Page 1: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Northern Connector Project Industry Briefing

30th Sep 2015

#9872385

Page 2: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

I would like to acknowledge the Kaurna people of whose land

we meet on today. I also pay my respects to their Elders past

and present and extend that respect to other Aboriginal and

Torres Strait Islander people who are present today.

Northern Connector

Page 3: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Agenda • Introduction

• Industry Advocate

• Northern Connector Project

• Torrens Junction Project

• DPTI Projects

• APY Lands

• Moving Forward

Northern Connector

Page 4: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Northern Connector Industry Briefing

Industry Participation Policy

Wednesday 30th September 2015

Page 5: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

5 Office of the Industry Advocate

Industry Participation Advocate To build Awareness, to Create Opportunities, to Initiate Change

Page 6: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

6 Office of the Industry Advocate

Our Objectives

Build capacity of local businesses to successfully tender for Government contracts

Policy and practices that remove impediments and support local participation

Procurement reforms that provide greater economic benefit to the State and local businesses

Page 7: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

7 Office of the Industry Advocate

Industry Participation Policy Employment, Investment, Supply inputs

Page 8: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

8 Office of the Industry Advocate

Key Drivers of Economic Contribution from Procurement

directly linked to the delivery of contracts on behalf of the

South Australian Government

SUPPLY INPUTS Value of goods and supplies

sourced from South Australian businesses

EMPLOYMENT Number of South Australian

jobs or labour hours

INVESTMENT Amount of new capital expenditure in South

Australia

The physical location or the registered office of a business does not necessarily translate to economic benefit to the State. This is primarily through jobs, investment and supply inputs

Page 9: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Currently a minimum weighting of 10% applies across the following sectors; • Heavy and civil engineering construction • Professional, scientific and technical services • Non-residential building construction • Electrical equipment manufacturing

Recent DPTI projects have 15% Industry Participation; Recognising the importance of economic contribution to an award of contract.

Page 10: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

10 Office of the Industry Advocate

Current Industry Participation Requirements

CONTRACT VALUE

REQUIREMENT

$22,000 to $220,000

• Can the product or service be

sourced within the State or region. • Obtain one quote from a local

source. • Employment Contribution Test

applies to primary and secondary contracts.

Page 11: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

11 Office of the Industry Advocate

Current Industry Participation Requirements

CONTRACT VALUE

REQUIREMENT

$220,000 to $4m (metro) or $1m (regional)

• Employment Contribution Test –

minimum weighting of 5% • Is there merit for increasing the

weighting

Page 12: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

12 Office of the Industry Advocate

Current Industry Participation Requirements

CONTRACT VALUE

REQUIREMENT

Above $4m (metro) or $1m (regional)

• Industry Participation evaluation –

minimum weighting of 5% or 10%*

• Industry Participation Plan required

• Is there merit for increasing the IP

weighting

Page 13: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

13 Office of the Industry Advocate

Industry Participation Plan requirements

THE PURPOSE OF THIS SECTION IS TO MEASURE THE

POTENTIAL ECONOMIC BENEFIT TO THE STATE THROUGH THE

USE OF LOCAL LABOUR. We are seeking the number of labour hours your business will employ directly to

deliver the contract should you be successful.

Page 14: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

14 Office of the Industry Advocate

Industry Participation Plan requirements

THE PURPOSE OF THIS SECTION IS TO MEASURE THE POTENTIAL

ECONOMIC BENEFIT TO THE STATE THROUGH THE CAPITAL EXPENDITURE.

• What is the total value of investment to be sourced from within South

Australia?

• What is the total value of investment to be permanently located in South

Australia?

Page 15: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

15 Office of the Industry Advocate

Industry Participation Plan requirements

THE PURPOSE OF THIS SECTION IS TO MEASURE THE POTENTIAL

ECONOMIC BENEFIT TO THE STATE THROUGH THE USE OF SUPPLY

INPUTS. (E.G. MERCHANDISE, FINISHED PRODUCTS, FOOD AND

BEVERAGES, SUPPLIES AND RAW MATERIALS)

• Will your business deliver this contract entirely in-house? • Will all supply inputs valued at $110,000 or more be sourced exclusively from

within South Australia?

• What supply inputs valued at over $110,000, will you purchase to deliver this

contract?

Page 16: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Industry Participation Plan Implementation: • Industry Participation Plan commitments become part of

contract conditions • Early engagement with industry • Input from OIA on work packages • Industry Advisory Committee/Reference group • Commitments to use SA based suppliers and

subcontractors • Subcontractors bound by the same SA Industry

Participation requirements • Monitoring and reporting

Page 17: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

17 Office of the Industry Advocate

CONNECTING WITH BUSINESS PROGRAM Supplying to Government Workshops A Suppliers Guide to Winning Government Business

Northern Connector Project

Topics covered include: • Knowing Your Customer • Understanding the Rules • Understanding the Process • Finding Opportunities • Building Relationships • Tendering to Win

Page 18: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Contact

www.industryadvocate.sa.gov.au

Office of the Industry Advocate Level 13, 99 Gawler Place ADELAIDE SA 5001 T: +61 8 8226 8956 E: [email protected]

Page 19: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Northern Connector Project • Introduction – background

• Purpose and Objectives

• Strategic Context

• Progress to Date

• Early Works

• Major Works

• Moving Forward

Northern Connector

Page 20: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Adelaide’s North-South Corridor

Northern Connector (due for completion 2019/20)

Northern Connector Project

Page 21: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Funded Sections • Darlington Upgrade Project • Torrens Road to River Torrens • Northern Connector Project

» $985m

Unfunded Sections • Regency Road to Torrens Road • Torrens Road to Anzac Highway • Anzac Highway to Ayliffes Road

Northern Connector

Page 22: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Objective • To deliver a new non-stop road corridor between the

Northern Expressway and South Road Superway

Benefits • Significant improved freight access to the Port of Adelaide

and surrounding industrial areas; • Improved road safety and efficiency; • Reduction in travel times; • Local employment – Jobs, Jobs, Jobs !!!

Northern Connector

Page 23: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Northern Connector Project

“People to places. Businesses to markets”

• Integration of transport infrastructure with land use planning

- future urban growth areas (including areas under investigation)

- new strategic employment lands

Source: 30 Year Plan for Greater Adelaide (DPTI 2010)

NORTHERN CONNECTOR PROJECT

Page 24: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Progress to Date

Northern Connector Project

• Commenced in 2008 and on-going Community and stakeholder

engagement

• Integrated Road & Rail Project (January 2009; November 2009) • Road Project Only (August 2012) → Threshold status on Priority List

Submissions to Infrastructure Australia

• July 2011 Development and release of the

Project Impact Report

• May 2015 Development and release of Scoping Report for 10 Year Delivery Strategy

• 14 September 2015 Joint Australian Government and SA Government funding commitment

Page 25: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Northern Connector Project

Project Scope

• A new road (15.5 kilometres), three lanes in each direction, between the Northern Expressway and the South Road Superway

• A shared-use (16 kilometres) pedestrian and cycle path

• Four road interchanges: - Northern Exp. / Port Wakefield Rd interchange - Waterloo Corner Rd interchange - Bolivar Rd interchange - South Rd / Port River Exp. Interchange

NORTHERN EXPRESSWAY

SOUTH ROAD SUPERWAY

NORTHERN CONNECTOR

PROJECT

Page 26: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Interchange with Port Wakefield Road

Northern Connector

Page 27: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Waterloo Corner Road Interchange

Northern Connector

Page 28: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Bolivar Road Interchange

Northern Connector

Page 29: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Interchange with Port River Expressway

Page 30: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Typical Cross-Section

Northern Connector Project

north of Ridley salt fields

through Ridley salt fields

Page 31: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Visualisation

Northern Connector

Page 32: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Northern Connector Project

Project Scope (continued)

• Earth embankment (i.e. partial sea wall) through salt fields (i.e. forming embankment for future rail corridor)

• Wetland offset or rehabilitation areas (for flood storage, water quality treatment and habitat)

NORTHERN EXPRESSWAY

SOUTH ROAD SUPERWAY

NORTHERN CONNECTOR

PROJECT

Page 33: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Challenges

• Timeframes to achieve necessary statutory and internal approvals (e.g. EPBC, Aboriginal heritage, Public Works Committee, procurement) may impact the commencement of the delivery program

• Development of the Ridley salt field site – nature and timing currently unknown

• Timeframes to undertake acquisitions and secure right-of-entry may result in delays to works program, including: - approximately 40% land parcels already Government owned

Northern Connector Project

Page 34: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Challenges

• Construction interfaces with existing Northern Expressway and South Road Superway, and service relocations

• Impacts of other infrastructure projects across Australia

• Capacity of local industry

Northern Connector Project

Page 35: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Workforce Participation Allocation of at least 20% of on-site labour hours to the employment of people from the following Target Groups:

• Aboriginal and Torres Strait Islander

• Displaced automotive workers

• People with barriers to employment

• Trainees / cadets / apprentices

• Local people

• JOBS, JOBS, JOBS

Northern Connector Project

Page 36: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Local Industry Participation Working with the Industry Advocate • Building capacity of Aboriginal Business;

• Increasing opportunities for Aboriginal & Torres Strait Islanders;

• Supporting local business enterprises;

• Share in the delivery of construction projects;

• Developing skills, qualifications and expertise.

Workforce Participation

Northern Connector

Page 37: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Meeting the Targets DPTI will assist in meeting the targets by:

• Partnerships with contractors, CCF, Indigenous groups to provide training and job opportunities for displaced automotive workers and others from the target groups

• Early local employment opportunities

• A new paradigm - A new approach – How will we make a difference?

Workforce Participation

Northern Connector

Page 38: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Northern Connector Project

Early Works

Proposed early work packages include:

• Site investigations

• Bolivar Road / Kings Road upgrade (local civil Contractors)

• Robinson Road upgrade (local civil Contractors)

• Trial embankment (employment training opportunities)

• Service re-locations

NORTHERN EXPRESSWAY

SOUTH ROAD SUPERWAY

NORTHERN CONNECTOR

PROJECT

ROBINSON ROAD

Page 39: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Northern Connector Project

Early Works (Jan 2016)

Bolivar Road / Kings Road upgrade and Robinson Road

• Construct Only Contract - Tender to be released in November 2015

• DPTI finalising designs for Contractors to price

• Commence works in January 2016

NORTHERN EXPRESSWAY

SOUTH ROAD SUPERWAY

NORTHERN CONNECTOR

PROJECT

ROBINSON ROAD

Page 40: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Northern Connector Project

Early Works (Jan 2016)

Trial Embankment

• pre-loading/earthworks - 1.2 million tonnes of existing stockpiled fill

• Partnerships with contractors, CCF, Indigenous groups to provide training and job opportunities for displaced automotive workers and others from the target groups

• Early local employment opportunities

NORTHERN EXPRESSWAY

SOUTH ROAD SUPERWAY

NORTHERN CONNECTOR

PROJECT

Page 41: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Environmental Issues

Northern Connector

Birds: • threatened ecological communities, bird species and their habitats

may be impacted by the project.

• DPTI will submit a referral to the Federal Minister for the Environment to determine if the project requires approval under the Environment Protection and Biodiversity Conservation (EPBC) Act.

• Opportunities to minimise project impact to native vegetation, fauna habitats and wetlands will need to be investigated/provided.

Page 42: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Environmental Issues

Northern Connector

Contamination: • Approximately 500 000 m3 of waste fill/intermediate

waste soil is located at materials storage facilities along the corridor (Northern Expressway/Port Wakefield Road; Roberts Lane, Waterloo Corner; Summer Road, Waterloo Corner).

• It is available for reuse on the project in line with EPA requirements.

Page 43: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Environmental Issues

Northern Connector

Sustainability:

• The project will be registered to pursue a design and as-built rating under the Infrastructure Sustainability Council of Australia's (ISCA) rating scheme.

Page 44: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Geotechnical Investigations

Northern Connector

Previously undertaken (2009 to 2010): • Planning Investigation along alignment by Aurecon

followed by a further investigation in Saltworks

• Northern Connector Fill Source Investigations by DPTI

• Limited Shallow Investigation in Saltworks by DPTI

• Limited Investigations south of Barker Inlet by DPTI for Northern Connector and Coffey for the Superway

Page 45: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Geotechnical Investigations

Northern Connector

Inferred Soil Conditions north of Bolivar • Generally very stiff clay soils, with local areas of sand

and occasional shallow groundwater

Inferred Soil Conditions south of Bolivar • Variable marine and estuarine sediments, consisting of

soft clays, loose sands, and organic underlain by very stiff clay

• Issues to consider shallow saline groundwater, consolidation and creep settlements of embankments, actual or potential acid sulphate soils

Page 46: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Geotechnical Investigations

Northern Connector

Page 47: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Geotechnical Investigations

Northern Connector

Proposed Investigations: • Detailed Geotechnical Investigation along centreline and

at interchanges (commence November 2015)

• Trial Embankment to be constructed in saltworks where alignment crosses deepest estuarine sediments (constructed during November 2015)

• Sampling of Stockpiled Material for DPTI Material Classification to reuse in embankments (commence Oct 2015)

Page 48: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Geotechnical Investigations

Northern Connector

Page 49: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Key Stakeholders Asset Management

DPTI Project Team DPTI

Specifications

D & C Consortia

Working Together– One Team

Northern Connector

Page 50: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Procurement Model – Collaborative D&C

• Collaboration;

• Shared understanding;

• Organisational alignment;

• Relationship building;

• Enable early commencement; collaboration is everything

Northern Connector

Page 51: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Evaluation & Registrants Presentations to Shortlist for RFT Completed by 19 November 2015

EOI Phase – Close 5 November 2015

Positive Guidance Sessions (individual teams)

Issue EOI to Registered Consortia 15 October 2015

Northern Connector

Selection Process – Overview

Page 52: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

DPTI Assessment February & March 2016

RFT – Close 12 February 2016

Positive Guidance Session/Workshops December 2015 & January 2016

Release Request for Tender 20 November 2015

Northern Connector

Selection Process – Overview

Page 53: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Design and Construct Contract Executed April 2016

Commence Construction May 2016

Project Completed Second half of 2019

Selection Process – Overview

Northern Connector

Page 54: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Select two (2) Consortia to participate in the RFT phase:

• Corporate track record;

• Consortia team (team fit) – no beauty parades

• Workforce participation – A new paradigm

• Delivery strategy / Methodology, A Challenge will be set for the southern end interchange, how will you build it ?

• Identify Risk and Opportunities

• Commercial terms

Expression of Interest

Northern Connector

Page 55: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

EOI – 3 Weeks Call date: 15 October 2015 Close Date: 5 November 2015 Mandatory and Assessed Criteria (page limits – must be adhered to).

Expression of Interest

Northern Connector

Page 56: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

• Team binder to be used for all correspondence and documentation;

• Bidding consortiums shall nominate a primary contact to receive all correspondence and documentation;

• If you require further information a Request For Information project mail type is to be submitted via Team Binder

Tender Documentation

Northern Connector

Page 57: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Moving Forward

Companies / Consortia wishing to participate in the Expression of Interest documentation, please keep attention to Tenders SA, EOI will be released from this site. Pre-registration is encouraged prior to EOI release:

By – Email to [email protected] On –Team Binder address, soon to be advised.

Northern Connector

Page 58: Northern Connector Project Industry Briefing 30th Sep 2015 · Workforce Participation . Allocation of at least 20% of on- site labour hours to the employment of people from the following

Thank you www.infrastructure.sa.gov.au/nsc/northern_connector

Northern Connector Project