north sea energy infrastructure - sintef...offshore platforms 0 12 investments (10y): € 28 bn 4 x...

29
North Sea Energy Infrastructure: Status and outlook Patrick Piepers Asset Management TenneT EERA Deepwind 2019

Upload: others

Post on 23-May-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

North Sea Energy Infrastructure:Status and outlook

Patrick PiepersAsset Management TenneTEERA Deepwind 2019

Page 2: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

Deepwind ?

� Average depth DEA: -36,0m LAT� Deepest point (1): -71,5m LAT

2

Page 3: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

Strategy 2002: “ strenghten and build ”

� One strong, independent transmission grid� Expansion cross border connections� One cross border high voltage grid� Strenghten the Dutch electricity grid

3

Page 4: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

A leading TSO in Europe

2002 2017

Asset base (€ bn) 1 20.4

Staff 276 4,068

Connections (km) 2,686 22,500

Offshore connections(km) 0 4,700

Offshore platforms 0 12 Investments (10Y): € 28 bn

4

X 20

X 15

X 8

Page 5: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

Strong development offshore windCOP21 : radical change in electricity generation mix• 230 GW offshore wind capacity, 180 GW to be developed in the North Sea in

2050

• 70 GW offshore wind capacity in the North Sea in 2030WindEurope forecast

5

PBL forecast • 60 GW offshore wind capacity in the Dutch part of the North Sea in 2050

Page 6: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

NL: Phase I: 2019 – 2023 (+3.5 GW)

Year Capacity Area

2019 700 MW Borssele

2020 700 MW Borssele

2021 700 MW Hollandse Kust (zuid)

2022 700 MW Hollandse Kust (zuid)

2023 700 MW Hollandse Kust (noord)

6

• 3,500 MW: 5 x 700 MW• Standardized concept• AC connections

Page 7: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

700MW AC Substations , focus• Standardization

– Layout– Functionality– Operation– However some freedom for contractor (EPC contract)

• Lean Design– Unmanned– No helideck– No seawater– No diesel generator– Simple HVA/C

Nice to have

Need to have

7

Page 8: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

8

• Lessons learned

700MW AC Substations, focus

Borssele HKZ HKN

Tender started Q3

2018

Significant cost reduction due tostandardization

(Engineering, Risk profile, Project management, Eff iciency, …).

Page 9: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

700MW AC Substations, innovation

220 kV AC220 kV AC

9

AC technology limited due to increasing reactive power in longer cables. Intermediate compensation feasible but costly

Possible cost reduction due to subsea intermediatecompensation

SINTEF Byggforsk

SINTEF Energi SINTEF Ocean

Subhydro AS

Page 10: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

10

Page 11: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

11

Page 12: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

GE: Untill 2025 yearly 900MW HVDCYear Capacity Project

Operational

2009 62 alpha ventus

2010 400 BorWin1

2015 800 BorWin2

2015 800 DolWin1

2016 916 DolWin2

2015 576 HelWin1

2015 690 HelWin2

2014 113 Riffgat

2015 864 SylWin1

2017 111 Nordergründe

Under construction

2019 900 BorWin3

2018 900 DolWin3

2023 900 DolWin6

To be built

2023 900 DolWin5

2024 900 BorWin5

2025 ? BorWin612

Page 13: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

900MW HVDC, focus • Existing Platforms ���� OPEX reduction

– Long term unmanned– New logistic concepts

• New Platforms ���� CAPEX reduction– Lean design– Standardization– Direct 66kV link

13

Page 14: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

NL: Phase II: 2024 – 2030 (+7 GW)

Year Wind Area Power

2024 HKWest Alpha 700 MW HVAC

2025 HKWest Beta 700 MW HVAC

2026 Ten Noorden van de

Waddeneilanden

700 MW HVAC

2027-

2030

IJmuiden Ver 4000 MW HVDC

2027-

2030

? 900 MW

14

Page 15: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

Challenge: Cost

15

• Limited cost reduction in grid connections. • Longer offshore connections lead to increase in cos t

Page 16: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

Large HVDC connections (1,2-2GW)• Grid quality (HVAC cables result in deteriorating grid quality) • More cost effective then HVAC• Less cables (Ecology & Stakeholder)

Netherlands aim � 2GW (525kV)Requires market adaptations to ensure system reserve

Germany � limited by 2K criteria (Cable temperature)

18

Page 17: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

Large HVDC connections (1.2 -2GW)

Bi-Pole

• 2GW • 525kV • Bi-Pole • Double converter rooms • ≥6 transformers

19

Page 18: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

16Connecting >7 GW directly to shore results in significant congestion

NL challenge: Onshore connections

Connection points are illustrative

Page 19: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

GE challenge : Onshore connections

17

Page 20: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

20

Conclusion : grid analysis 2024 - 2030

AC connections

AC and DC connections

DC connections

+GW offshore wind

+11.5

Deep inland (cross border?) DC connectionsand system changes

AC and DC stations in coastal zone

2024-2030

+4.5

No measures needed

Page 21: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

Future development will needinnovation

WindConnector Connection of oil&gas platforms

More offshore windIsland soiutions

21

Page 22: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

WindConnector between NL and UK

• Better usage of infrastructure

• Integration of electricity markets NL and UK

• Saving costs on connecting offshore wind farms22

Page 23: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

Elektrification of Oil&Gas platforms

• Potential CO2 reduction

• Client connections offshore

23

Page 24: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

Cost optimization: jacket or island?

Artificial island as hub for DC offshore infrastructure22

Page 25: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

Phase III: 2030 – 2050 For large scale offshore wind everything is needed

• One international offshore grid• System integration• Power to Gas• Storage• Electrification of Industry & Transport• Interconnection• Most of all: clarity on the way forward!

Think Big! 24

Page 26: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

Phase III: 2030 – 2050 (+ 48 GW?)

• Large scale wind farms• Location: depth & wind• Power Link Hub• Wind Connector• Hub & Spoke

25

Page 27: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

Questions

26

Page 28: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

TenneT is a leading European electricity transmission system operator (TSO) with its main activities in the Netherlands and Germany. With approximately 22,500 kilometres of high-voltage connections we ensure a secure supply of electricity to 41 million end-users.

www.tennet.eu

Taking power further

Page 29: North Sea Energy Infrastructure - SINTEF...Offshore platforms 0 12 Investments (10Y): € 28 bn 4 X 20 X 15 X8 Strong development offshore wind COP21 : radical change in electricity

Liability and copyright of TenneT

This PowerPoint presentation is offered to you by TenneT TSO B.V. ('TenneT'). The content of the presentation – including all texts, images and audio fragments – is protected by copyright laws. No part of the content of the PowerPoint presentation may be copied, unless TenneT has expressly offered possibilities to do so, and no changes whatsoever may be made to the content. TenneT endeavours to ensure the provision of correct and up-to-date information, but makes no representations regarding correctness, accuracy or completeness.

TenneT declines any and all liability for any (alleged) damage arising from this PowerPoint presentation and for any consequences of activities undertaken on the strength of data or information contained therein.

Disclaimer