regions. As a result, the Balancing Authority audits scheduled for each of the registered entities were combined into one joint audit by WECC and SERC. The audit took place between October 23, 2007 and October 25, 2007, with both WECC and SERC Audit Teams present and jointly reviewing evidence of compliance. The Audit Team reviewed three documents submitted by CECD: (1) Master BA Protocol PER-002-0, (2) CECD Protocols PER-002-0, and (3) Training Notebook. The Audit Team also interviewed CECD’s Director of Compliance, Director of Operations Management, and Senior Counsel to assist in determining compliance with this Standard. The Audit Team determined that this training program documentation presented a list of topics operators need to learn, but the list did not constitute training program objectives. Further, this Standard requires the entity to define training program objectives that are the entity’s objectives, not a vendor’s objectives for a particular training course. This Standard specifically requires that the training program objectives “reference the knowledge and competencies needed to apply those standards, procedures, and requirements to normal, emergency, and restoration conditions.” The Audit Team concluded that DEAA had a violation of PER-002-0 R3.1 because the training program did not contain clearly defined objectives which described the expected outcomes. WECC’s Enforcement Team reviewed the Audit evaluation and DEAA’s completed Mitigation Plan and determined that CECD, acting on behalf of DEAA, had failed to define a set of training program objectives for its Balancing Authority operating positions. RELIABILITY IMPACT STATEMENT- POTENTIAL AND ACTUAL WECC determined that the violation posed a minimal risk and did not pose a serious or substantial risk to the reliability of the bulk power system (BPS) because although CECD’s training documentation did not contain training objectives, CECD did have a training program, with a specified list of topics Operators need to learn (even if that list did not technically qualify as objectives) and was training its operators in system operations. IS THERE A SETTLEMENT AGREEMENT YES NO WITH RESPECT TO THE VIOLATION(S), REGISTERED ENTITY

NEITHER ADMITS NOR DENIES IT (SETTLEMENT ONLY) YES ADMITS TO IT YES DOES NOT CONTEST IT (INCLUDING WITHIN 30 DAYS) YES

Attachment a

Dynegy Arlington Valley, LLC Page 4 of 10

WITH RESPECT TO THE ASSESSED PENALTY OR SANCTION, REGISTERED ENTITY ACCEPTS IT/ DOES NOT CONTEST IT YES

III. DISCOVERY INFORMATION METHOD OF DISCOVERY

SELF-REPORT SELF-CERTIFICATION COMPLIANCE AUDIT COMPLIANCE VIOLATION INVESTIGATION SPOT CHECK COMPLAINT PERIODIC DATA SUBMITTAL EXCEPTION REPORTING

DURATION DATE(S) 6/18/076

(when the Standard became mandatory and enforceable) through 4/28/08 (Mitigation Plan completion)

DATE DISCOVERED BY OR REPORTED TO REGIONAL ENTITY 10/23/07 – 10/25/07

IS THE VIOLATION STILL OCCURRING YES NO IF YES, EXPLAIN

REMEDIAL ACTION DIRECTIVE ISSUED YES NO PRE TO POST JUNE 18, 2007 VIOLATION YES NO

IV. MITIGATION INFORMATION

FOR FINAL ACCEPTED MITIGATION PLAN:

MITIGATION PLAN NO. MIT-07-1586 DATE SUBMITTED TO REGIONAL ENTITY 2/27/09 DATE ACCEPTED BY REGIONAL ENTITY 3/19/09 DATE APPROVED BY NERC 4/27/09 DATE PROVIDED TO FERC 4/28/09

IDENTIFY AND EXPLAIN ALL PRIOR VERSIONS THAT WERE ACCEPTED OR REJECTED, IF APPLICABLE N/A 6 The Regional Determination Summary document incorrectly states that the violation began on October 24, 2007.

Attachment a

Dynegy Arlington Valley, LLC Page 5 of 10

MITIGATION PLAN COMPLETED YES NO

EXPECTED COMPLETION DATE Submitted as complete EXTENSIONS GRANTED N/A ACTUAL COMPLETION DATE 4/28/08

DATE OF CERTIFICATION 2/27/09 CERTIFIED COMPLETE BY REGISTERED ENTITY AS OF 4/28/08

DATE OF VERIFICATION LETTER 4/8/09 VERIFIED COMPLETE BY REGIONAL ENTITY AS OF 4/28/08

ACTIONS TAKEN TO MITIGATE THE ISSUE AND PREVENT RECURRENCE The training objectives were added to DEAA’s program. CECD sent personnel to Train the Trainer courses provided by SERC and reviewed the training program and relevant documentation. CECD modified the training documentation to include the appropriate training objectives. The revised training objectives were included in CECD’s Operating Guides and released to system operators for review. LIST OF EVIDENCE REVIEWED BY REGIONAL ENTITY TO EVALUATE COMPLETION OF MITIGATION PLAN OR MILESTONES (FOR CASES IN WHICH MITIGATION IS NOT YET COMPLETED, LIST EVIDENCE REVIEWED FOR COMPLETED MILESTONES)

• Constellation Energy Training Program effective April 28, 2008 showed that training objectives had been added to the program; and

• Balancing Authority Operating Protocols was the original document that included these objectives.

V. PENALTY INFORMATION

TOTAL ASSESSED PENALTY OR SANCTION OF $0 FOR ONE VIOLATION OF RELIABILITY STANDARDS. (1) REGISTERED ENTITY’S COMPLIANCE HISTORY

PREVIOUSLY FILED VIOLATIONS OF ANY OF THE INSTANT RELIABILITY STANDARD(S) OR REQUIREMENT(S) THEREUNDER YES NO LIST VIOLATIONS AND STATUS

Attachment a

Dynegy Arlington Valley, LLC Page 6 of 10

ADDITIONAL COMMENTS CECD performs the Balancing Authority requirements for other registered entities (listed below) with violations of PER-002-0 R3/3.1. A Notice of Confirmed Violation (NOCV) covering a violation of PER-002-0 R3.1 for City of North Little Rock, AR (NCR01201) in the SERC Region (NOC-037) was filed with FERC under NP08-37-000 on June 6, 2008. On July 3, 2008, FERC issued an order stating it would not engage in further review of the Notice of Penalty. Five separate NOCV’s each covering a violation of PER-002-0 R3.1 for Batesville Balancing Authority (NCR01179), City of Conway, AR (NCR01198), City of Ruston, LA (NCR01203), City of West Memphis, AR (NCR01204) and Union Power Partners, LLC (NCR01355) designated as NOC-036, NOC-038, NOC-039, NOC-040 and NOC-041, respectively, were filed with FERC under NP09-12-000, NP09-10-000, NP09-11-000, NP09-14-000 and NP09-13-000, respectively, on January 21, 2009. Each of the five entities is registered in the SERC Region. On February 19, 2009, FERC issued an order stating it would not engage in further review of the Notices of Penalty. On October 14, 2009, NERC submitted an Omnibus filing under NP10-2-000 which addressed violations for certain registered entities including a violation of PER-002-0 R3, among others, for New Harquahala Generating Company, LLC (NCR05263) in the WECC Region. On November 13, 2009, FERC issued an order stating it would not engage in further review of the violations addressed in the Omnibus Notice of Penalty. A Settlement Agreement covering a violation of PER-002-0 R3 for Gila River Power (NCR05169) in the WECC Region (NOC-603) was filed with FERC under NP11-90-000 on January 31, 2011. On March 2, 2011, FERC issued an order stating it would not engage in further review of the Notice of Penalty. WECC did not consider these prior violations an aggravating factor in determining the penalty because they were simultaneous violations that were all discovered during the same October 2007 audit of CECD.

PREVIOUSLY FILED VIOLATIONS OF OTHER RELIABILITY STANDARD(S) OR REQUIREMENTS THEREUNDER YES NO

LIST VIOLATIONS AND STATUS

Attachment a

Dynegy Arlington Valley, LLC Page 7 of 10

ADDITIONAL COMMENTS A NOCV covering two violations of VAR-002-1 R2 for Dynegy, Inc.7

in the SERC Region (NCR00200) (NOC-10) was filed with FERC under NP09-16-000 on March 31, 2009. On April 30, 2009, FERC issued an order stating it would not engage in further review of the Notice of Penalty.

On October 14, 2009, NERC submitted an Omnibus filing under NP10-2-000 which addressed violations for certain registered entities including violations of PER-002-0 R1, R2 and R4, PER-003-0 R1 and PRC-001-1 R4 for New Harquahala Generating Company, LLC (NCR05263) and VAR-002-1 R2 for Dynegy, Inc. (NCR05136) in the WECC Region. On November 13, 2009, FERC issued an order stating it would not engage in further review of the violations addressed in the Omnibus Notice of Penalty.

A Settlement Agreement covering violations of FAC-008-1 R1 for Dynegy, Inc. in the ReliabilityFirst Corporation (ReliabilityFirst) Region (NCR00200) (NOC-432) was filed with FERC under NP10-98-000 on April 28, 2010. On May 28, 2010, FERC issued an order stating it would not engage in further review of the Notice of Penalty.

A Settlement Agreement covering violations of PRC-005-1 R2.1 for Dynegy, Inc. in the ReliabilityFirst Region (NCR00200) (NOC-564) filed with FERC under NP10-178-000 on September 30, 2010. On October 29, 2010, FERC issued an order stating it would not engage in further review of the Notice of Penalty.

A Settlement Agreement covering violations of PRC-005-1 R2.1 for Dynegy, Inc. in the SERC Region (NCR00200) (NOC-568) was filed with FERC under NP10-152-000 on July 30, 2010. On August 27, 2010, FERC issued an order stating it would not engage in further review of the Notice of Penalty.

A Settlement Agreement covering violations of VAR-002-1 R2 for Dynegy, Inc. in the WECC Region (NCR00200) (NOC-425) was filed with FERC under NP10-144-000 on July 30, 2010. On August 27, 2010, FERC issued an order stating it would not engage in further review of the Notice of Penalty.

A Settlement Agreement covering violations of PRC-005-1 R2.1 for Dynegy, Inc. in the WECC Region (NCR00200) (NOC-590) filed with FERC under NP10-183-000 on September 30, 2010. On October 29, 2010, FERC issued an order stating it would not engage in further review of the Notice of Penalty.

7 Dynegy, Inc. owned the Arlington Valley facility for the duration of the violation.

Attachment a

Dynegy Arlington Valley, LLC Page 8 of 10

The Settlement Agreement for Gila River Power discussed above (NOC-603) also covered a violation of IRO-STD-006-0 WR1 which was filed with FERC under NP11-90-000 on January 31, 2011. On March 2, 2011, FERC issued an order stating it would not engage in further review of the Notice of Penalty. WECC determined that the prior violations should not serve as a basis for aggravating the penalty because they involved standards that are not the same or similar to the instant standard. Moreover, there was nothing in the record to suggest that broader corporate issues were implicated.

(2) THE DEGREE AND QUALITY OF COOPERATION BY THE REGISTERED ENTITY (IF THE RESPONSE TO FULL COOPERATION IS “NO,” THE ABBREVIATED NOP FORM MAY NOT BE USED.)

FULL COOPERATION YES NO IF NO, EXPLAIN

(3) THE PRESENCE AND QUALITY OF THE REGISTERED ENTITY’S COMPLIANCE PROGRAM IS THERE A DOCUMENTED COMPLIANCE PROGRAM

YES NO UNDETERMINED EXPLAIN

WECC reviewed CECD’s compliance program at the Audit but did not consider it a factor in the penalty determination. WECC found that: the ICP is disseminated to those employees that have a direct responsibility for compliance with reliability standards; CECD has ICP oversight staff; ICP oversight staff is supervised at a high level in the organization; the ICP oversight staff has independent access to the CEO and/or board of directors; CECD operates the ICP such that it is independent of staff responsible for compliance with the Reliability Standards; the ICP is budgeted and staffed; the senior management reviews periodic reports of the ICP; the ICP includes training for employees that have a direct responsibility for compliance with reliability standards; the ICP includes internal auditing procedures; and it includes disciplinary action for employees involved in violations of the Reliability Standards, when applicable.

Attachment a

Dynegy Arlington Valley, LLC Page 9 of 10

EXPLAIN SENIOR MANAGEMENT’S ROLE AND INVOLVEMENT WITH RESPECT TO THE REGISTERED ENTITY’S COMPLIANCE PROGRAM, INCLUDING WHETHER SENIOR MANAGEMENT TAKES ACTIONS THAT SUPPORT THE COMPLIANCE PROGRAM, SUCH AS TRAINING, COMPLIANCE AS A FACTOR IN EMPLOYEE EVALUATIONS, OR OTHERWISE.

See above. (4) ANY ATTEMPT BY THE REGISTERED ENTITY TO CONCEAL THE VIOLATION(S) OR INFORMATION NEEDED TO REVIEW, EVALUATE OR INVESTIGATE THE VIOLATION.

YES NO IF YES, EXPLAIN (5) ANY EVIDENCE THE VIOLATION(S) WERE INTENTIONAL (IF THE RESPONSE IS “YES,” THE ABBREVIATED NOP FORM MAY NOT BE USED.)

YES NO IF YES, EXPLAIN (6) ANY OTHER MITIGATING FACTORS FOR CONSIDERATION

YES NO IF YES, EXPLAIN (7) ANY OTHER AGGRAVATING FACTORS FOR CONSIDERATION

YES NO IF YES, EXPLAIN (8) ANY OTHER EXTENUATING CIRCUMSTANCES

YES NO IF YES, EXPLAIN

WECC determined that the penalty was appropriate because the violation was discovered in October 2007 in the initial period of transition to mandatory Reliability Standards during which time FERC authorized enhanced discretion regarding penalties.

Attachment a

Dynegy Arlington Valley, LLC Page 10 of 10

EXHIBITS:

SOURCE DOCUMENT Regional Determination of Alleged Violation Summary discovery date October 24, 2007 MITIGATION PLAN Mitigation Plan Submittal Form dated February 27, 2009 CERTIFICATION BY REGISTERED ENTITY CONTAINED THEREIN

See Mitigation Plan

VERIFICATION BY REGIONAL ENTITY Verification of Completion dated April 8, 2009 OTHER RELEVANT INFORMATION:

NOTICE OF ALLEGED VIOLATION AND PROPOSED PENALTY OR SANCTION ISSUED DATE: 2/3/098

OR N/A

SETTLEMENT DISCUSSIONS COMMENCED DATE: OR N/A NOTICE OF CONFIRMED VIOLATION ISSUED DATE: 9/2/10 OR N/A SUPPLEMENTAL RECORD INFORMATION DATE(S) OR N/A REGISTERED ENTITY RESPONSE CONTESTED FINDINGS PENALTY BOTH DID NOT CONTEST HEARING REQUESTED YES NO DATE OUTCOME APPEAL REQUESTED

8 The Regional Determination Summary document incorrectly states that the Notice of Alleged Violation and Proposed Penalty or Sanction was issued on January 30, 2009.

Attachment b

DEAA’s Responses to the Notice of Alleged Violation and Proposed Penalty or Sanction dated February 27,

2009 and April 6, 2009

o VIA Email

Constellation Energy Control and Dispatch, LLC A Member of Ctmstell(uioll Energy 500 D(l ll{l.~ SIre!!' , IIm iSlotl , Te.\"fIs 77{)02

February 27, 2009

Mark W. Maher Chief Operating Officer Western Electricity Coordinating Council 615 Arapeen Drive Suite 210 Salt Lake City, UT 84 I 08

RE: Response 1O Notice of Alleged Violation and Proposed Penalty or Sanction NERC Violation #: WECC200700439 WECC Violation #: DEAA WECC2007447

Mr. Maher,

Constellation Energy Control and Dispatch, LLC (CECD), as the Balancing Authority services provider for Dynegy Arlington Valley. LLC (DEAA), received a Notice of Alleged Violation and Proposed Penalty on February 3, 2009. As described in the notice WECC must be notified within 30 days of this date of DEAA 's decision to: (Option I) not contest the Alleged Violation or the recommended penalty or sanction, (Option 2) not contest the Alleged Violation yet contest the recommended penalty or sanction, or (Option 3) contest both the Alleged Violation and the recommended penalty or sanction.

DEAA is choosing Option 3 at this time and contesting the Alleged Violation with PER-002-0, Requirement 3. Attached to this letter is an overview of the facts that related to the audit and possible violation ofPER-002-0, R 3.1. Of specific concern is that WECC's NoAV reflects a violation of all of PER-002 Requirement 3, however the audit team and SERC's enforcement efforts on this matter were specific to Requirement 3. 1.

DEAA i:s alsu submilling a Mitigation Plan that was implemented and completed on Apri l 28, 2008, for PER-002-0, Requirement 3. I.

If you have any questions or concerns please feel free to contact myself or CJ Ingersoll.

o Constellation Energy Control and Dispatch, LLC ...r Member of CmlSlella/ion Energy SOO 0(//111.\' Street, 1I0/lsl0II , Te.m s 77002

CEeD is the Balancing Authority Services Provider for multiple Balancing Authorities located in both WEee and SERe regions. As a result, the Balancing Authority audits scheduled for each of the Registered Entities were combined into one joint audit by WEee and SERe at the CEeD control center in Houston, Texas. The audit took place between October 23, 2007 and October 25, 2007, with both WECC and SERC audit teams' present and jointly reviewing evidence of compliance. The audit team provided an exit briefing on the last day of the audit and a summary of the findings that would be included in the report. The audit team detennined compliance with all the Reliability Standards reviewed during the audit with the exception ofPER-002-0, Requirement 3. t [A training program with a set of training objectives that are defined. based on NERe and Regional Reliability Organization standards, entity operating procedures. and applicable regulatDlY requirements. These objectives shall reference the knowledge and competencies needed to apply those standard, procedures, and requirements to normal. emergency, and restoration conditions/or the Transmission Operator and Balancing Authority operating positions.] During the exit briefing the audit team indicated that they would provide information about lhe possible violation ofPER-002, RJ. I to their respective Regional Enforcement Divisions. CECD was infonned that the individual Compliance Enforcement Divisions at SERC and WECC would independently evaluate the evidence relating to the Balancing Authorities located within their jurisdiction to detennine if a Notice of AJ leged Violation should be issued.

The SERC region issued Notices of Alleged Violation for PER-002-0, RJ . l on December 29. 2007. for the Balancing Authorities within SERC's enforcement jurisdiction. On January 28, 2008, a letter was issued by CECD on behalf of the Balancing Authority responding to the Notice of Alleged Violation. Neither the violation of PER-002. RJ.l, nor the penalty amount of zero dollars ($0.00) was disputed. On the same day a mitigation plan was submitted to SERC that would modify CECD's training program to establish compliance with PER-002, R3.I. Specifical ly, CECD sent CECD personnel to Train the Trainer courses and modified training documentation to include the necessary training objectives. The Train the Trainer courses were completed by November 29, 2007. The training program was reviewed for modification by February 28, 2008. The training objectives were included in the training program on April 25, 2008. Finally, the M.itigation Plan and evidence of completion were provided to SERC on April 28, 2008.

The M.itigation of the PER-D02, RJ.l violation for the Balancing Authorities service by CECD, including any possible violations by the WECC Balancing Authorities, was completed on April 28, 2008. NERC has approved the mitigation plans and a Notice of Penalty has been filed at FERC for the Balancing Authorities in SERC, as this was the only Region that has determined there was a sufficient basis for initialing a fonnal enforcement process. The infonnation is summarized below.

Entity

Constellation Energy Control and Dispatch, LLC A Mcmher of Ctm."Ilelllllitllt El1ergy 500 Dill/tis Stree" H OI/SIOII, Tex lls 77002

Date Notice of Penalty Filed with FERC

City of West Memphis 01 /21/09 Union Power Partners 01/21109 Batesville 01 /21/09 City of Ruston 01/21 /09 City of Conway 0112 1/09 City of Benton 06/06/08 City of North Little Rock 06/06108

Penalty Filing ID

$0 NP09-14-000 $0 NP09-13-000 $0 NP09-12-000 $0 NP09-11-000 $0 NP09-10-000 $0 NP08-36-000 $0 NP08-37-000

WECC issued a Notice of Alleged Violation of PER-002, R3 DEAA on February 3, 2009.

Constellation Energy Control and Dispatch, LLC A Member 0fColIs/ellttti",t Ellergy 5()(J Dal/tU' S treet. HtUlJ(/JII, T /!..\"tI,\· 77001

VIA Email and WECC Portal

April 6, 2009

Mark W. Maher Chief Operating Officer Western Electricity Coordinating Council 6 15 Arapeen Drive Suite 210 Salt Lake City, UT 841 08

RE: Response to Notice of Alleged Violation and Proposed Penalty or Sanction NERC Violation #: WECC200700439 WECC Violation #: DEAA WECC2007447

Mr. Maher,

Constellation Energy Control and Dispatch, LLC (CECD), as the Balancing Authority services provider for Dynegy Arlington Valley, LLC (DEAA), received a Notice of Alleged Violation and Proposed Penalty (NoAV) on February 3, 2009. In response to the NoA V, DEAA contested the Alleged Violation and the recommended penalty or sanction as a result of concerns with the Alleged Violation reflecting a violation for Requirement 3 instead of the specific Requirement, R3.I . DEAA also submitted the Mitigation Plan that was implemented and completed on April 28, 2008, for PER-002-0, Requirement 3. 1, as part of the enforcement actions undertaken by the SERC Regional Entity for this same matter.

In subsequent discussions with WECC, WECC agreed to supplement the record to clearly indicate that the violation related to Requirement 3. 1 to alleviate DEAA's concerns, and as a result DEAA hereby agrees to accept the violation and proposed penalty of zero dollars.

If you have any questions or concerns please feel free to contact myself or CJ Ingersoll.

~" Vice President CECD

Attachment c

WECC’s Regional Determination of Alleged Violation Summary for PER-002-0 R3 with discovery date

October 24, 2007

Non-Public and CONFIDENTIAL

Page 1 of 2 Regional Determination of Alleged Violation Dated: April 13, 2009, Version 1

Regional Determination of Alleged Violation Summary Region: WECC Registered Entity: Arlington Valley, LLC NERC Registry ID: NCR03049 NERC Violation ID: WECC200700439 Date Alleged Violation reported to or discovered by WECC: 10/24/2007 Method of Discovery: Compliance Audit Standard: PER-002-0 Requirement: 3 Regional description of Alleged Violation: No objectives are identified as part of the operator training program. Repeat Alleged Violation: . Yes X No If Yes, NERC Violation ID:

NAVAPS Issue Date: 01/30/2009 Violation Risk Factor: HIGH Violation Severity Level (VSL): LNC - Level 2 Regional Determination of VSL: Regional Determination of Impact to BPS: Regional Detailed Description of Impact to BPS: Minimal Begin Date of Alleged Violation: 10/24/2007 Time of Alleged Violation: End Date of Alleged Violation: Mitigation Plan Submittal Date: 02/27/2009 Mitigation Plan Target Completion Date: 04/28/2008 Registered Entity Certification of Closure Date: 02/27/2009 Mitigation Plan Actual Completion Date: 04/28/2008 Additional Comments:

For Public Release - March 30, 2011

Non-Public and CONFIDENTIAL

Page 1 of 2 Regional Determination of Alleged Violation Dated: April 13, 2009, Version 1

WECC Contact:

Name: Chris Luras Title: Manager of Enforcement Phone Number: 801-582-0353 Email: [email protected]

For Public Release - March 30, 2011

Attachment d

DEAA’s Mitigation Plan and Certification of Mitigation Plan Completion therein submitted

February 27, 2009

NERC I'OORTbI A ME R l e" ", ELEC:TRIt: RE1.I A I3ILITV CORPORAT ION

Mitigation Plan Submittal Form New I;><:l or Revised 0

Date this Mitigation Plan is being submitted : 02/27/09

If this Mitigation Plan has already been completed: • Check th is box I;><:l • Provide the Date of Completion of the Mitigation Plan: 04/28/08 • Evidence supporting full compliance must be submitted along with this

Mitigation Plan Submittal Form

Section A: Compliance Notices & Mitigation Plan Reguirements

A.1 Notices and requirements applicable to Mitigation Plans and this Submittal Form are set forth in "Attachment A - Compliance Notices & Mitigation Plan Requirements" to this form. Review Attachment A and check this box I;><:l to indicate that you have reviewed and understand the information provided therein . This Submittal Form and the Mitigation Plan submitted herein are incomplete and cannot be accepted unless the box is checked.

Section B: Registered Entity Information

8.1 Identify you r organization:

Registered Entity Name: Dynegy Arlington Valley, LLC Registered Entity Address: Two Tower Center, 11th Floor, East Brunswick, NJ 08816 NERC Compliance Registry ID: NCR05135

8.2 Identify the individual in your organization who will be the Entity Contact regarding this Mitigation Plan . Please see Section 6.2 of the WECC Compliance Monitoring and Enforcement Program (CMEP) for a description of the qualifications requi red of the Entity Contact.'

Name: CJ Ingersoll

I A copy of the W ECC CMEP is posted on W ECC's website at http://www.wecc.bizldocu ments/li brary/complia neelman ualsJ Att%20A %20-%20WECC%20CMEP.pdf. Registered Entities are responsible for following all applicable WECC CMEP procedures. W ECC strongly recommends that registered entities become familiar with the WECC CMEP and its requirements, as they may be amended from time to time.

Rev. 3/20108, v2

FOR PUBLIC RELEASE - MARCH 30, 2011

Westem Electricity Coordinating Council

Title: Vice President Email: Phone:

NERC NORTH "Mf~ICAN ELEC T R IC RELI"IJILITV COR ""ORATION

Section C: Identity of Alleged or Confirmed Reliability Standard Violations Associated with this Mitigation Plan

This Mitigation Plan is associated with the alleged or confimned violation(s) of the reliability standard/requirements listed below:

C.1 Standard: PER-002-0 [Identify by Standard Acronym (e.g. FAC-001-1)]

C.2 Requirement(s) violated and vio lation dates: [Enter infonnation in the foJ/owing Table)

NERC Violation WECC Violation 10 # Requirement Violation 10# (i f known] Violated Risk

[if known] (e.g. R3) Factor

WECC200700439 OEM WECC2007447 3. 1 Medium

Alleged or Method of confirmed Detection Violation (e.g. audit,

Date(1 self-report, (MM/OOIYY) investigation)

6118/07 Audit

(.) Note: The Alleged or Confirmed Violation Date shall be: (i) the date the violation occurred; (ii) the date that the violation was self-reported ; or (iii) the date upon which WECC has deemed the violation to have occurred. Please contact WECC if you have questions regarding which date to use .

C.3 Identify the cause of the alleged or confimned vio[ation(s) identified above:

The documentation on the Operator Training Program needed to capture more detailed objectives. [Provide your response here; additional detailed information may be provided as an attachment as necessary)

C.4 [Optional] Provide any relevant additional information regarding the alleged or confirmed violations associated with this Mitigation Plan :

Rev. 3/20/08, v2

FOR PUBLIC RELEASE - MARCH 30, 2011

NERC NORTt1 A.MER1CI'N ~LECTRIC RELIABILITY CORPORAT ION

CECD is the Balancing Authority Services Provider for multiple Balancing Authorities located in both WEce and SERe regions. As a result, the Balancing Authority audits scheduled for each of the Registered Entities were combined into one joint audit by WECC and SERe at the CEeD control center in Houston, Texas. The audit took place between October 23, 2007 and October 25, 2007, with both WECC and SERe audit teams present and jointly reviewing evidence of compliance. The audit team provided an exit briefing on the last day of the audit and a summary of the findings that would be included in the report. The audit team detennined compliance with all the Reliability Standards reviewed during the audit with the exception of PER-002-0, Requirement 3. 1 [A training program with a set of training objectives that are defined. based on NERC and Regional Reliabi lity Organization standards, entity operating procedures, and applicable regulatory requirements. These objectives shall reference the knowledge and competencies needed to apply those standard, procedures, and requirements to normal, emergency, and restoration conditions for the Transmission Operator and Balancing Authority operating positions.] During the exit briefing the audit team indicated that they would provide information about the possible violation of PER-002, R3. 1 to their respective Regional Enforcement Divisions. CECD was infonned that the individual Compliance Enforcement Divisions at SERC and WECC would independent ly evaluate the evidence relating to the Balancing Authorities located within their jurisdiction to determine if a Notice of Alleged Violation should be issued.

The SERC region issued Notices of Alleged Violation on December 29, 2007, for the Balancing Authorities within SERC's enforcement jurisdiction. On January 28, 2008, a lener was issued by CECD on behalf of the Balancing Authority responding to the Notice of Alleged Violation. Neither the violation of PER-002, R3. 1, nor the penalty amount of zero dollars ($0.00) was di sputed. On the same day a mitigation plan was submitted to SERC that would modifY CECD's training program to establ ish compliance with PER-002, R3.1. Specifically, eEen sent CECD personnel to Train the Trainer courses and modified training documentation to include the necessary training objectives. The Train the Trainer courses were completed by November 29, 2007. The training program was reviewed for modification by February 28, 2008 . The training objectives were included in the training program on April 25, 2008. Finally, the Mitigation Plan and evidence of completion were provided to SERC on April 28, 2008.

The Mitigation of the PER-002, RJ . I violation for the Balancing Authorities service by CECD, including any possible violations by the WECC Balancing Authorities, was completed on Apri l 28, 2008. NERC has approved the mitigation plans and a Notice of Penalty has been filed at FERC for the Balancing Authorities in SERC, as thi s was the only Region that has detennined there was a sufficient basis for initiating a formal enforcement process.

{Provide your response here; additional detailed information may be provided as an attachment as necessary]

Rev. 3/20/08, v2

FOR PUBLIC RELEASE - MARCH 30, 2011

Section 0: Details of Proposed Mitigation Plan

Mitigation Plan Contents

NERC N O RT!1 .... M ERIC ... '" EL ECT I'IIC R EL, AI1I ILIT V COr:lPOR .... T ION

0. 1 Identify and describe the action plan, including specific tasks and actions that your organization is proposing to undertake, or which it undertook if this Mitigation Plan has been completed, to correct the violations identified above in Part C.2 of this form :

The Balancing Authority sent personnel to Train the Trainer cources provided by SERe and is currently reviewing the training program and relevant documentation. In coordination with training subject-matter experts at SERe. the Balancing Authority worked to modify training docwnentation to include appropriate training objectives. The revised training objectives were included in the Balancing Authority Operating Guides and released to system operators for rev iew. The revised objectives and evidence of insertion in the training program were provided to SERe on Apriil 28, 2008. (Provide your response here; additional detailed information may be provided as an attachment as necessary]

Check this box [8] and proceed to Section E of this form if this Mitigation Plan, as set forth in Part 0.1, has already been completed; othelWise respond to Part 0.2, 0.3 and, optionally, Part 0.4, below.

Mitigation Plan Timeline and Milestones

0 .2 Provide the timetable for completion of the Mitigation Plan, including the completion date by which the Mitigation Plan will be fully implemented and the alleged or confirmed violations associated with th is Mitigation Plan corrected:

D.3 Enter Milestone Activities, with completion dates, that your organization is proposing for this Mtligation Plan:

Milestone Activity Proposed Completion Date' (milestones cannot be more than 3 months

aDart)

(. ) Note: Implementation milestones should be no more than three (3) months apart for Mitigation Plans with expected completion dates more than three (3) months from the date of submission.

Rev. 3/20/08, v2

FOR PUBLIC RELEASE - MARCH 30, 2011

NERC NORTH AMERICA N EL E C T f'lIC R ELI" I3 ILIT Y CORPOR"TION

As set forth in CMEP 6.6, adverse consequences could result from fai lure to complete, on a timely basis, all required actions in this Mitigation Plan, including implementation of milestones. A request for an extension of the completion date of any milestone or of the Mitigation Plan must be received by W ECC at least five (5) business days before the relevant milestone or completion date.

[Note: Provide your response here; additional detailed information may be provided as an attachment as necessary)

Additional Relevant Information (Optional)

0.4 If you have any relevant additional information that you wish to include regarding the Mitigation Plan , milestones, milestones dates and completion date proposed above you may include it here:

[Provide your response here: additional detailed information may be provided as an attachment as necessary1

Rev. 3/20108 , v2

FOR PUBLIC RELEASE - MARCH 30, 2011

Section E: Interim and Future Reliability Risk

NERC NORTH AMERIC:AN I;LI;C T RIC RELtA B 'LI T V C:OR~ORA"'ON

Check this box ~ and proceed and respond to Part E.2, below, if this Mitigation Plan, as set forth in Part 0 .1, has already been completed.

Abatement of Interim BPS Reliability Risk

E.1 While your organization is implementing the Mitigation Plan proposed in Part D of this form, the reliability of the Bulk Power System may remain at higher risk or be othenwise negatively impacted until the plan is successfully completed. To the extent they are known, reasonably suspected or anticipated: (i) identify any such risks or impacts; and (ii) discuss any actions that your organization is planning to take or is proposing as part of the Mitigation Plan to mitigate any increased risk to the reliability of the bulk power system while the Mitigation Plan is being implemented:

[Provide your response here; additional detaited information may be provided as an attachment as necessary1

Prevention of Future BPS Reliability Risk

E.2 Describe how successful completion of the Mitigation Plan as laid out in Part D of this form will prevent or minimize the probability that your organization will incur further violations of the same or similar reliability standards requirements in the future:

In working with subject matter experts in training CEeD has been able to created docmentation on training objectives that meets the expectations of an auditor revlelwng the training program. [Provide your response here; additional detailed information may be provided as an attachment as necessary)

E.3 Your organization may be taking or planning other action, beyond that listed in the Mitigation Plan, as proposed in Part D.1, to prevent or minimize the probability of incurring further violations of the same or similar standards requirements listed in Part C.2 , or of other reliability standards. If so, identify and describe any such action , including milestones and completion dates:

Rev. 3/20108, v2

FOR PUBLIC RELEASE - MARCH 30, 2011

NERC NO~TH A ME RICAN ELECTRlC I'lELIA(3ILIT Y CORPORATION

(Provide your response here; additional detailed information may be provided as an attachment as necessary)

Rev. 3/20/08, v2

FOR PUBLIC RELEASE - MARCH 30, 2011

Section F: Authorization

NERC NORTH .... M£RI!:A N ELEC T RIC R E LI .... S ILIT V C:OI'IPORAT IOH

An authorized individual must sign and date this Mitigation Plan Submittal Form. By doing so, this individual, on behalf of your organization:

a) Submits the Mitigation Plan, as laid out in Section 0 of this fomn , to WECC for acceptance by WECC and approval by NERC, and

b) If applicable, certifies that the Mitigation Plan, as laid out in Section 0 of this form, was completed (i) as laid out in Section 0 of this fomn and (ii) on or before the date provided as the 'Date of Completion of the Mitigation Plan' on this form, and

c) Acknowledges:

1. I am [Vice President) of [Constellation Energy Control and Dispatch).

2. I am an officer, employee, attorney or other person authorized to sign this Mitigation Plan on beha~ of [Oynegy Arlington Valley, LLC].

3. understand [Constellation Energy Control and ~ispatch) obligations to comply with Mitigation Plan requirements and WECC or ERO remedial action directives and I have reviewed the WECC and ERO documents related to these obligations, including, but not lim~ed to, the WECC CMEP and the NERC Rules of Procedure.

4. I have read and am familiar with the contents of the foregoing Mitigation Plan.

5. [Constellation Energy Control and Dispatch) agrees to be bound by, and comply with, the Mitigation Plan, including the timetable completion date, as approved by WECC and approved by NERC.

Authorized Signature: ;:::=-!i:::;:;i::::==C;:I./::::-:===C:: (Electronic si natu Ie: see CMEP Section 3.0)

Name (Print):JT Thomp on Title: Vice President Date: 2/27/09

Rev. 3/20/08, v2

FOR PUBLIC RELEASE - MARCH 30, 2011

NE

Section G: Comments and Additional Information

You may use this area to provide comments or any additional relevant information not previously addressed in this form .

[Provide your response here; additional detailed information may be provided as an attachment as necessary]

Section H: WECC Contact and Instructions for Submission

Please direct any questions regarding completion of this form to: Mike Wells, Sr. Compliance Engineer Email: [email protected] Phone: (801) 883-6884

For guidance on submitting this form, please refer to the "WECC Compliance Data Submittal Policy". This policy can be found on the Compliance Manuals website as Manual 2.12:

http ://www.wecc.bizlwrap.php?file=lwrap/Compliance/manuals.html

Rev. 3120108, v2

FOR PUBLIC RELEASE - MARCH 30, 2011

NERC NOR T H "MERICA'" fLfC T I'I'C RELIABILITV CORPORATION

Attachment A - Compliance Notices & Mitiqation Plan Requirements

I. Section 6.2 of the WECC CMEP sets forth the information that must be included in a Mitigation Plan. The Mitigation Plan must include:

(1) The Registered Entity's point of contact for the Mitigation Plan, who shall be a person (1) responsible for fi ling the Mitigation Plan, (ii) technically knowledgeable regarding the Mitigation Plan, and (iii) authorized and competent to respond to questions regarding the status of the Mitigation Plan. This person may be the Registered Entity's point of contact described in Section 2.0.

(2) The Alleged or Confirmed Violation(s) of Reliability Standard(s) the Mitigation Plan will correct.

(3) The cause of the Alleged or Confirmed Violation(s).

(4) The Registered Entity's action plan to correct the Alleged or Confirmed Violation(s).

(5) The Registered Entity's action plan to prevent recurrence of the Alleged or Confirmed violation(s) .

(6) The anticipated impact of the Mitigation Plan on the bulk power system re liability and an action plan to mitigate any increased risk to the reliability of the bulk power-system while the Mitigation Plan is being implemented.

(7) A timetable for completion of the Mitigation Plan including the completion date by which the Mitigation Plan will be fully implemented and the Alleged or Confirmed Violation(s) corrected.

(8) Implementation milestones no more than three (3) months apart for Mitigation Plans with expected completion dates more than three (3) months from the date of submission.

(9) Any other information deemed necessary or appropriate.

(10) The Mitigation Plan shall be signed by an officer, employee, attorney or other authorized representative of the Registered Entity, which if applicable, shall be the person that signed the Self-Certification or Self Reporting submittals.

II. This submittal form may be used to provide a required Mitigation Plan for review and approval by WECC and NERC.

Rev. 3/20108, v2

FOR PUBLIC RELEASE - MARCH 30, 2011

NERC N OJ'l TH .... ME R lc:: ... 1'I EL EC:T RIC: RELI A!3 IL I T V C OR P O RATION

Western ElectricityCoordinating Council III. The Mitigation Plan shall be submitted to the WECC and NERC as

confidential information in accordance with Section 9.3 of the WECC CMEP and Section 1500 of the NERC Rules of Procedure.

IV. This Mitigation Plan form may be used to address one or more related Alleged or Confirmed Violations of one Reliability Standard. A separate Mitigation Plan is required to address violations with respect to each additional Reliability Standard, as applicable.

V. If the Mitigation Plan is approved by WECC and NERC, a copy of the Mitigation Plan will be provided to the Federal Energy Regulatory Commission in accordance with applicable Commission rules, regulations and orders.

VI. Either WECC or NERC may reject a Mitigation Plan that it determines to be incomplete or inadequate. If the Mitigation Plan is rejected by either WECC or NERC, the Registered Entity will be notified and required to submit a revised Mitigation Plan.

VII. In accordance with Section 7.0 of the WECC CMEP, remedial action directives also may be issued as necessary to ensure reliability of the bulk power system.

Rev. 3/20108, v2

FOR PUBLIC RELEASE - MARCH 30, 2011

Attachment e

WECC’s Verification of Mitigation Plan Completion dated April 8, 2009

CONFIDENTIAL

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L • W W W . W E C C . B I Z 6 1 5 A R A P E E N D R I V E • S U I T E 2 1 0 • S A L T L A K E C I T Y • U T A H • 8 4 1 0 8 - 1 2 6 2 • P H 8 0 1 . 5 8 2 . 0 3 5 3 • F X 8 0 1 . 5 8 2 . 3 9 1 8

April 8, 2009 CJ Ingersoll Director Dynegy Arlington Valley, LLC One Allen Center,500 Dallas Street, Suite 3015 Houston, Texas 77002 NERC Registration ID: NCR05135 Subject: Certification of Completion Response Letter Dear CJ Ingersoll, The Western Electricity Coordinating Council (WECC) has received the Certification of Completion and supporting evidence on 2/27/2009 for Dynegy Arlington Valley, LLC DEAA’s alleged violation of Reliability Standard PER-002-0 and Requirement(s) 3. Listed below is the outcome of WECC’s official review. WECC has accepted the Certification of Completion for Requirement(s) 3 of the Reliability Standard PER-002-0 and have found these requirements to be fully mitigated. No further mitigation of these requirements will be required at this time. If you have any questions or concerns, please contact Mike Wells at [email protected]. Thank you for your assistance in this effort. Sincerely, Laura Scholl Laura Scholl Managing Director of Compliance LS:cm cc: Denise Ayers, DEAA VP, Constellation Energy Control and Dispatch Lisa Milanes, WECC Manager of Compliance Program Administration Mike Wells, WECC Senior Compliance Engineer

Laura SchollManaging Director of Compliance

801.819.7619 [email protected]

For Public Release - March 30, 2011

Attachment f

Notice of Filing

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

Dynegy Arlington Valley, LLC Docket No. NP11-___-000

NOTICE OF FILING March 30, 2011

Take notice that on March 30, 2011, the North American Electric Reliability

Corporation (NERC) filed a Notice of Penalty regarding Dynegy Arlington Valley, LLC in the Western Electricity Coordinating Council region.

Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. On or before the comment date, it is not necessary to serve motions to intervene or protests on persons other than the Applicant.

The Commission encourages electronic submission of protests and interventions

in lieu of paper using the “eFiling” link at http://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426.

This filing is accessible on-line at http://www.ferc.gov, using the “eLibrary” link and is available for review in the Commission’s Public Reference Room in Washington, D.C. There is an “eSubscription” link on the web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email [email protected], or call (866) 208-3676 (toll free). For TTY, call (202) 502-8659. Comment Date: [BLANK]

Kimberly D. Bose, Secretary