    NORTH STREET RECONSTRUCTION PROJECT

    Department of Public Works - Public Information Meeting

    Tuesday, March 6, 2012 (City Hall, Hearing Room, 7pm)

    Presentation Available: www.northamptonma.gov/dpw/Engineering

  • 7/31/2019 North St Meeting 03-06-2012

    2/20

    Recent History

    2007 North Street becomes a priority for repaving

    2008 DPW survey completed for repaving in 2009

    2009 Bay State Gas replaces gas lines, delaying repaving June 2010 DPW Public Information Meeting (27 people)

    Began process for neighborhood input: Discussed traffic calming

    .

    October 2010 Website Neighborhood Survey for Traffic Calming

    (74 responders ranked 22 possible improvements)

    This survey showed that responders ranked pedestrian safety and

    accessibility as their highest priority, with drainage, reducing truck

    traffic, and planting more trees running a close second. The next tier

    of ranking were bike lanes, and improvements to curbing and

    pavement markings.

  • 7/31/2019 North St Meeting 03-06-2012

    3/20

    Early 2011 Further confirmation that utility improvements need

    to be included on North Street causing higher project costs.Budget constraints push North Street to 2012, and Conz Street

    Reconstruction takes priority.

    Recent History (continued)

    reconstruction including utility replacement (water, sewer and

    drainage), traffic calming, sidewalks, curbing, crosswalks,

    accessibility, pavement markings, and signage.

    Summer 2012 North Street Reconstruction Expected to Begin!(Warning: Probably will get worse before it gets better.)

    Tonight: Present Improvements and 3 Conceptual Designs.

    Gather feedback from residents.

  • 7/31/2019 North St Meeting 03-06-2012

    4/20

    IMPROVEMENT: Replace Water, Sewer & Drainage Infrastructure

  • 7/31/2019 North St Meeting 03-06-2012

    5/20

    IMPROVEMENT: Pavement Markings

    DOUBLE YELLOW CENTER LINE W/ SHOULDER LINES

    ~3,000 FT LENGTH:

    BATES ST. TO INTERSECTION

    OF MARKET ST/WALNUT ST.

    11 FT TRAVEL LANES:NARROWER LANES TO

    REDUCE SPEEDS

  • 7/31/2019 North St Meeting 03-06-2012

    6/20

    IMPROVEMENT: Install Curbing to Define Roadway

    Multiple types of existing curbing

    Bituminous runs with granite radii

    Remove and reset granite curb from

    Market St. to Highland Ave

    Propose narrowing Lincoln Ave throat

  • 7/31/2019 North St Meeting 03-06-2012

    7/20

    IMPROVEMENT: Install Curbing to Define Roadway (continued)

    Propose narrowing Market Street throat.

  • 7/31/2019 North St Meeting 03-06-2012

    8/20

    DRAINAGE IMPROVEMENT: Crown & Grade Road & Add Catch Basins

  • 7/31/2019 North St Meeting 03-06-2012

    9/20

  • 7/31/2019 North St Meeting 03-06-2012

    10/20

    TREE CONCERNS:

    Provide Tree Protection Stump Removal

  • 7/31/2019 North St Meeting 03-06-2012

    11/20

    PROPOSE: New Sidewalk Along Cemetery

    TREE PLANTINGS:

    DPW will consider treeplantings on private property.

    Care of these trees is owners

    responsibility.

  • 7/31/2019 North St Meeting 03-06-2012

    12/20

    SIDEWALK CONCERNS

    Private property sidewalk transitions for several feet provided for in contract.

    Discussion with owner may be required on a case by case basis.

  • 7/31/2019 North St Meeting 03-06-2012

    13/20

    SIDEWALK CONCERNS

    Responsibility of owner to trim vegetation on private property or

    remove plants before construction begins.

  • 7/31/2019 North St Meeting 03-06-2012

    14/20

    IMPROVEMENT: Crosswalks/Signage

    Provide up to 7 crosswalks along North Street meeting current DPW standards

    (16) Crosswalks at all side streets

    MUTCD Approved Signage

    (on BOTH sides of posts)

  • 7/31/2019 North St Meeting 03-06-2012

    15/20

    OTHER SIGNAGE

    LARGER STOP SIGNS, INTERSECTION AHEAD WARNING, 30 MPH,

    NO PARKING, CURVES (WITH ADVISORY SPEED LIMIT)

  • 7/31/2019 North St Meeting 03-06-2012

    16/20

    IMPROVEMENT: Two Raised Crosswalks Under Consideration

    JACKSON STREET SCHOOL

  • 7/31/2019 North St Meeting 03-06-2012

    17/20

    IMPROVEMENT: Two Raised Crosswalks Under Consideration

    JACKSON STREET SCHOOL

  • 7/31/2019 North St Meeting 03-06-2012

    18/20

    CITY EMERGENCY ROUTE MAP

    Primary Route for Police-Fire Vehicles

    *Need to discuss raised feature plans for approval.

    NORTH ST: 30 MPH

    SPEED REGULATION #7346

    ISSUED ON January 14, 1986

  • 7/31/2019 North St Meeting 03-06-2012

    19/20

    PARKING: (D.A. Sullivan and Market/North Intersection

  • 7/31/2019 North St Meeting 03-06-2012

    20/20

    Concept Plans

    Concept 1 Replacement in kind Concept 2 Layout, sidewalks and green

    space improvements

    Concept 3 Bike Lane