nppd’s ainsworth wind energy facility & current wind rfp wind power 2008 conference
DESCRIPTION
NPPD’s Ainsworth Wind Energy Facility & Current Wind RFP Wind Power 2008 Conference November 11, 2008 Dave Rich. Nebraska Public Power District 2007 Overview (Annual). Revenue - $781 Million 18.8 billion kWh sold 2,226 employees 3,132 MW of generation, 5100 miles of transmission - PowerPoint PPT PresentationTRANSCRIPT
NPPD’s Ainsworth Wind Energy Facility & Current Wind RFP
Wind Power 2008 ConferenceNovember 11, 2008Dave Rich
o Revenue - $781 Million
o 18.8 billion kWh sold
o 2,226 employees
o 3,132 MW of generation, 5100 miles of transmission
o Primarily a wholesale power supplier to municipalities, other public power districts and cooperatives
o Average Retail – 6.21¢
o Average Firm Wholesale – 3.93¢
o Provides almost ½ the electricity consumed in Nebraska
o Nebraska has consistently been among the 10 lowest cost states for electricity
2
3
2%Oil
20%Natural Gas
20%Nuclear
7%Hydro2%
Wind/Solar/ Geo Thermal
49%Coal
National 2006
9%Hydro*
6%Purchases
24%Nuclear 4%
Natural Gas & Oil
57%Coal
1%Wind
NPPD 2007
* Includes hydro purchases from the federal government
34% Non-CO2 Emitting
29% Non-CO2 Emitting
Fuel Mix for ElectricityPercent by Resource
Large site – can optimize wind turbine placement
Close to existing transmission that can support the wind facility with minimal added costs
Based on wind monitoring at more than 8 sites
Minimal disruption to existing land use
4
Positive support from local community and KBR Rural Public Power District
No significant environmental impacts
◦Bird monitoring
◦Beetle strategy
5
6
60 MW Total (59.4)
◦NPPD – 32 MW
◦ Jacksonville Electric Authority – 10 MW
◦Omaha Public Power District – 10 MW
◦Municipal Energy Agency of Nebraska – 7 MW
◦City of Grand Island – 1 MW
7
Facility Design:◦ 36 Vestas 1.65-megawatt turbines
◦ 269 foot (82m) rotor diameter
◦ Tubular steel towers - 230 feet (70m)
◦ Total Cost: $81.3 Million
◦ Employees: 6 Technicians
8
9
10
11
12Blade Repair IssueBlade Repair Issue
Bearing with spinning race on high speed shaft
Lifting device developed by VESTAS
13
14
15
NPPD Board Strategic Goal
◦NPPD will evaluate all forms of renewable resources feasible in Nebraska and incorporate them in the total mix of NPPD-owned generation and contract purchases, with a goal of achieving 10% of our energy supply for NPPD’s native load from renewable resources by 2020.
16
17
Target of adding 80 MW of wind-powered generation in 2010
Assuming the extension of Federal Production Tax Credits, lowest cost option is PPA
November 2008 - Plan to issue RFP
Spring 2009 - Proposals due
Fall 2009 – PPA Complete
18
Numerous project developers have acquired land and transmission interconnection queue positions
RFP will identify two NPPD sites
◦Transmission studies manageable
◦NPPD can select either or both sites
Will allow proposals that utilize land that is under NPPD or private control at these two sites
19
20