U. NIFIED MULTI-PURPOSE ID SYSTEM (E.O. 420). UPDATES. National Economic and Development Authority. K ey Implementation Milestones. Activity. TCD. April 13, 2005. EO 420 issued Date of publication (Mla Times and Daily Tribune) 3. Effectivity of EO 420 - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: NIFIED MULTI-PURPOSE  ID SYSTEM (E.O. 420)

1

NIFIED MULTI-PURPOSE ID SYSTEM (E.O. 420) NIFIED MULTI-PURPOSE ID SYSTEM (E.O. 420)

UU

National Economic and Development Authority

UPDATESUPDATES

Page 2: NIFIED MULTI-PURPOSE  ID SYSTEM (E.O. 420)

2

1. EO 420 issued

2. Date of publication (Mla Times and Daily Tribune)

3. Effectivity of EO 420 (15 days from publication)

4. IRR issuance (within 60 days from effectivity

of EO 420)

Key Implementation MilestonesKey Implementation Milestones

Activity TCD

April 13, 2005

April 26, 2005

May 11, 2005

NLT July 12, 2005

Page 3: NIFIED MULTI-PURPOSE  ID SYSTEM (E.O. 420)

3

Key Implementation MilestonesKey Implementation Milestones

Activity TCD

5. CRN design (format, algorithm)

June 6, 2005

6. GSIS and SSS ID records preparation/clean-up for CRN assignment

June 30, 2005

7. NSO generates/assigns CRN to SSS and/or GSIS as pilot agencies

July 7, 2005

Page 4: NIFIED MULTI-PURPOSE  ID SYSTEM (E.O. 420)

4

Implementation StatusImplementation Status

1. E.O. 420 already published in 2 newspapers of general circulation

2. Draft guidelines implementing EO 420 now being prepared; draft outline as

presented by NSO already reviewed/approved by TWG last May 3, 2005

3. GSIS and SSS biometrics data matching to clean up members data bases already

arranged to jumpstart use of CRN

Page 5: NIFIED MULTI-PURPOSE  ID SYSTEM (E.O. 420)

5

Implementation StatusImplementation Status

4. Met with CSC chairman, DBM secretary and agreed to phase in CSC Personnel Information System (CSC-PIS) with EO 420 thru the use of CRN as a unique identifier for government personnel

5. Draft NEDA memo order creating a National Task Force to Implement the Unified ID System in Government (NTF-UIDS) sent to proposed members for review/consideration

Page 6: NIFIED MULTI-PURPOSE  ID SYSTEM (E.O. 420)

6

Implementation StatusImplementation Status

6. Prepared EO 420 Primer and published in NEDA Web portal/distributed to major newspapers

7. Created “Updates on EO 420” page in NEDA Web portal, which includes a copy of EO 420; the DG’s powerpoint presentation on the EO; copy of EO 420 primer; and latest updates/developments on the implementation of the EO

Page 7: NIFIED MULTI-PURPOSE  ID SYSTEM (E.O. 420)

7

Implementation StatusImplementation Status

Page 8: NIFIED MULTI-PURPOSE  ID SYSTEM (E.O. 420)

8

Page 9: NIFIED MULTI-PURPOSE  ID SYSTEM (E.O. 420)

9

Implementation StatusImplementation Status

8. Made exploratory talks with PhilHealth on the possible phasing in of the Unified ID System per EO 420, with the PhilHealth ID card system, including possible use of PhilHealth’s extensive network infrastructure

Page 10: NIFIED MULTI-PURPOSE  ID SYSTEM (E.O. 420)

10

Petitions Filed with the SCPetitions Filed with the SC

1. Two (2) complaints have been filed with the Supreme Court against E.O. 420:

(a) filed by the KMU and NAFLU-KMU received May 11, 2005 (b) filed by Bayan Muna, received May 24, 20052. Dir. Abrenilla, AD Reyes and Atty. Dacayo

met with the OSG; background documents/information, rationale, key features of EO 420 already supplied to the OSG.

Page 11: NIFIED MULTI-PURPOSE  ID SYSTEM (E.O. 420)

11

Status of Petitions Filed with the SCStatus of Petitions Filed with the SC

3. The SC is expected to consolidate the two complaints and issue an order requesting comments on the complaints

The SolGen will submit the government’s response 10 days after receipt of the SC order