Inspection Date: October 23, 2017
New York State Department of TransportationGeneral Bridge Inspection Report
Structure Information
Postings
Number of Flags Issued New York State Inspection Overview
NBI Superstructure Condition:
NBI Deck Condition:
Federal NBI Ratings
NBI Substructure Condition:
NBI Channel Condition:
NBI Culvert Condition: N
7
6
7
5
Action Items
Inspector & Reviewer Signature Information
Political Unit:
WESTCHESTER
Number of Spans:
Date:
987DX
Jason Hager, P.E. 096817-1
Town of MOUNT PLEASANT
This Bridge is not a Ramp
Approximate Year Built:
Review Signature:
08 - POUGHKEEPSIE
Feature Carried:
General Type Main Span:
County:
7 - WEST
Region:
1
Robert Seeley, P.E. 076148-1
Not Posted
Not Posted
January 02, 2018
Inventoried Vertical Clearances:
SAW MILL RIVER
Code 88 - No Vehicles with R PermitsInventoried Posted Load:
Inspection Signature:
General Recommendation:
Date:
3 - Steel, 02 - Stringer/Multi-Beam or Girder
Feature Crossed:
1930
5
January 02, 2018
Orientation:
Primary Maintenance Responsibility:
Primary Owner:
Red PIA:
Red:
Yellow:
Safety PIA:
0
0
0
0
Vulnerability Reviews Recommended: NO
Further Investigation Requested: NO
Diving Inspection Requested: NO
New York State Department of Transportation
New York State Department of Transportation
Non-Structural Condition Observations noted: NO
BIN: 5500859
Report Printed: January 19, 2018 10:20:43 AM
Posted Load Matches Inventory: Yes On:
Under:
Processed by :
Page 1 of 23 Format Version 20171005
![Page 2: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/2.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
Overloads ObservedNo overload vehicles observed during this inspection.
Notes to Next InspectorThe BIN plate is on the right side of the begin abutment.2017 Access: Walking.There is soft sticky mud along the end abutment, use caution.
2017 - NONE
Improvements Observed
Additional Information
Snow FenceNone
Pedestrian Fence HeightNone
Bin Plate ConditionOK
Scour Critical Rating5 - Foundations stable for conditions; scour within limits
Page 2 of 23 Format Version 20171005
![Page 3: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/3.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
Field Notes
Staff Present During Inspection
Name Title Organization
SCOTT WALTS ATL LU
General Equipment Required for Inspection*
Access Type
13 - Walking
* For span specific equipment requirements refer to the Active Inventory's "Access Needs" tab in BDIS.
Detailed Time & Weather Conditions
Field Date Arrival Departure Temp (F) Weather Conditions
10/23/2017 12:30 PM 02:30 PM 70 MOSTLY CLOUDY
Inspection Times (hours)
10None
No
Time required for travel, inspection and report preparationLane closure usageRailroad flagging time
Page 3 of 23 Format Version 20171005
![Page 4: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/4.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
Element Assessment by Span
Element** Total Quantity Unit CS-1 CS-2 CS-3 CS-4 CS-5Span Number : 1
BA215 - Reinforced Concrete Abutment 107 ft 83 24 0
BA220 - Reinforced Concrete Pile/Cap Footing 107 ft 15 92
BA227 - Reinforced Concrete Pile 1 each 1
BA312 - Enclosed/Concealed Bearing 14 each 14 0
BA800 - Erosion or Scour 107 ft 27 6 74 0
BA850 - Backwall 74 ft 56 18 0
BA851 - Abutment Pedestal 14 each 9 5 0
EA215 - Reinforced Concrete Abutment 107 ft 85 22 0
EA220 - Reinforced Concrete Pile/Cap Footing 107 ft 107
EA227 - Reinforced Concrete Pile 1 each 1
EA312 - Enclosed/Concealed Bearing 14 each 14 0
EA800 - Erosion or Scour 107 ft 30 26 51 0
EA850 - Backwall 74 ft 51 23 0
EA851 - Abutment Pedestal 14 each 8 6 0
12 - Reinforced Concrete Deck 2116 ft2 1904 212 0
Element Assessment Summary Table
Element Total Quantity Unit CS-1 CS-2 CS-3 CS-4 CS-512 - Reinforced Concrete Deck 2116 ft2 1904 212 0
107 - Steel Open Girder/Beam 339 ft 259 80 0
215 - Reinforced Concrete Abutment 214 ft 168 46 0
220 - Reinforced Concrete Pile/Cap Footing 214 ft 15 199
227 - Reinforced Concrete Pile 2 each 2
312 - Enclosed/Concealed Bearing 28 each 28 0
330 - Metal Bridge Railing 87 ft 87 0
510 - Wearing Surfaces 1745 ft2 786 959 0
515 - Steel Protective Coating 2210 ft2 1810 320 80 0
800 - Erosion or Scour 214 ft 57 32 125 0
801 - Stream Hydraulics 1 each 1 0
810 - Sidewalk 200 ft2 190 10 0
850 - Backwall 148 ft 107 41 0
851 - Abutment Pedestal 28 each 17 11 0
Element Quantities
Page 4 of 23 Format Version 20171005
![Page 5: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/5.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
General Comments
Element** Total Quantity Unit CS-1 CS-2 CS-3 CS-4 CS-5510 - Wearing Surfaces 1745 ft2 786 959 0
107 - Steel Open Girder/Beam 339 ft 259 80 0
515 - Steel Protective Coating 1695 ft2 1295 320 80 0
330 - Metal Bridge Railing 87 ft 87 0
515 - Steel Protective Coating 515 ft2 515 0
801 - Stream Hydraulics 1 each 1 0
810 - Sidewalk 200 ft2 190 10 0
Inspection Notes
None
** Elements with a prefix designate the locations of BA-Begin Abutment, BW-Begin Wingwall, EA-End Abutment, EW-EndWingwall, CO-Culvert Outlet, and PR-Pier. No prefix generally indicates the element is part of the superstructure.
Element Condition Notes
TQ CS-1 CS-2 CS-3 CS-4 CS-5Span 1: 107 - Steel Open Girder/Beam-515 - Steel ProtectiveCoating 1695 1295 320 80 0 0
Referenced Photo(s): 4, 5, 6Condition State 3 Note
Referenced Sketch(es): None
2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately half of theirlength (photo 4). The paint is peeling and rust stained on the exposed bottom flanges of G2, G3, G4, and G9 (photos 5 and6).
TQ CS-1 CS-2 CS-3 CS-4 CS-5Span 1: BA800 - Erosion or Scour 107 27 6 74 0 0
Referenced Photo(s): 1, 2Condition State 3 Note
Referenced Sketch(es): 5
2017 – There is long standing degradation of the stream channel along the begin abutment stem. The footing is exposed atthe left and right sides of the begin abutment while there is soft siltation covering the footing under the center of the bridge.The maximum vertical exposure of the footing is approximately 2 feet near G2 (photos 1 and 2). See the attached ChannelProfile Along Begin Abutment sketch for more details. Readings are taken to the hard surface of the stream channel belowthe layer of siltation. No significant changes since the last inspection.
TQ CS-1 CS-2 CS-3 CS-4 CS-5Span 1: EA800 - Erosion or Scour 107 30 26 51 0 0
Referenced Photo(s): 3Condition State 3 Note
Referenced Sketch(es): 6
2017 – There is long standing degradation of the stream channel along the right 2/3 of the end abutment stem. There is softsiltation along the right side of the bridge which is covering the footing. The maximum vertical exposure of the footing isapproximately 2 feet near G10 (photo 3). See the attached Channel Profile Along End Abutment sketch for more details.Readings are taken to the hard surface of the stream channel below the layer of siltation. No significant changes since the
Page 5 of 23 Format Version 20171005
![Page 6: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/6.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
last inspection.
TQ CS-1 CS-2 CS-3 CS-4 CS-5Span 1: 801 - Stream Hydraulics 1 0 0 1 0 0
Referenced Photo(s): 3, 7, 8Condition State 3 Note
Referenced Sketch(es): 2
2017 – See attached Stream Hydraulics Defect History sketch (photos 3, 7, and 8).
Page 6 of 23 Format Version 20171005
![Page 7: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/7.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
17_01_Begin Abutment Footing at Left.JPGPhoto Number: 1 Photo Filename:
Attachment Description:Begin Abutment Footing atLeft
17_02_Right Corner of Begin Abutment.JPGPhoto Number: 2 Photo Filename:
Attachment Description:Right Corner of BeginAbutment
Inspection Photographs
Page 7 of 23 Format Version 20171005
![Page 8: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/8.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
17_03_Waterway Opening from End Right.Photo Number: 3 Photo Filename:
Attachment Description:Waterway Opening fromEnd Right
17_04_Underside of G1 from Begin.JPGPhoto Number: 4 Photo Filename:
Attachment Description:Underside of G1 from Begin
Page 8 of 23 Format Version 20171005
![Page 9: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/9.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
17_05_G2 G3 and G4 from Begin.JPGPhoto Number: 5 Photo Filename:
Attachment Description:G2 G3 and G4 from Begin
17_06_G9 from Begin.JPGPhoto Number: 6 Photo Filename:
Attachment Description:G9 from Begin
Page 9 of 23 Format Version 20171005
![Page 10: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/10.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
17_07_Left Stream Channel from Bridge.JPGPhoto Number: 7 Photo Filename:
Attachment Description:Left Stream Channel fromBridge
17_08_End Right Stream Bank.JPGPhoto Number: 8 Photo Filename:
Attachment Description:End Right Stream Bank
Page 10 of 23 Format Version 20171005
![Page 11: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/11.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
5500859 1 17BD186 Photo Location Plan.jpgSketch Filename:1Sketch Number:
Sketch Description: Photo Location Plan
Inspection Sketches
Page 11 of 23 Format Version 20171005
![Page 12: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/12.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
5500859 17 Stream Hydraulics Defect History.jpgSketch Filename:2Sketch Number:
Sketch Description: Stream Hydraulics Defect History
Page 12 of 23 Format Version 20171005
![Page 13: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/13.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
5500859 17BD226 Channel Cross-Section Readings.jpgSketch Filename:3Sketch Number:
Sketch Description: Channel Cross-Section Readings
Page 13 of 23 Format Version 20171005
![Page 14: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/14.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
5500859 17BD227 Channel Cross-Sections Along Fascias.jpgSketch Filename:4Sketch Number:
Sketch Description: Channel Cross-Sections Along Fascias
Page 14 of 23 Format Version 20171005
![Page 15: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/15.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
5500859 17BD230 Channel Profile Along Begin Abutment.jpgSketch Filename:5Sketch Number:
Sketch Description: Channel Profile Along Begin Abutment
Page 15 of 23 Format Version 20171005
![Page 16: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/16.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
5500859 17BD230 Channel Profile Along End Abutment.jpgSketch Filename:6Sketch Number:
Sketch Description: Channel Profile Along End Abutment
Page 16 of 23 Format Version 20171005
![Page 17: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/17.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
5500859_LOCATION_MAP.JPG
5500859_QUAD_MAP.JPG
Standard Photographs
Page 17 of 23 Format Version 20171005
![Page 18: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/18.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
AbutmentBegin.JPG
AbutmentEnd.JPG
Page 18 of 23 Format Version 20171005
![Page 19: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/19.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
ApproachBegin.JPG
ApproachEnd.JPG
Page 19 of 23 Format Version 20171005
![Page 20: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/20.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
ElevationLeft.JPG
ElevationRight.JPG
Page 20 of 23 Format Version 20171005
![Page 21: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/21.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
FeatureCrossedLeft.JPG
FeatureCrossedRight.JPG
Page 21 of 23 Format Version 20171005
![Page 22: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/22.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
Framing.JPG
TopOfDeck.JPG
Page 22 of 23 Format Version 20171005
![Page 23: New York State Department of Transportation General Bridge ... · 10/23/2017 · 2017 – The concrete encasement on bottom of G1 and G14 is cracked with efflorescence for approximately](https://reader033.vdocument.in/reader033/viewer/2022060802/6086873538006379e0033a72/html5/thumbnails/23.jpg)
BIN: 5500859 Bridge Inspection ReportInspection Date: October 23, 2017
WingwallEndRight.JPG
Page 23 of 23 Format Version 20171005