2
Capital Program Status
Project Category Current Budget Project Amount Spent
or Committed to Date
Percent Spent or
Committed to Date
Widening Programs $ 2,900,000,000 $ 2,600,000,000 90%
Bridge Improvements 1,700,000,000 1,130,000,000 66%
Roadway Improvements 1,100,000,000 950,000,000 86%
Interchange Improvements 800,000,000 300,000,000 38%
Facilities Improvements 500,000,000 200,000,000 40%
Total: $ 7,000,000,000 $ 5,180,000,000 74%
-
Status of Ocean and Monmouth County Projects
3
Project Project Cost Project Status
GSP Widening $222,000,000 Complete to Interchange 52
GSP Mainline Shoulder Reconstruction 229,000,000 Scheduled for completion in June 2015
Drainage Improvements - MP 100 – 121 15,000,000 Construction completed
Interchange 105 Improvements 52,000,000 Phase I, to be completed in Spring 2015. Phase II to be awarded in February 2015
Interchange 109 Improvements 60,000,000 In Final Design
Bridge Improvements 38,500,000 On going
VMS Program MP 55 – 121 19,000,000 Completed in Monmouth & Ocean County
Static Sign Improvements 16,000,000 Construction to be awarded in November
Total: $651,500,000
-
GSP 35 to 80 Widening
• 3 Phases • MP 63 to 80
(Completed 2011)
• MP 48-63
(Under Construction)
• MP 30-48
(Begin late 2014
• 3 Counties • Atlantic
• Burlington
• Ocean
• Length: 50 Miles
GSP Widening Program
MP 30 to MP 80
4
-
GSP Widening in Ocean County: MP 57.8 to MP 64.5
5
-
• 2 Counties • Ocean
• Monmouth
• Length: 16 Miles
• 3 Mitigation Sites • Ocean (1 Site)
• Monmouth (2 Sites)
GSP Shoulder Reconstruction Program
MP 83.5 to MP 99.5
6
-
(2’-16’) (2’-16’) (2’-16’) (2’-16’)
GSP Shoulder Reconstruction: MP 83.5 to MP 99.5
7
-
8
GSP MP 83.5 to 88.5
-
9
GSP MP 83 to 100 Program Component
GSP Interchanges 88 and 89
-
GSP MP 90.5 to 93.5
10
-
11
GSP MP 93.5 to 99.5
-
Shoulder Reconstruction
MP 83 - 100
12
-
Wall Township taken from Allaire Rd
13
-
Toms River Township
Church Road Bridge
14
-
Manasquan River Bridge
15
-
Northbound Over Route 34
16
-
Brick Township MP 93.7 NB
17
-
Interchange 105
18
-
Interchange 105
19
-
Interchange 105
20
-
Interchange 105
21
-
Garden State Parkway
Interchange 105 Improvements
22
Project Costs
Contract P300.264 – Reconstruction of Interchange 105 at Hope Road and NJ Route 36
$11,000,000
Contract P300.271 – Improvements to Interchange 105 Wayside Road Connection
24,000,000
Right of Way 5,000,000
Utility Relocations 2,500,000
Mitigation & Reforestation 1,500,000
Engineering (Design, Permitting and Supervision) 10,000,000
Total: $54,000,000
-
Garden State Parkway
Interchange 105 Improvements
Schedule
23
ITEM DATE
Award Design Contract July 26, 2011
Notice to Proceed, Design August 2011
Complete Design Contract P300.264 (Hope Road) December 2013
Complete Design Contract P300.271 (Wayside Road) December 2014
Environmental Permit Approval July 2014
Award Construction Contract P300.264 February 2014
Complete Construction Contract P300.264 Summer 2015
Award Construction Contract P300.271 Spring 2015
Complete Construction Contract P300.271 Summer 2017
-
Garden State Parkway
Interchange 109 Improvements
24
-
Garden State Parkway
Interchange 109 Improvements
25
Project Costs
Replacement of Mainline Bridges and
Improvements to Newman Springs Road (CR 520) 43,000,000
Right of Way 3,000,000
Utility Relocations 3,000,000
Mitigation & Reforestation 2,000,000
Engineering (Design, Permitting and Supervision) 9,000,000
Total: $60,000,000
-
Schedule
Garden State Parkway
Interchange 109 Improvements
26
ITEM DATE
Award Design Contract June 2014
Notice to Proceed, Design October 2014
Environmental Permit Approval December 2015
Complete Design Contract July 2016
Award Construction Contract August 2016
Complete Construction November 2018
-