no. 26/2011 - welcome to rdsordso.indianrailways.gov.in/works/uploads/file/quality... · ·...
TRANSCRIPT
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 1 of 30
QUALITY AUDIT REPORT ON
CORROSION REPAIRS OF COACHING STOCK
No. 26/2011
HUBLI WORKSHOP
SOUTH WESTERN RAILWAY
AUGUST-2011
QUALITY ASSURANCE (MECHANICAL) DIRECTORATE
RESEARCH DESIGNS & STANDARDS ORGANIZATION
MANAK NAGAR, LUCKNOW- 226011
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 2 of 30
QUALITY AUDIT REPORT ON CORROSION REPAIR OF
COACHING STOCK HUBLI WORKSHOP, S.W. RAILWAY
Introduction:
Quality audit of Hubli Workshop has been carried out by Quality Assurance
Directorate, Mumbai and its team on 4th and 5th August, 2011. The quality audit
was done in accordance with Coaching Maintenance Manual and Technical
pamphlet No. C-7602 Rev.2 after preparing the check list. Following officers and
Supervisors have accompanied audit team during the audit:
1. Shri A.P.Soni, WM/Coaching
2. Shri Bili Angadi, ACMT
3. Shri Wilson, SSE/Welding
4. Shri Subhan, SSE/C.Repairs
5. Shri Chaudhra Reddy, CI/BTC
Discussions were also held with CWM/UBLS and Dy.CME’R’/UBLS
Observations:
1. Latest version of the Corrosion Manual for ICF/RCF built BG coaches issued by RDSO i.e. C-7602 (Rev.2) which had been circulated vide RDSO/s letter no.MC/CRN/REH dated 4.3.11 was not available.
2. Documentation needs improvement, especially with regard to inspection, identification and traceability, coach history, gradation of welders, etc. System for
ensuring traceability with regard to the fitters/welders deputed in a particular coach needs to be established
3. A separate inspection wing (independent of the corrosion repair shop) needs to be
created and training given to inspection staff 4. No pre-inspection check sheet is prepared
5. Surface is not being cleaned up to bare metal and the manual system using scrappers is not very effective. Improvement required in scrapping, cleaning and painting of the portion over trolley and other difficult-to-access areas
6. Improvement required in the quality of fabrication of headstock assemblies with regard to reduction in weld spatter, alignment of buffer holes, painting with PCN
123, etc. 7. Final camber is not being recorded while replacing the entire head stock assembly 8. Proper staggering of joints of sole bar needs to be ensured in all cases.
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 3 of 30
9. Use of PCN 123 for all applications below waist level is being done only on a very limited scale.
10. In case a welder fails in refresher, SSE/Welding decides as to what job is to be assigned to him. For example, Shri Bepari (T.No. 4772) had failed in bead
welding, he was being utilizing for tack welding. It is suggested that such welders may be automatically re-booked for refresher.
11. Of the 236 welders, only 60 have been given refresher training based on module
No.MECH.06 vide Railway Bd’s guidelines (VolII, May’06). 12. Roof shower testing facility is not working. As only one crane is available in the
lifting bay, another standby crane should be planned. 13. In some of the RCF manufactured coaches following deficiencies were
reported.
i. Coach No. SWR 99150 ACCN, outer head-stock was not welded with
stanchion and there was a gap on NCV end south side.
ii. Coach No. KR SWR 01272 CN : FRP tissue was coming out, FRP had been
applied directly over ROZC primer, no bituminous layer was available.
iii. RCF has turn out coaches with open turn under and sandwiched trough floor
in which condition of members above the trough floor cannot be determined
without removal of compreg flooring.
iv. Camber is not being properly maintained, as informed by the workshop, this
is resulting in truck height of upto 700 mm observed (limit 686-691mm).
14. In some of the ICF manufactured coaches following deficiencies were reported.
i. ICF has turn out coached with closed turn under and raised trough floor, the
closed turn unders are getting corroded.
ii. Coach No.SWR 06714 SLR – FRP tissue applied directly over red oxide, no
bitumen available.
15. Areas requiring action by RDSO as reported by workshop.
i. The wear limit for head stock is specified as 4mm vide CAMTECH manual, the same limit is specified as 20% vide C-7602 Rev2, this issue needs
clarification ii. Approved sources of Class IV wire for MIG-MAG welding to be developed by
RDSO
iii. There have been excessive cases of corrosion of body side doors espacially in new coaches turned out by PU’s, design improvement in terms of increasing
the thickness of Z channel may be suggested
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 4 of 30
Quality Assurance Directorate (Mechanical), RDSO Lucknow Check Sheet for Quality Audit of Corrosion Repair of the Coaches during
POH attention at shop (Based on CAMTECH Maintenance Manual for BG coaches of ICF Design and
RDSO Technical pamphlet No. C-7602 / Rev 2) While doing the audit, ensure that the below mentioned activities are carried out as
specified in the maintenance manual / technical pamphlet. Wherever the activities are not performed correctly indicate the method adopted or the nature of non-
compliance.
S.
No.
Item Clause No. Remarks
1. General
1.1 Ensure that the coaches are given
POH at the specified intervals.
103
(Chg.Manu
al)
Yes, being done. The out turn
and extent of renewal of
items during corrosion repair
is as per Annexure E
1.2 Ensure that the coach body is lifted off
the bogies using two 25t cranes each
or by four lifting jacks of 15t each and
coach body is not lifted from one end
only.
105c, 105d
(Chg.Manu
al)
Coach body lifted from both
sides using a single 60T EOT
crane with two lifting tackles
moving in a transverse
direction, one set of jacks
also available
2. Inspection
2.1 Ensure that the entire under frame is
cleaned of dust, rust, scales etc. from
the underneath through turn under
holes.
105f
(Chg.Manu
al)
Yes, being done. However,
quality of scrapping needs
improvement.
2.2 Ensure that the portion, which gets
covered and becomes difficult to reach
after the coach is lowered, is painted
with one coat of anti-corrosive paint
before lowering the coach body.
105g
(Chg.Manu
al)
Yes, being done, however,
improvement is required.
2.3 The system exists to inspect and
repair of under frame members after
the coach body is lifted off the bogies
and placed on trestles.
202a
(Chg.Manu
al)
Yes, system exists.
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 5 of 30
2.4 Ensure that the under frame is
thoroughly inspected for locating cracked/bent/corroded members and the components like sole bar and
trough floor which are not visible are examined by tapping with a spiked
hammer.
Ensure that inspecting staff are competent and trained staff who have
thorough knowledge of integral coaches.
Adequate instruments such as spiked hammer, torch etc., should be provided to enable proper and
thorough inspection being carried out.
202c (i)
(Chg Manual)
Yes, being done.
No separate inspection wing
is available. The nominated staff of corrosion shop themselves carry out
inspection They are being paid an additional allowance
of 15% of basic pay
Yes, available.
2.5 Trough Floor: Examine visually from below for signs of corrosion
supplemented by tapping with a spiked hammer.
2.6.1 (C-7602
Rev2)
Yes, being done.
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 6 of 30
2.6 Inspection of Sole bars, body
pillars and turn under (when turn
under has elongated holes): The
sole bars, body pillars and turn under
in the bays under and adjoining
lavatories should be examined visually
from below the coach and through the
elongated holes in the turn under after
removing accumulated dirt and
cleaning the inside surfaces. A torch
light may be used to facilitate
inspection. The inside of the sole bar
above the trough floor, however,
cannot be visually inspected. If
incidence of corrosion is noticed in the
bottom half of the sole bar, the trough
floor should be cut to a width of
300mm and requisite length for
examining the inside top half. If
heavy corrosion is noticed, the side
wall should be cut to a height of
500mm from the bottom of the turn
under covering sufficient length and
all the exposed parts, after scrapping
and cleaning should then be examined
to determine the extent of corrosion.
2.6.2.1
(C-7602 Rev2),
202d Chg Manual)
Yes, being done
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 7 of 30
2.7 Inspection of Sole bars, body
pillars and turn under (when turn under does not have holes): Coaches without elongated holes in
the turn under, should be visually examined, supplemented by tapping
with spiked hammer on the bottom of the turn under as well as the lower half of the sole bar from inside. If
corrosion is suspected, a 100 mm dia hole in the bottom of turn under in
the suspected area should be cut without damaging the pillar, for examining the inside. If signs of
corrosion are noticed, side wall up to a height of 500mm from bottom of
turn under should be cut for thorough examination.
The elongated holes shall be provided in turn unders of all Non-AC coaches
similar to ICF drg. No. GS-1-4-009 & GS-1-4-011.
2.6.2.2 (C-
7602 Rev2)
Yes, being done
Turn unders that are changed
are provided with elongated holes of size slightly lesser
than the drawing.
100% turn under at least
upto the second lifting pad is
being changed during
refurbishing.
2.8 Sole bar, turn under and pillars
above the lifting pads: If signs of corrosion are noticed, the side wall sheet above the lifting pads
should be cut to a height of 500mm above the turn under and to a length
of half a meter on either side of the lifting pads and the structural members scraped, cleaned and
examined minutely to ascertain the extent of corrosion.
2.6.3 (C-
7602 Rev2)
Yes, being done
2.9 Pillars behind the sliding door
pockets of SLRs and Parcel Vans: The pockets for the sliding doors should be opened and the
accumulated dust dislodged and thoroughly cleaned.
2.6.5 (C-
7602 Rev2)
Yes, being done
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 8 of 30
2.10 Sole bars, pillars at door corners:
These members should be examined visually in the same manner as described at para 2.6.2. If corrosion
is noticed, the turn under to a width of half a metre from the door corner
should be cut and the accumulated dust dislodged. The structural members should be thoroughly
scraped, cleaned and examined carefully to assess the extent of
corrosion.
2.6.6 (C-
7602 Rev2)
Yes, being done
2.11 Battery box frames: The battery box frames should be visually examined for signs of corrosion.
2.7.12 (C-
7602 Rev2)
Yes, being done
2.12 Where the corrosion noticed is of a
very minor nature and has just started there is no need to renew
parts. The paints and rust should be thoroughly cleaned to reach the bare metal and the surface treated with
two coats of primer.
3.1.2 (C-
7602 Rev2)
Cleaning and scrapping
needs to be improved, the present manual system of
using scrappers is not very effective and cleaning up to bare metal not achieved.
2.13 Head Stock
2.13.
1
Head stock: The inner head stock, the
outer head stock and the stiffening immediately behind the buffers
including stiffening tubes and the junction of the sole bar at the head stock should be visually examined for
incidence of corrosion. After removing the buffer assembly, the head stock
should be carefully examined as corrosion has been primarily noticed at this location
2.6.4 (C-
7602 Rev2)
Yes, being done
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 9 of 30
2.14 Check list: After completion of
inspection of the entire coach shell, including members / components which may not have been listed in
para 2.6 and 2.7, the members affected by corrosion should be
distinctly marked to indicate the entire area affected by corrosion requiring repairs by replacement / modification
as the case may be. Appropriate items in the check list (RDSO drawing
No.-CG-10090 to CG-10093) should be filled in showing details of the member to be attended to for
corrosion repairs.
2.8 (C-
7602 Rev2)
No pre-inspection report
is being prepared,
inspection has been carried
out at the incoming shed
(without lifting) to decide
whether coach is to be
nominated for corrosion
repair.
3 Trough floor : Drill 19mm diameter holes in the valleys between two
isolating plates. Note: In the case of coaches fitted
with stainless steel trough floor, same procedure shall be followed for repair,
using austenitic stainless steel and special low heat input type electrodes (Refer to Annexure XIII of C-7602
Rev2). 13.
Annexure IV (C-7602
Rev2)
Yes, being done.
Yes, being done.
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 10 of 30
4 Head Stock
Instructions for replacement of Outer Head Stock during Corrosion Repairs:-
1. (i)Dismantle the buffers and check the
buffer base periphery for corrosion and the bolt holes for securing buffers for wear and oblongivity/cracks.
2. 3. (ii)If the depth of corrosion below the
buffer base is insignificant, the bolt holes are not worn out and no cracks have developed, clean the rust and
paint. 4.
5. (iii)Replace the buffer base. 6. 7. (iv)If corrosion is not significant and
bolt holes for securing of buffers are worn out / have become oblong, the
holes should be filed up by welding and re-drill if required.
8.
(v)If the corrosion is significant (i.e. loss in section is more than 20% of
original thickness) replace the buffer base.
1. 2.
3.
(vi)Carry out necessary stripping
4. (vii)Gas cut the head stock beam
along with the vestibule sill and other corroded components and the end wall
sheet, ensuring that no damage is caused to the anti-telescopic stanchions, sole bar and the stiffener
tube behind the buffers. 5.
Annexure V
(C-7602 Rev2)
Yes, being done.
Yes, being done.
Yes, being done. Buffer bolts are checked for
oblong, if required these are filled up with welding and re-
drilled.
Outer headstock is changed in case of 50% loss of section
thickness. This loss of thickness is checked visually.
Workshop has indented a UST gauge for measuring thickness of structural
members.
Yes, being done.
Yes, being done.
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 11 of 30
(viii)Grind sole bar flanges, stiffener
tubes behind buffer (center stiffener) and floor stiffener stanchions to match with the head stock.
6. (ix)Remove all existing paint of visible area by steel wire brush to bare metal
& prepare the visible surface for painting.
7.
8. (x)Prepare a new head stock beam arrangement complete with 8 mm
steel plate to drawing No ICF/STD-1-2-002. Before welding ensure correctness of the bolt hole size for
buffer bolts in headstock beam as well as stiffeners (Item 5,15, 6,16) are
welded in the head stock in position. 9.
10. (xi)Check for straightness of head
stock and over all alignment. 11.
12. (xii)Full weld the new head stock to the sole bar, stiffener tubes, anti telescopic stanchions, floor stiffeners
and guide angles. Weld a new vestibule sill over the headstock.
(xiii)Welding shall be done by ‘D’ class electrodes to IRS – M 28 (latest Rev.)
or class IV MIG/MAG welding wires as per specification IRS-M46 (latest Rev.)
13. 14. (xiv)Paint the head stock and all
visible members by high performance
anticorrosion epoxy coating RDSO specification No M & C
/PCN/123/2006.
Yes, being done.
Paint does not get
removed upto bare metal
as the manual system of
using scrappers is not
very effective
Yes, being done.
Yes, being done.
Yes, being done. However,
checked coach no. KRSWR 96496 GS NCV end south
side, outer headstock welding was non-uniform and flange welding was inadequate in
some localized areas
D class electrodes not used, refer Annexure B
High performance
anticorrosion epoxy coating
RDSO specification No M & C
/PCN/123/2006 is only being
used on trial basis in few
coaches. Two coats of ROZC
primer, two coats of
bituminous paint and finally
one coat of enamel paint is
applied on the new head
stock
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 12 of 30
4.1 Instructions for replacement of
Head Stock Assembly during Corrosion Repairs:-
1. (i)If the corrosion is significant i.e. loss
in thickness of section is more than 20% of original thickness at any
location on inner head stock and their other members, the assembly should be replaced.
2. 3.
4. 5. (ii)Measure the Camber of the coach
by “Piano Wire System”, and also
measure the height of the bottom flange of the head stock from the rail
level.
6.
7.
8. 9.
10. 11. 12.
13. 14.
15. (iii)Fabricate the complete head stock with 8mm outer beam (outer head stock) to RCF Drawing No CC12230 or
ICF drawing No. ICF/STD-1-2-001 on a welding manipulator for facilitating
down hand full welding or procure from trade.
(iv)Paint the head stock and all visible members by high performance anticorrosive epoxy coating to RDSO
specification M & C /PCN/123/2006.
Annexure VI
(C-7602
Rev2)
Headstock is changed in case
of 50% loss of section thickness. This loss of
thickness is checked visually. Workshop has indented a UST gauge for measuring
thickness of structural members
Camber is measured during refurbishment but not
recorded. Checked coach no. SWR
00804 WCB in which camber at coach bolster was 30mm and at headstock was 15mm
i.e. reverse camber.
In order to maintain the buffer height, without having to provide excess packing on
the trolley, the head stock assembly is fitted at a slightly
greater height as compared to the original reading
Yes, being done. Headstock assemblies are being
fabricated on manipulator. Inspected one such
assembly, some spatter was noticed and buffer holes in the outer beam and inner
plate were slightly offset, requiring rectification of the
holes through gas cutting High performance
anticorrosion epoxy coating RDSO specification No M &
C/PCN/123/2006 used only on trial basis in some coaches. Workshop was of
the view that the same cannot be implemented in all
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 13 of 30
(vi)Measure the final camber of the coach at the ends, if required re-
adjusts it accordingly. (vi)Welding shall be done by ‘D’ class
electrodes to IRS – M 28 (latest Rev.) or class IV MIG/MAG welding wires as
per specification IRS-M46 (latest Rev.)
coaches in view of fund
constraints. Two coats of ROZC primer, two coats of bituminous paint and finally
one coat of enamel paint is applied on the new head
stock assembly
Not measured.
D class electrodes not used, head stock assembly is
fabricated using CO2 welding, refer Annexure B
5 Sole Bar
5.1 Instructions for Corrosion repairs
of sole bars (Ref: RDSO drawing No.-CG-10101)
(i)After carrying out necessary stripping, cut off the sole bar and
grind the edges and prepare for a ‘V’ butt joint as shown in the sketch. (ii)Prepare a new sole bar piece of the
requisite length with edges suitable for a ‘V’ butt joint.
(iii)Tack weld the new sole bar piece at both ends.
(iv)Check and ensure straightness of the sole bar and overall alignment. (v)Tack weld cross bearers, if any, to
the new sole bar piece. (vi)Weld both ends of the sole bar
(vii)Weld cross bearers, support piece and trough floor. (viii)Weld new body pillar part,
sidewall sheet and turn under. These components also require replacement
whenever a part of sole bar is replaced for corrosion.
Notes:
Annexure II
(C-7602 Rev2)
V groove is formed through grinding on the web portion,
same is not formed on the flange portion. Same as above.
Yes, being done.
Yes, being done. Yes, being done.
Yes, being done.
Yes, being done. Yes, being done.
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 14 of 30
(i)If sole bar of length more than
2400mm requires replacement the same should be done in lengths not exceeding 2400mm at each stage.
(ii)If the sole bar at head stock location requires renewal, the sole bar
to a distance of 300mm towards body bolster from the inner headstock should also be replaced as shown in
detail ‘X’. (iii)If the coach under repair has its
under frame and body pillars up to waist rail level pasted with FRP tissue, the portions of the FRP tissue
damaged during corrosion repairs should be painted with RDSO
Specification M & C /PCN/123/2006 for high performance anticorrosion epoxy.
1 2
3 4 5
6 7
8 9
10 (iv)Whenever a portion of the sole bar is replaced during corrosion repairs, the bottom portion of sidewall pillars
at this location should also be simultaneously replaced.
11 (v)If sole bars are to be replaced on both sides of the body bolster the joints should be staggered and both
ends of the body bolster should not be attended to simultaneously.
Sole bars of lengths upto
2400mm are used
Yes, being done
High performance
anticorrosion epoxy coating
RDSO specification No. M &
C/PCN/123/2006 not used. In
case of new sole bars / body
pillars, two coats of ROZC
primer, two coats of
bituminous paint, FRP tissue
and finally one coat of
bituminous paint is applied.
In case of FRP tissue
damaged during repairs, one
coat of ROZC primer followed
by two coats of bitumen paint
are applied
Yes being done.
In coach no.SWR 93488 GS
noticed that the joints in sole bar between the head stock
and coach bolster had not been staggered
6 Outturn of the workshop and
renewal of structural members
Refer Annexure ‘E’
7 Tubular frame below lavatories
Examine visually the tubes and joints for incidence of corrosion.
202d (vii)
(Chg
Manual)
Yes, being done
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 15 of 30
Corroded tubes shall be replaced. If
corrosion is extreme, entire tubular frame should be replaced.
8 Repairs to draw and buffing gear support structure
Examine the draw gear support structure for corrosion, breakage, etc.
If the corrosion is light, scrap off the rust to bare metal, clean well and re-paint. If the corrosion is heavy,
replace the corroded angle or gusset plate with new support angle.
Draw gear and buffers stripped in each POH
Yes, being done, however scrapping up to bare
metal not ensured, one coat of enamel paint applied
Similarly examine the buffing gear
support structure for corrosion, breakage, etc. If the corrosion is light, scrap off the rust to bare metal, clean
well and re-paint. If the corrosion is heavy, replace the corroded angle or
stiffeners.
Yes, being done, however
scrapping up to bare
metal not ensured, one
coat of enamel paint applied
9 Repairs to centre pivots
Clean and examine the centre pivot
for bent, wear, cracks. Cracks shall be detected by doing chalk testing or
magnaflux dye penetrant test. If the centre pivot is found cracked or worn beyond repair, it should be replace.
Check the mounting bolts for loose or missing. Tighten and lock the bolts
with locking plate.
209 (Chg
Manual)
Chalk testing of Centre Pivot
is done. Locking plate is renewed 100%
10 Water tank support structure
Examine the water tank support
structure for corrosion, breakage, wear, etc. If the corrosion is light,
scrap off the rust to bare metal, clean well and re-paint. If the corrosion, breakage are beyond repair, replace
the corroded angle with new angle of suitable size as per the requirement.
Replace the rubber/wooden packing if perished or damaged.
210 (Chg
Manual)
Yes, being done. Proper
securing of the rubber/wooden packing over
the water tank suspension to be ensured
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 16 of 30
11 Material used
11.1 Refer Annexure A below 202e (i)
(Chg
Manual)
Clause 3.1,
Annexure
XII, XIII
(C-7602
Rev2)
Refer Annexure A
12 Tool and plant : Refer Annexure D
below
213 (Chg
Manual)
Refer Annexure D
13 Painting
13.1 Procedure detailed in Code of Practice
for painting of all metal coaches should be followed for cleaning and
painting of surfaces which are attended to during corrosion repairs. Effective supervision and inspection
should be introduced at all important stages of corrosion repairs.
3.5 (C-7602
Rev2) 212 (Chg
Manual)
In case of non-renewal of
components, manual scrapping is done followed by
application of spray paint. However, quality of scrapping / painting needs to be
improved. Inspected coach no. SWR 99286 CN
(refurbished). Bituminous paint had not been completely applied at the
bottom of the body pillars and some traces of ROZC
primer were visible. FRP tissue was coming off from the edges of the body pillars.
Scrapping of trough floor and under frame members
required improvement. Painting of coach bolster and portion above trolley required
to be improved.
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 17 of 30
The parts used for repairs should be
given proper surface treatment and applied with protective paint. Relatively thick sections such as sole
bars, cross bearers, etc. should preferably be grit blasted and
immediately thereafter given a protective coat of red oxide zinc chromate primer paint.
Grit blasting is not being
done at present. Order for grit blasting plant for components had been placed
(Contract No. COFMOW/IR/S-4029/P-11/OP-1860 dated
09.03.2011 awarded to M/s Surface International, F-32/ MIA, Phase-1, Basni,
Jodhpur-342005). However, due to lesser diameter of
table, some of these components shall have to be put diagonally.
For new sole bar and body
pillars, two coats of ROZC
primer, two coats of
bituminous paint, FRP tissue
final coat of bituminous paint
is being applied. For new
head stock, two coats of
ROZC primer, two coats of
bituminous paint and a final
coat of enamel paint is
applied. Rust converter is
being applied prior to
painting with ROZC primer.
Epoxy paint is being applied
on trial basis in few coaches.
13.2 Paints should be of the prescribed
quality conforming to the relevant
IS/IRS specification.
Paints used as per following
specn are used: ROZC primer
to IS2074/62, Bituminous
paint to IRS P 3096, Enamel
paint to IS8662, Rust
converter to Specn. No. IS
13515/ 1992
13.3 If the condition of the paint so
warrants or at every 5th POH of a
coach, the paint should be completely
removed to the bare metal and the
coach repainted as per paint schedule
A'. If the general condition of the paint
1201c
(Chg.Manu
al)
At present, ‘A’ schedule
painting not done. However,
a coach sand blasting booth
was under commissioning
after which it shall be
possible to carry out ‘A’
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 18 of 30
is good, follow paint schedule `C'. schedule painting
14 Welding
14.1 Corrosion repair is required to be
carried out to the best standard of workmanship. Trained and
experienced welders should be deputed for carrying out welding under careful supervision of qualified
welding supervisors. Suitable arrangements should be made for dry
storage of electrodes. Approved class electrodes suitable for vertical and overhead welding should only be used
for corrosion repairs. Reference may be made in this connection to the
approved brands of electrodes issued by RDSO (Refer Annexure B and C below).
3.5 (C-7602
Rev2) 212 (Chg
Manual)
Refer Annexure D
Though list of staff deputed
on a particular coach is maintained in the daily work distribution diary, summary
of the same is not available along with the coach details
for ease of traceability at a later date, also no record of whether the assigned work
completed satisfactorily maintained
Interacted with welder Shri P.Dandapani, he seemed to
be quite knowledgeable.
Of a total of 236 welders, approx. 25 welders are
deputed for corrosion repair. Of these, 3 welders are trained in CO2 welding.
Few good welders have been
identified who are deputed for head stock/sole bar, however, no documentary
evidence for the same was available
14.2 All repairs of cracks should be carried out by gouging and welding by
suitable electrodes.
212 (Chg
Manual)
V groove is formed through
gas cutting and grinding in
case of head stock (8mm), it
is formed by grinding alone in
case of sole bar. However, V
groove is not formed on the
flange portion of sole bar.
14.3 No electric welding on the coach should be carried out without proper
earthing from near the portion being welded on such that the return current has a distinct path (earth) which
should not be allowed through the
212 (Chg
Manual)
Proper earthing ensured
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 19 of 30
bogies and rails. In the absence of
such earthing, the return current passes through axle roller bearings causing pitting of rollers and bearing
failure in service.
14.4 Instruction for Welding of D Class electrodes and welder quality:-
1. While welding with D class electrodes following special care should be taken as these are basic
coated electrodes. a) The electrode must be preheated
to about 2500C for two hours or as recommended by electrode manufactures before use.
b) While welding with AC, the welding transformer must have minimum
OCV-80 volts for its smooth running.
c) If welding with DC equipment, the
electrode must be connected with positive terminal of equipment.
d) During positional welding, 4 mm or less diameter electrodes to be preferred for better control of
bead.
2. Welding shall be preferred in flat position; vertical up welding shall be used in place of vertical down.
3. For the periodical checking of
competency of welder the Railway should follow IS: 7310 (Part-1).
Welder approval test record may be kept as per appendix-A of this IS specification.
Refr : Annexure
XIII of C-7607 Rev2)
D class Electrodes not used due to problem of heavy smoke generation.
For pre-heating of electrodes,
both fixed and portable ovens are available.
Generally, AC plants not used, few transformer based
plants are being phased out. Yes, being done
During positional welding, 3.15mm electrodes used
Yes, being done
For periodical competency,
welders are tested for horizontal, vertical and flat
welds as per clause 5.2 (b) of IS: 7310 Part-I, 1974. The test pieces are prepared in
presence of JE/Welding (BTC) and CMS and are
tested for visual (spatter, undercut, fusion, etc.) and subsequently subject to bend
test. The issue of also testing the welders for vertical up
and flat welding as per clause 5.2(d) of IS: 7310 Part-I, 1974 (as such type of
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 20 of 30
4. RDSO specification No M & C
/PCN/123/2006 for high performance anticorrosion epoxy coating to be adopted in all under frame member
where Bituminous solution and Emulsion where painted earlier.
5. Stainless steel cutting shall be
done with arc cutting by two methods: i) By using class N1 electrodes as
per IRS M-28-Rev.2. ii) Portable plasma arc cutting
machine
welding is predominantly
used during corrosion repair) was discussed.
High performance
anticorrosion epoxy coating to RDSO specification No M & C /PCN/123/2006 is being
applied on trial basis in few coaches. However, mostly
ROZC primer, Bituminous paint, FRP tissue and Enamel paint is used.
Stainless steel cutting done
using class N1 electrodes as per IRS M-28-Rev.2.
14.5 Welding machines CO2 (Kempee make),
rectifier, inverter and transformer based machines are available.
Oil cooled transformer based
machines are being phased out.
CheckedC Checked welding plant Nos.A-0918 (inverter based)
& 120021235, though the gauges of current/voltage
were working, no calibration sticker was available. No gauges for voltage and
current available in plant no.120019069
14.6 Improvements made Workshop has recently introduced CO2 welding for
under frame. At present, approximately, 50% of CO2 welding and 50% of arc
welding is carried out.
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 21 of 30
15 Design improvements /
modifications :Several design improvements / modifications for eliminating / minimizing corrosion
have been issued by the RDSO/ICF/RCF from time to time.
Brief details of these together with the action to be taken by the Railways are given below:
3.2(C-7602
Rev2)
15.1 Stiffening of sole bars at
doorways including luggage compartment doorways of SLR
coaches.
3.2.1(C-
7602 Rev2)
Inside boxing of sole bar is
done, however, for some
SLR, outside boxing is done.
15.2 Trough Floor: 13mm diameter holes provided in the valleys of trough floor for drainage of condensation were
increased to 19mm so as to allow quicker drainage in coaches turned out
by ICF since 1968. This modification may be incorporated in all coaches, if not already done. Whenever trough
floor is laid painted with M & C /PCN/123/2006 for high performance
anticorrosion epoxy, these holes should be pierced through.
3.2.4(C-
7602 Rev2)
SS trough floor is used.
19mm holes are provided
through drilling. However,
checked coach No. SWR
93488 GS in which holes of
less diameter had been made
at some locations of the
trough floor through arc
welding using N1 electrode.
15.3 Stainless Steel trough floor: Presently, since 1998 ICF is turning
out all coaches also with austenitic stainless steel trough floor. Coaches
provided with austenitic stainless steel trough floor should be repaired with equivalent material using proper
electrodes as mentioned in Annexure– XIII.
3.2.5(C-
7602 Rev2)
S.S. Trough floor is used,
wherever replaced.
15.4 Body Side doors: Since 1976 body
side doors have been modified as shown at detail ‘X’ on RDSO drawing No. CG-10083 with completely open
bottom and a removable inside panel to facilitate inspection of the out side
panel. Body side door should be modified as indicated in ‘Annexure – IX’ if not already done.
3.2.7(C-
7602 Rev2)
Body side door repair is being
carried out as specified. Pivots are being checked and replaced with SS, if required.
However, screwed inside panels for facilitating
inspection not provided in some coaches (checked coach no. SWR 00723 SLR,
removable inside panel for
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 22 of 30
inspection not available in
any of the doors) One new door was not having
screwed inspectional panel on the inside.
15.5 Flooring : Compartment, doorway/gangway
Floor construction arrangement shall consist of 2.0 mm thick Vinyl sheet laid over 12 mm compreg board. All
the joints in Vinyl sheet shall be hot air welded to avoid seepage of water.
In addition, aluminum chequered plate shall be provided over PVC in the doorway/gangway portion.
Lavatoties : SS inlay, with proper
slope, single piece vinyl sheet
Luggage compartment : (i)compreg with PVC followed by steel chequered
plates, or (ii)compreg with floor coat compound to RDSO Specification No. C-9704
Pantry cars :compreg with dovetail
joints sloping towards centre of hall with drain tray and drain holes should be provided. Epoxy coating should be
provided over the compreg.
3.2.8/9/10/
11 (C-7602
Rev2)
Flooring of compreg and PVC
provided, hot air welding carried out, proper slope maintained. In few coaches,
epoxy based floor coat provided in the lavatories,
doorway/gangway and compartment
SS inlay provided, same
stiffened prior to fitment, proper slope maintained
Being ensured.
Flooring of compreg with
epoxy coating provided on trial basis in the entire coach (except kitchen room) in few
pantry cars.
15.6 Battery box frames: Corroded
battery boxes should be replaced with new battery box of the same design.
3.2.13(C-
7602 Rev2)
Being ensured
16 Documentation:-
After corrosion repairs are completed, particulars should be entered in the check lists. A diagram of the in
standard A-4 size should be marked suitably to indicate the parts of the
shell replaced during corrosion repair with specific details of the location and
extent of corrosion. The diagram and the check list should be filed in a folder maintained for each coach.
4.0 (C-7602 Rev2)
A4 size diagrams indicating the work carried out have been recently introduced,
coach history is not being maintained, the folders of
corrosion repair work are maintained month wise, not
coach wise
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 23 of 30
Annexure A
Specification for materials used in corrosion repairs of shell:-
(Ref : Clause 3.1 and Annexure XII of C-7607 Rev2)
S.No Item Specification No. Actually used by W/s
1. Steel sheets for manufacture of Approved sources from RDSO/ICF/RCF.
Yes
1.1 Trough floor 2 mm for IRSM – 41 Gr.I, 1.7 mm for austenitic stainless steel.
1.7 mm austenitic stainless steel, AISI
301
1.2 Pillars, sidewall sheet, light
rail, waist rail and end wall sheet
2 mm for IRSM – 41 Gr. I. Yes
1.3 Car line 2 mm for IRS M – 41 Gr.I. Yes
1.4 Roof sheet and longitudinal
stiffeners
1.6 mm for IRS M – 41 Gr.I. 2mm, IRS M – 41 Gr.I.
1.5 Cant rail and ribs 3.15 mm for IRSM-41 Gr.I. Yes
1.6 Other structural members like sole bar stiffeners
IRS: M – 41 Gr.I. Yes
2. Steel plates for manufacture of Approved sources from RDSO/ICF/RCF.
Yes
2.1 Sole bars and turn under 5 mm for IRSM – 41 Gr.I. Yes
2.2 Cross bearers above and below
trough floor, end wall stanchions
4 mm for IRSM – 41 Gr.I. 5mm, IRSM – 41 Gr.I
2.3 Outer headstock beam 8 mm for IRSM – 41 Gr.I. Yes
2.4 Other structural members like
sole bar stiffeners
IRSM -41 Gr.I. Yes
3. Tubes for tubular frame below
lavatory
IS:1239 Pt.I Tab.3 Yes
3.1 Sheets like skirting plate floor
side moulding
IRSM – 41 Gr.I. Yes
3.2 Plates IRSM – 41 Gr.I. Yes
4. Paint RDSO specification No. M & C /PCN/123/2006 for high performance anticorrosion epoxy
coating.
ROZC primer to IS2074/62, Bituminous paint to IRS P 3096,
Enamel paint to IS: 8662, Rust converter
to Specn. No. IS 13515/ 1992
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 24 of 30
Annexure B
Instruction for Welding Electrode & Welding Wire for different combination of Steel Material:-
(Refr : Annexure – XIII of C-7607 Rev2)
Electrode & Welding Wire:
Welding electrode and MIG/MAG welding wire for welding of different types of steels
are:
S.No. Description MMAW Electrode As per
IRS M-28- 2002 (Amendment-2)
MIG/MAG welding wire As per
IRS M-46-2003 (Amendment-1)
Remarks
1. IRSM-41 with IRSM-41
‘D’ class Class IV For head stock / sole bar
: Electrodes Class A2,
Wire Class I
For body panel :
Electrodes Class A1
D class electrodes not
used due to heavy
smoking.
3. IRSM-41with AISI 301
M4 Class Class VII Electrodes Class M4
6. AISI 301/AISI304 with IS:2062 E-250
M4 Class Class VII Electrodes Class M4
7. IS: 2062 E-250 to IS: 2062 E-250 or
IS:1239 Pt.I Tab.3
A3/B1 Class Cass I
Electrodes Class A1
8. IRSM-41 with IS:
2062 E-250
‘D’ Class Class IV
Electrodes Class M4
9. AISI 301 with AISI
301
Electrodes Class M2
Checked the following electrode boxes: (i)AWS E 6013 Class A1 manufactured by
M/s.KUCHHAL Welding Electrodes (RDSO approved).
(ii)Class M-4 electrodes manufactured by M/s.Seth Electrodes Pvt.Ltd., on
25.12.2010.
(iii)Class M-2 electrodes manufactured by M/s Classis Electrodes on 22.2.2011
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 25 of 30
Annexure C-1
VARIOUS TRAININGS SPECIFIED FOR WELDERS BY RAILWAY BOARD (Reference Railway Board’s letter no.E(MPP)99/19/1/VolIII dated 21.3.06)
Module No. Syllabus/duration
MODULE NO. (MECH 21)
Department MECHANICAL Category ALL ARTISAN TRADES
Duration 12 Days Stage REFRESHER Activity C&W DEPOT, WORKSHOPS PERIODICITY: AFTER EVERY 3 YEARS
MOD.NO. DESCRIPTION DURATION IN DAYS ME/ R1 - REVISION OF CRICITCAL MAINTENANCE PRACTICES
- INTRODUCTION TO LATEST MODIFICATION IN ROLLING STOCK - FAMILIARIZATION WITH NEW TECHNOLOGICAL
DEVELOPMENTS IN ROLLING STOCK, MATERIAL HANDLING EQUIPMENTS, SUB-ASSEMBLIES AND
MATERIALS - FOCUS ON PREVAILING PROBLEMS - RECOMMENDED VISIT TO THE PLACE OF BEST /
DESIRABLE MAINTENANCE PRACTICE AREA / SHED / WORKSHOP /DEPOT /PRODUCTION UNIT.
MODULE NO. (MECH 14)
Department MECHANICAL Category WELDER
Duration 72 Days Stage PROMOTION FROM UNSKILLED TO SKILLED Activity C&W DEPOT, WORKSHOPS
TECHNICAL QUALIFICATION - NON-ITI/ITI MOD.NO. DESCRIPTION DURATION IN DAYS
MECH 01 ME / 042 KNOWLEDGE OF DIFFERENT TYPES OF WELDING:
06 ARC WELDING, GAS WELDING, CO2 WELDING, TIG, MIG ME / 301 APPARATUS FOR WELDING, SELECTION FOR
ELECTRODES 06 TYPES OF WELDING JOINTS, SURFACE PREPARATION
ME / 302 PROPERTIES OF WELDABLE MATERIALS 06 ME /303 WELDING DEFECTS, INSPECTION & TESTING OF WELDS 06
ME /304 SAFETU PRECAUTIONS , SAFETY GADGETS 02 ME / 045 TYPES OF ROLLING STOCK USED ON INDIAN
RAILWAYS 06 ME /305 RECLAMATION / REPAIRS OF COMPONENTS BY WELDING 06
VIZ. KNUCKLES, BRAKE BEAMS, WEARING SURFACES ETC. ME/061 BASIC IDEA OF TRAIN LIGHTING & AIR
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 26 of 30
CONDITIONING 03
ME / MSK MULTISKILLING: INTRODUCTION AND PRACTICAL 30 TRAINING IN ALL TRADES REQUIRED IN THE WORKSHOP
ME/ GEN THEORATICAL SESSION: INCENTIVE SCHEME, WORKSHOP 05
ACCOUNTING, JOB CARD, SYSTEM OF MATERIAL PROCUREMENT, INTRODUCTION TO COMPUTERS VISIT TO A MAJOR C&W DEPOT, CRWS BHOPAL, 05
ANY WAGON MANUFACTURING FIRM
MODULE NO.
(MECH 06)
Department MECHANICAL
Category WELDER Duration 26 Weeks Stage INDUCTION TO SKILLED (RRB)
Activity WORKSHOPS TECHNICAL QUALIFICATION - ITI MOD.NO. DESCRIPTION DURATION IN WEEKS
MECH 01 ME/001 FOUNDATION 02
ME/002 SAFETY, FIRE FIGHTING, CLEANLINESS, FIRST AID 01 ME / O42 KNOWLEDGE OF DIFFERENT TYPES OF WELDING 01
ARC WELDING, GAS WELDING, CO2 WELDING, TIG, MIG ME / 301 APPARATUS FOR WELDING, SELECTION OF
ELECTRODES, 01 TYPES OF WELDING JOINTS, SURFACE PREPARATION ME / 303 WELDING DEFECTS, INSPECTION & TESTING OF
WELDS 01 SAFETY PRECAUTIONS , SAFETY GADGETS
ME / 045 TYPES OF ROLLING STOCK USED ON INDIAN RAILWAYS 01 ME / 305 RECLAMATION / REPAIRS OF COMPONENTS BY
WELDING 01 VIZ. KNUCKLES, BRAKE BEAMS, WEARING SURFACES ETC.
ME / 306 PRACTICAL ON THE JOB TRAINING IN VARIOUS SECTIONS 10
OF THE W/SHOP VIZ. CARRIAGE SHOP, WAGON SHOP ETC. ME / MSK MULTISKILLING: INTRODUCTION AND PRACTICAL 05
TRAINING IN ALL TRADES REQUIRED IN THE WORKSHOP ME/ GEN THEORATICAL SESSION: INCENTIVE SCHEME,
WORKSHOP 02 ACCOUNTING, JOB CARD, SYSTEM OF MATERIAL PROCUREMENT, INTRODUCTION TO COMPUTERS
VISIT TO A MAJOR C&W DEPOT, CRWS BHOPAL, 01 ANY WAGON MANUFACTURING FIRM
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 27 of 30
Annexure C-II
TRAINING ACTUALLY ACCORDED AT BTC/UBLS.
S.No. Category Duration Year Remarks
2009 2010 2011
1. RRB 6 months -- 22 10 Syllabus prepared as per
module No.MECH.06 vide
Railway Bd’s guidelines
(VolII, May’06)
2. Refresher 12 days 93 135 156
(incl. 60
welders)
Previously refresher was
combined for all trades. For
the last two months,
separate refresher course as
per syllabus based module
No.MECH.06 vide Railway
Bd’s guidelines (VolII,
May’06) has been
introduced
3. Promotion
from
unskilled
to skilled
21 days This training is mixed for all
trades. Individual training
for welders vide module
No.MECH.14 (specified
duration 72 days) is not
provided
BTC has 5 class rooms that are well equipped.
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 28 of 30
Annexure D
LIST OF TOOLS AND PLANT
Lifting shop
1. EOT cranes
2. Trestles for coach body
3. Inspection torches 4. Spiked hammers 5. Ball peen hammers
6. Goggles for inspection staff
7. Measuring tape 8. Measuring scale
Remarks
All
available
Corrosion Repair Shop
1. EOT cranes
2. Trestles for coach body
3. Gas cutting plants 4. Multi-operator welding
plants
5. CO2 Welding plant 6. Electrical angle
grinders 7. Pneumatic hand
grinders
8. Component painting equipment
Remarks
Only one crane of 60T with
two lifting tackles available. Coaches lifted from both
ends. No standby crane available.
Available
Available Single operator welding plants
Available Available
Not available
Spray painting is done. Workshop has planned to go
in for a plant for degreasing / rinsing followed by application of rust converter
/ primer.
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 29 of 30
Annexure E
Outturn
Vide Railway Board’s letter No.2011-10 (w) 814/1 dated 18.2.1, following targets
have been given to Hubli Workshop :
S.No. POH Refurbishment Total
Non-ac AC Total Non-ac AC Total Non-ac AC Total
Target
50 8 58 10 1 11 60 9 69
Actual outturn (2011-12)
April 49 7 56 8 1 9 57 8 65
May 74 7 81 5 1 6 79 8 87
June 55 6 61 5 3 8 60 9 69
July 57 6 63 11 1 12 68 7 75
Total 261 35 296
Note : (i)An average of 11.94 days were taken for POH and 48.73 days for
Refurbishment in the period April’11 to July’11
(ii)Refurbishment is done after about 10 years of coach life.
(iii)The w/s caters to coaches of SWR and KRCL
Extent of renewal of items during corrosion repair
The extent of renewal of head stock / sole bar, etc. for the period April’11 to July’11 is as
mentioned below:
Sr.
No.
Item Refurbishment (total chs
35)
POH (total chs 261)
Quantity Quantity per
ch
Quantity Quantity per ch
1 Head stocks 13 nos. 0.37 nos. - -
QA 26/2011 CORROSION REPAIR OF COACHING STOCK, UBLS, SW RAILWAY Page 30 of 30
(Complete Module)
2 Head Stocks (Outer) - - 21 nos. 0.08 nos.
3 Panel patches 1211 m 34.6 m 242 m 0.93 m
4 Body pillars 1474 nos. 42.11 nos. 295 nos. 1.13 nos.
5 Sole bars 223 m 6.37 m 45 m 0.17 m
6 Turn under 902 m 25.77 m 180 m 0.69 m
7 Cross channels 146 nos. 4.17 nos. 29 nos. 0.11 nos.
8 Trough floor 196 sqm 5.6 sqm 39 sqm 0.15 sqm