neutronic activation analysis for iter fusion reactor activation analysis for iter fusion reactor...
TRANSCRIPT
1
Neutronic Activation Analysis for ITER Fusion Reactor
Barbara Caiffi
100° Congresso Nazionale SIF
2
Outlook
Nuclear Fusion
International Thermonuclear Experimental Reactor (ITER)
Neutronics Computational Tools
Activation Analysis for ITER Reactor
3
1 g ( 21H,3
1H) 7*108 KJ
1 g 235U 8*107 KJ1 g petrol 40 KJ1 g coal 0.04 KJ
Nuclear Fusion
How much energy from...
D + T → 4He (3,5 MeV) + n (14,1 MeV)
Q=17.6 MeV
4
Fuel Availability on the Earth DEUTERIUM: natural abundance 0.0154 % of H → reserve in the oceans 2 1016 Kg
TRITIUM: β radioactive with 12 years half life, not available in large quantities
What is available?
LITHIUM:
from 1 kg of Lithium can be produced 0.43 kg of tritium Lithium reserve in Earth crust [1] → 1.3 10 9 Kg , TRITIUM: 5.6 10 8 Kg
Lithium reserve in the ocean [1] → 2.3 1014 Kg TRITIUM: 1014 Kg
1kg of D-T fuel produces 7* 108 MJ ≈ 200 GWh
Year World Energy Consumption: 145 Gwh[2]
[1]U.S. Geological Survey, 2012, commodity summaries 2011: U.S. Geological Survey[2]IEA, Annual Report 2013
Fusion could fulfil energy supply for 1.5 billion years
n+ 6Li → t + α + 4.8 MeVn+ 7Li → n + t + α -2.8 MeV
5
Iced DT pellet as a fuel Heating trough laser compression Works in pulse mode only
Inertial Confinement
How to Achieve Fusion
Magnetic Confinement
At temperature required for fusion to occur, plasma is completely ionized
Charge particles can be confined using magnetic field
Application of this concept are the Tokamak (like ITER)
6
TokamakRESULTING FIELD LINES
The plasma is a secondary winding of a transformer. The resultant toroidal plasma current provides for Ohmic
heating and generates the poloidal magnetic field Bθ
Poloidal coils generated an additional toroidal magnetic field B
φ
for greater stability
7
Economy of a TokamakIgnition : fusion charge products compensate for energy loss ( α in the case of DT plasma).
n τE>3T
f c , abQab<σ v>ab(T )4(1+δab)
−Abr√T=F (T )
Break-even : Fusion energy released must exceed the energy supplied.
E FUηIN E IN
=Q p=1
~2 1020 m-3s
~2 1019 m-3s
~25
n : ions density τ
E : confinement time
nτE
8
Where we are now?
Maior radius 6.2 mMinor radius 2 mVolume 830 m3
Plasma current 15 MAToroidal field 5.3 TDensity 10 20 m-3
Peak Temperature 2*108 KFusion Power 500 MWPlasma Burn 300-500 s
ITER parameters
9
500 MW of fusion power from 50 MW input power
MAIN GOAL: Q>10
ITER SITE: Cadarache (France)
TER TIMELINE:2008: Site levelling2010: Start Tokamak complex excavation2013: Start Tokamak complex construction2014: Arrival of first manufactured components2015: Begin tokamak assembly 2019: Complete tokamak assembly2020: First Plasma2027: First D-T Operation
ITER Project
CADARACHE
10
ITER Machine
28 m
30 m
11
28 m
30 m
ITER Machine
VACUUM VESSEL
12
28 m
30 m
ITER Machine
BLANKET
VACUUM VESSEL
13
28 m
30 m
ITER Machine
BLANKET
VACUUM VESSEL
DIVERTOR
14
28 m
30 m
ITER Machine
BLANKET
VACUUM VESSEL
DIVERTOR
POLOIDAL FIELD COILS
15
30 m
ITER Machine
BLANKET
VACUUM VESSEL
DIVERTOR
POLOIDAL FIELD COILS
TOROIDAL FIELD COILS
28 m
16
28 m
30 m
ITER Machine
BLANKET
VACUUM VESSEL
DIVERTOR
POLOIDAL FIELD COILS
TOROIDAL FIELD COILS
CENTRALSOLENOID
17
ITER Machine
28 m
30 m
VACUUM VESSEL
44 openings (“ports”):● 18 upper ports● 17 equatorials ports● 9 lower ports
18
Neutronics in Fusion Technology
induce radioactivity in the structural materials as well as in the coolant
damage materials through atom displacement, affecting mechanical and electric
properties.
produce hydrogen and helium, which make welding difficult if > 1 appm
heat superconducting coils reducing their effectiveness
Neutrons:
These effects must be studied!
DT Fusion Reaction
QDT
=17.6 MeVP
FUSION=500 MW
Φn=1014 n/cm2s
on the First WallNEUTRON14.1 MeV
80% of total energy
19
Shutdown Dose RateThe safety on a fusion plant requires a deep knowledge of the radiation map due to: “prompt” neutron and γ γ produced by activated material, in particular after the shutdown,
when maintenance is planned.
Three step procedure:
Monte Carlo calculation of the spectral neutron flux in the materials
Deterministic calculation of the radioactivity induced by neutrons as a function of irradiation or decay time
Monte Carlo γ transport and calculation of the dose rate in the region of interest
20
Rigorous 2 Steps (R2S) Method
INPUT CODE OUTPUT
●MCNP Input File (3D geometry, materials, cross section libraries, neutron source)
MCNP5 - N Neutron flux and spectra map
1) Monte Carlo neutron transport2) Deterministic activation calculation3) Monte Carlo γ transport
21
Rigorous 2 Steps (R2S) Method
Neutron flux n/cm2s
INPUT CODE OUTPUT
●MCNP Input File (3D geometry, materials, cross section libraries, neutron source)
MCNP5 - N Neutron flux and spectra map
VOXEL
Neutron spectrum
1) Monte Carlo neutron transport2) Deterministic activation calculation3) Monte Carlo γ transport
22
Rigorous 2 Steps (R2S) Method
INPUT CODE OUTPUT
●MCNP Input File (3D geometry, materials, cross section libraries, neutron source)
MCNP5 - N Neutron flux and spectra map
1) Monte Carlo neutron transport2) Deterministic activation calculation3) Monte Carlo γ transport
23
Rigorous 2 Steps (R2S) Method1) Monte Carlo neutron transport2) Deterministic activation calculation3) Monte Carlo γ transport
INPUT CODE OUTPUT
●MCNP Input File (3D geometry, materials, cross section libraries, neutron source)
MCNP5 - N Neutron flux and spectra map
●Material●Irradiation Scenario●Decay Time
FISPACTActivity map
γ source
24
Rigorous 2 Steps (R2S) Method1) Monte Carlo neutron transport2) Deterministic activation calculation3) Monte Carlo γ transport
INPUT CODE OUTPUT
●MCNP Input File (3D geometry, materials, cross section libraries, neutron source)
MCNP5 - N Neutron flux and spectra map
●Material●Irradiation Scenario●Decay Time
FISPACTActivity map
γ source
● MCNP Input File(3D geometry, materials, cross section libraries, γ source)● γ-to-dose factors
MCNP5 - P Shutdown dose rate map
25
Direct 1 Step (D1S) Method
Substitute Capture with activation-induced radiative decay. Neutron and decay γ transport treated in a single run. Special, ad hoc generated, “capture ”cross section data.
(n,γ prompt
) (n,γ activation decay
)
Cons: Ad hoc libraries should be produced for the activation dose relevant
nuclides, so an a priori decision has to be made. Each set of libraries is suitable just for 1 cooling interval.
26
Shutdown Dose Rate BenchmarksShutdown Dose Rate Benchmark at FNG[3]
Shutdown Dose Rate Benchmark at JET[4]
[3] P. Batistoni, M. Angelone, L. Petrizzi, M. Pillon, Benchmark Experiment for the Validation of Shut-Down Activation and Dose Rate in a Fusion Device, J. Nucl. Sci. Techn., Suppl. 2, p. 974-977 (2002) [4]PETRIZZI, L., et al, “Benchmarking of Monte Carlo based shutdown dose rate calculations for applications to JET”, ICRS-10, Madeira, 2004
Mock-up of ITER First Wall (Water & Steel IG)
Max diff < 25%
Agreement between a factor 2 -3
In JET benchmark agreement is worse because of the lack of information about the technical drawing ( geometry, impurity content)
Good experimantal vs calculated data agreement
27
ITER project goals:100 μSv/h 106 s after the shutdown in the Port Interspace Region [ ϕ~107 n/
(cm2s)] where maintenance is planned
4m
3m 2m
PORT PLUG
PORT INTERSPACE
BIOSHIELD
PIPE FORESTTBM FRAME
TBM 2
TBM 1
Shutdown Dose Rate in the ITER European TBM Port
28
European Test Blanket Module (TBM) Port
Modules for tritium production tests, containing: Breeder (lithium) Neutron multiplier to improve efficiency
n+ 6Li → t + α + 4.8 MeV
n+ 7Li → n + t + α -2.8 MeV
HCPB Breeder Unit
HCLLBreeder Unit
Inlet LiPb Pipe
Outlet LiPb Pipe
Helium cooled plates Helium cooled
plates Lithiated pebbles + beryllium pebbles
Helium Cooled Pebble Bed (HCPB): Breeder: lithiated ceramic pebbles (Li
4SiO
4 or Li
2TiO
3 )
Neutron Multiplier: beryllium pebbles
Helium Cooled Lithium Lead (HCLL):Breeder & Neutron Multiplier: PbLi eutectic (liquid at operating temperatures)
29
XZ SECTION
XY SECTION
B-Lite:
Official Model for ITER neutronic analysis Represents 40°sector of the reactor Contains only main components TBM Port represented as an homogenized water-
steel block Contains 21216 cells, 27920 surfaces, 26 materials Run 57 histories per second per core (109 histories
take 24h using 250 cores)6 m
8 m
CAD drawing of the TBM Port
ITER ModelMCNP Model
PORT PLUG
PORT INTERSPACE
30
ITER Model
900 1000 1100 1200 1300 1400 1500
PORT PLUG
PORTINTERSPACE
MESH1MESH2
y[cm]
TFC
TFC
BLANKET
VACUUM VESSEL
TBM1
PORT PLUG
PORTINTERSPACE
x[cm]
VERTICAL CUT
900 1000 1100 1200 1300 1400 1500
z[cm]
350
250
150
50
-50
-150
-250
MESH1MESH2TFC
TFC
HORIZONTAL CUT
300
200
100
0
-100
-200
-300
TBM2
BIOSHIELD
CRYOSTAT BIOSHIELD
CRYOSTAT
x[cm]
31
PORT PLUG
NEUTRON FLUX[n/cm2s]
x[cm]875 975 1075 1175
z[cm]
1E14
1E12
1E10
1E8
1E6
215
165
115
65
15
-35
-85
1014n/cm2s 106n/cm2s 108n/cm2s 107n/cm2s108n/cm2s
PORT INTERSPACE
Calculation performed on rectangular mesh imposed over the geometry (voxel dimensions 10*10*10 cm3)
Jobs run on 600 cores with MPI capability (ENEA cluster CRESCO) , time 24 h
109 histories required variance
reduction techniques (Weight Windows)
250
150
50
-50
-150
z[cm]
x[cm]
1.0E8
5.6E7
3.2E7
1.8E7
1.0E7
NEUTRON FLUX[n/cm2s]
1200 1300 1400 1500 1600
Neutron Flux Map
32
LIMIT
Shutdown Dose Rate [μSv/h] 12 days after the shutdown Shutdown Dose Rate [μSv/h]
Shutdown Dose Rate exceeds the limit imposed by the ITER project (100 μSv/h 12 days after the shutdown) close to cryostat and Pipe Forest structure.
Gaps and other experimental ports are the main responsible of the dose Optimization of the gaps and of the experimental port cross talk is currently under investigation
Shutdown Dose Rate in the Maintenance Area Model
Impurity content of Steel 316 IG :- Co60 0.05% wgt – 70% dose -Ta182 0.01% wgt -22% dose
ACTIVATION GAMMA SOURCE[γ/cm3s]
33
LIMIT
Shutdown Dose Rate [μSv/h] 12 days after the shutdown Shutdown Dose Rate [μSv/h]
Shutdown Dose Rate exceeds the limit imposed by the ITER project (100 μSv/h 12 days after the shutdown) close to cryostat and Pipe Forest structure.
Gaps and other experimental ports are the main responsible of the dose Optimization of the gaps and of the experimental port cross talk is currently under investigation
Shutdown Dose Rate in the Maintenance Area Model
ACTIVATION GAMMA SOURCE[γ/cm3s]
Impurity content of Steel 316 IG :- Co60 0.05% wgt – 70% dose -Ta182 0.01% wgt -22% dose
34
Shutdown Dose Rate [μSv/h]
LIMIT
12 days after the shutdown Shutdown Dose Rate [μSv/h]
Shutdown Dose Rate exceeds the limit imposed by the ITER project (100 μSv/h 12 days after the shutdown) close to cryostat and Pipe Forest structure.
Gaps and other experimental ports are the main responsible of the dose Optimization of the gaps and of the experimental port cross talk is currently under investigation
Shutdown Dose Rate in the Maintenance Area Model
ACTIVATION GAMMA SOURCE[γ/cm3s]
Impurity content of Steel 316 IG :- Co60 0.05% wgt – 70% dose -Ta182 0.01% wgt -22% dose
35
Shutdown Dose Rate in the Maintenance Area Model
Port PlugPort
Interspace
LOWERPORT
EQ.PORT
UPPERPORT
Shutdown Dose Rate exceeds the limit imposed by the ITER project (100 μSv/h 12 days after the shutdown) close to cryostat and Pipe Forest structure.
Gaps and other experimental ports are the main responsible of the dose Optimization of the gaps and of the experimental port cross talk is currently under investigation
Monte Carlo Model
x[cm]875 975 1075 1175
z[cm]1E14
1E12
1E10
1E8
1E6
215
165
115
65
15
-35
-85
1014n/cm2s 106n/cm2s 108n/cm2s
Neutron Flux in Port Plug
n/(cm2s)
36
Conclusions● The worldwide efforts in fusion technology aim at developing, in the long-term, power reactors which can contribute substantially to the supply of electricity.
●The construction and operation of the experimental fusion device ITER (”International Thermonuclear Experimental Reactor”) is an essential next step towards this long-term goal.
● The availability of qualified computational tools and nuclear data for the neutron transport simulation and the calculation of activation and material damage is a pre-requisite to enable reliable design calculations for these facilities.
● An automated R2S shutdown dose rate calculation tool was made and used to evaluate the actual design European TBM Port.
● From preliminary results, the shutdown dose rate in the region of maintenance is higher that 100 μSv/h. The main contribution is due to the cross-talk with the other experimental ports, which must be better described in the MCNP model and further investigated.
37
ThankYou!