nrc-ge meeting 03-08-06-confirmatory melcor analysis of … · 2012. 11. 21. · fl812 fl813 fl814...
TRANSCRIPT
ERIEnergy Research, Inc.
CONFIRMATORY MELCOR CONFIRMATORY MELCOR ANALYSIS OF SEVERE ACCIDENTS ANALYSIS OF SEVERE ACCIDENTS
FOR ESBWRFOR ESBWR
by:by:Z. Yuan, M. Zavisca, A. Krall and M. KhatibZ. Yuan, M. Zavisca, A. Krall and M. Khatib--RahbarRahbar
Energy Research, Inc.Energy Research, Inc.6167 Executive Blvd.6167 Executive Blvd.
Rockville, Maryland 20852Rockville, Maryland 20852
U. S. Nuclear Regulatory Commission Meeting With General Electric Company On ESBWR Severe Accident Sequences and
Thermal-Hydraulic Uncertainties
March 8, 2006
2
ERIEnergy Research, Inc.
OUTLINEOUTLINEObjective of the NRC MELCOR analysesMELCOR Modeling of ESBWR
• Nodalization• Other modeling aspects• StatusPre-Accident Initialization/Steady-State
3
ERIEnergy Research, Inc.
OUTLINE (Cont.)OUTLINE (Cont.)
Results of Preliminary Calculations• Accident Scenario• Simulated Cases
Case 1: With MCCI! Lower Head Sensitivity Calculations
Case 2: Without MCCI
Remaining Data NeedsList of Plant Calculations
4
ERIEnergy Research, Inc.
OBJECTIVESOBJECTIVESTo support the design certification review of severe accident risk by NRC in
Independent assessment of severe accident responseConfirmatory assessment of representative radiological release estimatesDevelopment of uncertainties in the initial and boundary conditions for analysis of selected severe accident issues (e.g., ex-vessel steam explosion)
5
ERIEnergy Research, Inc.
MELCOR Model DevelopmentMELCOR Model DevelopmentDeveloped initial input deck for MELCOR 1.8.6 using GE design data (November 18, 2005)This deck subjected to an independent QA and review Due to problems with MELCOR 1.8.6, model was converted to MELCOR 1.8.5 and revised based on QA & review comments.Plan to perform limited calculations for ESBWR using MELCOR 1.8.6 when the code is ready.
6
ERIEnergy Research, Inc.
MELCOR Model Development (Cont)MELCOR Model Development (Cont)Deck conversion to MELCOR 1.8.5:
Flat-bottom RPV instead of the new hemispherical LHMinor changes to core nodalization (to enhance running time)Minor changes to the suppression pool (water) nodalization in response to QA & review commentsUpdated design data based on MFN05-142, 06-003, 06-009, 06-029
7
ERIEnergy Research, Inc.
CORE/RPV NODALIZATIONCORE/RPV NODALIZATION• The core nodalization:
5 radial rings, 13 axial levels (9 for active fuel, 1 above top of active fuel, 1 between bottom of active fuel & top of the core plate, 2 in the lower plenum).
• Separate Control Volumes (CV) used for each ring, heated channels and the bypass regions• 1 CV used for every 3 axial levels of active fuel region, plus
another level of CV for regions above the active fuel.• As a result, a total of 25 CVs for the core (4 levels x 5 rings
for the core channels plus 5 for the bypass).
8
ERIEnergy Research, Inc.
101102103104105
106
107
108
109
110
111
112
113
114
115
116
117
118
Ring 1 Ring 2 Ring 3 Ring 4 Ring 5
Low
er P
lenu
mA
ctiv
e Fu
el
Core Plate
CV135
CV134
CV133
CV132
CV131
CV120
Upper Core Structure (e.g., top guides)
Cor
e Sh
roud
RPV Lower Head
ORIGINAL MELCOR
1.8.6 Model
9
ERIEnergy Research, Inc.
101
102
103
104
105
106
107
108
109
110
111
112
113
Ring 1 Ring 2 Ring 3 Ring 4 Ring 5
Low
er P
lenu
mA
ctiv
e Fu
el
Core Plate
CV134
CV133
CV132
CV131
CV120
Upper Core Structure (e.g., top guides)
RPV Lower Head
LATEST MELCOR
1.8.5 Model
10
ERIEnergy Research, Inc.
CORE/RPV NODALIZATION (Cont.)CORE/RPV NODALIZATION (Cont.)• Other CVs used inside RPV to represent:
• Lower plenum;• Separators (inside volume of the steam separators) and mixing
plenum/partitioned chimney;• Dryers and steam dome region;• Separator return to upper downcomer, combined with the liquid
drain area outside the steam separators; and• Lower downcomer.
• 2 CVs used to represent 4 main steam lines (1 CV for one of the lines, and 1 CV combines the remaining 3 lines, allowing simulation of a break in one line).
• Feed water system has been modeled (using external mass and energy sources in the CV package and CFs)
11
ERIEnergy Research, Inc.
Dryer / Steam Dome
Sepa
rato
r Ret
urn
to
Upp
er D
ownc
omer
Separators /Chimney Plenum
Chimney Partition
Core / Bypass
Lower Plenum
Low
er D
ownc
omer
190
134
180185
1xx 2xx
120
110
139
149
159
169
179
191
180
185139 149 159 169 179
11014
4
154
164
174
134 234 144 244 154 254 164 264 174 274
334 344 354 364 374
133
143
153
163
173
133
143
153
163
173
333 343 353 363 373
132
142
152
162
172
132
142
152
162
172
332 342 352 362 372336 346 356 366
131
141
151
161
171
131
231
141
241
151
251
161
261
171
271
331 341 351 361 371
130 230 140 240 150 250 160 260 170 270
FeedwaterInlet
190
12
ERIEnergy Research, Inc.
CONTAINMENT NODALIZATIONCONTAINMENT NODALIZATION• Each of the 4 divisions of the 3 GDCS pools is
represented individually (also modeled the 2 divisions existing for GDCS #2). One CV used for each of 3 GDCS pools, along with controlled flow paths for injection, equalization & deluge lines.
• 6 units of PCCS are represented by 2 sets of CVs & FLs. (1 single & 5 combined).
• 4 units of IC are represented by 2 sets of CVs (1 single & 3 combined).
13
ERIEnergy Research, Inc.
CONTAINMENT NODALIZATION (Cont)CONTAINMENT NODALIZATION (Cont)
• PCCS & IC modeled mechanistically• Condensation and drainage of water inside
tubes modeled inside the MELCOR HS package, using a film tracking network.
• PCCS and IC inlet lines modeled as CVs and HSs.
• Heat transfer from drywell (upper head) to the “reactor well” water is included.
14
ERIEnergy Research, Inc.
Lower Drywell
Lower Plenum
Dow
ncom
er
Core / Bypass
Chimney Partition
Separators /Chimney Plenum
Dryer / Steam Dome
Wetwell
GDCS-1MSL
MSL
Turb
ine
Build
ing
Drywell Head
IC Pool
PCCS Pool IC-1 IC-2/3/4 PCCS Pool
Envi
ronm
ent
GDCS-2 GDCS-3
Dry
wel
l Shi
eldw
all A
nnul
us
Upp
er D
ryw
ell
DW
Dow
ncom
er
Vent
Wetwell
400
120
190
180
110
185
524524
522
610
195
196
198
430
420
410
900
620 630
440
515
511
512
513514
521
522
523524
810
817
816815814813812811
710
717
716715714713712711
720
727
726725724723722721
820
827
826825824823822821
FL51
5FL
514
FL51
3FL
512
FL554
FL553
FL552
FL551
FL52
5FL
524
FL52
3FL
522
FL441
FL451
FL461
FL440
FL411 (vacuum break)
FL895
FL728
FL829
FL631
FL633
FL630 FL632FL622
FL620
FL621
FL623
FL820FL810
FL410
FL415
FL495(DPV)
FL100 (FW in)
FL400
FL420
FL729
FL720
FL199 (VB)
FL198 (BDL)
850
FL719
FL710
FL718FL819
FL818
FL593(Eq. Line)
FL193
FL194
FL590(break to CV410)
FL195
FL196
FL592
FL591
FL613
FL612(from
CV410)
FL811FL812
FL813
FL814
FL815
FL816
FL817
FL711FL712
FL713
FL714
FL715
FL716
FL717
FL721FL722
FL723
FL724
F725
FL726
FL727
FL821FL822
FL823
FL824
FL825
FL826
FL827
FL611
FL614(from GDCS-1)
FL615(from GDCS-1)
Dry
/ S
epar
ator
Sto
rage
Tan
k
890
750
850
FL795
FL890FL890
FL901FL902
FL632
Mid
dle
Dry
wel
l
405
FL412
FL418(Leakage)
FL498(Normal Containment
Leakage)
FL629FL594(Eq. LineBreak)
Reactor Well 892FL
809
FL83
9 FL494(CIS)
FL499(Cont.Rupture)
809
819
15
ERIEnergy Research, Inc.
OTHER MODELING ASPECTSOTHER MODELING ASPECTS• Containment spray system and venting system
have been included (noting that the missing design data need to be requested from GE).
• Refill of PCC/IC pool is included via a control function to maintain coverage of PCCS tubes.
• BiMAC system has not been explicitly modeled (the intended impact of BiMAC may be investigated through a parametric representation within MELCOR; otherwise, specific design information may be required).
16
ERIEnergy Research, Inc.
STATUSSTATUS
• All aspects of the model, peer review and QA comments have been documented.
• NRC staff have been involved in all aspects of this work (including direct involvement in steady-state calculations).
17
ERIEnergy Research, Inc.
STATUS (Cont.)STATUS (Cont.)• A complete 1.8.5 model is available and
initial confirmatory calculations are underway.• Results of a representative accident scenario with
limited comparisons to the GE submittal completed (not yet documented).
• List of representative scenarios to be analyzed has been prepared and discussed with the NRC staff.
• Baseline MELCOR calculations should be completed, pending the receipt of requested data from GE.
• Anticipate completion (MELCOR) within 2-3 months.
18
ERIEnergy Research, Inc.
PREPRE--ACCIDENT INITIALIZATIONACCIDENT INITIALIZATION• Approach developed in collaboration with NRC.• Set full power (4500 MW) and the design feedwater flow
rate (2451 kg/s) for the duration of simulation.• Approach to steady-state was relatively smooth• Iterated with specified loss coefficients to arrive at
pressure drop and flow rates (feedwater, recirculation and steam) listed in the DCD:• Additional work is needed to resolve the apparent differences with
DCD conditions• Clarification on the physical locations of the referenced pressure
differentials needed from GE• Need detailed information on the various form loss coefficients
from lower plenum to the chimney region (along the core), the leakage flow paths from the chimney and separators to the downcomer.
19
ERIEnergy Research, Inc.
PRELIMINARY RESULTS (PREPRELIMINARY RESULTS (PRE--ACCIDENT ACCIDENT INITIALIZATION)INITIALIZATION)
0
2000
4000
6000
8000
10000
12000
14000
16000
-500 -450 -400 -350 -300 -250 -200 -150 -100 -50 0
time [sec]
Mas
s Fl
ow R
ate
[kg/
s]
Total flow rate through the core (CFVALU.910)Feedwater flow rate (CFVALU.127)Flow rate from outside the separators to DC (FL-MFLOW.191)Total flow rate through the main steam lines
20
ERIEnergy Research, Inc.
RPV PressureRPV Pressure
7
7.05
7.1
7.15
7.2
7.25
7.3
7.35
7.4
-500 -450 -400 -350 -300 -250 -200 -150 -100 -50 0
time [sec]
Pres
sure
[MPa
]
Steam dome (CVH-P.190)Separators (CVH-P.180)Chimney (CVH-P.139)Core region (CVH-P.134)Core region (CVH-P.131)Lower plenum (CVH-P.120)Downcomer (CVH-P.110)
21
ERIEnergy Research, Inc.
Pressure Drop Between Various Core Pressure Drop Between Various Core Control VolumesControl Volumes
0.0E+00
1.0E+04
2.0E+04
3.0E+04
4.0E+04
5.0E+04
6.0E+04
7.0E+04
8.0E+04
-500 -450 -400 -350 -300 -250 -200 -150 -100 -50 0
time [sec]
Pres
sure
dro
p (P
a)
CV120-CV131CV131-CV132CV132-CV133CV133-CV134CV134-CV139CV134-CV120
22
ERIEnergy Research, Inc.
Fuel TemperatureFuel Temperature
0
200
400
600
800
1000
1200
1400
-500 -450 -400 -350 -300 -250 -200 -150 -100 -50 0
time [sec]
Tem
pera
ture
[K]
COR-TFU.103COR-TFU.104COR-TFU.105COR-TFU.106COR-TFU.107COR-TFU.108COR-TFU.109COR-TFU.110COR-TFU.111COR-TFU.112COR-TFU.203COR-TFU.204COR-TFU.205COR-TFU.206COR-TFU.207COR-TFU.208COR-TFU.209COR-TFU.210COR-TFU.211COR-TFU.212
23
ERIEnergy Research, Inc.
MELCOR SteadyMELCOR Steady--State Results vs. GE DCD State Results vs. GE DCD ValuesValues
Parameters Design value Simulated value Steam flow rate (kg/s) 2433 2437 Feedwater flow rate (kg/s) 2451 2439 Core coolant flow rate (kg/s) 9034-10584 9454 System pressure, nominal in steam dome (kPa) 7171 7179 System pressure, nominal core design (kPa) 7240 7243 Core inlet temperature (°C) 543-545 543 Total core pressure drop (from bottom of the core support plate to top of the core) (kPa) 70.0 47.0
Core plate pressure drop (kPa) 41.3 31.5 Core maximum exit void fraction 0.916 0.90 Downcomer liquid level (m) 17.27 17.6
24
ERIEnergy Research, Inc.
MELCORMELCOR--Simulated Accident ScenarioSimulated Accident ScenarioTransient event initiated by a loss of feedwater (i.e., scenario T_DP_nIN of the ESBWR PRA):
Short or long-term coolant injection to RPV not available (i.e., GDCS injection to RPV & wetwell injection through equalization lines not available).ADS is assumed to be actuated if downcomer water level drops below 11 m.Heat removal by ICs not credited.PCC & PCC/IC pool makeup available (thereby allowing long-term containment heat removal).GDCS deluge system is also available for injection onto the lower drywell floor.
25
ERIEnergy Research, Inc.
MELCORMELCOR--Simulated Accident Scenario Simulated Accident Scenario (Cont.)
Two cases considered:Case 1: MCCI allowed to occur (assuming MELCOR standard basaltic concrete composition).Case 2: MCCI suppressed
26
ERIEnergy Research, Inc.
Preliminary Results Preliminary Results (Case 1: With MCCI)(Case 1: With MCCI)
Event Value
RPV depressurization starts (DPVs open), hour 0.33
Start of core uncovery, hour 0.86
Start time of gap release from fuel, hour 1.08 Range of relocation periods in various core regions (i.e., fuel temperature exceeds 2500 K), hour 1.69 – 3.82
Local failure of the lower core plate (i.e., T=1273K), hour 2.26 – 2.52
Gross failure (melting) of the lower core plate (i.e., T> 1700K), hour N/A
RPV lower head penetration failure, hour 3.91
Start of MCCI, hour 4.20
27
ERIEnergy Research, Inc.
Preliminary Results Preliminary Results (Case 1: With MCCI) (Cont.)(Case 1: With MCCI) (Cont.)
Event Value
Water in reactor cavity reaches saturation, hour 4.36
Actuation of the cavity deluge system, hour 7.26
Time of GDCS water depletion, hour 9.0
Total in-vessel hydrogen generation, kg 603 Percentage of total core zirconium oxidized prior to vessel breach, % 18.0
Pressure in upper drywell at 24 hours, bar-abs 12.5
Maximum atmosphere temperature in upper drywell, K 801 Water level in drywell at 24 hours (relative to bottom of the RPV), m 11.5
Total combustible gas generation due to MCCI at 24 hours, kg 4426 kg of CO3038 kg of H2
Axial concrete erosion at 24 hours, m 1.42
28
ERIEnergy Research, Inc.
RPV Pressure (Case 1: With MCCI)RPV Pressure (Case 1: With MCCI)Pressure in the RPV
0
1
2
3
4
5
6
7
8
9
10
0 5 10 15 20 25
time [hr]
Pres
sure
[MPa
]
RPV pressure (CVH-P.190)
29
ERIEnergy Research, Inc.
RPV Water Level (Case 1: RPV Water Level (Case 1: with MCCI)with MCCI)
0
2
4
6
8
10
12
14
16
0 5 10 15 20 25
time [hr]
Wat
er L
evel
[m]
Water level in the vessel
30
ERIEnergy Research, Inc.
Fuel TemperatureFuel Temperature
(Case 1: with MCCI)(Case 1: with MCCI)
0
500
1000
1500
2000
2500
3000
0 2 4 6 8 10
time [hr]
Tem
pera
ture
[K]
COR-TFU.104COR-TFU.112COR-TFU.204COR-TFU.212COR-TFU.304COR-TFU.312COR-TFU.404COR-TFU.412COR-TFU.504COR-TFU.512
31
ERIEnergy Research, Inc.
Temperature of Debris on the Core Temperature of Debris on the Core PlatePlate (Case 1: with MCCI)(Case 1: with MCCI)
0
500
1000
1500
2000
2500
3000
0 2 4 6 8 10 12 14
time [hr]
Tem
pera
ture
[K]
COR-TPD.103COR-TPD.203COR-TPD.303COR-TPD.403COR-TPD.503
32
ERIEnergy Research, Inc.
Debris Temperature in the Lower Debris Temperature in the Lower PlenumPlenum (Case 1: with MCCI)(Case 1: with MCCI)
0
500
1000
1500
2000
2500
0 2 4 6 8 10 12 14
time [hr]
Tem
pera
ture
[K]
COR-TPD.101COR-TPD.201COR-TPD.301COR-TPD.401COR-TPD.501
33
ERIEnergy Research, Inc.
Total InTotal In--Vessel Hydrogen Vessel Hydrogen GenerationGeneration (Case 1: with MCCI)(Case 1: with MCCI)
0
100
200
300
400
500
600
700
800
900
0 5 10 15 20 25
time [hr]
Mas
s [k
g]
COR-DMH2-TOT
34
ERIEnergy Research, Inc.
Total Gas Generation Due to CoreTotal Gas Generation Due to Core--Concrete Interaction (Case 1: with MCCI)Concrete Interaction (Case 1: with MCCI)
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
0 5 10 15 20 25
time [hr]
Mas
s [k
g]
CAV-MEX.CO.1CAV-MEX.CO2.1CAV-MEX.H2.1CAV-MEX.H2O.1
35
ERIEnergy Research, Inc.
Upper Drywell and Wetwell Pressure Upper Drywell and Wetwell Pressure (Case 1: with MCCI)(Case 1: with MCCI)
0.0E+00
2.0E+05
4.0E+05
6.0E+05
8.0E+05
1.0E+06
1.2E+06
1.4E+06
0 5 10 15 20 25
time [hr]
Pre
ssur
e [P
a]
CVH-P.410CVH-P.515Containmnet rupture pressure
36
ERIEnergy Research, Inc.
Containment Concrete Floor Containment Concrete Floor Temperature Temperature (Case 1: with MCCI)(Case 1: with MCCI)
300
350
400
450
500
550
0 5 10 15 20 25
time [hr]
Tem
pera
ture
[K]
HS-TEMP.4000105Deluge system activation setpoint
37
ERIEnergy Research, Inc.
Debris Pool Temperature in the Lower Debris Pool Temperature in the Lower Drywell (Case 1: with MCCI)Drywell (Case 1: with MCCI)
0
500
1000
1500
2000
2500
0 5 10 15 20 25
time [hr]
Tem
pera
ture
[K]
CAV-T.HMX.1Basaltic Concrete Decomposition Temperature
38
ERIEnergy Research, Inc.
Water Level on the Containment Water Level on the Containment Floor (Drywell)Floor (Drywell) (Case 1: with MCCI)(Case 1: with MCCI)
-10
-5
0
5
10
15
0 5 10 15 20 25
time [hr]
Wat
er L
evel
[m]
Water level in the drywellBottom of drywell
39
ERIEnergy Research, Inc.
MELCOR 1.8.5 CPU TimeMELCOR 1.8.5 CPU Time
(Case 1: with MCCI)(Case 1: with MCCI)
0
5
10
15
20
25
30
0 5 10 15 20 25
time [hr]
CPU
Tim
e (h
r)
CPU Time
40
ERIEnergy Research, Inc.
Sensitivity to MELCOR Lower Head Sensitivity to MELCOR Lower Head Model ParametersModel Parameters
Cases
HTC (debris-
LH) (W/m2K)
Debris
quenching HTC
(W/m2K)
Debris dryout HTC
(W/m2K)
Debris fall velocity
(m/s)
Particulate debris size
(m)
Porosity of
particulate debris
Conduction enhancement
for molten components
Radiation exchange
factor
Candling HTC
(W/m2K)
Case 1 1000 (def.) 100 (def.) ~11 (def.
C1242) 1.0 (def) 0.001 0.3 3200K/0.01 (def) 0.25 (def) 1000 (def)
Case 2 100
Case 3 10000
Case 4 0.5
Case 5 20(2) 220 0.025 0.4 FCELR and FCELA=0.1 others=0.25
7500 for UO2, Zr,
ZrO2 others=2500
Case 6 Best Estimate
200 1300 0.025 0.5 FCELR and FCELA=0.1 others=0.25
7500 for UO2, Zr,
ZrO2 others=2500
41
ERIEnergy Research, Inc.
Sensitivity to MELCOR Lower Head Sensitivity to MELCOR Lower Head Model Parameters (Cont.)Model Parameters (Cont.)
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
Case 1 Case 2 Case 3 Case 4 Case 5 Case 6 (Bestestimate)
Scenario
Tim
e (h
r)
Start time of MCCITime of RPV lower head penetration failureStart time when melt mass relocates to the lower plenum
42
ERIEnergy Research, Inc.
Comparison With MAAP Results (Case 2: Comparison With MAAP Results (Case 2: Without MCCI)Without MCCI)
Event MAAP* MELCOR
RPV depressurization starts (DPVs open), hour 8.6×10-3 0.33
Start of core uncovery, hour 0.36 0.86 Onset of core damage (i.e., fuel temperature exceeds 2500 K), hour 0.97 1.69
RPV lower head penetration failure, hour 6.3 3.91
Deluge system actuated, hour 6.3 7.9
Containment (upper drywell) pressure at 24 hours, bar-abs 5.0 4.8
Containment (lower drywell) temperature at 24 hours, K 425 427
Containment fail/vent, hour N/A N/A
PCCS heat removal at 24 hours, MW 18.5 22.7 Water level in drywell at 24 hours (relative to bottom of the RPV), m 13.1 12.5
Axial concrete erosion in 24 hours, m 0.07 0.0
Mass fraction of noble gases released to environment 9.0×10-4 8.7×10-4
Mass fraction of CsI released to environment 7.4×10-5 1.8×10-5
*MAAP results taken from NEDC-33201P (Rev 0)
43
ERIEnergy Research, Inc.
RPV Pressure (Case 2: Without MCCI)RPV Pressure (Case 2: Without MCCI)
0
1
2
3
4
5
6
7
8
9
10
0 5 10 15 20 25
time [hr]
Pres
sure
[MPa
]
CVH-P.190MAAP Results
MAAP results taken from NEDC-33201P (Rev 0)
44
ERIEnergy Research, Inc.
Upper Drywell and Wetwell PressureUpper Drywell and Wetwell Pressure
(Case 2: Without MCCI)(Case 2: Without MCCI)
0.0E+00
1.0E+05
2.0E+05
3.0E+05
4.0E+05
5.0E+05
6.0E+05
0 5 10 15 20 25
time [hr]
Pres
sure
[Pa]
CVH-P.410CVH-P.515MAAP Results
MAAP results taken from NEDC-33201P (Rev 0)
45
ERIEnergy Research, Inc.
Lower Drywell TemperatureLower Drywell Temperature
(Case 2: Without MCCI)(Case 2: Without MCCI)
0
100
200
300
400
500
600
0 5 10 15 20 25
time [hr]
Tem
pera
ture
[K]
CVH-TVAP.405MAAP results
MAAP results taken from NEDC-33201P (Rev 0)
46
ERIEnergy Research, Inc.
Decay Heat Generation and Heat Removal by Decay Heat Generation and Heat Removal by PCCS (Case 2: Without MCCI)PCCS (Case 2: Without MCCI)
0
50
100
150
200
250
300
350
0 5 10 15 20 25
time [hr]
Pow
er [M
W]
Decay heatHeat removal by PCCSMAAP results
MAAP results taken from NEDC-33201P (Rev 0)
47
ERIEnergy Research, Inc.
Water Level in the Drywell Water Level in the Drywell
(Case 2: Without MCCI)(Case 2: Without MCCI)
-10
-5
0
5
10
15
0 5 10 15 20 25
time [hr]
Wat
er le
vel [
m]
Water level in drywellMAAP results
MAAP results taken from NEDC-33201P (Rev 0)
48
ERIEnergy Research, Inc.
Release of Noble Gases to the EnvironmentRelease of Noble Gases to the Environment
(Case 2: Without MCCI)(Case 2: Without MCCI)
1.0E-05
1.0E-04
1.0E-03
1.0E-02
1.0E-01
1.0E+00
0 5 10 15 20 25
time [hr]
Xe
rele
ase
frac
tion
[-]
MELCOR results (RN1-TYCLT-1-2.9)MAAP results
MAAP results taken from NEDC-33201P (Rev 0)
49
ERIEnergy Research, Inc.
Release of CsI to the Environment Release of CsI to the Environment
(Without MCCI)(Without MCCI)
1.0E-08
1.0E-07
1.0E-06
1.0E-05
1.0E-04
1.0E-03
1.0E-02
1.0E-01
1.0E+00
0 5 10 15 20 25
time [hr]
CsI
rele
ase
frac
tion
[-]
MELCOR results (RN1-TYCLT-16-2.9)MAAP results
MELCOR calculations use the CORSOR-BOOTH option for in-vessel releasesMAAP results taken from NEDC-33201P (Rev 0)
50
ERIEnergy Research, Inc.
SUMMARYSUMMARY
Generally, MELCOR and MAAP results are in reasonable agreementDesirable to have a discussion of MAAP modeling/parametric assumptions to better resolve some of the observed differences, e.g.,
Debris/water/LH interactions
Comparison of calculated source term
51
ERIEnergy Research, Inc.
• Containment spray system• The elevation of the containment spray header inside
the drywell;• Spray water temperature; and• Spray mean droplet diameter.
• Containment venting system• Elevations of containment venting system in both the
suction and the discharge sides; and• Length of various pipe sections in the vent lines.
REMAINING DATA NEEDSREMAINING DATA NEEDS
52
ERIEnergy Research, Inc.
REMAINING DATA NEEDS (Cont.)REMAINING DATA NEEDS (Cont.)
• PCCS and IC system• The pipe wall thickness of the PCCS and IC inlet lines.• The inlet pipe location relative to PCCS/IC pool and if it is
insulated
• Additional BiMAC system design data may become necessary, after the DCD information is more carefully examined.
53
ERIEnergy Research, Inc.
Planned CalculationsRationale for selection of scenarios:o To provide initial & boundary conditions for NRC
confirmatory analyses (e.g., FCI, DCH, BiMAC, etc.)o To enable limited comparison to MAAP predictionso To assess sensitivity to design/operational aspects (e.g.,
sprays)o To support other NRC objectives
“Frequency-dominant”, “risk-dominant” and “consequence-dominant” scenarios will be examined, together with influence of various assumptions and sensitivity cases
54
ERIEnergy Research, Inc.
Case MELCOR SCENARIO
ACC. CLASS
COMMENTS
EXPLORATORY OR
CONFIRMATORY SENSITIVITIES
1 T_DP_nIN I High CDF,
Representative of low pressure sequences
Confirm BiMAC availability, PCCS damage/failure after core
damage
2a T_IRV_DP_nIN_nD I
Highest societal risk &
3rd highest societal consequences &
individual risk
Confirm Concrete types, overlaying water pool
2b T_IRV_DP_nIN_nDv I
3rd highest individual risk Confirm
2c T_IRV_DP_nIN_nD_M I
2nd highest risk & consequences &
individual risk Confirm
2d T_IRV_DP_nIN_nD_1in I
3rd highest societal
consequences Confirm
3a T_DP_nIN_W 2 II
Containment failure prior to CD, CHR fails @ 24
hrs Confirm
4 T_IC24_nD III
Representative of high-
pressure scenarios. Add DCH, HPME/creep rupture of MSL nozzles
and/or SRV
Explore Drywell spray activation impact on LDL water level
5
n/a (similar to #3, 15 cm GDCS
equalization line break)
II
Frequency-dominant
low-pressure sequence. Highest CDF LOCA
with initially intact containment
Explore
6a T_AT_DP_2x IV
3rd high societal risk Confirm
7a BOC_SD_nECC V
Highest societal consequences
Confirm