Issue A 25/03/15 1 NR/L2/OHS/133 Issue 1 March 2015 Code of Practice for Planning & Delivering Safe Work

Upload: tranliem

Post on 01-Feb-2018

230 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

1

NR/L2/OHS/133 Issue 1 March 2015 Code of Practice for

Planning & Delivering Safe Work

Page 2: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

2

Contents

Briefing and Implementation Plan

• Module 1 Awareness brief – For ALL staff

• Module 1a Why change? • Module 1b NR/L2/OHS/133 core awareness brief• Module 1c New competencies• Module 1d New technology, Proscient & Permits to Work• Module 1e When a Safe Work Leader & Permit to Work is required

Page 3: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

3

Briefing & Implementation Plan

Page 4: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

4

Planning & Delivering Safe Work – Introduction of NR/L2/OHS/133 Code of Practice for Planning & Delivering Safe Work

Safety, Technical & Engineering

National Supply Chain

Network Operations

Group Digital Railway

Maintenance

Investment Projects

Professional Development & Training

External Bodies

ORR, RSSB, RAIB

Sentinel

Sentinel Sponsors

Professional Heads

Heads of Engineering

Track

Electrical Power

Control & Comms

Plant & T&RS

Systems Engineering

Building, Geotech & Structures

Route Asset Managers

Route Asset Engineers

Signal Sighting Engineers

Specialist Trainers

Discipline Maintenance Engineers

Delivery Unit Teams

Planning Team

System Support Manager

Principal Contractor Licence

Railway Contractor Certificate

Route Management Teams

Route Control Teams

Electrical Control Operators

Implementation ManagersCascade

Cascade

Cascade

Central PDSW Programme

Cascade

Cascade

Cascade Cascade

Page 5: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

5

Implementation & future changes and briefing plan

Quarterly briefings will be undertaken throughout the phased implementation period, and through post implementation reviewAny changes highlighted during implementation will be briefed throughout the process

Phased

Implementation

NR/L2/OHS/133

April 15

Page 6: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

6

Phased Earliest ‘Go Live’ Dates & Training Plan

Planning & Delivering Safe Work (PDSW)  ‐

2015 tranche rollout planOriginal target Go Live 

date OR

Review date

Route Tranche Feb March April May June July August Sept Oct Nov Dec

East Midlands 1 20th Mar 17th Apr 16th Mar

Anglia 1 30th Mar 27th Apr Under Review

LNE – South 2 30th Mar 27th Apr Under Review

Scotland 1 29th May 26th June 1st June

Wales 3 29th June 27th July

LNE North & Central 2 13th July 10th Aug

LNW – North 2 20th July 17th Aug

LNW – South 2 20th July 17th Aug

Western 3 3rd Aug 31st Aug Under review

South East 3 5th Oct 2nd Nov

Wessex 3 26th Oct 23rd Nov

Training ‐

target for completion Go Live ‐

earliest date

Currently Under Review

Page 7: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

7

NR/L2/OHS/133 Issue 1 March 2015 Detailed Awareness Brief

Module 1 Issue A 25/03/2015

Page 8: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

8

Why Change?Module 1a Issue A 25/03/2015

Page 9: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

9

The need for change – our safety record

• Trends in infrastructure worker fatalities and weighted injuries

Page 10: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

10

P&DSWPhil Hufton & Justin Page

10 point plan

Page 11: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

11

Network Rail is committed to eliminating workforce fatalities and all major injuries

Improving workforce safety is not only the right thing to do from a moral and ethical perspective, it's also good business. Safety and performance go hand-in-hand

Working in the rail industry can be dangerous. It is an inherently hazardous environment, with the potential for harm ever present. To protect our people, public, passengers and the environment, it is vital that there are effective management systems to control these hazards, including the use of safe systems of work

Background

Page 12: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

12

Background

Network Rail aims to create an environment where everyone feels personally responsible for acting, behaving and working safely, and understands the part they play in keeping themselves and others safe. In this environment, there should be no ambiguity. For any site of work, everyone involved should know exactly who has overall responsibility for safety and work delivery

We want people to do it; not because they are told to, but because they want to

Page 13: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

13

Our Brief

To review good practices in managing safety and the Control of Work outside NR and specifically explore the value of a Permit to Work system

To consider the current NR process and develop a concept for a workable risk based permit to work system.

Page 14: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

14

Standardise process of undertaking work on NR Infrastructure

Manage and reduce risks of injury and/or fatality

Provide clarification of responsibilities and accountabilities

Mandate communication activities

Increase understanding of risks and safety controls

Introduce standardised risk assessment and safety controls

Improve competence of individuals

Planning and Delivering Safe Work has been designed to:

Page 15: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

15

NR/L2/OHS/133 Issue 1 March 2015

Module 1b Issue A 25/03/2015

Page 16: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

16

Phased Compliance to NR/L2/OHS/133

Planning and Delivering Safe Work (PDSW) has a phased implementation plan:

April 2015 onwards

Routes, aligned business units, Principal Contractor Licence (PCL) and Railway Contractor Certificate (RCC) holders will go through a ‘Go Live’ process

Current working practices remain until ‘Go Live’ has been achieved

Once the ‘Go Live’ criteria has been met NR/L2/OHS/133 and PDSW protocols will be implemented

Page 17: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

17

Changes to existing standardsNR/L2/OHS/019 Safety of People Working On or Near the Line

As Routes implement PDSW protocol NR/L2/OHS/019 withdrawn for that Route

Letter of Instruction (LOI) to NR/L2/OHS/133 covering GZAM/GZAC

Once National deployment of PDSW protocol achieved, NR/L2/OHS/019 will be fully withdrawn Nationally

RT9909 Record of Arrangements & Briefing Forms

Following the FIRST Route ‘Go Live’ RT9909 will be withdrawn NATIONALLY for incident response and replaced with a new ‘Incident Response Permit’ (*Route TNC’s to 019/RT9909 required)

Following Route ‘Go Live’ RT9909 will be fully withdrawn from that Route and a Lookout/Site Warden Certificate introduced

Page 18: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

18

Scope of NR/L2/OHS/133 Issue 1The standard provides guidance on the permit to work system

The permit to work system must be followed by all parties working on behalf of

Network Rail

The standard is complementary to and to be used in conjunction with:

Existing Rule Books

Existing Regulations

Existing Legislation

Existing Standards

Existing Processes

Existing Procedures

Existing Permits

Page 19: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

19

What’s NewNew concept, building on and complementary to existing process

Introduction of the ‘permit to work system’ introducing 3 important aspects

A number of new competencies and system roles

New Processes

New electronic permitting technology, Proscient

Page 20: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

20

New CompetenciesModule 1c Issue A 25/03/2015

Page 21: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

21

Who is in charge?

Page 22: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

22

Safe Work Leader (SWL) Introduced in the December 2014 Rule Book

Compliance from April 2015

SWL involvement during the planning process

Responsibility for operational and task risk

3 Levels of competence

A Safe Work Leader must be an employee* of:

Network Rail

A Principal Contractor who holds a Principal Contractor Licence

A Railway Contractors Certificate Holder

Page 23: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

23

Safe Work Leader Level 1 (SWL1)SWL1 is experienced in leading a team while working on an open line, in a line blockage, on the lineside or off lineside

If there are two or more SWL1s or individuals working alone (IWA) who need a line blockage at the same place and same time, a protection controller (PC) should be appointed to take overall control of the shared line blockage.

The PC should carry out their duties in accordance with the Rule Book

Page 24: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

24

The role of Controller of Site Safety (COSS)

Safe Work Leaders will lead work outside of a T3 possession

The COSS competence is embedded within the Safe Work Leader

Once PDSW go live achieved you will no longer see a COSS outside of a T3 possession

COSS’s will still exist within possessions

Page 25: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

25

Safe Work Leader Level 2 (SWL2)SWL2 is experienced in planning and managing worksites within possessions and has the ability to lead and manage the interface risks associated with multiple tasks

The SWL2 considers interface risks associated with multiple tasks.

They should confirm that the relevant task leader (TL) has considered the risks and identified controls

The TL is the functional, contractor or principal contractor representative responsible for leading a work area within a worksite in a possession

The TL, acting as the key contact during the planning process, arranges the collation & provision of the relevant permit (s) for their work area

Page 26: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

26

Management of protection on adjacent lines

Line Blockage

Where planned line blockage (s) are required in direct association with work being undertaken in a possession, the SWL2 in charge of the work will consider these requirements during the planning process and generation of the permit (s) to work.

This includes the arrangements for line blockages required immediately before or after the possession and in direct association with the work, and/or for safe access and egress

Where required the SWL2 can appoint a Protection Controller (PC) to manage the line blockage on behalf of all parties who are required to will share the protection

Page 27: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

27

Management of protection on adjacent lines

Equipment Warning

Where equipment warning (ATWS/LOWS/TOWS) is required in direct association with work being undertaken in a possession, the SWL2 in charge of the work will consider these requirements during the planning and generation of the permit (s) to work.This includes the arrangements for equipment warning required immediately before or after the possession and in direct association with the work, and/or for safe access and egress

Where appropriate the SWL2 can appoint a competent person* undertaking the work to manage the equipment warningWhere two or more groups/individuals need to share the same equipment warning, the SWL2 must ensure that the arrangements for sharing protection and briefed to and understood by all parties*the competent person must be competent as, or accompanied by a Controller of Site Safety (COSS)

Unassisted lookout warning protection needs to be managed by a competent SWL

Page 28: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

28

During the planning process, if it becomes apparent that the worksite requires a greater capability in strategic and risk management, a SWL Level 3 (SWL3) shall be appointed to undertake the role of Safe Work Manager (SWM) on site

This could be due to a number of factors including, but not exhaustive:

the workload for one individual

the complexity and management of the permit (s)

the complexity of the task

Is a Safe Work Leader Level 2 (SWL2) enough?

Page 29: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

29

Safe Work Leader Level 3 (SWL3)The SWL3 carries out the role of Safe Work Manager (SWM) on site is experienced in planning and project managing worksites in possessions which require a higher level of strategic and risk management

The SWM WILL appoint an Engineering Supervisor (ES) to support him/her in managing the associated work load

The ES is responsible for all of their duties associated with the Rule Book

Page 30: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

30

The role of Engineering Supervisor (ES)

Safe Work Leaders will be in charge of work sites within T3 possessions

The ES competence is embedded within Safe Work Leader Level 2

Once PDSW go live achieved you will no longer see an ES in a T3 possession, unless a Safe Work Manager has been appointed

Page 31: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

31

Additional competencies

Page 32: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

32

New Technology Proscient and Permits to Work

Module 1d Issue A 25/03/2015

Page 33: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

33

A map is visible in the technology:Highest location risks

Icons to represent other permits in process and their state in the life cycle

Proscient Technology to generate a Permit to Work

Page 34: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

34

Proscient Technology to generate a Permit to Work

During the planning of the work the nature of the work is determined and the appropriate Risk Assessment Template (RAT) is selectedThere are four types of permit and RATs:

Lineside

Off Lineside

On or Near the line Non-Intrusive

On or Near the line Intrusive

The risk assessment tool and templates shall be used by Network Rail for all planned work

These are available to PCL and RCC holders, but they do not have to specifically use these, NR/L3/INI/CP/044 can still be used.

They shall have processes in place to manage task risk and the risk detail captured in Proscient

Page 35: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

35

Hazards, Risks and Controls

The risk assessment tool covers two types of risk assessment:

Non-escalated risk assessment

Escalated risk assessment

Controls can be assigned to people

Control points can be added to the permit to work

Permits can be linked in order to create additional controls

Page 36: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

36

Roles within the life cycle of the permit to work

Suitably trained and competent people play their part in developing the Permit to Work during the planning process

On site and after completion of the work there are defined processes and responsibilities

Page 37: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

37

When a Safe Work Leader & Permit to Work is required

Module 1e Issue A 25/03/2015

Page 38: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

38

SWL/Permit to Work decision map

Page 39: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

39

NB: Individuals Working alone do not require SWL, they require IWA & PTW

Page 40: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

40

NB: Individuals Working alone do not require SWL, they require IWA & PTW

Page 41: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

41

ASPRO = Asset Protection

Page 42: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

42

Contents Additional Modules ‘Go Live’ April – June 15• Module 2 New Forms• Module 3 New Products• Module 4 Roles within the permit to work system• Module 5 The permit to work lifecycle• Module 6 Incident Response• Module 7 Possession Support Staff• Module 8 Accountability and Responsibility• Module 9 Construction & Management of Permit(s) to Work for a • multiple task worksite in a possession• Module 10 Safe Work Manager and Engineering Supervisor Interface• Module 11 Interface with other legislation, regulations, permits, standards etc• Module 12 High level awareness for other Track Safety competence holders• Module 13 NR/L2/OHS/019 disposition• Module 14 The NR development of Proscient (including link to demo)• Module 15 IWA interface with the Permit to Work System• Module 16 Training and Competence • Module 17 Where can I learn more?• Module 18 Changes to Proscient – for people who have been trained• Module 19 Introduction of SWL and translation into existing standards

Additional modules used for detailed and/or

targeted briefs

Page 43: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Issue A 25/03/15

43

QUESTIONS

Contact: [email protected]

Page 44: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Rule Book Handbook 1 allows people to Walk on the Infrastructure using their PTS competence. The existing Rule Book allowance still applies:

Clarification 1: Network Rail Employees Walking to a place to do work which is within the Operational Railway Boundary and requires a Permit to Work DO need to consider the safe access and egress arrangements and controls within the permit to work for the workClarification 2: Non Network Rail Employees (PCL/RCC's) Walking to a place of work which is On or Near the Line DO need to consider the safe access and egress arrangements and controls within the permit to worl for the workClarification 3:People that are using the Rule Book Handbook 1 allowance to walk on the Infrastructure to get to a location which does NOT require a permit to work, do NOT need a permit to work

There are a number of activities which can take place on Network Rails Infrastructure WITHOUT the need for a Permit to Work

A list of these are contained below

A permit to work is NOT required where the work is directly related to facilities management, unless there is a risk to the safe running of the operational railway

A Rail Incident Officer (RIO) does NOT require a Permit to Work

Blue light services requesting access direct to the signaller do NOT require a Permit to Work, including:- Fire- Police- Ambulance- Coast Guard- Bomb DisposalOnce specific controls and a safe system of work is identified, an Incident Response Permit to Work will be utilised

Designated Persons (DP) continue to work to existing operational standards and do NOT require a Permit to Work

Pilotmen continue to work to existing operational standards and do NOT require a Permit to Work

A Signaller can still work under their own protection and do NOT require a Permit to Work

Network Rail ScopeClarification Re-Issued 11th May 2015

Page 45: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Our primary objective is to improve work force safety

a. Working in a hazardous environment and/or undertaking hazardous work

The following examples are intended to provide more context and clarity

d.Undertaking work which could DIRECTLY impact on the safe running of the operational railwayDirectly includes activities taking place adjacent to the operational railway which could cause a derailment risk (eg obstruction or instability etc) and additional controls are requiredDirectly does NOT include Signalling, Telecoms & E&P activities unless they could create a derailment risk. Risks to the safe running of the operational railway as a result of Telecoms, E&P and Signalling activities shall be managed using existing standards and procedures

There is a secondary opportunity to improve the safety of passengers and public by adding additional processes and controls when undertaking work which can impact on the safe running of the operational railway

It is a fact that there will initially be a different scope of 'when a permit to work' is required for work being led by Network Rail and work being led by PCL's or RCC's

This is an interim position, and in time PCL's and RCC's will also work to the NR scope, following the introduction of a further competence covering activities which are not 'On or Near the Line'

Once live with PDSW Protocols Network Rail employees will require a permit to work in MORE instances than when they currently require a Safe System of Work Pack.

This is a deliberate acceleration of the intended final scope, and is designed to improve our consideration of and management of task risks and associated controls when either:

There is still some abiguity around the Network Rail Employee Scope of when a Permit to Work is required

When in doubt, a permit to work IS required

Network Rail ScopeClarification Re-Issued 11th May 2015

Page 46: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Boundary

When working on a structure (eg Bridge) and

additional controls are required to protect the safe running of the operational

railway

When undertaking a task known to potentially result in personal harm (eg: picking up hyperdermic needles, moving batteries containing battery acid AND additional PPE is

requiredWhen additional safety controls are required (eg. Use of Harness, line blockage, PPE etc)

Off LinesideOutside of the Railway

Boundary

3m from running edge to the boundary including the boundary

When the work you are undertaking can DIRECTLY impact on the safe running of the operational railway

Directly includes activities taking place adjacent to the operational railway which could cause a derailment risk and additional controls are required (eg obstruction, instability etc)

Directly does NOT include Signalling, Telecoms & E&P activities. Risks to the safe running of the operational railway as a result of Telecoms, Signalling & E&P

activities shall be managed using existing standards and procedures

When loading/unloading materials within the boundary and the lift requires a machine or more than 1 person to carry

On or Near the Line (Intrusive or Non Intrusive)

3m from outside running rail

When your procedures require you to have an electrical isolation ** see notes in guidance of when a PTW is NOT required

Lineside & the Boundary(3m from nearest running rail to the boundary (including the boundary))

When using motorised power tools

When the environment has hazardous features and additional controls are required (eg.incline on embankment)

When breaking groundWhen required to enter a confined space

Working at Height

When your procedures require you to have an

electrical isolation* see notes in guidance of

when a PTW is NOT

Minimum requirements When a Permit to Work IS required. (If in doubt a Permit to Work IS Required)

Permit to Work Req'd

Network Rail ScopeClarification Re-Issued 11th May 2015

Page 47: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Clarification When a Permit to Work is NOT required.

A permit to work is NOT required when the work is directly related to facilities management unless there is a direct risk to the safe running of the operational railway

(If in doubt a Permit to Work IS Required)

You do NOT require a permit to work where the activity requires no additional risk controls to be applied

Off LinesideOutside of the Railway Boundary

You always require a Permit to Work when your procedures require you to have an electrical isolation

You do NOT require a permit to work when using pre-installed interfaces (eg switches, buttons, meters etc)You do NOT require a permit to work when you are

testing using an approved meter and no additional risk controls are required

You do NOT require a permit to work when working on a Signaller panel / workstation unless additional risk

controls are required

Excluding facilities, You always require a Permit to Work when your procedures require you to have an electrical

isolationNote: when the facility you are entering requires an Electrical Permit you do require a Permit to Work

You do NOT require a permit to work when using a pre-installed interface (eg. switches, buttons, meters etc)You do NOT require a permit to work when you are

testing using an approved meter and no additional risk controls are required

You do NOT require a permit to work when working on Signaller panel / workstation unless additional risk

controls are required

You do NOT require a permit to work when task only involves hand tools (including battery powered) and no

additional risk controls are required (eg no isolation, harness additional PPE etc)

You do NOT require a permit to work when working on a structure (eg Bridge) off the railway boundary and no

additional controls are required to protect the safe runningof the operational railway

Permit to Work Req'd

On or Near the Linewithin 3m from nearest running rail

Permit to Work Required

Lineside & the BoundaryFrom 3m from nearest running rail to the boundary, including the

Network Rail ScopeClarification Re-Issued 11th May 2015

Page 48: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Ref: PDSW-HRV-INS-12-12-2014 0000 Version: 2.1 Creation Date: March 2015 (post matrix review) Compliance Date: TBC

Safe Work Leader (SWL) – Addendum to Consultation (To be read in conjunction with main consultation document)

1.0 The purpose of this addendum is to detail the minimum payment

arrangements for those undertaking SWL duties and to describe the process for managing disputes around permit acceptance..

1.1 Payment Arrangements for those undertaking the Role of SWL

1.1.1 All individuals undertaking SWL1 duties must have been trained

and deemed competent at the appropriate level.

1.1.2 Individuals undertaking SWL duties will be paid a minimum of Technician (or equivalent rate) for all time undertaking the duties.

1.1.3 HGD Payment will be paid in line with current T&C’s

In addition

1.2 Individuals undertaking SWL1 duties will be paid a minimum of the

appropriate Team Leader (or equivalent rate) where ALL of the following conditions Apply.

1.2.1 They have been correctly appointed as SWL in accordance with

Permit Arrangements 1.2.2 The activity is “On or Near the Line” as defined in Rule Book 1.2.3 The team consists of more than the SWL and members

provided solely for his/her protection 1.2.4 The required duties are more than a temporary transfer of

Permit from a Team Leader during ongoing activity. (Temporary transfer for part of shift would receive HGD to Team Leader in line with current T&C’s

1.3 Individuals undertaking Duties at SWL 2 level will be paid a minimum of the appropriate Team Leader ROP for time undertaking these duties consistent with current T&C’s.

1.4 These arrangements are intended to supplement existing HGD

arrangements and not replace them.

1.4.1 Existing HGD arrangements will continue to apply in line with current T&C’s and Matrix frameworks

1.4.2 Matrices will be brought into line with these principles for the SWL role. Until this occurs, the arrangements in this addendum will take precedence.

Page 49: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Ref: PDSW-HRV-INS-12-12-2014 0000 Version: 2.1 Creation Date: March 2015 (post matrix review) Compliance Date: TBC

2.0 Safe Work Leader Permit Dispute Resolution Process

2.1 The purpose of this addendum is to define the process to be used to

resolve dispute relating to the preparation, Authorisation and acceptance or use of permit, following the introduction of the Safe Work Leader (SWL) and new Permit to Work arrangements

2.2 Fundamental of the introduction of the SWL and the new control of work

process is the absolute requirement that the SWL undertaking the work must both accept the permit, and subsequently verify as fit for use at point of taking live.

2.3` For other than routine and cyclic low risk activity the SWL required to

undertake the work will be involved in the planning and authorising process prior to issue. For routine and cyclic low risk activity, an appropriate SWL will be involved in the permit production process.

2.4 It is possible for an SWL involved in the early stages to withhold

validating the permit until satisfied that it is appropriate for intended use. Action at this stage would result in re-planning in an iterative process until permit is fit for purpose.

2.5 Where there is material change to work content, the permit must be

reviewed and where necessary edited, re-authorised and re-issued prior to work commencing. Where change is substantial a new permit will be required. – (this is particularly relevant to late notice change).

2.6 In all cases the SWL must accept the Permit is appropriate before work

can commence. 2.7 In the event that a permit is declined by SWL at point of issue or at time

of go live, that results in dispute, the matter will be dealt with under the Work-safe Procedure.

2.8 It is accepted that the principles of the Permit to work arrangements fall

under the Fair Culture approach, jointly supported by NR and the TU’s. Investigations required related to the operation of the new arrangements will follow Fair Culture Principles and practice.

2.9 All instances of permit declination or refusal will be recorded and form

part of Post Implementation Review.

END

Document Compiled by A.J. Brookes P&DSW Programme Manager

Page 50: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Planning & Delivery of Safe Work SWL Competence Matrix Assimilation January 2015

Matrix Assimilation for SWL Competencies Summary Guidance - All Matrices The introduction of SWL is to be in accordance with the following framework Section Manager /Section Supervisor SWL1, SWL2, SWM (SWL3)# Team Leader - SWL1 and SWL2 as required#. Technician - SWL1 as required# Operative - # The selection of SWL for any given task must take into account additional competencies required to undertake the task in addition to the SWL competence. Principle of SWL is that Team Leaders or those regularly deputising hold the competence. Refer to main P&DSW National Consultation Document and Addendum for additional detail Under normal circumstances, the Team Leader is expected to undertake the role of SWL. It is recognised that relief arrangements will be required and when identified to undertake SWL duties for an entire shift, the following minimum payment arrangements will apply SWL1 Technician (basic) or equivalent (to be defined in matrix) to apply SWL2 Team Leader (basic) or equivalent (to be defined in matrix) to apply SWM / SWL3 Supervisor rate (as applied locally) When undertaking SWL duties for less than a shift, current HGD arrangements will apply. Individual Matrix Assimilations are shown in Following Sections

Page 1 of 1 A.J Brookes

January 2015

Page 51: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

East Midlands Area ex SERCo Proposed PDSWL Assimilation

Band pre 2bc 2bc Grade Scale Level SWL Comments

A1 Team Leader Team Leader NW3801 SPICOP Advanced

A2 Track Chargeman Team Leader NW3802 PICOP Advanced SWL2 If not A2 Advanced grade then only paid rate when undertaking role

A3 Track Chargeman Team Leader NW3803 ES Intermediate

A3 Track Chargeman Team Leader NW3803 4774 Basic SWL1 If not A3 Basic grade then only paid rate when undertaking role

A3 Track Chargeman Team Leader NW3803 Standard

A5 Leading Trackman Technician NW3805 Advanced

A5 Leading Trackman Technician NW3805 COSS Basic

A7 Trackman Operative NW3807 Advanced

A7 Trackman Operative NW3807 Basic

Band Job 2bc Grade Scale Level

A1 S&T 4 Team Leader NW3801 Advanced SWL2 If not A1 Advanced grade then only paid rate when undertaking role

A1 S&T 4 Team Leader NW3801 Intermediate SWL1 If not A1 Intermediate grade then only paid rate when undertaking role

A3 S&T 3 Technician NW3803 Advanced

A3 S&T 3 Technician NW3803 Intermediate

A3 S&T 3 Technician NW3803 Basic

A5 S&T2 Operative NW3805 Intermediate

A5 S&T2 Operative NW3805 Basic

Band Job 2bc Grade Scale Level

A1 Shift Spvr Working Supervisor NW3801 Advanced

A1 Shift Spvr Working Supervisor NW3801 Intermediate SWL2 If not A1 Intermediate grade then only paid rate when undertaking role

A3 Snr Lmn Team Leader NW3803 Advanced

A3 Snr Lmn Team Leader NW3803 Intermediate

A3 Snr Lmn Team Leader NW3803 Basic SWL1 If not A3 Basic grade then only paid rate when undertaking role

A5 Lineman Technician NW3805 Intermediate

A5 Lineman Technician NW3805 Basic

A7 T Lineman Operative NW3807 Basic

Band Job 2bc Grade Scale Level

A1 Snr D&P Tech Team Leader NW3801 Advanced SWL2 If not A1 Advanced grade then only paid rate when undertaking role

A1 Snr D&P Tech Team Leader NW3801 Intermediate

A1 Snr D&P Tech Team Leader NW3801 Basic SWL1 If not A1 Basic grade then only paid rate when undertaking role

A2 D&P Tech Technician NW3802 Intermediate

A2 D&P Tech Technician NW3802 Basic

Payment arrangements for those undertaking the role of SWL are attached as an addendum. Please Note - Activities currently carried out solely by a Technician with protection will not attract HGD to Team Leader SWL1

Please Note - For S&T and D&P Team Leaders matrix progression is not dependant on holding ES/SWL2 competency, However in line with the agreed 2bc competency matrices both roles can be requested to hold the ES/SWL2 competency subject to the agreed number of core competencies not being exceeded.

Page 52: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Network Rail, 1 Eversholt Street, London NW1 2DN.

Letter of Instruction: NR/BS/LI/352 Issue date: 17/04/2015 Compliance date: 17/04/2015 Expiry date: NR/L2/OHS/133 Issue 2 compliance date Contact details: David Burgess

Standard affected: NR/L2/OHS/133 (Issue 1), Code of Practice for Planning and Delivering Safe Work (PDSW)

1 Reason for issue To support implementation of the permit to work system, NR is introducing a new standard NR/L2/OHS/133 Code of Practice for Planning and Delivering Safe Work. This standard and this Letter of Instruction will replace NR/L2/OHS/019 Safety of People Working On or Near the Line.

Planning and Delivering Safe Work (PDSW) has a phased implementation plan. Routes, aligned business units, Principal Contractor Licence (PCL) and Railway Contractor Certificate (RCC) holders will go through a ‘Go Live’ process. Once the ‘Go Live’ criteria have been met NR/L2/OHS/133 Code of Practice for Planning and Delivering Safe Work will be implemented.

As Routes implement and adopt NR/L2/OHS/133 the national phased withdrawal of NR/L2/OHS/019 Safety of People Working On or Near the Line will begin for that Route. Once national deployment of the PDSW protocol is achieved, NR/L2/OHS/019 will be fully withdrawn.

This Letter of Instruction contains relevant content from within the NR/L2/OHS/019 standard that shall be complied with, over and above the requirements contained within NR/L3/OHS133 Issue 1.

2 Scope Many of the requirements in the NR/L2/OHS/019 standard have been superseded and are now contained in NR/L2/OHS/133. The parts of NR/L2/OHS/019 standard that remain current can be found within this document.

This document summarises the requirements contained in the NR/L2/OHS/019 standard which are not covered within NR/L2/OHS/133, so remain applicable.

3 Introduction Planning and Delivering Safe Work (PDSW) has been designed to:

standardise the process of undertaking work on Network Rail infrastructure

manage and reduce the risks of injury and/or fatality through clarification of safety responsibilities and accountabilities

mandate communication activities such that appropriate levels of understanding of risks and safety controls are maintained

mitigate the risks of injury and/or fatality through comprehensive risk assessment and implementation of standardised safety controls

improve the competence of individuals.

Page 53: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Network Rail, 1 Eversholt Street, London NW1 2DN. PDSW includes the permit to work system, introducing three important aspects:

A number of new competencies and system roles

New processes

New electronic permitting technology, Proscient

These changes provide clarity around the accountability and responsibility for planning and delivering safe work.

4 Definitions and Abbreviations 4.1 Definitions Access Co-ordinator Access co-ordinator within Maintenance Delivery Units or an other person who co-ordinates access requests Green Zone A site of work on or near the line within which there are no train movements. (The only exception to this is within a worksite within a possession for movements of engineering trains or on-track plant. These movements will be made at walking pace.) Green Zone Access Co-ordinator An individual who has been trained and passed competent in Core Planner Skills 2 and who can optimise planned work and arrange bookings in the appropriate systems. Green Zone Access Management The system used to book Green Zone protection that is not required to be published in the Weekly Operating Notice or that is scheduled to take place within eight weeks. Individual Working Alone A person appointed and certified as competent to provide their own protection to enable them to carry out activities in accordance with the requirements of the Rule Book (GE/RT8000). National Hazard Directory A database that identifies the hazards on Network Rail’s controlled infrastructure. It also includes other useful information, which should be considered during the planning work. On or near the line As defined in the Rule Book Handbook 1 (GE/RT8000/HB1) Permit to Work The paper certificate or form, which is used to capture the requirements of the permit to work. Whether it is manually or electronically generated, it is a detailed document which authorises specific people to carry out specific work, at a specific site, at a specific time, and sets out the controls necessary to complete the job safety. The Network Rail permit to work is electronically generated using Proscient technology. PICOP Pack A pack produced by Network Rail NDS using PPS (refer to NR/L2/NDS/202, Principles, Timescales and Functional Responsibilities for Engineering Work, Access and Heavy Resource

Page 54: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Network Rail, 1 Eversholt Street, London NW1 2DN. Planning) or by other means. The mandatory content of PICOP packs is included in NR/L3/NDS/303 T3 Possession of the Line for Engineering Work Delivery Requirements. Position of Safety As defined within the Rule Book Handbook 1 (GE/RT8000/HB1) Possession A line is under possession when arrangements have been carried out to block the line completely to the normal passage of trains in accordance with the Rule Book GR/RT8000 so that engineering trains or on track plant can be used. Red Zone A site of work on or near the line, which is not protected from train movements Safe System of Work Arrangements to make sure a workgroup, including lookouts, that is to walk or work on or near the line is not put in danger by passing trains or movements. This includes the arrangements for: entry to and exit from railway infrastructure walking on or near the line walking to or from a site of work setting up and withdrawing protection or warning arrangements carrying out work.

Safe Work Leader The role of an employee of Network Rail, a principal contractor who holds a trackside principal contractor licence or a contractor who has gained a railway contractors certificate, who manages safe delivery of work. Verification Authority The role which verifies the contents of the permit to work in advance of authorisation. Weekly Operating Notice The official notice referred to in Rules and Regulations for giving details of: Temporary speed restrictions; Engineering arrangements; Signalling and permanent way alterations; Amendments to National Operations Publications (NOPs), Sectional Appendices and other

notices. 4.2 Abbreviations Abbreviation Full term IWA Individual Working Alone GZAC Green Zone Access Co-ordinator GZAM Green Zone Access Management NSC National Supply Chain PICOP Person in Charge of Possession PPS Possession Planning System SSOW Safe System of Work SWL Safe Work Leader WON Weekly Operating Notices

Page 55: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Network Rail, 1 Eversholt Street, London NW1 2DN. 5 Planning Roles and Responsibilities 5.1 The Planner The Planner is responsible for planning the work. The Planner shall plan a proposed SSOW within the permit to work, applying the principles of the Hierarchy of Safe Systems of Work (see clause 5.3 of NR/L2/OHS/133 Issue 1). The Planner shall be assessed and certified as competent in Planning & Delivering Safe Work and assessed as competent to the requirements of the Network Rail document “Training and Assessment Arrangements for Core Planner Skills” (available through Network Rail Competence & Training Management). To assist them develop a SSOW plan, Planners shall have access to, and extract information from, documents such as:

• the Sectional Appendix; • the National Hazard Directory; • signalling diagrams

Training shall be provided to enable Planners to read and interpret the content of these documents. These documents shall be supplemented with (where appropriate):

• photographs or other visual aids to help validate assumptions about the site of work (particularly when planning Red Zone working);

• track diagrams; • a site visit, if required

The Planner shall, upon receipt of a rejected planned SSOW review the SSOW and the reasons for its rejection. The Planner shall then make any changes required to create an appropriate SSOW. 5.2 The Access Co-ordinator The Access Co-ordinator shall obtain the required disruptive track access through NSC on behalf of the Infrastructure Maintenance organisation, liaising with the Planner until the access has been secured. 5.3 Green Zone Access Co-ordinator The Green Zone Access Co-ordinator shall arrange the required track access using the Green Zone Access Management system (GZAM) for work taking place in less than 8 weeks from the request date or for work which is not required to be published in the WON. They shall respond to the Planner (requester) within a reasonable time period with regards to what track access has been secured. 5.4 The NSC Planning Specialist The NSC Planning Specialist shall arrange the required track access using the Possession Planning System (PPS) for work which is required to be published in the WON or takes place in over 8 weeks from the request date. They shall respond to Planner (requester) within a reasonable time period.

Page 56: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Network Rail, 1 Eversholt Street, London NW1 2DN. 6 The Safe System of Work Planning Process in Normal Circumstances

a. If planned Green Zone protection is required the Planner shall apply to NSC for this using PPS or GZAM (depending on the timescales and potential for the work to affect safety of the line) via the Access Coordinator.

b. The NSC Planning (Delivery) team shall consider all requests for track access, optimise the requests to provide the required protection and either approve or decline the requests within a reasonable time period.

c. Should the protection be changed or declined by the NSC Planning (Delivery) team, the Planner shall reconsider the work and the protection offered or available.

d. Once appropriate protection has been decided and arranged by NSC (where applicable), the Planner shall plan the SSOW and record this using the Permit to Work.

7 Planning Line Blockages

If the planned SSOW requires any line or lines to be blocked or a possession of the line to be taken in accordance with the Rule Book, then the blockage or possession shall be requested in accordance with Network Rail’s planning requirements as follows:

• line blockages and possessions which are required to be published in the WON shall be

requested using the Possession Planning System (PPS); • line blockages which do not need to be published in the WON shall be requested via

Network Rail’s Green Zone Access Co-ordinator (usually the NSC Planning Assistant (Delivery)) or arranged through formalised local agreements.

NOTE 1: It might not be necessary to block lines to create a fenced or separated Green Zone. In Exceptional Circumstances it may be possible to arrange a line blockage or a possession at short notice via either the relevant signaller or the relevant Network Rail Control. NOTE 2: Signallers might not be able to grant the lineside request when it is made; therefore preplanning of protection arrangements is strongly advised. 8 Protecting Work Using Green Zones 8.1 Availability of Green Zones Green Zone working is the preferred method of protection for all personnel on or near the line. Therefore each Network Rail Route shall look to maximise the opportunities for Green Zone working to take place by:

• working with contractors and Network Rail planners to programme work; • taking account of maintenance requirements within timetable planning processes, in

particular giving consideration to: • the impact of any proposed changes to the timing or density of traffic on the availability of

line blockage(s); and • reducing or rescheduling services where access for maintenance is inadequate

The creation of Green Zone working opportunities by blocking lines between normal train services should be considered by Routes as part of the timetable planning processes.

Page 57: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Network Rail, 1 Eversholt Street, London NW1 2DN. 8.2 Green Zone Guide Network Rail and Infrastructure Contractors shall co-operate, so that as far as is reasonably possible, work is programmed into Green Zones. To facilitate this, Network Rail shall publish a Green Zone Guide(s) containing the following information on a line of route basis:

• when it is likely to be possible to block one or more lines without disrupting train services; • arrangements for 'booking' blockages of line(s); • circumstances when requests to block lines will not be granted.

The Green Zone Guide(s) shall be made available to all parties who need to plan or undertake work on or near the line for Network Rail. 8.3 Possession Planning When planning work in possessions the risks from train movements on open lines adjacent or close to the possession, and movements of engineer’s trains, on track machines (OTM) and on track plant (OTP) within the possession, shall be taken into account. Where there are open lines adjacent to the possession, Planners shall specify the SSOW to be adopted in relation to these lines, taking particular account of the distance between the blocked and open lines and the fact that this distance could vary through the length of the possession. The requirements of the Rule Book and the Hierarchy of Safe Systems of Work described in NR/L2/OHS/133 shall be applied in respect of the open lines, with the highest practicable option being selected. The verification and detailed planning of the SSOW for the open lines shall be completed by the nominated verification authority for the permit to work. All movements of engineer’s trains, OTM and OTP present a risk to track staff so wherever possible movements shall either be avoided entirely or kept separate from work groups. This may require the division of the worksite into discrete “movements” and “work” areas to enable the creation of Green Zones. If it is not possible to restrict movements on the line under possession to extreme caution, a Red Zone SSOW shall be planned. Similarly, when there are no movements within the possession, but an adjacent line is open to traffic and neither fences nor Site Wardens are provided, a Red Zone SSOW shall be planned. Only when the criteria for Green Zones are met in respect of both the open and blocked lines may a Green Zone system of work be planned. Alternative means of achieving work on the railway infrastructure (e.g. using plant or machinery) should always be considered before requiring people to go on or near the line. 8.4 Publication of Possessions and Line Blockages in Weekly Operating Notices Details of any possession shall be published in the WON or Engineering Notice unless the possession is taken:

• in an emergency; or • in Exceptional Circumstances.

The Planner shall decide whether line blockages need to be published in the WON. Items that are required to be published in the WON shall be entered into PPS according to the requirements laid out in NR/L2/NDS/202, Principles, Timescales and Functional Responsibilities for Engineering

Page 58: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Network Rail, 1 Eversholt Street, London NW1 2DN. Work, Access and Heavy Resource Planning) and NR/L3/NDS/303 T3 Possession of the Line for Engineering Work Delivery Requirements. 9 Red Zone Working Prohibitions 9.1 General Prohibitions Red Zone Working shall not be permitted:

a) where the total warning time required exceeds 45 seconds; b) where there are three or more running lines open to traffic between the site of work and the

designated position(s) of safety; or c) at locations where the Network Rail National Hazard Directory prohibits Red Zone working

(see clause 9.2). In addition, Red Zone working with warning given by Lookouts shall not be permitted in any of the following circumstances:

• where more than two Lookouts (excluding site and touch Lookouts) are required to provide warning of trains approaching from any one direction;

• where more than four Lookouts (excluding site and touch Lookouts) are required to provide warning of trains approaching from all required directions; or

• where the sighting distance that can be achieved with Lookouts is insufficient to provide the warning time required.

9.2 Network Rail National Hazard Directory In addition to the prohibitions set out in clause 9.1, Network Rail prohibits all forms of Red Zone working at locations:

a) where there is not, as an absolute minimum, one directly accessible position of safety capable of accommodating at least two people located every 50 metres (160 feet) along the track side so that it is never necessary to walk more than 25 metres (80 feet) along the track side to reach a position of safety. (Directly accessible means without the need to climb on to, or over, a structure such as a wall, railings or a platform to reach a position of safety);

b) where it is determined by the Infrastructure Maintenance Delivery Manager that, for any other reason, the risk of people being struck by trains during Red Zone working is unacceptable.

NOTE 3: Examples of locations at which Network Rail may prohibit Red Zone working could include tunnels, multiple track areas and the approaches to busy terminal stations. Details of these locations and the reasons for the prohibition shall be published in the Network Rail National Hazard Directory as required by Network Rail standard NR/L2/MTC/006, Maintenance and Content of a Hazard Directory. 9.3 Working Where Red Zone Working is normally prohibited It shall be permissible to undertake Red Zone working where it would normally be prohibited by clauses 9.1 b) or 9.2 a), provided that no suitable opportunity for Green Zone working is available and the following arrangements are implemented to control the risk of persons being struck by trains:

Page 59: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Network Rail, 1 Eversholt Street, London NW1 2DN. • in the case of 9.1 b), where there would be three or more running lines open to traffic

between the site of work and the designated position of safety, Red Zone working shall be permitted if one or more of these lines are blocked to provide adequate position(s) of safety;

• in the case of 9.2 a), where there would be more than 25 metres (80 feet) along the track

side to a directly accessible position of safety capable of accommodating at least two people, Red Zone working shall be permitted if either:

o one or more lines are blocked to provide adequate position(s) of safety; or o work is to take place in a possession and adequate warning arrangements can be

established, taking into account the number and speed of train movements within the possession.

9.4 Track Inspection and Patrolling at Locations Where Red Zone Working is normally prohibited The Network Rail Infrastructure Maintenance Delivery Manager is required to determine and specify the arrangements for track patrolling and inspection to take place in accordance with the requirements of Network Rail Specification NR/L2/TRK/001, Inspection and Maintenance of Permanent Way. Any permit to work provided to an SWL/IWA for a track patrolling, inspection or other moving worksite that includes sections of the route where Red Zone working is prohibited shall include for each such section either:

• documentation for planned blockage(s) of the line to allow safe passage through the Red Zone prohibited area; or

• instructions as to where to leave and return to the track to safely avoid the Red Zone prohibited area.

10 The Permit to Work Pack

A Permit to Work Pack shall comprise:

• the permit to work • a copy of the relevant PICOP pack (where appropriate) • additional signalling or track diagrams (where appropriate)

Note 4: PICOP packs are produced by Network Rail NSC using PPS (refer to NR/L2/NDS/202, Principles, Timescales and Functional Responsibilities for Engineering Work, Access and Heavy Resource Planning) or by other means.

11 Monitoring

Senior responsible managers within Network Rail and Infrastructure Contracting organisations shall have processes in place to monitor the level of work carried out under Green Zone and Red Zone conditions.

Network Rail shall also have processes in place to monitor the workload of signallers and their performance in granting and/or refusing line blockages to create Green Zones.

Page 60: NR/L2/OHS/133 Issue 1 March 2015 - rmt · PDF fileModule 1e When a Safe Work Leader & Permit to Work is required. ... NR/L2/OHS/133 Issue 1 March 2015 ... NR/L2/OHS/019 will be

Network Rail, 1 Eversholt Street, London NW1 2DN.

Authorisation of Standard Owner Authorised by

------------------------------------------------------------------- Emma Head

Authorisation of appropriate Delivery Function authority Authorised by ------------------------------------------------------------------- Not Applicable

4 Recipients

Post

PDSW Implementation Managers

Network Rail Area Directors

NSC Competence Specialist

NSC Business Managers

NSC Senior Operations Delivery Managers

Signalling & Operations Competence Specialist

Operations Risk Advisors

Infrastructure Maintenance Competence & Assessment Manager

Route Workforce Health, Safety & Environment Advisor

IP Programme Heads of HSEA

Head of Occupational Health & Safety

Holders of SWL competence (internal & external)

Holders of Core Planner Skills Competence Levels 1 & 2 (Internal & External)

All line managers of individuals holding SWL, IWA and Planner competence

5 Details of briefing or cascade communication process This letter of instruction will be briefed in conjunction with the briefing of NR/L2/OHS/133 Code of Practice for Planning and Delivering Safe Work.